Project Geographic District
22
Project Building Identifier
K193
Project School Name
P.S. 193 - BROOKLYN
Project Description
FULL PROGRAM ACCESSIBILITY / LOW VOLTAGE ELECTRICAL SYSTEM / PARAPETS / EXTERIOR MASONRY / ROOFS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
8/21/2023
Project Phase Planned End Date
1/25/2024
Project Phase Actual End Date
4/4/2024
Project Budget Amount
1167416
Final Estimate Of Actual Costs Through End Of Phase Amount
970029
Total Phase Actual Spending Amount
883303
Dsf Number S
DSF0001008653, DSF0000987593, DSF0001012375, DSF0001012376, DSF0001085832