Project Geographic District
17
Project Building Identifier
K091
Project School Name
P.S. 91 - BROOKLYN
Project Description
ELECTRICAL SYSTEM UPGRADE / FLOOD ELIMINATION / WINDOWS / EXTERIOR MASONRY / PARAPETS / ROOFS
Project Phase Name
CM,F&E
Project Status Name
Complete
Project Phase Actual Start Date
9/18/2023
Project Phase Planned End Date
2/3/2026
Project Phase Actual End Date
12/31/2025
Project Budget Amount
1015426
Final Estimate Of Actual Costs Through End Of Phase Amount
813335
Total Phase Actual Spending Amount
803605
Dsf Number S
DSF0000985982, DSF0000985977, DSF0001083854, DSF0001061435, DSF0001061434, DSF0001061433