Capital Project Schedules and Budgets

List of capital projects with managing organization, phase status and project costs.

Housing & Development School Construction Authority (SCA) Dataset 2xh6-psuq 14 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
14
Project Geographic District : 14 • Project Building Identifier: K196 • Project School Name: I.S. 582 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K196
Project School Name
I.S. 582 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY24 RESO A AUDITORIUM UPGRADE
Project Phase Name
CM,F&E
Project Status Name
Complete
Project Phase Actual Start Date
6/25/2025
Project Phase Planned End Date
5/20/2026
Project Phase Actual End Date
3/4/2026
Project Budget Amount
66009
Final Estimate Of Actual Costs Through End Of Phase Amount
41657
Total Phase Actual Spending Amount
40134
Dsf Number S
DSF0001086019
14
Project Geographic District : 14 • Project Building Identifier: K196 • Project School Name: I.S. 582 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K196
Project School Name
I.S. 582 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY24 RESO A AUDITORIUM UPGRADE
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
6/25/2025
Project Phase Planned End Date
5/20/2026
Project Phase Actual End Date
3/4/2026
Project Budget Amount
968127
Final Estimate Of Actual Costs Through End Of Phase Amount
416498
Total Phase Actual Spending Amount
306316
Dsf Number S
DSF0001086019
14
Project Geographic District : 14 • Project Building Identifier: K196 • Project School Name: I.S. 582 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K196
Project School Name
I.S. 582 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY24 RESO A AUDITORIUM UPGRADE
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
6/12/2024
Project Phase Planned End Date
11/14/2024
Project Phase Actual End Date
10/25/2024
Project Budget Amount
66009
Final Estimate Of Actual Costs Through End Of Phase Amount
62870
Total Phase Actual Spending Amount
49851
Dsf Number S
DSF0001086019
14
Project Geographic District : 14 • Project Building Identifier: K196 • Project School Name: I.S. 582 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K196
Project School Name
I.S. 582 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY24 RESO A AUDITORIUM UPGRADE
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
12/8/2023
Project Phase Planned End Date
4/11/2024
Project Phase Actual End Date
6/6/2024
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
17214
Total Phase Actual Spending Amount
17214
Dsf Number S
DSF0001086019
14
Project Geographic District : 14 • Project Building Identifier: K196 • Project School Name: P.S. 196 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K196
Project School Name
P.S. 196 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-ABATE & REPAIR DAMAGED WOOD FLOORING IN RM#329 APPROX 120 SFT SUB CONCRETE LEVELING COMPOUND IS
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
4/3/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
4/11/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
38010
Total Phase Actual Spending Amount
1014
Dsf Number S
SCA0000075713
14
Project Geographic District : 14 • Project Building Identifier: K196 • Project School Name: P.S. 196 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K196
Project School Name
P.S. 196 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-P.S RESPONSE ACTION ABATEMENT ABATE AND REPLACE/REPAIR DAMAGED MATERIALS 5420 - 420 - WOMEN'S T
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
3/24/2026
Project Phase Planned End Date
IEH
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
1186
Total Phase Actual Spending Amount
436
Dsf Number S
SCA0000075642
22
Project Geographic District : 22 • Project Building Identifier: K197 • Project School Name: P.S. 197 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K197
Project School Name
P.S. 197 - BROOKLYN
Project Type
DIIT - RESOA
Project Description
FY25 RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
150000
Total Phase Actual Spending Amount
150000
Dsf Number S
DSF0001112606
22
Project Geographic District : 22 • Project Building Identifier: K197 • Project School Name: P.S. 197 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K197
Project School Name
P.S. 197 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY19 RESO A HYDROPONICS LAB
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
4/12/2019
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
119721
Total Phase Actual Spending Amount
108631
Dsf Number S
DSF0000890651
22
Project Geographic District : 22 • Project Building Identifier: K197 • Project School Name: P.S. 197 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K197
Project School Name
P.S. 197 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY23 RESO A AUDITORIUM UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
128880
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001035467
22
Project Geographic District : 22 • Project Building Identifier: K197 • Project School Name: P.S. 197 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K197
Project School Name
P.S. 197 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY21 RESO A BATHROOM UPGRADE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
9/23/2021
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
100000
Total Phase Actual Spending Amount
97892
Dsf Number S
DSF0001008342
22
Project Geographic District : 22 • Project Building Identifier: K197 • Project School Name: P.S. 197 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K197
Project School Name
P.S. 197 - BROOKLYN
Project Type
Fast Track Projects
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
11/21/2024
Project Phase Planned End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
538039
Total Phase Actual Spending Amount
485944
Dsf Number S
DSF0001087421
22
Project Geographic District : 22 • Project Building Identifier: K197 • Project School Name: P.S. 197 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K197
Project School Name
P.S. 197 - BROOKLYN
Project Type
Fast Track Projects
Project Description
FY26 RESO A BATHROOM UPGRADES
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
FTK
Project Phase Planned End Date
FTK
Project Phase Actual End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
200000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001163793
22
Project Geographic District : 22 • Project Building Identifier: K197 • Project School Name: P.S. 197 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K197
Project School Name
P.S. 197 - BROOKLYN
Project Type
SCA CIP
Project Description
PERM FIX- REINFORCING SUPPORT ELEMENTS @ K197
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
8/5/2024
Project Phase Planned End Date
8/4/2025
Project Budget Amount
93800
Final Estimate Of Actual Costs Through End Of Phase Amount
404326
Total Phase Actual Spending Amount
404000
Dsf Number S
DSF0001111959
22
Project Geographic District : 22 • Project Building Identifier: K197 • Project School Name: P.S. 197 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K197
Project School Name
P.S. 197 - BROOKLYN
Project Type
SCA CIP
Project Description
ROOM CONVERSION (CSR)
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
185307
Final Estimate Of Actual Costs Through End Of Phase Amount
185307
Total Phase Actual Spending Amount
11766
Dsf Number S
DSF0001114233
22
Project Geographic District : 22 • Project Building Identifier: K197 • Project School Name: P.S. 197 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K197
Project School Name
P.S. 197 - BROOKLYN
Project Type
SCA CIP
Project Description
PERM FIX- REINFORCING SUPPORT ELEMENTS @ K197
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
8/5/2024
Project Phase Planned End Date
8/4/2025
Project Budget Amount
1507500
Final Estimate Of Actual Costs Through End Of Phase Amount
1497385
Total Phase Actual Spending Amount
1318192
Dsf Number S
DSF0001111959
22
Project Geographic District : 22 • Project Building Identifier: K197 • Project School Name: P.S. 197 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K197
Project School Name
P.S. 197 - BROOKLYN
Project Type
SCA CIP
Project Description
ROOM CONVERSION (CSR)
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
461435
Final Estimate Of Actual Costs Through End Of Phase Amount
461435
Total Phase Actual Spending Amount
200260
Dsf Number S
DSF0001114233
22
Project Geographic District : 22 • Project Building Identifier: K197 • Project School Name: P.S. 197 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K197
Project School Name
P.S. 197 - BROOKLYN
Project Type
SCA CIP
Project Description
PERM FIX- REINFORCING SUPPORT ELEMENTS @ K197
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
2/12/2024
Project Phase Planned End Date
7/15/2024
Project Phase Actual End Date
5/14/2024
Project Budget Amount
67000
Final Estimate Of Actual Costs Through End Of Phase Amount
228351
Total Phase Actual Spending Amount
182583
Dsf Number S
DSF0001111959
22
Project Geographic District : 22 • Project Building Identifier: K197 • Project School Name: P.S. 197 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K197
Project School Name
P.S. 197 - BROOKLYN
Project Type
SCA CIP
Project Description
ROOM CONVERSION (CSR)
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
6/13/2025
Project Phase Planned End Date
9/5/2025
Project Phase Actual End Date
10/15/2025
Project Budget Amount
32100
Final Estimate Of Actual Costs Through End Of Phase Amount
0
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001114233
22
Project Geographic District : 22 • Project Building Identifier: K197 • Project School Name: P.S. 197 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K197
Project School Name
P.S. 197 - BROOKLYN
Project Type
SCA CIP
Project Description
ROOM CONVERSION (CSR)
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
6/13/2025
Project Phase Planned End Date
6/13/2025
Project Phase Actual End Date
6/13/2025
Project Budget Amount
8025
Final Estimate Of Actual Costs Through End Of Phase Amount
0
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001114233
22
Project Geographic District : 22 • Project Building Identifier: K197 • Project School Name: P.S. 197 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K197
Project School Name
P.S. 197 - BROOKLYN
Project Type
SCA CIP
Project Description
PERM FIX- REINFORCING SUPPORT ELEMENTS @ K197
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
11/28/2023
Project Phase Planned End Date
4/15/2024
Project Phase Actual End Date
2/8/2024
Project Budget Amount
13400
Final Estimate Of Actual Costs Through End Of Phase Amount
23478
Total Phase Actual Spending Amount
23478
Dsf Number S
DSF0001111959
22
Project Geographic District : 22 • Project Building Identifier: K197 • Project School Name: P.S. 197 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K197
Project School Name
P.S. 197 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
PATH OF TRAVEL RESO A PLAYGROUND UPGRADE
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
0
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001113575
22
Project Geographic District : 22 • Project Building Identifier: K197 • Project School Name: P.S. 197 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K197
Project School Name
P.S. 197 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
PATH OF TRAVEL RESO A PLAYGROUND UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
0
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001113575
22
Project Geographic District : 22 • Project Building Identifier: K197 • Project School Name: P.S. 197 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K197
Project School Name
P.S. 197 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
PATH OF TRAVEL RESO A PLAYGROUND UPGRADE
Project Phase Name
Design
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
0
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001113575
22
Project Geographic District : 22 • Project Building Identifier: K197 • Project School Name: P.S. 197 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K197
Project School Name
P.S. 197 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
PATH OF TRAVEL RESO A PLAYGROUND UPGRADE
Project Phase Name
Scope
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
0
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001113575
22
Project Geographic District : 22 • Project Building Identifier: K197 • Project School Name: P.S. 197 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K197
Project School Name
P.S. 197 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-AHERA P.S RESPONSE ACTION ABATEMENT SOFT CONCRETE FILLER FLOORING MATERIAL AT SPACES - 7010,700
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
5/26/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
6/23/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
43961
Total Phase Actual Spending Amount
436
Dsf Number S
SCA0000076054
22
Project Geographic District : 22 • Project Building Identifier: K198 • Project School Name: P.S. 198 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K198
Project School Name
P.S. 198 - BROOKLYN
Project Type
DIIT - RESOA
Project Description
FY26 RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
100000
Total Phase Actual Spending Amount
100000
Dsf Number S
DSF0001163794
22
Project Geographic District : 22 • Project Building Identifier: K198 • Project School Name: P.S. 198 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K198
Project School Name
P.S. 198 - BROOKLYN
Project Type
DIIT - RESOA
Project Description
FY22 RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
100000
Total Phase Actual Spending Amount
100000
Dsf Number S
DSF0001033500
22
Project Geographic District : 22 • Project Building Identifier: K198 • Project School Name: P.S. 198 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K198
Project School Name
P.S. 198 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY25 RESO A AUDITORIUM UPGRADE / PATH OF TRAVEL RESO A AUDITORIUM UPGRADE
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
60000
Final Estimate Of Actual Costs Through End Of Phase Amount
62626
Total Phase Actual Spending Amount
28675
Dsf Number S
DSF0001112607, DSF0001113576
22
Project Geographic District : 22 • Project Building Identifier: K198 • Project School Name: P.S. 198 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K198
Project School Name
P.S. 198 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY24 RESO A (MA) CAFETERIA UPGRADE / PATH OF TRAVEL RESO A (MA) CAFETERIA UPGRADE
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
10/8/2025
Project Phase Planned End Date
9/2/2026
Project Budget Amount
161628
Final Estimate Of Actual Costs Through End Of Phase Amount
175401
Total Phase Actual Spending Amount
40127
Dsf Number S
DSF0001086022, DSF0001087017
22
Project Geographic District : 22 • Project Building Identifier: K198 • Project School Name: P.S. 198 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K198
Project School Name
P.S. 198 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY24 RESO A (MA) CAFETERIA UPGRADE / PATH OF TRAVEL RESO A (MA) CAFETERIA UPGRADE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
10/8/2025
Project Phase Planned End Date
9/2/2026
Project Budget Amount
1143120
Final Estimate Of Actual Costs Through End Of Phase Amount
750000
Total Phase Actual Spending Amount
22797
Dsf Number S
DSF0001086022, DSF0001087017
22
Project Geographic District : 22 • Project Building Identifier: K198 • Project School Name: P.S. 198 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K198
Project School Name
P.S. 198 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY25 RESO A AUDITORIUM UPGRADE / PATH OF TRAVEL RESO A AUDITORIUM UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
880000
Final Estimate Of Actual Costs Through End Of Phase Amount
880000
Total Phase Actual Spending Amount
2451
Dsf Number S
DSF0001112607, DSF0001113576
22
Project Geographic District : 22 • Project Building Identifier: K198 • Project School Name: P.S. 198 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K198
Project School Name
P.S. 198 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY24 RESO A (MA) CAFETERIA UPGRADE / PATH OF TRAVEL RESO A (MA) CAFETERIA UPGRADE
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
6/17/2024
Project Phase Planned End Date
10/16/2024
Project Phase Actual End Date
4/1/2025
Project Budget Amount
77940
Final Estimate Of Actual Costs Through End Of Phase Amount
114833
Total Phase Actual Spending Amount
109137
Dsf Number S
DSF0001086022, DSF0001087017
22
Project Geographic District : 22 • Project Building Identifier: K198 • Project School Name: P.S. 198 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K198
Project School Name
P.S. 198 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY25 RESO A AUDITORIUM UPGRADE / PATH OF TRAVEL RESO A AUDITORIUM UPGRADE
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
11/26/2025
Project Phase Planned End Date
3/30/2026
Project Phase Actual End Date
4/17/2026
Project Budget Amount
60000
Final Estimate Of Actual Costs Through End Of Phase Amount
66229
Total Phase Actual Spending Amount
61496
Dsf Number S
DSF0001112607, DSF0001113576
22
Project Geographic District : 22 • Project Building Identifier: K198 • Project School Name: P.S. 198 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K198
Project School Name
P.S. 198 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY25 RESO A AUDITORIUM UPGRADE / PATH OF TRAVEL RESO A AUDITORIUM UPGRADE
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
2/25/2025
Project Phase Planned End Date
10/23/2025
Project Phase Actual End Date
11/24/2025
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
33693
Total Phase Actual Spending Amount
33693
Dsf Number S
DSF0001112607, DSF0001113576
22
Project Geographic District : 22 • Project Building Identifier: K198 • Project School Name: P.S. 198 - BROOKLYN
Project Geographic District
22
Project Building Identifier
K198
Project School Name
P.S. 198 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY24 RESO A (MA) CAFETERIA UPGRADE / PATH OF TRAVEL RESO A (MA) CAFETERIA UPGRADE
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
11/21/2023
Project Phase Planned End Date
7/11/2024
Project Phase Actual End Date
6/10/2024
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
34211
Total Phase Actual Spending Amount
34211
Dsf Number S
DSF0001086022, DSF0001087017
21
Project Geographic District : 21 • Project Building Identifier: K199 • Project School Name: P.S. 199 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K199
Project School Name
P.S. 199 - BROOKLYN
Project Type
DIIT - RESOA
Project Description
FY25 RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
Complete
Project Phase Actual Start Date
11/6/2025
Project Phase Planned End Date
DIIR
Project Phase Actual End Date
2/4/2026
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
50000
Total Phase Actual Spending Amount
50000
Dsf Number S
DSF0001112608
21
Project Geographic District : 21 • Project Building Identifier: K199 • Project School Name: P.S. 199 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K199
Project School Name
P.S. 199 - BROOKLYN
Project Type
Fast Track Projects
Project Description
FY25 RESO A STEM LAB
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
FTK
Project Phase Planned End Date
FTK
Project Phase Actual End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
14500
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001112609
21
Project Geographic District : 21 • Project Building Identifier: K199 • Project School Name: P.S. 199 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K199
Project School Name
P.S. 199 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS CAMERA INSTALLATION
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
4/17/2024
Project Phase Planned End Date
3/12/2025
Project Budget Amount
161894
Final Estimate Of Actual Costs Through End Of Phase Amount
162716
Total Phase Actual Spending Amount
132327
Dsf Number S
DSF0001035009
21
Project Geographic District : 21 • Project Building Identifier: K199 • Project School Name: P.S. 199 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K199
Project School Name
P.S. 199 - BROOKLYN
Project Type
SCA CIP
Project Description
ROOFS / PARAPETS / EXTERIOR MASONRY / WINDOWS
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
7/22/2024
Project Phase Planned End Date
1/7/2027
Project Budget Amount
950040
Final Estimate Of Actual Costs Through End Of Phase Amount
585378
Total Phase Actual Spending Amount
578566
Dsf Number S
DSF0001012500, DSF0001012501, DSF0001012502, DSF0001087230
21
Project Geographic District : 21 • Project Building Identifier: K199 • Project School Name: P.S. 199 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K199
Project School Name
P.S. 199 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS CAMERA INSTALLATION
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
4/17/2024
Project Phase Planned End Date
3/12/2025
Project Budget Amount
227360
Final Estimate Of Actual Costs Through End Of Phase Amount
207548
Total Phase Actual Spending Amount
184298
Dsf Number S
DSF0001035009
21
Project Geographic District : 21 • Project Building Identifier: K199 • Project School Name: P.S. 199 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K199
Project School Name
P.S. 199 - BROOKLYN
Project Type
SCA CIP
Project Description
ROOFS / PARAPETS / EXTERIOR MASONRY / WINDOWS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
7/22/2024
Project Phase Planned End Date
1/7/2027
Project Budget Amount
15268501
Final Estimate Of Actual Costs Through End Of Phase Amount
14198912
Total Phase Actual Spending Amount
12727880
Dsf Number S
DSF0001012500, DSF0001012501, DSF0001012502, DSF0001087230
21
Project Geographic District : 21 • Project Building Identifier: K199 • Project School Name: P.S. 199 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K199
Project School Name
P.S. 199 - BROOKLYN
Project Type
SCA CIP
Project Description
ROOFS / PARAPETS / EXTERIOR MASONRY / WINDOWS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
11/9/2023
Project Phase Planned End Date
6/28/2024
Project Phase Actual End Date
4/29/2024
Project Budget Amount
678600
Final Estimate Of Actual Costs Through End Of Phase Amount
418041
Total Phase Actual Spending Amount
417555
Dsf Number S
DSF0001012500, DSF0001012501, DSF0001012502, DSF0001087230
21
Project Geographic District : 21 • Project Building Identifier: K199 • Project School Name: P.S. 199 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K199
Project School Name
P.S. 199 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS CAMERA INSTALLATION
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
7/3/2023
Project Phase Planned End Date
12/29/2023
Project Phase Actual End Date
10/18/2023
Project Budget Amount
17640
Final Estimate Of Actual Costs Through End Of Phase Amount
9472
Total Phase Actual Spending Amount
9472
Dsf Number S
DSF0001035009
21
Project Geographic District : 21 • Project Building Identifier: K199 • Project School Name: P.S. 199 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K199
Project School Name
P.S. 199 - BROOKLYN
Project Type
SCA CIP
Project Description
ROOFS / PARAPETS / EXTERIOR MASONRY / WINDOWS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
6/14/2023
Project Phase Planned End Date
12/13/2023
Project Phase Actual End Date
10/6/2023
Project Budget Amount
135720
Final Estimate Of Actual Costs Through End Of Phase Amount
154698
Total Phase Actual Spending Amount
153597
Dsf Number S
DSF0001012500, DSF0001012501, DSF0001012502, DSF0001087230
21
Project Geographic District : 21 • Project Building Identifier: K199 • Project School Name: P.S. 199 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K199
Project School Name
P.S. 199 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS CAMERA INSTALLATION
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
6/15/2023
Project Phase Planned End Date
10/17/2023
Project Phase Actual End Date
7/3/2023
Project Budget Amount
3920
Final Estimate Of Actual Costs Through End Of Phase Amount
2368
Total Phase Actual Spending Amount
2368
Dsf Number S
DSF0001035009
20
Project Geographic District : 20 • Project Building Identifier: K200 • Project School Name: P.S. 200 - BROOKLYN
Project Geographic District
20
Project Building Identifier
K200
Project School Name
P.S. 200 - BROOKLYN
Project Type
DIIT - RESOA
Project Description
RESO A (MA) TECHNOLOGY
Project Phase Name
Purch & Install
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
50000
Total Phase Actual Spending Amount
50000
Dsf Number S
DSF0001008617
20
Project Geographic District : 20 • Project Building Identifier: K200 • Project School Name: P.S. 200 - BROOKLYN
Project Geographic District
20
Project Building Identifier
K200
Project School Name
P.S. 200 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY25 RESO A DIGITAL SIGN
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
100000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001112611
20
Project Geographic District : 20 • Project Building Identifier: K200 • Project School Name: P.S. 200 - BROOKLYN
Project Geographic District
20
Project Building Identifier
K200
Project School Name
P.S. 200 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY23 RESO A BATHROOM UPGRADES
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
3/11/2024
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
296545
Total Phase Actual Spending Amount
191091
Dsf Number S
DSF0001035469
20
Project Geographic District : 20 • Project Building Identifier: K200 • Project School Name: P.S. 200 - BROOKLYN
Project Geographic District
20
Project Building Identifier
K200
Project School Name
P.S. 200 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY25 RESO A CAFETERIA UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
200000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001112610
20
Project Geographic District : 20 • Project Building Identifier: K200 • Project School Name: P.S. 200 - BROOKLYN
Project Geographic District
20
Project Building Identifier
K200
Project School Name
P.S. 200 - BROOKLYN
Project Type
Fast Track Projects
Project Description
FY26 RESO A BATHROOM UPGRADES
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
FTK
Project Phase Planned End Date
FTK
Project Phase Actual End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
160000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001163795