Capital Project Schedules and Budgets

List of capital projects with managing organization, phase status and project costs.

Housing & Development School Construction Authority (SCA) Dataset 2xh6-psuq 14 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
21
Project Geographic District : 21 • Project Building Identifier: K303 • Project School Name: R. CARSON SCL OF COASTAL ST-K
Project Geographic District
21
Project Building Identifier
K303
Project School Name
R. CARSON SCL OF COASTAL ST-K
Project Type
SCA CIP RESOA
Project Description
RESO A ROOM CONVERSIONS/PARTITIONING / PATH OF TRAVEL RESO A ROOM CONVERSIONS/PARTITIONING
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
3/23/2023
Project Phase Planned End Date
11/30/2023
Project Phase Actual End Date
10/19/2023
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
18692
Total Phase Actual Spending Amount
18692
Dsf Number S
DSF0001083692, DSF0001085815
21
Project Geographic District : 21 • Project Building Identifier: K303 • Project School Name: R. CARSON SCL OF COASTAL ST-K
Project Geographic District
21
Project Building Identifier
K303
Project School Name
R. CARSON SCL OF COASTAL ST-K
Project Type
SCA CIP RESOA
Project Description
FY24 RESO A IPDVS CAMERA INSTALLATION
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
11/2/2023
Project Phase Planned End Date
3/7/2024
Project Phase Actual End Date
11/15/2023
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
2855
Total Phase Actual Spending Amount
2855
Dsf Number S
DSF0001086076
21
Project Geographic District : 21 • Project Building Identifier: K303 • Project School Name: R. CARSON SCL OF COASTAL ST-K
Project Geographic District
21
Project Building Identifier
K303
Project School Name
R. CARSON SCL OF COASTAL ST-K
Project Type
SCA CIP RESOA
Project Description
RESO A ROOM CONVERSION / PATH OF TRAVEL RESO A ROOM CONVERSION
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
4/19/2024
Project Phase Planned End Date
12/26/2024
Project Phase Actual End Date
12/20/2024
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
40423
Total Phase Actual Spending Amount
40423
Dsf Number S
DSF0001112072, DSF0001113765
21
Project Geographic District : 21 • Project Building Identifier: K303 • Project School Name: I.S. 303 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K303
Project School Name
I.S. 303 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-ABATE AND REPLACE FLOOR TILES AHERA # 2115 - LIFTING FLOOR TILES
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
12/24/2025
Project Phase Planned End Date
IEH
Project Phase Actual End Date
5/9/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
16623
Total Phase Actual Spending Amount
1979
Dsf Number S
SCA0000075218
21
Project Geographic District : 21 • Project Building Identifier: K303 • Project School Name: I.S. 303 - BROOKLYN
Project Geographic District
21
Project Building Identifier
K303
Project School Name
I.S. 303 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-ABATE AND REPLACE 9X9 GREEN FLOOR- FLOOR TILES AHERA SPACE ID 2090E GYM OFFICE
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
2/11/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
5/9/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
14413
Total Phase Actual Spending Amount
539
Dsf Number S
SCA0000075419
16
Project Geographic District : 16 • Project Building Identifier: K304 • Project School Name: K140 SPED - BROOKLYN
Project Geographic District
16
Project Building Identifier
K304
Project School Name
K140 SPED - BROOKLYN
Project Type
Fast Track Projects
Project Description
FY26 RESO A ROOM CONVERSION
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
FTK
Project Phase Planned End Date
FTK
Project Phase Actual End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
200000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001163136
16
Project Geographic District : 16 • Project Building Identifier: K304 • Project School Name: BRIGHTER CHOICE COMMUN SCHL - K
Project Geographic District
16
Project Building Identifier
K304
Project School Name
BRIGHTER CHOICE COMMUN SCHL - K
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / FIRE ALARM SYSTEM REPLACEMENT
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
9/18/2023
Project Phase Planned End Date
9/6/2025
Project Budget Amount
1318621
Final Estimate Of Actual Costs Through End Of Phase Amount
1507638
Total Phase Actual Spending Amount
1295443
Dsf Number S
DSF0000912350, DSF0001014355
16
Project Geographic District : 16 • Project Building Identifier: K304 • Project School Name: BRIGHTER CHOICE COMMUN SCHL - K
Project Geographic District
16
Project Building Identifier
K304
Project School Name
BRIGHTER CHOICE COMMUN SCHL - K
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / FIRE ALARM SYSTEM REPLACEMENT
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
9/18/2023
Project Phase Planned End Date
9/6/2025
Project Budget Amount
15694471
Final Estimate Of Actual Costs Through End Of Phase Amount
14585765
Total Phase Actual Spending Amount
11251465
Dsf Number S
DSF0000912350, DSF0001014355
16
Project Geographic District : 16 • Project Building Identifier: K304 • Project School Name: BRIGHTER CHOICE COMMUN SCHL - K
Project Geographic District
16
Project Building Identifier
K304
Project School Name
BRIGHTER CHOICE COMMUN SCHL - K
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / FIRE ALARM SYSTEM REPLACEMENT
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
9/16/2022
Project Phase Planned End Date
3/24/2023
Project Phase Actual End Date
5/9/2023
Project Budget Amount
730453
Final Estimate Of Actual Costs Through End Of Phase Amount
500757
Total Phase Actual Spending Amount
494720
Dsf Number S
DSF0000912350, DSF0001014355
16
Project Geographic District : 16 • Project Building Identifier: K304 • Project School Name: BRIGHTER CHOICE COMMUN SCHL - K
Project Geographic District
16
Project Building Identifier
K304
Project School Name
BRIGHTER CHOICE COMMUN SCHL - K
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / FIRE ALARM SYSTEM REPLACEMENT
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
7/17/2019
Project Phase Planned End Date
12/3/2019
Project Phase Actual End Date
8/8/2022
Project Budget Amount
147804
Final Estimate Of Actual Costs Through End Of Phase Amount
142251
Total Phase Actual Spending Amount
142251
Dsf Number S
DSF0000912350, DSF0001014355
13
Project Geographic District : 13 • Project Building Identifier: K305 • Project School Name: I.S. 492- BROOKLYN
Project Geographic District
13
Project Building Identifier
K305
Project School Name
I.S. 492- BROOKLYN
Project Type
DOE - RESOA
Project Description
FY24 RESO A BATHROOM UPGRADES
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
346954
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001086077
19
Project Geographic District : 19 • Project Building Identifier: K306 • Project School Name: P.S. 306 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K306
Project School Name
P.S. 306 - BROOKLYN
Project Type
DIIT - RESOA
Project Description
FY26 RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
100000
Total Phase Actual Spending Amount
100000
Dsf Number S
DSF0001163137
19
Project Geographic District : 19 • Project Building Identifier: K306 • Project School Name: P.S. 306 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K306
Project School Name
P.S. 306 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY25 RESO A LIBRARY UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
500000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001112674
19
Project Geographic District : 19 • Project Building Identifier: K306 • Project School Name: P.S. 306 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K306
Project School Name
P.S. 306 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY22 RESO A STEM LAB
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
8/4/2023
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
174250
Total Phase Actual Spending Amount
56020
Dsf Number S
DSF0001033059
19
Project Geographic District : 19 • Project Building Identifier: K306 • Project School Name: P.S. 306 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K306
Project School Name
P.S. 306 - BROOKLYN
Project Type
DOE - Skilled Trades
Project Description
ACE BOILER BURNER CONVERSIONS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
6/30/2021
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
2393506
Total Phase Actual Spending Amount
1884308
Dsf Number S
DSF0000912463
19
Project Geographic District : 19 • Project Building Identifier: K306 • Project School Name: P.S. 306 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K306
Project School Name
P.S. 306 - BROOKLYN
Project Type
DOE - Skilled Trades
Project Description
WATER HEATERS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
4/4/2017
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
75200
Total Phase Actual Spending Amount
10056
Dsf Number S
DSF0000782639
19
Project Geographic District : 19 • Project Building Identifier: K306 • Project School Name: P.S. 306 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K306
Project School Name
P.S. 306 - BROOKLYN
Project Type
SCA CIP
Project Description
ROOFS / WINDOWS / EXTERIOR MASONRY / SITE WORK
Project Phase Name
CM,F&E
Project Status Name
Complete
Project Phase Actual Start Date
9/5/2023
Project Phase Planned End Date
9/3/2025
Project Phase Actual End Date
12/8/2025
Project Budget Amount
1001893
Final Estimate Of Actual Costs Through End Of Phase Amount
1061267
Total Phase Actual Spending Amount
1049285
Dsf Number S
DSF0001014393, DSF0001014394, DSF0001014395, DSF0001014404
19
Project Geographic District : 19 • Project Building Identifier: K306 • Project School Name: P.S. 306 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K306
Project School Name
P.S. 306 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
4/14/2025
Project Phase Planned End Date
3/9/2026
Project Budget Amount
159698
Final Estimate Of Actual Costs Through End Of Phase Amount
169791
Total Phase Actual Spending Amount
151656
Dsf Number S
DSF0001087447
19
Project Geographic District : 19 • Project Building Identifier: K306 • Project School Name: P.S. 306 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K306
Project School Name
P.S. 306 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
4/14/2025
Project Phase Planned End Date
3/9/2026
Project Budget Amount
254574
Final Estimate Of Actual Costs Through End Of Phase Amount
235228
Total Phase Actual Spending Amount
192062
Dsf Number S
DSF0001087447
19
Project Geographic District : 19 • Project Building Identifier: K306 • Project School Name: P.S. 306 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K306
Project School Name
P.S. 306 - BROOKLYN
Project Type
SCA CIP
Project Description
ROOFS / WINDOWS / EXTERIOR MASONRY / SITE WORK
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
9/5/2023
Project Phase Planned End Date
9/3/2025
Project Phase Actual End Date
12/8/2025
Project Budget Amount
15635113
Final Estimate Of Actual Costs Through End Of Phase Amount
14467183
Total Phase Actual Spending Amount
12972660
Dsf Number S
DSF0001014393, DSF0001014394, DSF0001014395, DSF0001014404
19
Project Geographic District : 19 • Project Building Identifier: K306 • Project School Name: P.S. 306 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K306
Project School Name
P.S. 306 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
4/24/2024
Project Phase Planned End Date
10/21/2024
Project Phase Actual End Date
9/11/2024
Project Budget Amount
19751
Final Estimate Of Actual Costs Through End Of Phase Amount
7167
Total Phase Actual Spending Amount
7167
Dsf Number S
DSF0001087447
19
Project Geographic District : 19 • Project Building Identifier: K306 • Project School Name: P.S. 306 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K306
Project School Name
P.S. 306 - BROOKLYN
Project Type
SCA CIP
Project Description
ROOFS / WINDOWS / EXTERIOR MASONRY / SITE WORK
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
9/27/2022
Project Phase Planned End Date
6/12/2023
Project Phase Actual End Date
4/19/2023
Project Budget Amount
702158
Final Estimate Of Actual Costs Through End Of Phase Amount
579315
Total Phase Actual Spending Amount
579315
Dsf Number S
DSF0001014393, DSF0001014394, DSF0001014395, DSF0001014404
19
Project Geographic District : 19 • Project Building Identifier: K306 • Project School Name: P.S. 306 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K306
Project School Name
P.S. 306 - BROOKLYN
Project Type
SCA CIP
Project Description
ROOFS / WINDOWS / EXTERIOR MASONRY / SITE WORK
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
6/2/2022
Project Phase Planned End Date
11/28/2022
Project Phase Actual End Date
9/23/2022
Project Budget Amount
140809
Final Estimate Of Actual Costs Through End Of Phase Amount
240482
Total Phase Actual Spending Amount
206214
Dsf Number S
DSF0001014393, DSF0001014394, DSF0001014395, DSF0001014404
19
Project Geographic District : 19 • Project Building Identifier: K306 • Project School Name: P.S. 306 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K306
Project School Name
P.S. 306 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
4/17/2024
Project Phase Planned End Date
8/16/2024
Project Phase Actual End Date
4/24/2024
Project Budget Amount
4389
Final Estimate Of Actual Costs Through End Of Phase Amount
1792
Total Phase Actual Spending Amount
1792
Dsf Number S
DSF0001087447
13
Project Geographic District : 13 • Project Building Identifier: K307 • Project School Name: P.S. 307 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K307
Project School Name
P.S. 307 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY24 RESO A PLAYGROUND UPGRADE
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
123694
Final Estimate Of Actual Costs Through End Of Phase Amount
123694
Total Phase Actual Spending Amount
66964
Dsf Number S
DSF0001086078
13
Project Geographic District : 13 • Project Building Identifier: K307 • Project School Name: P.S. 307 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K307
Project School Name
P.S. 307 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
PATH OF TRAVEL RESO A PLAYGROUND UPGRADE
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
2519
Final Estimate Of Actual Costs Through End Of Phase Amount
2519
Total Phase Actual Spending Amount
2519
Dsf Number S
DSF0001087025
13
Project Geographic District : 13 • Project Building Identifier: K307 • Project School Name: P.S. 307 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K307
Project School Name
P.S. 307 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
PATH OF TRAVEL RESO A PLAYGROUND UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
7036
Final Estimate Of Actual Costs Through End Of Phase Amount
7036
Total Phase Actual Spending Amount
357
Dsf Number S
DSF0001087025
13
Project Geographic District : 13 • Project Building Identifier: K307 • Project School Name: P.S. 307 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K307
Project School Name
P.S. 307 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY24 RESO A PLAYGROUND UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
1814174
Final Estimate Of Actual Costs Through End Of Phase Amount
1814174
Total Phase Actual Spending Amount
43038
Dsf Number S
DSF0001086078
13
Project Geographic District : 13 • Project Building Identifier: K307 • Project School Name: P.S. 307 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K307
Project School Name
P.S. 307 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY24 RESO A PLAYGROUND UPGRADE
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
7/9/2024
Project Phase Planned End Date
11/22/2024
Project Phase Actual End Date
4/8/2026
Project Budget Amount
123694
Final Estimate Of Actual Costs Through End Of Phase Amount
87053
Total Phase Actual Spending Amount
84520
Dsf Number S
DSF0001086078
13
Project Geographic District : 13 • Project Building Identifier: K307 • Project School Name: P.S. 307 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K307
Project School Name
P.S. 307 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
PATH OF TRAVEL RESO A PLAYGROUND UPGRADE
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
8/8/2024
Project Phase Planned End Date
12/12/2024
Project Phase Actual End Date
4/8/2026
Project Budget Amount
4987
Final Estimate Of Actual Costs Through End Of Phase Amount
4987
Total Phase Actual Spending Amount
4987
Dsf Number S
DSF0001087025
13
Project Geographic District : 13 • Project Building Identifier: K307 • Project School Name: P.S. 307 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K307
Project School Name
P.S. 307 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
PATH OF TRAVEL RESO A PLAYGROUND UPGRADE
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
5/15/2024
Project Phase Planned End Date
8/16/2024
Project Phase Actual End Date
7/30/2024
Project Budget Amount
8885
Final Estimate Of Actual Costs Through End Of Phase Amount
8885
Total Phase Actual Spending Amount
8885
Dsf Number S
DSF0001087025
13
Project Geographic District : 13 • Project Building Identifier: K307 • Project School Name: P.S. 307 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K307
Project School Name
P.S. 307 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY24 RESO A PLAYGROUND UPGRADE
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
12/5/2023
Project Phase Planned End Date
3/7/2024
Project Phase Actual End Date
6/27/2024
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
108690
Total Phase Actual Spending Amount
108690
Dsf Number S
DSF0001086078
13
Project Geographic District : 13 • Project Building Identifier: K307 • Project School Name: P.S. 307 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K307
Project School Name
P.S. 307 - BROOKLYN
Project Type
SCA Emergency Response
Project Description
EMERGENCY STABILIZATION
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
1/16/2019
Project Phase Planned End Date
EMER
Project Budget Amount
EMER
Final Estimate Of Actual Costs Through End Of Phase Amount
356655
Total Phase Actual Spending Amount
356655
Dsf Number S
SCA0000055865
13
Project Geographic District : 13 • Project Building Identifier: K307 • Project School Name: P.S. 307 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K307
Project School Name
P.S. 307 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-AHERA P.S RESPONSE ACTION ABATEMENT ABATE AND REPLACE/REPAIR DAMAGED MATERIALS 1017 - CRAWL SPA
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
3/11/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
5/3/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
46654
Total Phase Actual Spending Amount
2059
Dsf Number S
SCA0000075591
16
Project Geographic District : 16 • Project Building Identifier: K308 • Project School Name: P.S. 308 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K308
Project School Name
P.S. 308 - BROOKLYN
Project Type
DIIT - RESOA
Project Description
FY25 RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
Complete
Project Phase Actual Start Date
11/1/2025
Project Phase Planned End Date
DIIR
Project Phase Actual End Date
1/30/2026
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
75000
Total Phase Actual Spending Amount
75000
Dsf Number S
DSF0001112675
16
Project Geographic District : 16 • Project Building Identifier: K308 • Project School Name: P.S. 308 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K308
Project School Name
P.S. 308 - BROOKLYN
Project Type
SCA CIP
Project Description
PLAYGROUND UPGRADE
Project Phase Name
CM,F&E
Project Status Name
Complete
Project Phase Actual Start Date
9/16/2024
Project Phase Planned End Date
2/15/2026
Project Phase Actual End Date
11/17/2025
Project Budget Amount
178437
Final Estimate Of Actual Costs Through End Of Phase Amount
175497
Total Phase Actual Spending Amount
169564
Dsf Number S
DSF0001036311
16
Project Geographic District : 16 • Project Building Identifier: K308 • Project School Name: P.S. 308 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K308
Project School Name
P.S. 308 - BROOKLYN
Project Type
SCA CIP
Project Description
LOW-VOLTAGE ELECTRICAL SYSTEMS
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
4/10/2026
Project Phase Planned End Date
10/1/2027
Project Budget Amount
415910
Final Estimate Of Actual Costs Through End Of Phase Amount
40387
Total Phase Actual Spending Amount
39619
Dsf Number S
DSF0001092832
16
Project Geographic District : 16 • Project Building Identifier: K308 • Project School Name: P.S. 308 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K308
Project School Name
P.S. 308 - BROOKLYN
Project Type
SCA CIP
Project Description
PLAYGROUND UPGRADE
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
9/16/2024
Project Phase Planned End Date
2/15/2026
Project Phase Actual End Date
11/17/2025
Project Budget Amount
2867739
Final Estimate Of Actual Costs Through End Of Phase Amount
2676419
Total Phase Actual Spending Amount
2436887
Dsf Number S
DSF0001036311
16
Project Geographic District : 16 • Project Building Identifier: K308 • Project School Name: P.S. 308 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K308
Project School Name
P.S. 308 - BROOKLYN
Project Type
SCA CIP
Project Description
LOW-VOLTAGE ELECTRICAL SYSTEMS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
4/10/2026
Project Phase Planned End Date
10/1/2027
Project Budget Amount
4196910
Final Estimate Of Actual Costs Through End Of Phase Amount
3848703
Total Phase Actual Spending Amount
16518
Dsf Number S
DSF0001092832
16
Project Geographic District : 16 • Project Building Identifier: K308 • Project School Name: P.S. 308 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K308
Project School Name
P.S. 308 - BROOKLYN
Project Type
SCA CIP
Project Description
PLAYGROUND UPGRADE
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
5/30/2023
Project Phase Planned End Date
10/16/2023
Project Phase Actual End Date
2/5/2024
Project Budget Amount
127455
Final Estimate Of Actual Costs Through End Of Phase Amount
288080
Total Phase Actual Spending Amount
268324
Dsf Number S
DSF0001036311
16
Project Geographic District : 16 • Project Building Identifier: K308 • Project School Name: P.S. 308 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K308
Project School Name
P.S. 308 - BROOKLYN
Project Type
SCA CIP
Project Description
LOW-VOLTAGE ELECTRICAL SYSTEMS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
6/17/2024
Project Phase Planned End Date
12/20/2024
Project Phase Actual End Date
4/30/2025
Project Budget Amount
264670
Final Estimate Of Actual Costs Through End Of Phase Amount
229030
Total Phase Actual Spending Amount
191695
Dsf Number S
DSF0001092832
16
Project Geographic District : 16 • Project Building Identifier: K308 • Project School Name: P.S. 308 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K308
Project School Name
P.S. 308 - BROOKLYN
Project Type
SCA CIP
Project Description
LOW-VOLTAGE ELECTRICAL SYSTEMS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
1/5/2024
Project Phase Planned End Date
4/5/2024
Project Phase Actual End Date
6/5/2024
Project Budget Amount
56715
Final Estimate Of Actual Costs Through End Of Phase Amount
48807
Total Phase Actual Spending Amount
48807
Dsf Number S
DSF0001092832
16
Project Geographic District : 16 • Project Building Identifier: K308 • Project School Name: P.S. 308 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K308
Project School Name
P.S. 308 - BROOKLYN
Project Type
SCA CIP
Project Description
PLAYGROUND UPGRADE
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
11/1/2022
Project Phase Planned End Date
2/3/2023
Project Phase Actual End Date
5/15/2023
Project Budget Amount
25491
Final Estimate Of Actual Costs Through End Of Phase Amount
98752
Total Phase Actual Spending Amount
98752
Dsf Number S
DSF0001036311
16
Project Geographic District : 16 • Project Building Identifier: K308 • Project School Name: P.S. 308 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K308
Project School Name
P.S. 308 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-AHERA P.S RESPONSE ACTION DETAILED SCOPE PROVIDED IN EMAIL
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
2/18/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
4/7/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
181662
Total Phase Actual Spending Amount
812
Dsf Number S
SCA0000075450
16
Project Geographic District : 16 • Project Building Identifier: K309 • Project School Name: P.S. 309 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K309
Project School Name
P.S. 309 - BROOKLYN
Project Type
DOE - RESOA
Project Description
RESO A HYDROPONICS LAB
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
9/17/2025
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
5521
Total Phase Actual Spending Amount
495
Dsf Number S
DSF0001033540
16
Project Geographic District : 16 • Project Building Identifier: K309 • Project School Name: P.S. 309 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K309
Project School Name
P.S. 309 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY25 RESO A AUDITORIUM UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
270571
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001112676
16
Project Geographic District : 16 • Project Building Identifier: K309 • Project School Name: P.S. 309 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K309
Project School Name
P.S. 309 - BROOKLYN
Project Type
DOE - Skilled Trades
Project Description
DEP GREEN INFRASTRUCTURE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
10/6/2025
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
417368
Total Phase Actual Spending Amount
267780
Dsf Number S
DSF0000865738
16
Project Geographic District : 16 • Project Building Identifier: K309 • Project School Name: P.S. 309 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K309
Project School Name
P.S. 309 - BROOKLYN
Project Type
SCA CIP
Project Description
PARAPETS
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
299605
Final Estimate Of Actual Costs Through End Of Phase Amount
299605
Total Phase Actual Spending Amount
25607
Dsf Number S
DSF0001092864
16
Project Geographic District : 16 • Project Building Identifier: K309 • Project School Name: P.S. 309 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K309
Project School Name
P.S. 309 - BROOKLYN
Project Type
SCA CIP
Project Description
PLANYC CLIMATE CONTROL / PLANYC BOILER CONVERSION
Project Phase Name
CM,F&E
Project Status Name
Complete
Project Phase Actual Start Date
8/10/2023
Project Phase Planned End Date
8/8/2025
Project Phase Actual End Date
7/11/2025
Project Budget Amount
485170
Final Estimate Of Actual Costs Through End Of Phase Amount
850892
Total Phase Actual Spending Amount
842283
Dsf Number S
DSF0000941045, DSF0000960645
16
Project Geographic District : 16 • Project Building Identifier: K309 • Project School Name: P.S. 309 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K309
Project School Name
P.S. 309 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
6/8/2026
Project Phase Planned End Date
5/3/2027
Project Budget Amount
44899
Final Estimate Of Actual Costs Through End Of Phase Amount
21642
Total Phase Actual Spending Amount
5102
Dsf Number S
DSF0001087448