Capital Project Schedules and Budgets

List of capital projects with managing organization, phase status and project costs.

Housing & Development School Construction Authority (SCA) Dataset 2xh6-psuq 14 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
18
Project Geographic District : 18 • Project Building Identifier: K285 • Project School Name: I.S. 285 - BROOKLYN
Project Geographic District
18
Project Building Identifier
K285
Project School Name
I.S. 285 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-PLEASE ABATE ACM 9X9 FLOOR TILES THAT NEED TO BE REMOVED AND REPLACE ROOM 106,107,118,202,206 M
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
12/10/2025
Project Phase Planned End Date
IEH
Project Phase Actual End Date
1/9/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
123042
Total Phase Actual Spending Amount
3573
Dsf Number S
SCA0000075201
22
Project Geographic District : 22 • Project Building Identifier: K286 • Project School Name: K811 SPED - BROOKLYN
Project Geographic District
22
Project Building Identifier
K286
Project School Name
K811 SPED - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY20 RESO A AUDITORIUM UPGRADE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
8/4/2022
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
250000
Total Phase Actual Spending Amount
170378
Dsf Number S
DSF0000913178
22
Project Geographic District : 22 • Project Building Identifier: K286 • Project School Name: K811 SPED - BROOKLYN
Project Geographic District
22
Project Building Identifier
K286
Project School Name
K811 SPED - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY22 RESO A ROOM CONVERSION
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
118000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001033135
22
Project Geographic District : 22 • Project Building Identifier: K286 • Project School Name: K811 SPED - BROOKLYN
Project Geographic District
22
Project Building Identifier
K286
Project School Name
K811 SPED - BROOKLYN
Project Type
DOE - Skilled Trades
Project Description
BATHROOM UPGRADE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
7/19/2019
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
170000
Total Phase Actual Spending Amount
159922
Dsf Number S
DSF0000889051
22
Project Geographic District : 22 • Project Building Identifier: K286 • Project School Name: K811 SPED - BROOKLYN
Project Geographic District
22
Project Building Identifier
K286
Project School Name
K811 SPED - BROOKLYN
Project Type
Fast Track Projects
Project Description
FY26 RESO A ROOM CONVERSION
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
FTK
Project Phase Planned End Date
FTK
Project Phase Actual End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
160000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001163128
22
Project Geographic District : 22 • Project Building Identifier: K286 • Project School Name: K811 SPED - BROOKLYN
Project Geographic District
22
Project Building Identifier
K286
Project School Name
K811 SPED - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / LOW VOLTAGE ELECTRICAL SYSTEM
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
882631
Final Estimate Of Actual Costs Through End Of Phase Amount
882631
Total Phase Actual Spending Amount
113010
Dsf Number S
DSF0000912810, DSF0001014094
22
Project Geographic District : 22 • Project Building Identifier: K286 • Project School Name: K811 SPED - BROOKLYN
Project Geographic District
22
Project Building Identifier
K286
Project School Name
K811 SPED - BROOKLYN
Project Type
SCA CIP
Project Description
PARAPETS / FLOOD ELIMINATION / ROOFS / EMERGENCY GENERATOR / EXTERIOR MASONRY
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
1466234
Final Estimate Of Actual Costs Through End Of Phase Amount
1466234
Total Phase Actual Spending Amount
75299
Dsf Number S
DSF0001120227, DSF0001120224, DSF0001120226, DSF0001144140, DSF0001144139
22
Project Geographic District : 22 • Project Building Identifier: K286 • Project School Name: K811 SPED - BROOKLYN
Project Geographic District
22
Project Building Identifier
K286
Project School Name
K811 SPED - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / LOW VOLTAGE ELECTRICAL SYSTEM
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
14185141
Final Estimate Of Actual Costs Through End Of Phase Amount
14185141
Total Phase Actual Spending Amount
198586
Dsf Number S
DSF0000912810, DSF0001014094
22
Project Geographic District : 22 • Project Building Identifier: K286 • Project School Name: K811 SPED - BROOKLYN
Project Geographic District
22
Project Building Identifier
K286
Project School Name
K811 SPED - BROOKLYN
Project Type
SCA CIP
Project Description
PARAPETS / FLOOD ELIMINATION / ROOFS / EMERGENCY GENERATOR / EXTERIOR MASONRY
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
12942387
Final Estimate Of Actual Costs Through End Of Phase Amount
12942387
Total Phase Actual Spending Amount
23997
Dsf Number S
DSF0001120227, DSF0001120224, DSF0001120226, DSF0001144140, DSF0001144139
22
Project Geographic District : 22 • Project Building Identifier: K286 • Project School Name: K811 SPED - BROOKLYN
Project Geographic District
22
Project Building Identifier
K286
Project School Name
K811 SPED - BROOKLYN
Project Type
SCA CIP
Project Description
PARAPETS / FLOOD ELIMINATION / ROOFS / EMERGENCY GENERATOR / EXTERIOR MASONRY
Project Phase Name
Design
Project Status Name
In-Progress
Project Phase Actual Start Date
1/7/2026
Project Phase Planned End Date
6/9/2026
Project Budget Amount
823771
Final Estimate Of Actual Costs Through End Of Phase Amount
823771
Total Phase Actual Spending Amount
19604
Dsf Number S
DSF0001120227, DSF0001120224, DSF0001120226, DSF0001144140, DSF0001144139
22
Project Geographic District : 22 • Project Building Identifier: K286 • Project School Name: K811 SPED - BROOKLYN
Project Geographic District
22
Project Building Identifier
K286
Project School Name
K811 SPED - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / LOW VOLTAGE ELECTRICAL SYSTEM
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
8/31/2022
Project Phase Planned End Date
3/9/2023
Project Phase Actual End Date
2/10/2025
Project Budget Amount
630451
Final Estimate Of Actual Costs Through End Of Phase Amount
632964
Total Phase Actual Spending Amount
481789
Dsf Number S
DSF0000912810, DSF0001014094
22
Project Geographic District : 22 • Project Building Identifier: K286 • Project School Name: K811 SPED - BROOKLYN
Project Geographic District
22
Project Building Identifier
K286
Project School Name
K811 SPED - BROOKLYN
Project Type
SCA CIP
Project Description
PARAPETS / FLOOD ELIMINATION / ROOFS / EMERGENCY GENERATOR / EXTERIOR MASONRY
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
1/31/2025
Project Phase Planned End Date
6/17/2025
Project Phase Actual End Date
1/6/2026
Project Budget Amount
179422
Final Estimate Of Actual Costs Through End Of Phase Amount
181166
Total Phase Actual Spending Amount
75395
Dsf Number S
DSF0001120227, DSF0001120224, DSF0001120226, DSF0001144140, DSF0001144139
22
Project Geographic District : 22 • Project Building Identifier: K286 • Project School Name: K811 SPED - BROOKLYN
Project Geographic District
22
Project Building Identifier
K286
Project School Name
K811 SPED - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / LOW VOLTAGE ELECTRICAL SYSTEM
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
8/29/2019
Project Phase Planned End Date
1/17/2020
Project Phase Actual End Date
6/8/2021
Project Budget Amount
126090
Final Estimate Of Actual Costs Through End Of Phase Amount
190795
Total Phase Actual Spending Amount
190795
Dsf Number S
DSF0000912810, DSF0001014094
22
Project Geographic District : 22 • Project Building Identifier: K286 • Project School Name: K811 SPED - BROOKLYN
Project Geographic District
22
Project Building Identifier
K286
Project School Name
K811 SPED - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-ABATE/REPAIR AND REPLACE TILES, PIPE INSULATION 316A/4316A - TELEPHONE CLOSET (9X9 FLR TILE & M
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
8/14/2025
Project Phase Planned End Date
IEH
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
49875
Total Phase Actual Spending Amount
1410
Dsf Number S
SCA0000074676
22
Project Geographic District : 22 • Project Building Identifier: K286 • Project School Name: K811 SPED - BROOKLYN
Project Geographic District
22
Project Building Identifier
K286
Project School Name
K811 SPED - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-ABATE AND REMOVE APPROX 90 FEET OF ACM PIPE COVER IN THE PIPE CHASE . LOCATED IN ROOM 134B. PA
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
2/19/2026
Project Phase Planned End Date
IEH
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
19767
Total Phase Actual Spending Amount
1474
Dsf Number S
SCA0000075456
13
Project Geographic District : 13 • Project Building Identifier: K287 • Project School Name: P.S. 287 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K287
Project School Name
P.S. 287 - BROOKLYN
Project Type
DIIT - Project Connect
Project Description
CLASSROOM CONNECTIVITY
Project Phase Name
Purch & Install
Project Status Name
In-Progress
Project Phase Actual Start Date
11/1/2019
Project Phase Planned End Date
DIIT
Project Budget Amount
DIIT
Final Estimate Of Actual Costs Through End Of Phase Amount
445236066
Total Phase Actual Spending Amount
226357
Dsf Number S
DSF0000959874
13
Project Geographic District : 13 • Project Building Identifier: K287 • Project School Name: P.S. 287 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K287
Project School Name
P.S. 287 - BROOKLYN
Project Type
DIIT - RESOA
Project Description
RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
102000
Total Phase Actual Spending Amount
102000
Dsf Number S
DSF0001113824
13
Project Geographic District : 13 • Project Building Identifier: K287 • Project School Name: P.S. 287 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K287
Project School Name
P.S. 287 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY25 RESO A BATHROOM UPGRADES
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
300000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001112671
13
Project Geographic District : 13 • Project Building Identifier: K287 • Project School Name: P.S. 287 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K287
Project School Name
P.S. 287 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY21 RESO A AUDITORIUM UPGRADE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
9/18/2024
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
301078
Total Phase Actual Spending Amount
299794
Dsf Number S
DSF0001008221
13
Project Geographic District : 13 • Project Building Identifier: K287 • Project School Name: P.S. 287 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K287
Project School Name
P.S. 287 - BROOKLYN
Project Type
DOE - RESOA
Project Description
RESO A- RESO A HYDROPONICS LAB
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
209604
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001083927
13
Project Geographic District : 13 • Project Building Identifier: K287 • Project School Name: P.S. 287 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K287
Project School Name
P.S. 287 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
8/6/2025
Project Phase Planned End Date
7/1/2026
Project Budget Amount
146446
Final Estimate Of Actual Costs Through End Of Phase Amount
163433
Total Phase Actual Spending Amount
107936
Dsf Number S
DSF0001087445
13
Project Geographic District : 13 • Project Building Identifier: K287 • Project School Name: P.S. 287 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K287
Project School Name
P.S. 287 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
8/6/2025
Project Phase Planned End Date
7/1/2026
Project Budget Amount
186896
Final Estimate Of Actual Costs Through End Of Phase Amount
171887
Total Phase Actual Spending Amount
114723
Dsf Number S
DSF0001087445
13
Project Geographic District : 13 • Project Building Identifier: K287 • Project School Name: P.S. 287 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K287
Project School Name
P.S. 287 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
9/13/2024
Project Phase Planned End Date
3/14/2025
Project Phase Actual End Date
2/12/2025
Project Budget Amount
14501
Final Estimate Of Actual Costs Through End Of Phase Amount
3431
Total Phase Actual Spending Amount
3431
Dsf Number S
DSF0001087445
13
Project Geographic District : 13 • Project Building Identifier: K287 • Project School Name: P.S. 287 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K287
Project School Name
P.S. 287 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
9/10/2024
Project Phase Planned End Date
1/13/2025
Project Phase Actual End Date
9/13/2024
Project Budget Amount
3222
Final Estimate Of Actual Costs Through End Of Phase Amount
858
Total Phase Actual Spending Amount
858
Dsf Number S
DSF0001087445
13
Project Geographic District : 13 • Project Building Identifier: K287 • Project School Name: P.S. 287 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K287
Project School Name
P.S. 287 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-P.S RESPONSE ACTION ABATEMENT ABATE AND REPAIR CERAMIC TILE MASTIC IN THE FOLLOWING LOCATIONS:
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
5/15/2026
Project Phase Planned End Date
IEH
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
750
Total Phase Actual Spending Amount
0
Dsf Number S
SCA0000075976
21
Project Geographic District : 21 • Project Building Identifier: K288 • Project School Name: P.S. 288 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K288
Project School Name
P.S. 288 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY21 RESO A ROOM CONVERSION
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
7/1/2022
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
337272
Total Phase Actual Spending Amount
108860
Dsf Number S
DSF0001008443
21
Project Geographic District : 21 • Project Building Identifier: K288 • Project School Name: P.S. 288 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K288
Project School Name
P.S. 288 - BROOKLYN
Project Type
DOE - RESOA
Project Description
RESO A CAFETERIA UPGRADE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
4/24/2024
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
404822
Total Phase Actual Spending Amount
4064
Dsf Number S
DSF0001083919
21
Project Geographic District : 21 • Project Building Identifier: K288 • Project School Name: P.S. 288 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K288
Project School Name
P.S. 288 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY22 RESO A STEM LAB
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
226262
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001033536
21
Project Geographic District : 21 • Project Building Identifier: K288 • Project School Name: P.S. 288 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K288
Project School Name
P.S. 288 - BROOKLYN
Project Type
Fast Track Projects
Project Description
RESO A STEM LAB
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
FTK
Project Phase Planned End Date
FTK
Project Phase Actual End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
16000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001114085
21
Project Geographic District : 21 • Project Building Identifier: K288 • Project School Name: P.S. 288 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K288
Project School Name
P.S. 288 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
CM,F&E
Project Status Name
Complete
Project Phase Actual Start Date
10/19/2023
Project Phase Planned End Date
9/12/2024
Project Phase Actual End Date
4/2/2025
Project Budget Amount
160118
Final Estimate Of Actual Costs Through End Of Phase Amount
148275
Total Phase Actual Spending Amount
110186
Dsf Number S
DSF0001034605
21
Project Geographic District : 21 • Project Building Identifier: K288 • Project School Name: P.S. 288 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K288
Project School Name
P.S. 288 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
10/19/2023
Project Phase Planned End Date
9/12/2024
Project Phase Actual End Date
4/2/2025
Project Budget Amount
219988
Final Estimate Of Actual Costs Through End Of Phase Amount
199962
Total Phase Actual Spending Amount
172734
Dsf Number S
DSF0001034605
21
Project Geographic District : 21 • Project Building Identifier: K288 • Project School Name: P.S. 288 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K288
Project School Name
P.S. 288 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
3/8/2023
Project Phase Planned End Date
8/31/2023
Project Phase Actual End Date
4/26/2023
Project Budget Amount
17068
Final Estimate Of Actual Costs Through End Of Phase Amount
11551
Total Phase Actual Spending Amount
11551
Dsf Number S
DSF0001034605
21
Project Geographic District : 21 • Project Building Identifier: K288 • Project School Name: P.S. 288 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K288
Project School Name
P.S. 288 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
3/1/2023
Project Phase Planned End Date
6/29/2023
Project Phase Actual End Date
3/8/2023
Project Budget Amount
3793
Final Estimate Of Actual Costs Through End Of Phase Amount
2860
Total Phase Actual Spending Amount
2860
Dsf Number S
DSF0001034605
17
Project Geographic District : 17 • Project Building Identifier: K289 • Project School Name: P.S. 289 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K289
Project School Name
P.S. 289 - BROOKLYN
Project Type
DIIT - RESOA
Project Description
FY26 RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
50000
Total Phase Actual Spending Amount
50000
Dsf Number S
DSF0001163129
17
Project Geographic District : 17 • Project Building Identifier: K289 • Project School Name: P.S. 289 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K289
Project School Name
P.S. 289 - BROOKLYN
Project Type
DOE - Skilled Trades
Project Description
REPLACE TELEDYNE LAARS HOT WATER BOILER
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
7/11/2019
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
42686
Total Phase Actual Spending Amount
41377
Dsf Number S
DSF0000872616
17
Project Geographic District : 17 • Project Building Identifier: K289 • Project School Name: K396 SPED - BROOKLYN
Project Geographic District
17
Project Building Identifier
K289
Project School Name
K396 SPED - BROOKLYN
Project Type
Fast Track Projects
Project Description
FY26 RESO A ROOM CONVERSION
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
FTK
Project Phase Planned End Date
FTK
Project Phase Actual End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
200000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001163130
17
Project Geographic District : 17 • Project Building Identifier: K289 • Project School Name: P.S. 289 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K289
Project School Name
P.S. 289 - BROOKLYN
Project Type
SCA CIP
Project Description
ROOFS / EXTERIOR MASONRY / ELECTRIFICATION/HEAT PUMP SYSTEMS / FULL PROGRAM ACCESSIBILITY / FIRE SPRINKLER SYSTEM / FIRE ALARM SYSTEM / WINDOWS / ELECTRICAL SERVICE UPGRADE / LIGHTING UPGRADE
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
6777092
Final Estimate Of Actual Costs Through End Of Phase Amount
6777092
Total Phase Actual Spending Amount
563026
Dsf Number S
DSF0001064893, DSF0001120282, DSF0001114051, DSF0001114064, DSF0001144199, DSF0001114639, DSF0001114638, DSF0001144195, DSF0001144189
17
Project Geographic District : 17 • Project Building Identifier: K289 • Project School Name: P.S. 289 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K289
Project School Name
P.S. 289 - BROOKLYN
Project Type
SCA CIP
Project Description
ROOFS / EXTERIOR MASONRY / ELECTRIFICATION/HEAT PUMP SYSTEMS / FULL PROGRAM ACCESSIBILITY / FIRE SPRINKLER SYSTEM / FIRE ALARM SYSTEM / WINDOWS / ELECTRICAL SERVICE UPGRADE / LIGHTING UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
67095588
Final Estimate Of Actual Costs Through End Of Phase Amount
67095588
Total Phase Actual Spending Amount
252473
Dsf Number S
DSF0001064893, DSF0001120282, DSF0001114051, DSF0001114064, DSF0001144199, DSF0001114639, DSF0001114638, DSF0001144195, DSF0001144189
17
Project Geographic District : 17 • Project Building Identifier: K289 • Project School Name: P.S. 289 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K289
Project School Name
P.S. 289 - BROOKLYN
Project Type
SCA CIP
Project Description
ROOFS / EXTERIOR MASONRY / ELECTRIFICATION/HEAT PUMP SYSTEMS / FULL PROGRAM ACCESSIBILITY / FIRE SPRINKLER SYSTEM / FIRE ALARM SYSTEM / WINDOWS / ELECTRICAL SERVICE UPGRADE / LIGHTING UPGRADE
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
11/24/2025
Project Phase Planned End Date
7/8/2026
Project Phase Actual End Date
5/20/2026
Project Budget Amount
4236541
Final Estimate Of Actual Costs Through End Of Phase Amount
1987242
Total Phase Actual Spending Amount
1710745
Dsf Number S
DSF0001064893, DSF0001120282, DSF0001114051, DSF0001114064, DSF0001144199, DSF0001114639, DSF0001114638, DSF0001144195, DSF0001144189
17
Project Geographic District : 17 • Project Building Identifier: K289 • Project School Name: P.S. 289 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K289
Project School Name
P.S. 289 - BROOKLYN
Project Type
SCA CIP
Project Description
ROOFS / EXTERIOR MASONRY / ELECTRIFICATION/HEAT PUMP SYSTEMS / FULL PROGRAM ACCESSIBILITY / FIRE SPRINKLER SYSTEM / FIRE ALARM SYSTEM / WINDOWS / ELECTRICAL SERVICE UPGRADE / LIGHTING UPGRADE
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
6/27/2024
Project Phase Planned End Date
9/11/2025
Project Phase Actual End Date
11/24/2025
Project Budget Amount
909850
Final Estimate Of Actual Costs Through End Of Phase Amount
659259
Total Phase Actual Spending Amount
655507
Dsf Number S
DSF0001064893, DSF0001120282, DSF0001114051, DSF0001114064, DSF0001144199, DSF0001114639, DSF0001114638, DSF0001144195, DSF0001144189
17
Project Geographic District : 17 • Project Building Identifier: K289 • Project School Name: P.S. 289 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K289
Project School Name
P.S. 289 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-OIL TANK LINE/PIPE INSULATION ABATEMENT FOR ISOLATION VALVE INSTALLS
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
2/6/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
6/27/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
15087
Total Phase Actual Spending Amount
1724
Dsf Number S
SCA0000075401
19
Project Geographic District : 19 • Project Building Identifier: K290 • Project School Name: P.S. 290 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K290
Project School Name
P.S. 290 - BROOKLYN
Project Type
DOE - Skilled Trades
Project Description
WATER HEATERS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
1/3/2017
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
105572
Total Phase Actual Spending Amount
15746
Dsf Number S
DSF0000782405
32
Project Geographic District : 32 • Project Building Identifier: K291 • Project School Name: I.S. 291 - BROOKLYN
Project Geographic District
32
Project Building Identifier
K291
Project School Name
I.S. 291 - BROOKLYN
Project Type
DIIT - RESOA
Project Description
FY26 RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
200000
Total Phase Actual Spending Amount
200000
Dsf Number S
DSF0001163131
32
Project Geographic District : 32 • Project Building Identifier: K291 • Project School Name: I.S. 291 - BROOKLYN
Project Geographic District
32
Project Building Identifier
K291
Project School Name
I.S. 291 - BROOKLYN
Project Type
DIIT - RESOA
Project Description
FY13 RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
180000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0000821730
32
Project Geographic District : 32 • Project Building Identifier: K291 • Project School Name: I.S. 291 - BROOKLYN
Project Geographic District
32
Project Building Identifier
K291
Project School Name
I.S. 291 - BROOKLYN
Project Type
SCA CIP
Project Description
IDA FLOOD ELIMINATION / PATH OF TRAVEL NON-IDA FLOOD ELIMINATION / IDA INTERIOR SPACES
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
7/8/2024
Project Phase Planned End Date
7/7/2026
Project Budget Amount
520744
Final Estimate Of Actual Costs Through End Of Phase Amount
364888
Total Phase Actual Spending Amount
360720
Dsf Number S
DSF0001014182, DSF0001035059, DSF0001036332
32
Project Geographic District : 32 • Project Building Identifier: K291 • Project School Name: I.S. 291 - BROOKLYN
Project Geographic District
32
Project Building Identifier
K291
Project School Name
I.S. 291 - BROOKLYN
Project Type
SCA CIP
Project Description
ROOFS / PARAPETS / EXTERIOR MASONRY
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
1097250
Final Estimate Of Actual Costs Through End Of Phase Amount
1097250
Total Phase Actual Spending Amount
86807
Dsf Number S
DSF0001064935, DSF0001120325, DSF0001120327
32
Project Geographic District : 32 • Project Building Identifier: K291 • Project School Name: I.S. 291 - BROOKLYN
Project Geographic District
32
Project Building Identifier
K291
Project School Name
I.S. 291 - BROOKLYN
Project Type
SCA CIP
Project Description
IDA FLOOD ELIMINATION / PATH OF TRAVEL NON-IDA FLOOD ELIMINATION / IDA INTERIOR SPACES
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
7/8/2024
Project Phase Planned End Date
7/7/2026
Project Budget Amount
8031738
Final Estimate Of Actual Costs Through End Of Phase Amount
7263270
Total Phase Actual Spending Amount
4488967
Dsf Number S
DSF0001014182, DSF0001035059, DSF0001036332
32
Project Geographic District : 32 • Project Building Identifier: K291 • Project School Name: I.S. 291 - BROOKLYN
Project Geographic District
32
Project Building Identifier
K291
Project School Name
I.S. 291 - BROOKLYN
Project Type
SCA CIP
Project Description
ROOFS / PARAPETS / EXTERIOR MASONRY
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
11072250
Final Estimate Of Actual Costs Through End Of Phase Amount
11072250
Total Phase Actual Spending Amount
140640
Dsf Number S
DSF0001064935, DSF0001120325, DSF0001120327
32
Project Geographic District : 32 • Project Building Identifier: K291 • Project School Name: I.S. 291 - BROOKLYN
Project Geographic District
32
Project Building Identifier
K291
Project School Name
I.S. 291 - BROOKLYN
Project Type
SCA CIP
Project Description
ROOFS / PARAPETS / EXTERIOR MASONRY
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
3/17/2025
Project Phase Planned End Date
8/15/2025
Project Phase Actual End Date
11/7/2025
Project Budget Amount
698250
Final Estimate Of Actual Costs Through End Of Phase Amount
435401
Total Phase Actual Spending Amount
415625
Dsf Number S
DSF0001064935, DSF0001120325, DSF0001120327
32
Project Geographic District : 32 • Project Building Identifier: K291 • Project School Name: I.S. 291 - BROOKLYN
Project Geographic District
32
Project Building Identifier
K291
Project School Name
I.S. 291 - BROOKLYN
Project Type
SCA CIP
Project Description
IDA FLOOD ELIMINATION / PATH OF TRAVEL NON-IDA FLOOD ELIMINATION / IDA INTERIOR SPACES
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
1/26/2023
Project Phase Planned End Date
5/25/2023
Project Phase Actual End Date
6/9/2023
Project Budget Amount
362617
Final Estimate Of Actual Costs Through End Of Phase Amount
384479
Total Phase Actual Spending Amount
378350
Dsf Number S
DSF0001014182, DSF0001035059, DSF0001036332