Project Geographic District
21
Project Building Identifier
K199
Project School Name
P.S. 199 - BROOKLYN
Project Description
ROOFS / PARAPETS / EXTERIOR MASONRY / WINDOWS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
11/9/2023
Project Phase Planned End Date
6/28/2024
Project Phase Actual End Date
4/29/2024
Project Budget Amount
678600
Final Estimate Of Actual Costs Through End Of Phase Amount
418041
Total Phase Actual Spending Amount
417555
Dsf Number S
DSF0001012500, DSF0001012501, DSF0001012502, DSF0001087230