Project Geographic District
15
Project Building Identifier
K347
Project School Name
P.S. 321 - BROOKLYN
Project Description
PO18-ABATE/OPEN MARKED FLOOR TO REPAIR PIPE LOC: ROOM 3111, 3RD FL, SINGLE STALL ADULT BATHROOM 2' X
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
12/2/2025
Project Phase Planned End Date
IEH
Project Phase Actual End Date
1/27/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
38493
Total Phase Actual Spending Amount
2813
Dsf Number S
SCA0000075172