Capital Project Schedules and Budgets

List of capital projects with managing organization, phase status and project costs.

Housing & Development School Construction Authority (SCA) Dataset 2xh6-psuq 14 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
32
Project Geographic District : 32 • Project Building Identifier: K145 • Project School Name: P.S. 145 - BROOKLYN
Project Geographic District
32
Project Building Identifier
K145
Project School Name
P.S. 145 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-ABATE ACM FROM WASTELINE IN STAFF BATH ACROSS FROM ROOM 251 ACM MARKED WITH RED SPRAY PIANT APP
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
1/30/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
2/28/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
11835
Total Phase Actual Spending Amount
1558
Dsf Number S
SCA0000075360
14
Project Geographic District : 14 • Project Building Identifier: K147 • Project School Name: P.S. 147 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K147
Project School Name
P.S. 147 - BROOKLYN
Project Type
DIIT - RESOA
Project Description
FY24 RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
200000
Total Phase Actual Spending Amount
200000
Dsf Number S
DSF0001085995
14
Project Geographic District : 14 • Project Building Identifier: K147 • Project School Name: YOUNG WOMEN'S LEADERSHIP SCHOOL - BROOKLYN
Project Geographic District
14
Project Building Identifier
K147
Project School Name
YOUNG WOMEN'S LEADERSHIP SCHOOL - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY24 RESO A BATHROOM UPGRADES
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
1/2/2024
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
150000
Total Phase Actual Spending Amount
139969
Dsf Number S
DSF0001085994
14
Project Geographic District : 14 • Project Building Identifier: K147 • Project School Name: P.S. 147 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K147
Project School Name
P.S. 147 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY20 RESO A AUDITORIUM UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
1215268
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0000913225
14
Project Geographic District : 14 • Project Building Identifier: K147 • Project School Name: P.S. 147 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K147
Project School Name
P.S. 147 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY16 RESO A SUPPLEMENTAL COOLING
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
7/19/2017
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
671737
Total Phase Actual Spending Amount
626639
Dsf Number S
DSF0000822304
14
Project Geographic District : 14 • Project Building Identifier: K147 • Project School Name: P.S. 147 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K147
Project School Name
P.S. 147 - BROOKLYN
Project Type
DOE - Skilled Trades
Project Description
CAFETERIA ENHANCEMENT EXPERIENCE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
1/15/2026
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
702425
Total Phase Actual Spending Amount
437213
Dsf Number S
DSF0001111714
14
Project Geographic District : 14 • Project Building Identifier: K147 • Project School Name: P.S. 147 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K147
Project School Name
P.S. 147 - BROOKLYN
Project Type
Fast Track Projects
Project Description
FY26 RESO A STEM LAB
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
FTK
Project Phase Planned End Date
FTK
Project Phase Actual End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
400000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001163715
14
Project Geographic District : 14 • Project Building Identifier: K147 • Project School Name: P.S. 147 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K147
Project School Name
P.S. 147 - BROOKLYN
Project Type
SCA CIP
Project Description
ELECTRICAL SERVICE ROOM
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
3/3/2025
Project Phase Planned End Date
3/2/2026
Project Budget Amount
73500
Final Estimate Of Actual Costs Through End Of Phase Amount
208983
Total Phase Actual Spending Amount
198833
Dsf Number S
DSF0000893060
14
Project Geographic District : 14 • Project Building Identifier: K147 • Project School Name: P.S. 147 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K147
Project School Name
P.S. 147 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
6/3/2025
Project Phase Planned End Date
4/28/2026
Project Budget Amount
151943
Final Estimate Of Actual Costs Through End Of Phase Amount
145285
Total Phase Actual Spending Amount
142454
Dsf Number S
DSF0001087401
14
Project Geographic District : 14 • Project Building Identifier: K147 • Project School Name: P.S. 147 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K147
Project School Name
P.S. 147 - BROOKLYN
Project Type
SCA CIP
Project Description
FLOOR REPLACEMENT
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
394206
Final Estimate Of Actual Costs Through End Of Phase Amount
394206
Total Phase Actual Spending Amount
76964
Dsf Number S
DSF0001062249
14
Project Geographic District : 14 • Project Building Identifier: K147 • Project School Name: P.S. 147 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K147
Project School Name
P.S. 147 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
6/3/2025
Project Phase Planned End Date
4/28/2026
Project Budget Amount
193604
Final Estimate Of Actual Costs Through End Of Phase Amount
182685
Total Phase Actual Spending Amount
147675
Dsf Number S
DSF0001087401
14
Project Geographic District : 14 • Project Building Identifier: K147 • Project School Name: P.S. 147 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K147
Project School Name
P.S. 147 - BROOKLYN
Project Type
SCA CIP
Project Description
ELECTRICAL SERVICE ROOM
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
3/3/2025
Project Phase Planned End Date
3/2/2026
Project Budget Amount
1181250
Final Estimate Of Actual Costs Through End Of Phase Amount
1082682
Total Phase Actual Spending Amount
654392
Dsf Number S
DSF0000893060
14
Project Geographic District : 14 • Project Building Identifier: K147 • Project School Name: P.S. 147 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K147
Project School Name
P.S. 147 - BROOKLYN
Project Type
SCA CIP
Project Description
FLOOR REPLACEMENT
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
3977901
Final Estimate Of Actual Costs Through End Of Phase Amount
3977901
Total Phase Actual Spending Amount
144900
Dsf Number S
DSF0001062249
14
Project Geographic District : 14 • Project Building Identifier: K147 • Project School Name: P.S. 147 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K147
Project School Name
P.S. 147 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
7/30/2024
Project Phase Planned End Date
1/28/2025
Project Phase Actual End Date
1/22/2025
Project Budget Amount
15021
Final Estimate Of Actual Costs Through End Of Phase Amount
9695
Total Phase Actual Spending Amount
9695
Dsf Number S
DSF0001087401
14
Project Geographic District : 14 • Project Building Identifier: K147 • Project School Name: P.S. 147 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K147
Project School Name
P.S. 147 - BROOKLYN
Project Type
SCA CIP
Project Description
FLOOR REPLACEMENT
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
1/25/2024
Project Phase Planned End Date
6/10/2024
Project Phase Actual End Date
3/5/2025
Project Budget Amount
250859
Final Estimate Of Actual Costs Through End Of Phase Amount
145950
Total Phase Actual Spending Amount
131640
Dsf Number S
DSF0001062249
14
Project Geographic District : 14 • Project Building Identifier: K147 • Project School Name: P.S. 147 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K147
Project School Name
P.S. 147 - BROOKLYN
Project Type
SCA CIP
Project Description
ELECTRICAL SERVICE ROOM
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
2/6/2020
Project Phase Planned End Date
7/8/2020
Project Phase Actual End Date
10/27/2021
Project Budget Amount
52500
Final Estimate Of Actual Costs Through End Of Phase Amount
143101
Total Phase Actual Spending Amount
139301
Dsf Number S
DSF0000893060
14
Project Geographic District : 14 • Project Building Identifier: K147 • Project School Name: P.S. 147 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K147
Project School Name
P.S. 147 - BROOKLYN
Project Type
SCA CIP
Project Description
ELECTRICAL SERVICE ROOM
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
5/30/2019
Project Phase Planned End Date
9/30/2019
Project Phase Actual End Date
2/5/2020
Project Budget Amount
10500
Final Estimate Of Actual Costs Through End Of Phase Amount
43113
Total Phase Actual Spending Amount
43113
Dsf Number S
DSF0000893060
14
Project Geographic District : 14 • Project Building Identifier: K147 • Project School Name: P.S. 147 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K147
Project School Name
P.S. 147 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
7/23/2024
Project Phase Planned End Date
11/21/2024
Project Phase Actual End Date
7/30/2024
Project Budget Amount
3338
Final Estimate Of Actual Costs Through End Of Phase Amount
2424
Total Phase Actual Spending Amount
2424
Dsf Number S
DSF0001087401
14
Project Geographic District : 14 • Project Building Identifier: K147 • Project School Name: P.S. 147 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K147
Project School Name
P.S. 147 - BROOKLYN
Project Type
SCA CIP
Project Description
FLOOR REPLACEMENT
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
4/26/2023
Project Phase Planned End Date
9/27/2023
Project Phase Actual End Date
1/12/2024
Project Budget Amount
53755
Final Estimate Of Actual Costs Through End Of Phase Amount
21447
Total Phase Actual Spending Amount
21447
Dsf Number S
DSF0001062249
14
Project Geographic District : 14 • Project Building Identifier: K147 • Project School Name: YOUNG WOMEN'S LEADERSHIP SCHOOL - BROOKLYN
Project Geographic District
14
Project Building Identifier
K147
Project School Name
YOUNG WOMEN'S LEADERSHIP SCHOOL - BROOKLYN
Project Type
SCA Furniture & Equipment
Project Description
FY26 RESO A MOBILE SCIENCE LABS
Project Phase Name
F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
83000
Final Estimate Of Actual Costs Through End Of Phase Amount
83000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001163716
14
Project Geographic District : 14 • Project Building Identifier: K148 • Project School Name: K373 SPED - BROOKLYN
Project Geographic District
14
Project Building Identifier
K148
Project School Name
K373 SPED - BROOKLYN
Project Type
SCA CIP
Project Description
RPZ BACKFLOW PREVENTION DEVICES
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
231821
Final Estimate Of Actual Costs Through End Of Phase Amount
231821
Total Phase Actual Spending Amount
6515
Dsf Number S
DSF0001117617
14
Project Geographic District : 14 • Project Building Identifier: K148 • Project School Name: K373 SPED - BROOKLYN
Project Geographic District
14
Project Building Identifier
K148
Project School Name
K373 SPED - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / FIRE ALARM SYSTEM REPLACEMENT
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
11/15/2023
Project Phase Planned End Date
4/2/2026
Project Budget Amount
1057612
Final Estimate Of Actual Costs Through End Of Phase Amount
1389976
Total Phase Actual Spending Amount
1353889
Dsf Number S
DSF0001008652, DSF0001011574
14
Project Geographic District : 14 • Project Building Identifier: K148 • Project School Name: K373 SPED - BROOKLYN
Project Geographic District
14
Project Building Identifier
K148
Project School Name
K373 SPED - BROOKLYN
Project Type
SCA CIP
Project Description
RPZ BACKFLOW PREVENTION DEVICES
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
903709
Final Estimate Of Actual Costs Through End Of Phase Amount
903709
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001117617
14
Project Geographic District : 14 • Project Building Identifier: K148 • Project School Name: K373 SPED - BROOKLYN
Project Geographic District
14
Project Building Identifier
K148
Project School Name
K373 SPED - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / FIRE ALARM SYSTEM REPLACEMENT
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
11/15/2023
Project Phase Planned End Date
4/2/2026
Project Budget Amount
16930125
Final Estimate Of Actual Costs Through End Of Phase Amount
16161873
Total Phase Actual Spending Amount
10005387
Dsf Number S
DSF0001008652, DSF0001011574
14
Project Geographic District : 14 • Project Building Identifier: K148 • Project School Name: K373 SPED - BROOKLYN
Project Geographic District
14
Project Building Identifier
K148
Project School Name
K373 SPED - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / FIRE ALARM SYSTEM REPLACEMENT
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
7/22/2021
Project Phase Planned End Date
1/11/2022
Project Phase Actual End Date
10/12/2022
Project Budget Amount
752450
Final Estimate Of Actual Costs Through End Of Phase Amount
852904
Total Phase Actual Spending Amount
829351
Dsf Number S
DSF0001008652, DSF0001011574
14
Project Geographic District : 14 • Project Building Identifier: K148 • Project School Name: K373 SPED - BROOKLYN
Project Geographic District
14
Project Building Identifier
K148
Project School Name
K373 SPED - BROOKLYN
Project Type
SCA CIP
Project Description
RPZ BACKFLOW PREVENTION DEVICES
Project Phase Name
Design
Project Status Name
In-Progress
Project Phase Actual Start Date
6/29/2026
Project Phase Planned End Date
12/4/2026
Project Budget Amount
62867
Final Estimate Of Actual Costs Through End Of Phase Amount
62867
Total Phase Actual Spending Amount
4156
Dsf Number S
DSF0001117617
14
Project Geographic District : 14 • Project Building Identifier: K148 • Project School Name: K373 SPED - BROOKLYN
Project Geographic District
14
Project Building Identifier
K148
Project School Name
K373 SPED - BROOKLYN
Project Type
SCA CIP
Project Description
RPZ BACKFLOW PREVENTION DEVICES
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
10/29/2025
Project Phase Planned End Date
3/4/2026
Project Phase Actual End Date
6/26/2026
Project Budget Amount
15717
Final Estimate Of Actual Costs Through End Of Phase Amount
15636
Total Phase Actual Spending Amount
1039
Dsf Number S
DSF0001117617
14
Project Geographic District : 14 • Project Building Identifier: K148 • Project School Name: K373 SPED - BROOKLYN
Project Geographic District
14
Project Building Identifier
K148
Project School Name
K373 SPED - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / FIRE ALARM SYSTEM REPLACEMENT
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
2/24/2021
Project Phase Planned End Date
7/9/2021
Project Phase Actual End Date
7/13/2021
Project Budget Amount
150490
Final Estimate Of Actual Costs Through End Of Phase Amount
154460
Total Phase Actual Spending Amount
154460
Dsf Number S
DSF0001008652, DSF0001011574
14
Project Geographic District : 14 • Project Building Identifier: K148 • Project School Name: K373 SPED - BROOKLYN
Project Geographic District
14
Project Building Identifier
K148
Project School Name
K373 SPED - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-ABATE AND REPAIR 2 SF OF PIPE JOINT TO BROWN AIR CELL PIPE INS, 4 SF OF PIPE JOINT TO MAGNESIA
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
12/24/2025
Project Phase Planned End Date
IEH
Project Phase Actual End Date
3/22/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
43405
Total Phase Actual Spending Amount
335
Dsf Number S
SCA0000075237
14
Project Geographic District : 14 • Project Building Identifier: K148 • Project School Name: K373 SPED - BROOKLYN
Project Geographic District
14
Project Building Identifier
K148
Project School Name
K373 SPED - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-ABATE INSULATION IN BASEMENT BOILER ROOM BEHIND OLD BOILER, THROUGH WALL PIPE, ACM & FILL MARKE
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
3/12/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
6/27/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
9953
Total Phase Actual Spending Amount
2212
Dsf Number S
SCA0000075597
19
Project Geographic District : 19 • Project Building Identifier: K149 • Project School Name: P.S. 149 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K149
Project School Name
P.S. 149 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY26 RESO A ROOM CONVERSION
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
100000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001163111
19
Project Geographic District : 19 • Project Building Identifier: K149 • Project School Name: P.S. 149 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K149
Project School Name
P.S. 149 - BROOKLYN
Project Type
DOE - Skilled Trades
Project Description
ACE BOILER CONTROLS UPGRADE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
12/8/2021
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
60651
Total Phase Actual Spending Amount
59835
Dsf Number S
DSF0000866106
19
Project Geographic District : 19 • Project Building Identifier: K149 • Project School Name: P.S. 149 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K149
Project School Name
P.S. 149 - BROOKLYN
Project Type
SCA CIP
Project Description
FLOOD ELIMINATION / PARAPETS / ROOFS / WINDOWS / EXTERIOR MASONRY
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
1782767
Final Estimate Of Actual Costs Through End Of Phase Amount
1782767
Total Phase Actual Spending Amount
91863
Dsf Number S
DSF0001090027, DSF0001090030, DSF0001117631, DSF0001114470, DSF0001141561
19
Project Geographic District : 19 • Project Building Identifier: K149 • Project School Name: P.S. 149 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K149
Project School Name
P.S. 149 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
CM,F&E
Project Status Name
Complete
Project Phase Actual Start Date
1/24/2025
Project Phase Planned End Date
12/19/2025
Project Phase Actual End Date
4/30/2026
Project Budget Amount
151470
Final Estimate Of Actual Costs Through End Of Phase Amount
156724
Total Phase Actual Spending Amount
151229
Dsf Number S
DSF0001087402
19
Project Geographic District : 19 • Project Building Identifier: K149 • Project School Name: P.S. 149 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K149
Project School Name
P.S. 149 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
1/24/2025
Project Phase Planned End Date
12/19/2025
Project Phase Actual End Date
4/30/2026
Project Budget Amount
175740
Final Estimate Of Actual Costs Through End Of Phase Amount
171825
Total Phase Actual Spending Amount
150686
Dsf Number S
DSF0001087402
19
Project Geographic District : 19 • Project Building Identifier: K149 • Project School Name: P.S. 149 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K149
Project School Name
P.S. 149 - BROOKLYN
Project Type
SCA CIP
Project Description
FLOOD ELIMINATION / PARAPETS / ROOFS / WINDOWS / EXTERIOR MASONRY
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
17439058
Final Estimate Of Actual Costs Through End Of Phase Amount
17439058
Total Phase Actual Spending Amount
425
Dsf Number S
DSF0001090027, DSF0001090030, DSF0001117631, DSF0001114470, DSF0001141561
19
Project Geographic District : 19 • Project Building Identifier: K149 • Project School Name: P.S. 149 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K149
Project School Name
P.S. 149 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
3/22/2024
Project Phase Planned End Date
9/17/2024
Project Phase Actual End Date
8/13/2024
Project Budget Amount
13635
Final Estimate Of Actual Costs Through End Of Phase Amount
9032
Total Phase Actual Spending Amount
9032
Dsf Number S
DSF0001087402
19
Project Geographic District : 19 • Project Building Identifier: K149 • Project School Name: P.S. 149 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K149
Project School Name
P.S. 149 - BROOKLYN
Project Type
SCA CIP
Project Description
FLOOD ELIMINATION / PARAPETS / ROOFS / WINDOWS / EXTERIOR MASONRY
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
12/18/2025
Project Phase Planned End Date
5/21/2026
Project Phase Actual End Date
4/15/2026
Project Budget Amount
1102014
Final Estimate Of Actual Costs Through End Of Phase Amount
419776
Total Phase Actual Spending Amount
419776
Dsf Number S
DSF0001090027, DSF0001090030, DSF0001117631, DSF0001114470, DSF0001141561
19
Project Geographic District : 19 • Project Building Identifier: K149 • Project School Name: P.S. 149 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K149
Project School Name
P.S. 149 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
1/9/2024
Project Phase Planned End Date
5/8/2024
Project Phase Actual End Date
3/22/2024
Project Budget Amount
3030
Final Estimate Of Actual Costs Through End Of Phase Amount
2257
Total Phase Actual Spending Amount
2257
Dsf Number S
DSF0001087402
19
Project Geographic District : 19 • Project Building Identifier: K149 • Project School Name: P.S. 149 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K149
Project School Name
P.S. 149 - BROOKLYN
Project Type
SCA CIP
Project Description
FLOOD ELIMINATION / PARAPETS / ROOFS / WINDOWS / EXTERIOR MASONRY
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
7/11/2025
Project Phase Planned End Date
11/26/2025
Project Phase Actual End Date
11/12/2025
Project Budget Amount
237008
Final Estimate Of Actual Costs Through End Of Phase Amount
314497
Total Phase Actual Spending Amount
226785
Dsf Number S
DSF0001090027, DSF0001090030, DSF0001117631, DSF0001114470, DSF0001141561
23
Project Geographic District : 23 • Project Building Identifier: K150 • Project School Name: K077 SPED - BROOKLYN
Project Geographic District
23
Project Building Identifier
K150
Project School Name
K077 SPED - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY26 RESO A ROOM CONVERSION
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
250000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001163717
23
Project Geographic District : 23 • Project Building Identifier: K150 • Project School Name: K077 SPED - BROOKLYN
Project Geographic District
23
Project Building Identifier
K150
Project School Name
K077 SPED - BROOKLYN
Project Type
Fast Track Projects
Project Description
CTF ROOM CONVERSION (DIAL)
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
4/22/2026
Project Phase Planned End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
37913
Total Phase Actual Spending Amount
2840
Dsf Number S
DSF0001114074
23
Project Geographic District : 23 • Project Building Identifier: K150 • Project School Name: P.S. 150 - BROOKLYN
Project Geographic District
23
Project Building Identifier
K150
Project School Name
P.S. 150 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
CM,F&E
Project Status Name
Complete
Project Phase Actual Start Date
12/12/2024
Project Phase Planned End Date
11/6/2025
Project Phase Actual End Date
3/5/2026
Project Budget Amount
155396
Final Estimate Of Actual Costs Through End Of Phase Amount
158994
Total Phase Actual Spending Amount
154832
Dsf Number S
DSF0001087403
23
Project Geographic District : 23 • Project Building Identifier: K150 • Project School Name: P.S. 150 - BROOKLYN
Project Geographic District
23
Project Building Identifier
K150
Project School Name
P.S. 150 - BROOKLYN
Project Type
SCA CIP
Project Description
FLOOD ELIMINATION / ROOFS / WINDOWS / PARAPETS
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
1876843
Final Estimate Of Actual Costs Through End Of Phase Amount
1876843
Total Phase Actual Spending Amount
115311
Dsf Number S
DSF0001117650, DSF0001117653, DSF0001114304, DSF0001117654
23
Project Geographic District : 23 • Project Building Identifier: K150 • Project School Name: P.S. 150 - BROOKLYN
Project Geographic District
23
Project Building Identifier
K150
Project School Name
P.S. 150 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
12/12/2024
Project Phase Planned End Date
11/6/2025
Project Phase Actual End Date
3/5/2026
Project Budget Amount
172022
Final Estimate Of Actual Costs Through End Of Phase Amount
163516
Total Phase Actual Spending Amount
141495
Dsf Number S
DSF0001087403
23
Project Geographic District : 23 • Project Building Identifier: K150 • Project School Name: P.S. 150 - BROOKLYN
Project Geographic District
23
Project Building Identifier
K150
Project School Name
P.S. 150 - BROOKLYN
Project Type
SCA CIP
Project Description
FLOOD ELIMINATION / ROOFS / WINDOWS / PARAPETS
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
18939056
Final Estimate Of Actual Costs Through End Of Phase Amount
18939056
Total Phase Actual Spending Amount
232800
Dsf Number S
DSF0001117650, DSF0001117653, DSF0001114304, DSF0001117654
23
Project Geographic District : 23 • Project Building Identifier: K150 • Project School Name: P.S. 150 - BROOKLYN
Project Geographic District
23
Project Building Identifier
K150
Project School Name
P.S. 150 - BROOKLYN
Project Type
SCA CIP
Project Description
FLOOD ELIMINATION / ROOFS / WINDOWS / PARAPETS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
8/20/2025
Project Phase Planned End Date
1/26/2026
Project Phase Actual End Date
1/27/2026
Project Budget Amount
1194355
Final Estimate Of Actual Costs Through End Of Phase Amount
289407
Total Phase Actual Spending Amount
289407
Dsf Number S
DSF0001117650, DSF0001117653, DSF0001114304, DSF0001117654
23
Project Geographic District : 23 • Project Building Identifier: K150 • Project School Name: P.S. 150 - BROOKLYN
Project Geographic District
23
Project Building Identifier
K150
Project School Name
P.S. 150 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
5/7/2024
Project Phase Planned End Date
11/1/2024
Project Phase Actual End Date
8/7/2024
Project Budget Amount
13347
Final Estimate Of Actual Costs Through End Of Phase Amount
7799
Total Phase Actual Spending Amount
7799
Dsf Number S
DSF0001087403
23
Project Geographic District : 23 • Project Building Identifier: K150 • Project School Name: P.S. 150 - BROOKLYN
Project Geographic District
23
Project Building Identifier
K150
Project School Name
P.S. 150 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
5/3/2024
Project Phase Planned End Date
9/4/2024
Project Phase Actual End Date
5/7/2024
Project Budget Amount
2966
Final Estimate Of Actual Costs Through End Of Phase Amount
1950
Total Phase Actual Spending Amount
1950
Dsf Number S
DSF0001087403
23
Project Geographic District : 23 • Project Building Identifier: K150 • Project School Name: P.S. 150 - BROOKLYN
Project Geographic District
23
Project Building Identifier
K150
Project School Name
P.S. 150 - BROOKLYN
Project Type
SCA CIP
Project Description
FLOOD ELIMINATION / ROOFS / WINDOWS / PARAPETS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
5/16/2025
Project Phase Planned End Date
10/2/2025
Project Phase Actual End Date
8/5/2025
Project Budget Amount
255933
Final Estimate Of Actual Costs Through End Of Phase Amount
179905
Total Phase Actual Spending Amount
165848
Dsf Number S
DSF0001117650, DSF0001117653, DSF0001114304, DSF0001117654