Project Geographic District
20
Project Building Identifier
K104
Project School Name
P.S. 104 - BROOKLYN
Project Description
PLANYC BOILER CONVERSION / PLANYC CLIMATE CONTROL / COVID VENTILATION / COVID LOW VOLTAGE ELECTRICAL SYSTEMS / FLOOD ELIMINATION
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
4/20/2023
Project Phase Planned End Date
9/21/2023
Project Phase Actual End Date
5/9/2023
Project Budget Amount
1198300
Final Estimate Of Actual Costs Through End Of Phase Amount
1085744
Total Phase Actual Spending Amount
935027
Dsf Number S
DSF0000798257, DSF0000798260, DSF0000986211, DSF0001010957, DSF0001061643