Project Geographic District
15
Project Building Identifier
K169
Project School Name
P.S. 169 - BROOKLYN
Project Description
ROOF REPLACEMENT / EXTERIOR MASONRY / PARAPETS / WINDOWS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
1/15/2020
Project Phase Planned End Date
6/16/2020
Project Phase Actual End Date
4/29/2022
Project Budget Amount
739501
Final Estimate Of Actual Costs Through End Of Phase Amount
507702
Total Phase Actual Spending Amount
492435
Dsf Number S
DSF0000870633, DSF0000938713, DSF0000938712, DSF0000960696