Capital Project Schedules and Budgets

List of capital projects with managing organization, phase status and project costs.

Housing & Development School Construction Authority (SCA) Dataset 2xh6-psuq 14 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
20
Project Geographic District : 20 • Project Building Identifier: K164 • Project School Name: P.S. 164 - BROOKLYN
Project Geographic District
20
Project Building Identifier
K164
Project School Name
P.S. 164 - BROOKLYN
Project Type
SCA CIP
Project Description
EXTERIOR MASONRY / ROOFS / PARAPETS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
6/10/2024
Project Phase Planned End Date
10/25/2024
Project Phase Actual End Date
10/4/2024
Project Budget Amount
111605
Final Estimate Of Actual Costs Through End Of Phase Amount
138998
Total Phase Actual Spending Amount
138998
Dsf Number S
DSF0001090294, DSF0001117908, DSF0001117909
20
Project Geographic District : 20 • Project Building Identifier: K164 • Project School Name: P.S. 164 - BROOKLYN
Project Geographic District
20
Project Building Identifier
K164
Project School Name
P.S. 164 - BROOKLYN
Project Type
SCA CIP
Project Description
COVID VENTILATION / COVID FIRE ALARM REPLACEMENT
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
1/27/2021
Project Phase Planned End Date
5/27/2021
Project Phase Actual End Date
12/1/2021
Project Budget Amount
67750
Final Estimate Of Actual Costs Through End Of Phase Amount
96568
Total Phase Actual Spending Amount
96568
Dsf Number S
DSF0000987100, DSF0001011868
20
Project Geographic District : 20 • Project Building Identifier: K164 • Project School Name: P.S. 164 - BROOKLYN
Project Geographic District
20
Project Building Identifier
K164
Project School Name
P.S. 164 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-AHERA P.S RESPONSE ACTION ABATEMENT DETAILED SCOPE PROVIDED IN THE EMAIL
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
3/5/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
6/20/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
16619
Total Phase Actual Spending Amount
2171
Dsf Number S
SCA0000075540
23
Project Geographic District : 23 • Project Building Identifier: K165 • Project School Name: P.S. 165 - BROOKLYN
Project Geographic District
23
Project Building Identifier
K165
Project School Name
P.S. 165 - BROOKLYN
Project Type
DIIT - Project Connect
Project Description
CLASSROOM CONNECTIVITY
Project Phase Name
Purch & Install
Project Status Name
In-Progress
Project Phase Actual Start Date
11/1/2019
Project Phase Planned End Date
DIIT
Project Budget Amount
DIIT
Final Estimate Of Actual Costs Through End Of Phase Amount
445236066
Total Phase Actual Spending Amount
344187
Dsf Number S
DSF0000959811
23
Project Geographic District : 23 • Project Building Identifier: K165 • Project School Name: P.S. 165 - BROOKLYN
Project Geographic District
23
Project Building Identifier
K165
Project School Name
P.S. 165 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
83971
Final Estimate Of Actual Costs Through End Of Phase Amount
83971
Total Phase Actual Spending Amount
5752
Dsf Number S
DSF0001087410
23
Project Geographic District : 23 • Project Building Identifier: K165 • Project School Name: P.S. 165 - BROOKLYN
Project Geographic District
23
Project Building Identifier
K165
Project School Name
P.S. 165 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
327344
Final Estimate Of Actual Costs Through End Of Phase Amount
327344
Total Phase Actual Spending Amount
2737
Dsf Number S
DSF0001087410
23
Project Geographic District : 23 • Project Building Identifier: K165 • Project School Name: P.S. 165 - BROOKLYN
Project Geographic District
23
Project Building Identifier
K165
Project School Name
P.S. 165 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
10/21/2025
Project Phase Planned End Date
4/20/2026
Project Phase Actual End Date
4/2/2026
Project Budget Amount
22772
Final Estimate Of Actual Costs Through End Of Phase Amount
1485
Total Phase Actual Spending Amount
1485
Dsf Number S
DSF0001087410
23
Project Geographic District : 23 • Project Building Identifier: K165 • Project School Name: P.S. 165 - BROOKLYN
Project Geographic District
23
Project Building Identifier
K165
Project School Name
P.S. 165 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
10/9/2025
Project Phase Planned End Date
2/12/2026
Project Phase Actual End Date
10/21/2025
Project Budget Amount
5693
Final Estimate Of Actual Costs Through End Of Phase Amount
371
Total Phase Actual Spending Amount
371
Dsf Number S
DSF0001087410
23
Project Geographic District : 23 • Project Building Identifier: K165 • Project School Name: P.S. 165 - BROOKLYN
Project Geographic District
23
Project Building Identifier
K165
Project School Name
P.S. 165 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-AHERA P.S RESPONSE ACTION ABATEMENT ABATE AND REPLACE/REPAIR DAMAGED MATERIALS FELT PAPER UNDER
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
4/30/2026
Project Phase Planned End Date
IEH
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
8694
Total Phase Actual Spending Amount
944
Dsf Number S
SCA0000075884
19
Project Geographic District : 19 • Project Building Identifier: K166 • Project School Name: VAN SICLEN COMMUNITY MIDDLE SCHOOL
Project Geographic District
19
Project Building Identifier
K166
Project School Name
VAN SICLEN COMMUNITY MIDDLE SCHOOL
Project Type
DOE - RESOA
Project Description
FY25 RESO A SUPPLEMENTAL COOLING
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
1200000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001112592
19
Project Geographic District : 19 • Project Building Identifier: K166 • Project School Name: VAN SICLEN COMMUNITY MIDDLE SCHOOL
Project Geographic District
19
Project Building Identifier
K166
Project School Name
VAN SICLEN COMMUNITY MIDDLE SCHOOL
Project Type
DOE - RESOA
Project Description
FY24 RESO A LIBRARY UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
150000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001086005
19
Project Geographic District : 19 • Project Building Identifier: K166 • Project School Name: VAN SICLEN COMMUNITY MIDDLE SCHOOL
Project Geographic District
19
Project Building Identifier
K166
Project School Name
VAN SICLEN COMMUNITY MIDDLE SCHOOL
Project Type
SCA CIP RESOA
Project Description
FY25 RESO A AUDITORIUM UPGRADE
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
100692
Final Estimate Of Actual Costs Through End Of Phase Amount
100692
Total Phase Actual Spending Amount
29687
Dsf Number S
DSF0001112591
19
Project Geographic District : 19 • Project Building Identifier: K166 • Project School Name: VAN SICLEN COMMUNITY MIDDLE SCHOOL
Project Geographic District
19
Project Building Identifier
K166
Project School Name
VAN SICLEN COMMUNITY MIDDLE SCHOOL
Project Type
SCA CIP RESOA
Project Description
FY25 RESO A AUDITORIUM UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
1476813
Final Estimate Of Actual Costs Through End Of Phase Amount
1476813
Total Phase Actual Spending Amount
19966
Dsf Number S
DSF0001112591
19
Project Geographic District : 19 • Project Building Identifier: K166 • Project School Name: VAN SICLEN COMMUNITY MIDDLE SCHOOL
Project Geographic District
19
Project Building Identifier
K166
Project School Name
VAN SICLEN COMMUNITY MIDDLE SCHOOL
Project Type
SCA CIP RESOA
Project Description
FY25 RESO A AUDITORIUM UPGRADE
Project Phase Name
Design
Project Status Name
In-Progress
Project Phase Actual Start Date
8/26/2025
Project Phase Planned End Date
1/30/2026
Project Budget Amount
61993
Final Estimate Of Actual Costs Through End Of Phase Amount
61993
Total Phase Actual Spending Amount
8574
Dsf Number S
DSF0001112591
19
Project Geographic District : 19 • Project Building Identifier: K166 • Project School Name: VAN SICLEN COMMUNITY MIDDLE SCHOOL
Project Geographic District
19
Project Building Identifier
K166
Project School Name
VAN SICLEN COMMUNITY MIDDLE SCHOOL
Project Type
SCA CIP RESOA
Project Description
FY25 RESO A AUDITORIUM UPGRADE
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
2/7/2025
Project Phase Planned End Date
6/10/2025
Project Phase Actual End Date
8/21/2025
Project Budget Amount
21299
Final Estimate Of Actual Costs Through End Of Phase Amount
21299
Total Phase Actual Spending Amount
2273
Dsf Number S
DSF0001112591
17
Project Geographic District : 17 • Project Building Identifier: K167 • Project School Name: NEW BRIDGES
Project Geographic District
17
Project Building Identifier
K167
Project School Name
NEW BRIDGES
Project Type
DOE - RESOA
Project Description
FY23 RESO A ROOM CONVERSION
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
2/16/2024
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
72986
Dsf Number S
DSF0001035453
17
Project Geographic District : 17 • Project Building Identifier: K167 • Project School Name: K396 SPED - BROOKLYN
Project Geographic District
17
Project Building Identifier
K167
Project School Name
K396 SPED - BROOKLYN
Project Type
Fast Track Projects
Project Description
FY26 RESO A ROOM CONVERSION
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
FTK
Project Phase Planned End Date
FTK
Project Phase Actual End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
200000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001163725
17
Project Geographic District : 17 • Project Building Identifier: K167 • Project School Name: NEW BRIDGES
Project Geographic District
17
Project Building Identifier
K167
Project School Name
NEW BRIDGES
Project Type
SCA CIP
Project Description
COVID VENTILATION
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
7/5/2022
Project Phase Planned End Date
7/4/2023
Project Budget Amount
354200
Final Estimate Of Actual Costs Through End Of Phase Amount
881675
Total Phase Actual Spending Amount
857940
Dsf Number S
DSF0000961099
17
Project Geographic District : 17 • Project Building Identifier: K167 • Project School Name: NEW BRIDGES
Project Geographic District
17
Project Building Identifier
K167
Project School Name
NEW BRIDGES
Project Type
SCA CIP
Project Description
COVID VENTILATION
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
7/5/2022
Project Phase Planned End Date
7/4/2023
Project Budget Amount
5692500
Final Estimate Of Actual Costs Through End Of Phase Amount
6416388
Total Phase Actual Spending Amount
5152079
Dsf Number S
DSF0000961099
17
Project Geographic District : 17 • Project Building Identifier: K167 • Project School Name: NEW BRIDGES
Project Geographic District
17
Project Building Identifier
K167
Project School Name
NEW BRIDGES
Project Type
SCA CIP
Project Description
COVID VENTILATION
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
2/3/2021
Project Phase Planned End Date
7/9/2021
Project Phase Actual End Date
12/22/2021
Project Budget Amount
253000
Final Estimate Of Actual Costs Through End Of Phase Amount
602725
Total Phase Actual Spending Amount
483983
Dsf Number S
DSF0000961099
17
Project Geographic District : 17 • Project Building Identifier: K167 • Project School Name: NEW BRIDGES
Project Geographic District
17
Project Building Identifier
K167
Project School Name
NEW BRIDGES
Project Type
SCA CIP
Project Description
COVID VENTILATION
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
8/28/2020
Project Phase Planned End Date
12/28/2020
Project Phase Actual End Date
1/25/2021
Project Budget Amount
50600
Final Estimate Of Actual Costs Through End Of Phase Amount
86110
Total Phase Actual Spending Amount
86110
Dsf Number S
DSF0000961099
17
Project Geographic District : 17 • Project Building Identifier: K167 • Project School Name: NEW BRIDGES
Project Geographic District
17
Project Building Identifier
K167
Project School Name
NEW BRIDGES
Project Type
SCA CIP RESOA
Project Description
FY24 RESO A ROOM CONVERSION / PATH OF TRAVEL RESO A ROOM CONVERSION
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
9/25/2025
Project Phase Planned End Date
8/20/2026
Project Budget Amount
48501
Final Estimate Of Actual Costs Through End Of Phase Amount
67751
Total Phase Actual Spending Amount
28029
Dsf Number S
DSF0001086006, DSF0001087014
17
Project Geographic District : 17 • Project Building Identifier: K167 • Project School Name: NEW BRIDGES
Project Geographic District
17
Project Building Identifier
K167
Project School Name
NEW BRIDGES
Project Type
SCA CIP RESOA
Project Description
FY24 RESO A ROOM CONVERSION / PATH OF TRAVEL RESO A ROOM CONVERSION
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
9/25/2025
Project Phase Planned End Date
8/20/2026
Project Budget Amount
440000
Final Estimate Of Actual Costs Through End Of Phase Amount
315754
Total Phase Actual Spending Amount
4067
Dsf Number S
DSF0001086006, DSF0001087014
17
Project Geographic District : 17 • Project Building Identifier: K167 • Project School Name: NEW BRIDGES
Project Geographic District
17
Project Building Identifier
K167
Project School Name
NEW BRIDGES
Project Type
SCA CIP RESOA
Project Description
FY24 RESO A ROOM CONVERSION / PATH OF TRAVEL RESO A ROOM CONVERSION
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
7/31/2024
Project Phase Planned End Date
12/2/2024
Project Phase Actual End Date
3/17/2025
Project Budget Amount
30000
Final Estimate Of Actual Costs Through End Of Phase Amount
71603
Total Phase Actual Spending Amount
69499
Dsf Number S
DSF0001086006, DSF0001087014
17
Project Geographic District : 17 • Project Building Identifier: K167 • Project School Name: NEW BRIDGES
Project Geographic District
17
Project Building Identifier
K167
Project School Name
NEW BRIDGES
Project Type
SCA CIP RESOA
Project Description
FY24 RESO A ROOM CONVERSION / PATH OF TRAVEL RESO A ROOM CONVERSION
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
12/1/2023
Project Phase Planned End Date
6/27/2024
Project Phase Actual End Date
7/25/2024
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
25183
Total Phase Actual Spending Amount
25183
Dsf Number S
DSF0001086006, DSF0001087014
17
Project Geographic District : 17 • Project Building Identifier: K167 • Project School Name: NEW BRIDGES
Project Geographic District
17
Project Building Identifier
K167
Project School Name
NEW BRIDGES
Project Type
SCA IEH
Project Description
PO18-AHERA P.S RESPONSE ACTION ABATEMENT ABATE AND REPLACE FLOORING IN THE FOLLOWING LOCATIONS: MAIN
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
3/19/2026
Project Phase Planned End Date
IEH
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
11359
Total Phase Actual Spending Amount
609
Dsf Number S
SCA0000075627
15
Project Geographic District : 15 • Project Building Identifier: K169 • Project School Name: P.S. 169 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K169
Project School Name
P.S. 169 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY26 RESO A PHONE UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
65000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001163726
15
Project Geographic District : 15 • Project Building Identifier: K169 • Project School Name: P.S. 169 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K169
Project School Name
P.S. 169 - BROOKLYN
Project Type
Fast Track Projects
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
1/22/2025
Project Phase Planned End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
57989
Total Phase Actual Spending Amount
21308
Dsf Number S
DSF0001087411
15
Project Geographic District : 15 • Project Building Identifier: K169 • Project School Name: P.S. 169 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K169
Project School Name
P.S. 169 - BROOKLYN
Project Type
SCA CIP
Project Description
ROOF REPLACEMENT / EXTERIOR MASONRY / PARAPETS / WINDOWS
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
9/12/2022
Project Phase Planned End Date
9/10/2024
Project Budget Amount
1035301
Final Estimate Of Actual Costs Through End Of Phase Amount
1301587
Total Phase Actual Spending Amount
1287829
Dsf Number S
DSF0000870633, DSF0000938713, DSF0000938712, DSF0000960696
15
Project Geographic District : 15 • Project Building Identifier: K169 • Project School Name: P.S. 169 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K169
Project School Name
P.S. 169 - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / LOW VOLTAGE ELECTRICAL SYSTEM
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
967707
Final Estimate Of Actual Costs Through End Of Phase Amount
967707
Total Phase Actual Spending Amount
152793
Dsf Number S
DSF0000889377, DSF0000893420
15
Project Geographic District : 15 • Project Building Identifier: K169 • Project School Name: P.S. 169 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K169
Project School Name
P.S. 169 - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / LOW VOLTAGE ELECTRICAL SYSTEM
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
9738403
Final Estimate Of Actual Costs Through End Of Phase Amount
9738403
Total Phase Actual Spending Amount
197879
Dsf Number S
DSF0000889377, DSF0000893420
15
Project Geographic District : 15 • Project Building Identifier: K169 • Project School Name: P.S. 169 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K169
Project School Name
P.S. 169 - BROOKLYN
Project Type
SCA CIP
Project Description
ROOF REPLACEMENT / EXTERIOR MASONRY / PARAPETS / WINDOWS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
9/12/2022
Project Phase Planned End Date
9/10/2024
Project Budget Amount
16638778
Final Estimate Of Actual Costs Through End Of Phase Amount
15072268
Total Phase Actual Spending Amount
12340836
Dsf Number S
DSF0000870633, DSF0000938713, DSF0000938712, DSF0000960696
15
Project Geographic District : 15 • Project Building Identifier: K169 • Project School Name: P.S. 169 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K169
Project School Name
P.S. 169 - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / LOW VOLTAGE ELECTRICAL SYSTEM
Project Phase Name
Design
Project Status Name
In-Progress
Project Phase Actual Start Date
11/28/2018
Project Phase Planned End Date
5/16/2019
Project Budget Amount
614134
Final Estimate Of Actual Costs Through End Of Phase Amount
614134
Total Phase Actual Spending Amount
333922
Dsf Number S
DSF0000889377, DSF0000893420
15
Project Geographic District : 15 • Project Building Identifier: K169 • Project School Name: P.S. 169 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K169
Project School Name
P.S. 169 - BROOKLYN
Project Type
SCA CIP
Project Description
ROOF REPLACEMENT / EXTERIOR MASONRY / PARAPETS / WINDOWS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
1/15/2020
Project Phase Planned End Date
6/16/2020
Project Phase Actual End Date
4/29/2022
Project Budget Amount
739501
Final Estimate Of Actual Costs Through End Of Phase Amount
507702
Total Phase Actual Spending Amount
492435
Dsf Number S
DSF0000870633, DSF0000938713, DSF0000938712, DSF0000960696
15
Project Geographic District : 15 • Project Building Identifier: K169 • Project School Name: P.S. 169 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K169
Project School Name
P.S. 169 - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / LOW VOLTAGE ELECTRICAL SYSTEM
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
7/23/2018
Project Phase Planned End Date
12/7/2018
Project Phase Actual End Date
11/8/2018
Project Budget Amount
131600
Final Estimate Of Actual Costs Through End Of Phase Amount
178855
Total Phase Actual Spending Amount
170543
Dsf Number S
DSF0000889377, DSF0000893420
15
Project Geographic District : 15 • Project Building Identifier: K169 • Project School Name: P.S. 169 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K169
Project School Name
P.S. 169 - BROOKLYN
Project Type
SCA CIP
Project Description
ROOF REPLACEMENT / EXTERIOR MASONRY / PARAPETS / WINDOWS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
2/14/2019
Project Phase Planned End Date
7/1/2019
Project Phase Actual End Date
8/26/2019
Project Budget Amount
147899
Final Estimate Of Actual Costs Through End Of Phase Amount
189352
Total Phase Actual Spending Amount
188002
Dsf Number S
DSF0000870633, DSF0000938713, DSF0000938712, DSF0000960696
15
Project Geographic District : 15 • Project Building Identifier: K169 • Project School Name: P.S. 169 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K169
Project School Name
P.S. 169 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY20 RESO A PLAYGROUND UPGRADE
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
6/8/2026
Project Phase Planned End Date
8/31/2027
Project Budget Amount
51442
Final Estimate Of Actual Costs Through End Of Phase Amount
71799
Total Phase Actual Spending Amount
18986
Dsf Number S
DSF0000913230
15
Project Geographic District : 15 • Project Building Identifier: K169 • Project School Name: P.S. 169 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K169
Project School Name
P.S. 169 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY20 RESO A PLAYGROUND UPGRADE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
6/8/2026
Project Phase Planned End Date
8/31/2027
Project Budget Amount
754480
Final Estimate Of Actual Costs Through End Of Phase Amount
718096
Total Phase Actual Spending Amount
32205
Dsf Number S
DSF0000913230
15
Project Geographic District : 15 • Project Building Identifier: K169 • Project School Name: P.S. 169 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K169
Project School Name
P.S. 169 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY20 RESO A PLAYGROUND UPGRADE
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
9/10/2021
Project Phase Planned End Date
1/31/2022
Project Phase Actual End Date
12/5/2025
Project Budget Amount
51442
Final Estimate Of Actual Costs Through End Of Phase Amount
95443
Total Phase Actual Spending Amount
47872
Dsf Number S
DSF0000913230
15
Project Geographic District : 15 • Project Building Identifier: K169 • Project School Name: P.S. 169 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K169
Project School Name
P.S. 169 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY20 RESO A PLAYGROUND UPGRADE
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
3/24/2021
Project Phase Planned End Date
6/22/2021
Project Phase Actual End Date
8/12/2021
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
22577
Total Phase Actual Spending Amount
22577
Dsf Number S
DSF0000913230
15
Project Geographic District : 15 • Project Building Identifier: K169 • Project School Name: P.S. 169 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K169
Project School Name
P.S. 169 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-PLEASE ABATE AND CLEAN UP FALLEN DEBRIS FROM PIPE INSULATION LOCATION: KITCHEN STORAGE AREA LOC
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
1/7/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
1/18/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
12566
Total Phase Actual Spending Amount
12566
Dsf Number S
SCA0000075270
15
Project Geographic District : 15 • Project Building Identifier: K169 • Project School Name: P.S. 169 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K169
Project School Name
P.S. 169 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-ABATE AND REPLACE FLOORS AT LOCATIONS SPRINKLER CONTROL ROOM, ROOM 400, ROOM 412, ROOM 516 ROOM
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
5/21/2026
Project Phase Planned End Date
IEH
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
1257
Total Phase Actual Spending Amount
507
Dsf Number S
SCA0000076024
20
Project Geographic District : 20 • Project Building Identifier: K170 • Project School Name: P.S. 170 - BROOKLYN
Project Geographic District
20
Project Building Identifier
K170
Project School Name
P.S. 170 - BROOKLYN
Project Type
DIIT - RESOA
Project Description
FY26 RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
150000
Total Phase Actual Spending Amount
150000
Dsf Number S
DSF0001163727
20
Project Geographic District : 20 • Project Building Identifier: K170 • Project School Name: P.S. 170 - BROOKLYN
Project Geographic District
20
Project Building Identifier
K170
Project School Name
P.S. 170 - BROOKLYN
Project Type
DIIT - RESOA
Project Description
FY21 RESO A (MA) TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
50000
Total Phase Actual Spending Amount
50000
Dsf Number S
DSF0001008615
20
Project Geographic District : 20 • Project Building Identifier: K170 • Project School Name: P.S. 170 - BROOKLYN
Project Geographic District
20
Project Building Identifier
K170
Project School Name
P.S. 170 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY25 RESO A PLAYGROUND UPGRADE
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
60000
Final Estimate Of Actual Costs Through End Of Phase Amount
60000
Total Phase Actual Spending Amount
29023
Dsf Number S
DSF0001112593
20
Project Geographic District : 20 • Project Building Identifier: K170 • Project School Name: P.S. 170 - BROOKLYN
Project Geographic District
20
Project Building Identifier
K170
Project School Name
P.S. 170 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY25 RESO A PLAYGROUND UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
880000
Final Estimate Of Actual Costs Through End Of Phase Amount
880000
Total Phase Actual Spending Amount
33594
Dsf Number S
DSF0001112593
20
Project Geographic District : 20 • Project Building Identifier: K170 • Project School Name: P.S. 170 - BROOKLYN
Project Geographic District
20
Project Building Identifier
K170
Project School Name
P.S. 170 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY25 RESO A PLAYGROUND UPGRADE
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
12/11/2025
Project Phase Planned End Date
4/29/2026
Project Phase Actual End Date
4/14/2026
Project Budget Amount
60000
Final Estimate Of Actual Costs Through End Of Phase Amount
78529
Total Phase Actual Spending Amount
75545
Dsf Number S
DSF0001112593
20
Project Geographic District : 20 • Project Building Identifier: K170 • Project School Name: P.S. 170 - BROOKLYN
Project Geographic District
20
Project Building Identifier
K170
Project School Name
P.S. 170 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY25 RESO A PLAYGROUND UPGRADE
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
2/7/2025
Project Phase Planned End Date
5/8/2025
Project Phase Actual End Date
12/11/2025
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
32679
Total Phase Actual Spending Amount
32679
Dsf Number S
DSF0001112593
19
Project Geographic District : 19 • Project Building Identifier: K171 • Project School Name: I.S. 171 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K171
Project School Name
I.S. 171 - BROOKLYN
Project Type
DIIT - RESOA
Project Description
FY18 RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
Complete
Project Phase Actual Start Date
10/25/2025
Project Phase Planned End Date
DIIR
Project Phase Actual End Date
1/23/2026
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
150000
Total Phase Actual Spending Amount
150000
Dsf Number S
DSF0000867433
19
Project Geographic District : 19 • Project Building Identifier: K171 • Project School Name: I.S. 171 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K171
Project School Name
I.S. 171 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY16 RESO A GYMNASIUM
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
7/22/2022
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
208177
Total Phase Actual Spending Amount
186116
Dsf Number S
DSF0000844142