Capital Project Schedules and Budgets

List of capital projects with managing organization, phase status and project costs.

Housing & Development School Construction Authority (SCA) Dataset 2xh6-psuq 14 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
21
Project Geographic District : 21 • Project Building Identifier: K188 • Project School Name: P.S. 188 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K188
Project School Name
P.S. 188 - BROOKLYN
Project Type
DOE - Skilled Trades
Project Description
WASTE LINE REPLACEMENT
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
2/26/2021
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
84300
Dsf Number S
DSF0000987503
21
Project Geographic District : 21 • Project Building Identifier: K188 • Project School Name: P.S. 188 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K188
Project School Name
P.S. 188 - BROOKLYN
Project Type
Fast Track Projects
Project Description
EMERGENCY AUDITORIUM FLOOR
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
9/5/2018
Project Phase Planned End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
23085
Total Phase Actual Spending Amount
22680
Dsf Number S
DSF0000870923
21
Project Geographic District : 21 • Project Building Identifier: K188 • Project School Name: P.S. 188 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K188
Project School Name
P.S. 188 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
6/19/2025
Project Phase Planned End Date
5/14/2026
Project Budget Amount
182392
Final Estimate Of Actual Costs Through End Of Phase Amount
168890
Total Phase Actual Spending Amount
164453
Dsf Number S
DSF0001087416
21
Project Geographic District : 21 • Project Building Identifier: K188 • Project School Name: P.S. 188 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K188
Project School Name
P.S. 188 - BROOKLYN
Project Type
SCA CIP
Project Description
COVID VENTILATION
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
9/5/2023
Project Phase Planned End Date
9/3/2024
Project Budget Amount
337400
Final Estimate Of Actual Costs Through End Of Phase Amount
663267
Total Phase Actual Spending Amount
628658
Dsf Number S
DSF0001008592
21
Project Geographic District : 21 • Project Building Identifier: K188 • Project School Name: P.S. 188 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K188
Project School Name
P.S. 188 - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / ROOFS / PARAPETS / EXTERIOR MASONRY
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
9/11/2023
Project Phase Planned End Date
9/9/2026
Project Budget Amount
1430576
Final Estimate Of Actual Costs Through End Of Phase Amount
1353501
Total Phase Actual Spending Amount
1309140
Dsf Number S
DSF0000960700, DSF0001012272, DSF0001012273, DSF0001012274
21
Project Geographic District : 21 • Project Building Identifier: K188 • Project School Name: P.S. 188 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K188
Project School Name
P.S. 188 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
6/19/2025
Project Phase Planned End Date
5/14/2026
Project Budget Amount
248298
Final Estimate Of Actual Costs Through End Of Phase Amount
226099
Total Phase Actual Spending Amount
184254
Dsf Number S
DSF0001087416
21
Project Geographic District : 21 • Project Building Identifier: K188 • Project School Name: P.S. 188 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K188
Project School Name
P.S. 188 - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / ROOFS / PARAPETS / EXTERIOR MASONRY
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
9/11/2023
Project Phase Planned End Date
9/9/2026
Project Budget Amount
21842519
Final Estimate Of Actual Costs Through End Of Phase Amount
21958830
Total Phase Actual Spending Amount
16323762
Dsf Number S
DSF0000960700, DSF0001012272, DSF0001012273, DSF0001012274
21
Project Geographic District : 21 • Project Building Identifier: K188 • Project School Name: P.S. 188 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K188
Project School Name
P.S. 188 - BROOKLYN
Project Type
SCA CIP
Project Description
COVID VENTILATION
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
9/5/2023
Project Phase Planned End Date
9/3/2024
Project Budget Amount
5422500
Final Estimate Of Actual Costs Through End Of Phase Amount
8719527
Total Phase Actual Spending Amount
7648214
Dsf Number S
DSF0001008592
21
Project Geographic District : 21 • Project Building Identifier: K188 • Project School Name: P.S. 188 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K188
Project School Name
P.S. 188 - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / ROOFS / PARAPETS / EXTERIOR MASONRY
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
11/2/2022
Project Phase Planned End Date
4/7/2023
Project Phase Actual End Date
3/10/2023
Project Budget Amount
990021
Final Estimate Of Actual Costs Through End Of Phase Amount
1177951
Total Phase Actual Spending Amount
841772
Dsf Number S
DSF0000960700, DSF0001012272, DSF0001012273, DSF0001012274
21
Project Geographic District : 21 • Project Building Identifier: K188 • Project School Name: P.S. 188 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K188
Project School Name
P.S. 188 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
4/25/2024
Project Phase Planned End Date
10/22/2024
Project Phase Actual End Date
8/22/2024
Project Budget Amount
19265
Final Estimate Of Actual Costs Through End Of Phase Amount
19449
Total Phase Actual Spending Amount
19449
Dsf Number S
DSF0001087416
21
Project Geographic District : 21 • Project Building Identifier: K188 • Project School Name: P.S. 188 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K188
Project School Name
P.S. 188 - BROOKLYN
Project Type
SCA CIP
Project Description
COVID VENTILATION
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
2/9/2022
Project Phase Planned End Date
7/8/2022
Project Phase Actual End Date
9/7/2022
Project Budget Amount
241000
Final Estimate Of Actual Costs Through End Of Phase Amount
245561
Total Phase Actual Spending Amount
245561
Dsf Number S
DSF0001008592
21
Project Geographic District : 21 • Project Building Identifier: K188 • Project School Name: P.S. 188 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K188
Project School Name
P.S. 188 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
4/19/2024
Project Phase Planned End Date
8/20/2024
Project Phase Actual End Date
4/25/2024
Project Budget Amount
4281
Final Estimate Of Actual Costs Through End Of Phase Amount
4862
Total Phase Actual Spending Amount
4862
Dsf Number S
DSF0001087416
21
Project Geographic District : 21 • Project Building Identifier: K188 • Project School Name: P.S. 188 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K188
Project School Name
P.S. 188 - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / ROOFS / PARAPETS / EXTERIOR MASONRY
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
2/14/2020
Project Phase Planned End Date
11/22/2022
Project Phase Actual End Date
10/27/2022
Project Budget Amount
199005
Final Estimate Of Actual Costs Through End Of Phase Amount
237913
Total Phase Actual Spending Amount
237913
Dsf Number S
DSF0000960700, DSF0001012272, DSF0001012273, DSF0001012274
21
Project Geographic District : 21 • Project Building Identifier: K188 • Project School Name: P.S. 188 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K188
Project School Name
P.S. 188 - BROOKLYN
Project Type
SCA CIP
Project Description
COVID VENTILATION
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
1/29/2021
Project Phase Planned End Date
5/28/2021
Project Phase Actual End Date
2/9/2022
Project Budget Amount
48200
Final Estimate Of Actual Costs Through End Of Phase Amount
131109
Total Phase Actual Spending Amount
131109
Dsf Number S
DSF0001008592
21
Project Geographic District : 21 • Project Building Identifier: K188 • Project School Name: P.S. 188 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K188
Project School Name
P.S. 188 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-DRILL AND ABATE THE FOLLOWING: (1) 1-1/4' HOLE FROM THE EXTERIOR TO INTERIOR; EXACT LOCATION IS
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
12/24/2025
Project Phase Planned End Date
IEH
Project Phase Actual End Date
1/22/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
13187
Total Phase Actual Spending Amount
8437
Dsf Number S
SCA0000075225
21
Project Geographic District : 21 • Project Building Identifier: K188 • Project School Name: P.S. 188 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K188
Project School Name
P.S. 188 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-ABATE AND REMOVE ACM PIPE INSULATION FROM ROOM 158 - LOCATED ON THE 1ST FLR - 40 LINEAR FT (NEE
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
3/19/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
3/21/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
23721
Total Phase Actual Spending Amount
1541
Dsf Number S
SCA0000075630
17
Project Geographic District : 17 • Project Building Identifier: K189 • Project School Name: P.S. 189 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K189
Project School Name
P.S. 189 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY20 RESO A ROOM RENOVATION
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
12/6/2021
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
152582
Total Phase Actual Spending Amount
151530
Dsf Number S
DSF0000913237
17
Project Geographic District : 17 • Project Building Identifier: K189 • Project School Name: P.S. 189 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K189
Project School Name
P.S. 189 - BROOKLYN
Project Type
SCA Furniture & Equipment
Project Description
FY26 RESO A MOBILE SCIENCE LABS
Project Phase Name
F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
495000
Final Estimate Of Actual Costs Through End Of Phase Amount
495000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001163788
19
Project Geographic District : 19 • Project Building Identifier: K190 • Project School Name: P.S. 190 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K190
Project School Name
P.S. 190 - BROOKLYN
Project Type
DOE - Skilled Trades
Project Description
BATHROOM UPGRADES
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
7/5/2022
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
240352
Total Phase Actual Spending Amount
240352
Dsf Number S
DSF0001034222
19
Project Geographic District : 19 • Project Building Identifier: K190 • Project School Name: P.S. 190 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K190
Project School Name
P.S. 190 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATION
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
11/1/2024
Project Phase Planned End Date
8/27/2025
Project Budget Amount
162641
Final Estimate Of Actual Costs Through End Of Phase Amount
152788
Total Phase Actual Spending Amount
130416
Dsf Number S
DSF0001035019
19
Project Geographic District : 19 • Project Building Identifier: K190 • Project School Name: P.S. 190 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K190
Project School Name
P.S. 190 - BROOKLYN
Project Type
SCA CIP
Project Description
FLOOD ELIMINATION / ROOFS / PARAPETS / WINDOWS / EXTERIOR MASONRY
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
2142268
Final Estimate Of Actual Costs Through End Of Phase Amount
2142268
Total Phase Actual Spending Amount
84838
Dsf Number S
DSF0001118336, DSF0001118338, DSF0001118339, DSF0001118340, DSF0001142270
19
Project Geographic District : 19 • Project Building Identifier: K190 • Project School Name: P.S. 190 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K190
Project School Name
P.S. 190 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATION
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
11/1/2024
Project Phase Planned End Date
8/27/2025
Project Budget Amount
265780
Final Estimate Of Actual Costs Through End Of Phase Amount
240071
Total Phase Actual Spending Amount
209185
Dsf Number S
DSF0001035019
19
Project Geographic District : 19 • Project Building Identifier: K190 • Project School Name: P.S. 190 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K190
Project School Name
P.S. 190 - BROOKLYN
Project Type
SCA CIP
Project Description
FLOOD ELIMINATION / ROOFS / PARAPETS / WINDOWS / EXTERIOR MASONRY
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
21347002
Final Estimate Of Actual Costs Through End Of Phase Amount
21347002
Total Phase Actual Spending Amount
111785
Dsf Number S
DSF0001118336, DSF0001118338, DSF0001118339, DSF0001118340, DSF0001142270
19
Project Geographic District : 19 • Project Building Identifier: K190 • Project School Name: P.S. 190 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K190
Project School Name
P.S. 190 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATION
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
9/27/2023
Project Phase Planned End Date
3/27/2024
Project Phase Actual End Date
3/20/2024
Project Budget Amount
20621
Final Estimate Of Actual Costs Through End Of Phase Amount
5696
Total Phase Actual Spending Amount
5696
Dsf Number S
DSF0001035019
19
Project Geographic District : 19 • Project Building Identifier: K190 • Project School Name: P.S. 190 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K190
Project School Name
P.S. 190 - BROOKLYN
Project Type
SCA CIP
Project Description
FLOOD ELIMINATION / ROOFS / PARAPETS / WINDOWS / EXTERIOR MASONRY
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
11/6/2025
Project Phase Planned End Date
4/13/2026
Project Phase Actual End Date
4/10/2026
Project Budget Amount
1347314
Final Estimate Of Actual Costs Through End Of Phase Amount
389502
Total Phase Actual Spending Amount
378251
Dsf Number S
DSF0001118336, DSF0001118338, DSF0001118339, DSF0001118340, DSF0001142270
19
Project Geographic District : 19 • Project Building Identifier: K190 • Project School Name: P.S. 190 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K190
Project School Name
P.S. 190 - BROOKLYN
Project Type
SCA CIP
Project Description
FLOOD ELIMINATION / ROOFS / PARAPETS / WINDOWS / EXTERIOR MASONRY
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
5/13/2025
Project Phase Planned End Date
9/29/2025
Project Phase Actual End Date
9/23/2025
Project Budget Amount
289134
Final Estimate Of Actual Costs Through End Of Phase Amount
215840
Total Phase Actual Spending Amount
215840
Dsf Number S
DSF0001118336, DSF0001118338, DSF0001118339, DSF0001118340, DSF0001142270
19
Project Geographic District : 19 • Project Building Identifier: K190 • Project School Name: P.S. 190 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K190
Project School Name
P.S. 190 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATION
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
9/26/2023
Project Phase Planned End Date
1/30/2024
Project Phase Actual End Date
9/27/2023
Project Budget Amount
4582
Final Estimate Of Actual Costs Through End Of Phase Amount
1424
Total Phase Actual Spending Amount
1424
Dsf Number S
DSF0001035019
19
Project Geographic District : 19 • Project Building Identifier: K190 • Project School Name: P.S. 190 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K190
Project School Name
P.S. 190 - BROOKLYN
Project Type
SCA Furniture & Equipment
Project Description
FY26 RESO A MOBILE SCIENCE LABS
Project Phase Name
F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
6/5/2026
Project Budget Amount
240000
Final Estimate Of Actual Costs Through End Of Phase Amount
240000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001163115
17
Project Geographic District : 17 • Project Building Identifier: K191 • Project School Name: P.S. 191 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K191
Project School Name
P.S. 191 - BROOKLYN
Project Type
DIIT - RESOA
Project Description
FY26 RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
240000
Total Phase Actual Spending Amount
240000
Dsf Number S
DSF0001163116
17
Project Geographic District : 17 • Project Building Identifier: K191 • Project School Name: P.S. 191 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K191
Project School Name
P.S. 191 - BROOKLYN
Project Type
DOE - Skilled Trades
Project Description
DEP GREEN INFRASTRUCTURE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
4/10/2023
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
1044424
Total Phase Actual Spending Amount
386502
Dsf Number S
DSF0000889270
17
Project Geographic District : 17 • Project Building Identifier: K191 • Project School Name: P.S. 191 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K191
Project School Name
P.S. 191 - BROOKLYN
Project Type
DOE - Skilled Trades
Project Description
REPLACE LEAKING STEEL HOT WATER STORAGE TANK
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
8/1/2022
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
264343
Total Phase Actual Spending Amount
257334
Dsf Number S
DSF0000893772
17
Project Geographic District : 17 • Project Building Identifier: K191 • Project School Name: P.S. 191 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K191
Project School Name
P.S. 191 - BROOKLYN
Project Type
SCA CIP
Project Description
ELECTRIFICATION/HEAT PUMP SYSTEMS / WINDOWS / ELECTRICAL SERVICE UPGRADE / FIRE ALARM
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
2078497
Final Estimate Of Actual Costs Through End Of Phase Amount
2078497
Total Phase Actual Spending Amount
243817
Dsf Number S
DSF0001083815, DSF0001111856, DSF0001111858, DSF0001111860
17
Project Geographic District : 17 • Project Building Identifier: K191 • Project School Name: P.S. 191 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K191
Project School Name
P.S. 191 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
1/23/2025
Project Phase Planned End Date
2/26/2026
Project Budget Amount
145616
Final Estimate Of Actual Costs Through End Of Phase Amount
148127
Total Phase Actual Spending Amount
143966
Dsf Number S
DSF0001087417
17
Project Geographic District : 17 • Project Building Identifier: K191 • Project School Name: P.S. 191 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K191
Project School Name
P.S. 191 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
1/23/2025
Project Phase Planned End Date
2/26/2026
Project Budget Amount
182816
Final Estimate Of Actual Costs Through End Of Phase Amount
173710
Total Phase Actual Spending Amount
154828
Dsf Number S
DSF0001087417
17
Project Geographic District : 17 • Project Building Identifier: K191 • Project School Name: P.S. 191 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K191
Project School Name
P.S. 191 - BROOKLYN
Project Type
SCA CIP
Project Description
ELECTRIFICATION/HEAT PUMP SYSTEMS / WINDOWS / ELECTRICAL SERVICE UPGRADE / FIRE ALARM
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
32304275
Final Estimate Of Actual Costs Through End Of Phase Amount
32304275
Total Phase Actual Spending Amount
453113
Dsf Number S
DSF0001083815, DSF0001111856, DSF0001111858, DSF0001111860
17
Project Geographic District : 17 • Project Building Identifier: K191 • Project School Name: P.S. 191 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K191
Project School Name
P.S. 191 - BROOKLYN
Project Type
SCA CIP
Project Description
ELECTRIFICATION/HEAT PUMP SYSTEMS / WINDOWS / ELECTRICAL SERVICE UPGRADE / FIRE ALARM
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
11/22/2023
Project Phase Planned End Date
6/28/2024
Project Phase Actual End Date
5/6/2024
Project Budget Amount
1454172
Final Estimate Of Actual Costs Through End Of Phase Amount
1018346
Total Phase Actual Spending Amount
976148
Dsf Number S
DSF0001083815, DSF0001111856, DSF0001111858, DSF0001111860
17
Project Geographic District : 17 • Project Building Identifier: K191 • Project School Name: P.S. 191 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K191
Project School Name
P.S. 191 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
4/19/2024
Project Phase Planned End Date
10/16/2024
Project Phase Actual End Date
9/25/2024
Project Budget Amount
14184
Final Estimate Of Actual Costs Through End Of Phase Amount
15726
Total Phase Actual Spending Amount
15726
Dsf Number S
DSF0001087417
17
Project Geographic District : 17 • Project Building Identifier: K191 • Project School Name: P.S. 191 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K191
Project School Name
P.S. 191 - BROOKLYN
Project Type
SCA CIP
Project Description
ELECTRIFICATION/HEAT PUMP SYSTEMS / WINDOWS / ELECTRICAL SERVICE UPGRADE / FIRE ALARM
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
5/31/2023
Project Phase Planned End Date
11/29/2023
Project Phase Actual End Date
11/17/2023
Project Budget Amount
291793
Final Estimate Of Actual Costs Through End Of Phase Amount
259761
Total Phase Actual Spending Amount
230389
Dsf Number S
DSF0001083815, DSF0001111856, DSF0001111858, DSF0001111860
17
Project Geographic District : 17 • Project Building Identifier: K191 • Project School Name: P.S. 191 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K191
Project School Name
P.S. 191 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
2/14/2024
Project Phase Planned End Date
6/13/2024
Project Phase Actual End Date
4/19/2024
Project Budget Amount
3152
Final Estimate Of Actual Costs Through End Of Phase Amount
3932
Total Phase Actual Spending Amount
3932
Dsf Number S
DSF0001087417
17
Project Geographic District : 17 • Project Building Identifier: K191 • Project School Name: P.S. 191 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K191
Project School Name
P.S. 191 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-ABATE ACM PIPE WRAP IN CRAWL SPACE ON 5 PIPES RUNNING ALONSIDE EACH OTHER, MARKED IN RED APPROX
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
3/27/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
4/29/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
20807
Total Phase Actual Spending Amount
2237
Dsf Number S
SCA0000075672
20
Project Geographic District : 20 • Project Building Identifier: K192 • Project School Name: K036 SPED - BROOKLYN
Project Geographic District
20
Project Building Identifier
K192
Project School Name
K036 SPED - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY26 RESO A ROOM CONVERSION
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
250000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001163789
20
Project Geographic District : 20 • Project Building Identifier: K192 • Project School Name: P.S. 192 - BROOKLYN
Project Geographic District
20
Project Building Identifier
K192
Project School Name
P.S. 192 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-ABATE AND REMOVE ALL ELECTRICAL RACEWAYS CREATIJNG A TRIP HAZARD AND INSTALL NEW FLOORING
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
8/8/2025
Project Phase Planned End Date
IEH
Project Phase Actual End Date
2/12/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
1801
Total Phase Actual Spending Amount
1051
Dsf Number S
SCA0000074621
22
Project Geographic District : 22 • Project Building Identifier: K193 • Project School Name: P.S. 193 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K193
Project School Name
P.S. 193 - BROOKLYN
Project Type
DIIT - RESOA
Project Description
FY24 RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
100000
Total Phase Actual Spending Amount
100000
Dsf Number S
DSF0001086017
22
Project Geographic District : 22 • Project Building Identifier: K193 • Project School Name: P.S. 193 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K193
Project School Name
P.S. 193 - BROOKLYN
Project Type
DIIT - RESOA
Project Description
FY26 RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
100000
Total Phase Actual Spending Amount
100000
Dsf Number S
DSF0001163790
22
Project Geographic District : 22 • Project Building Identifier: K193 • Project School Name: P.S. 193 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K193
Project School Name
P.S. 193 - BROOKLYN
Project Type
DIIT - RESOA
Project Description
FY22 RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
534000
Total Phase Actual Spending Amount
534000
Dsf Number S
DSF0001033032
22
Project Geographic District : 22 • Project Building Identifier: K193 • Project School Name: P.S. 193 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K193
Project School Name
P.S. 193 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY21 RESO A CAFETERIA UPGRADE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
3/23/2022
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
604523
Total Phase Actual Spending Amount
257966
Dsf Number S
DSF0001008311
22
Project Geographic District : 22 • Project Building Identifier: K193 • Project School Name: P.S. 193 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K193
Project School Name
P.S. 193 - BROOKLYN
Project Type
Fast Track Projects
Project Description
LSP PVI DOMESTIC WATER HEATER
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
5/7/2019
Project Phase Planned End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
266226
Total Phase Actual Spending Amount
145443
Dsf Number S
DSF0000893807
22
Project Geographic District : 22 • Project Building Identifier: K193 • Project School Name: P.S. 193 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K193
Project School Name
P.S. 193 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
6/5/2026
Project Phase Planned End Date
4/30/2027
Project Budget Amount
60180
Final Estimate Of Actual Costs Through End Of Phase Amount
30470
Total Phase Actual Spending Amount
8438
Dsf Number S
DSF0001087418
22
Project Geographic District : 22 • Project Building Identifier: K193 • Project School Name: P.S. 193 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K193
Project School Name
P.S. 193 - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / LOW VOLTAGE ELECTRICAL SYSTEM / PARAPETS / EXTERIOR MASONRY / ROOFS
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
7/18/2024
Project Phase Planned End Date
1/3/2027
Project Budget Amount
1938624
Final Estimate Of Actual Costs Through End Of Phase Amount
1202165
Total Phase Actual Spending Amount
1150548
Dsf Number S
DSF0001008653, DSF0000987593, DSF0001012375, DSF0001012376, DSF0001085832
22
Project Geographic District : 22 • Project Building Identifier: K193 • Project School Name: P.S. 193 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K193
Project School Name
P.S. 193 - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / LOW VOLTAGE ELECTRICAL SYSTEM / PARAPETS / EXTERIOR MASONRY / ROOFS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
7/18/2024
Project Phase Planned End Date
1/3/2027
Project Budget Amount
24643557
Final Estimate Of Actual Costs Through End Of Phase Amount
22766905
Total Phase Actual Spending Amount
13766407
Dsf Number S
DSF0001008653, DSF0000987593, DSF0001012375, DSF0001012376, DSF0001085832