Capital Project Schedules and Budgets

List of capital projects with managing organization, phase status and project costs.

Housing & Development School Construction Authority (SCA) Dataset 2xh6-psuq 14 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
15
Project Geographic District : 15 • Project Building Identifier: K027 • Project School Name: RED HOOK NEIGHBORHOOD SCHOOL - K
Project Geographic District
15
Project Building Identifier
K027
Project School Name
RED HOOK NEIGHBORHOOD SCHOOL - K
Project Type
SCA IEH
Project Description
PO18-AHERA P.S RESPONSE ACTION ABATEMENT ABATE AND REPLACE/REPAIR DAMAGED MATERIALS CEILING PLASTER
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
4/1/2026
Project Phase Planned End Date
IEH
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
1389
Total Phase Actual Spending Amount
639
Dsf Number S
SCA0000075693
15
Project Geographic District : 15 • Project Building Identifier: K027 • Project School Name: RED HOOK NEIGHBORHOOD SCHOOL - K
Project Geographic District
15
Project Building Identifier
K027
Project School Name
RED HOOK NEIGHBORHOOD SCHOOL - K
Project Type
SCA IEH
Project Description
PO18-ABATE 9X9 FLOOR TILE MATERIALS SURROUNDING PIPE GOING IN BETWEEN FLOORS. LOCATED ON THE 3RD FL
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
2/9/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
2/18/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
17022
Total Phase Actual Spending Amount
499
Dsf Number S
SCA0000075411
15
Project Geographic District : 15 • Project Building Identifier: K029 • Project School Name: P.S. 29 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K029
Project School Name
P.S. 29 - BROOKLYN
Project Type
DOE - Lead Paint
Project Description
LEAD PAINT ABATEMENT
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
7/23/2025
Project Phase Planned End Date
DOEL
Project Budget Amount
DOEL
Final Estimate Of Actual Costs Through End Of Phase Amount
51000
Dsf Number S
NULL
15
Project Geographic District : 15 • Project Building Identifier: K029 • Project School Name: P.S. 29 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K029
Project School Name
P.S. 29 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY24 RESO A AUDITORIUM UPGRADE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
5/22/2024
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
750000
Dsf Number S
DSF0001085948
15
Project Geographic District : 15 • Project Building Identifier: K029 • Project School Name: P.S. 29 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K029
Project School Name
P.S. 29 - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / LOW VOLTAGE ELECTRICAL SYSTEMS
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
8/5/2024
Project Phase Planned End Date
8/4/2026
Project Budget Amount
1261512
Final Estimate Of Actual Costs Through End Of Phase Amount
806461
Total Phase Actual Spending Amount
708472
Dsf Number S
DSF0001034905, DSF0001060620
15
Project Geographic District : 15 • Project Building Identifier: K029 • Project School Name: P.S. 29 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K029
Project School Name
P.S. 29 - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / LOW VOLTAGE ELECTRICAL SYSTEMS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
8/5/2024
Project Phase Planned End Date
8/4/2026
Project Budget Amount
17859375
Final Estimate Of Actual Costs Through End Of Phase Amount
16287884
Total Phase Actual Spending Amount
8587841
Dsf Number S
DSF0001034905, DSF0001060620
15
Project Geographic District : 15 • Project Building Identifier: K029 • Project School Name: P.S. 29 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K029
Project School Name
P.S. 29 - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / LOW VOLTAGE ELECTRICAL SYSTEMS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
12/7/2022
Project Phase Planned End Date
5/25/2023
Project Phase Actual End Date
5/12/2023
Project Budget Amount
793750
Final Estimate Of Actual Costs Through End Of Phase Amount
725633
Total Phase Actual Spending Amount
671262
Dsf Number S
DSF0001034905, DSF0001060620
15
Project Geographic District : 15 • Project Building Identifier: K029 • Project School Name: P.S. 29 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K029
Project School Name
P.S. 29 - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / LOW VOLTAGE ELECTRICAL SYSTEMS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
5/12/2022
Project Phase Planned End Date
9/27/2022
Project Phase Actual End Date
11/14/2022
Project Budget Amount
158750
Final Estimate Of Actual Costs Through End Of Phase Amount
199388
Total Phase Actual Spending Amount
199388
Dsf Number S
DSF0001034905, DSF0001060620
15
Project Geographic District : 15 • Project Building Identifier: K029 • Project School Name: P.S. 29 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K029
Project School Name
P.S. 29 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-AHERA P.S RESPONSE ACTION ABATEMENT ABATE AND REPLACE/REPAIR DAMAGED MATERIALS ABATE PIPE INSUL
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
3/27/2026
Project Phase Planned End Date
IEH
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
1156
Total Phase Actual Spending Amount
406
Dsf Number S
SCA0000075673
15
Project Geographic District : 15 • Project Building Identifier: K029 • Project School Name: P.S. 29 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K029
Project School Name
P.S. 29 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-RESPONSE ACTION DUE TO OBSERVED DAMAGE (1000) BASEMENT HALLWAY - SOFT CONCRETE FILLER (1001) BO
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
7/29/2025
Project Phase Planned End Date
IEH
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
2310
Total Phase Actual Spending Amount
1560
Dsf Number S
SCA0000074526
15
Project Geographic District : 15 • Project Building Identifier: K029 • Project School Name: P.S. 29 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K029
Project School Name
P.S. 29 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-PLEASE FERFORM ACM TESTING ON LOOSE FLOOR TILE IN STAIRCASE H AND I , AND ROOM 500
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
12/29/2023
Project Phase Planned End Date
IEH
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
3858
Total Phase Actual Spending Amount
658
Dsf Number S
SCA0000072604
14
Project Geographic District : 14 • Project Building Identifier: K031 • Project School Name: P.S. 31 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K031
Project School Name
P.S. 31 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY24 RESO A AUDITORIUM UPGRADE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
3/2/2026
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
166175
Total Phase Actual Spending Amount
36555
Dsf Number S
DSF0001085950
14
Project Geographic District : 14 • Project Building Identifier: K031 • Project School Name: P.S. 31 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K031
Project School Name
P.S. 31 - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
9/22/2025
Project Phase Planned End Date
3/9/2028
Project Budget Amount
1119160
Final Estimate Of Actual Costs Through End Of Phase Amount
286537
Total Phase Actual Spending Amount
285835
Dsf Number S
DSF0000912347
14
Project Geographic District : 14 • Project Building Identifier: K031 • Project School Name: P.S. 31 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K031
Project School Name
P.S. 31 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
87211
Final Estimate Of Actual Costs Through End Of Phase Amount
87211
Total Phase Actual Spending Amount
2784
Dsf Number S
DSF0001087373
14
Project Geographic District : 14 • Project Building Identifier: K031 • Project School Name: P.S. 31 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K031
Project School Name
P.S. 31 - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
9/22/2025
Project Phase Planned End Date
3/9/2028
Project Budget Amount
17986500
Final Estimate Of Actual Costs Through End Of Phase Amount
16216325
Total Phase Actual Spending Amount
293149
Dsf Number S
DSF0000912347
14
Project Geographic District : 14 • Project Building Identifier: K031 • Project School Name: P.S. 31 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K031
Project School Name
P.S. 31 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
339973
Final Estimate Of Actual Costs Through End Of Phase Amount
339973
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001087373
14
Project Geographic District : 14 • Project Building Identifier: K031 • Project School Name: P.S. 31 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K031
Project School Name
P.S. 31 - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
10/30/2019
Project Phase Planned End Date
4/20/2020
Project Phase Actual End Date
5/12/2023
Project Budget Amount
799400
Final Estimate Of Actual Costs Through End Of Phase Amount
534445
Total Phase Actual Spending Amount
389200
Dsf Number S
DSF0000912347
14
Project Geographic District : 14 • Project Building Identifier: K031 • Project School Name: P.S. 31 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K031
Project School Name
P.S. 31 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
10/29/2025
Project Phase Planned End Date
4/28/2026
Project Phase Actual End Date
4/16/2026
Project Budget Amount
23650
Final Estimate Of Actual Costs Through End Of Phase Amount
20194
Total Phase Actual Spending Amount
20194
Dsf Number S
DSF0001087373
14
Project Geographic District : 14 • Project Building Identifier: K031 • Project School Name: P.S. 31 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K031
Project School Name
P.S. 31 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
10/7/2025
Project Phase Planned End Date
2/10/2026
Project Phase Actual End Date
10/29/2025
Project Budget Amount
5913
Final Estimate Of Actual Costs Through End Of Phase Amount
5049
Total Phase Actual Spending Amount
5049
Dsf Number S
DSF0001087373
14
Project Geographic District : 14 • Project Building Identifier: K031 • Project School Name: P.S. 31 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K031
Project School Name
P.S. 31 - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
5/13/2019
Project Phase Planned End Date
9/26/2019
Project Phase Actual End Date
10/1/2019
Project Budget Amount
159880
Final Estimate Of Actual Costs Through End Of Phase Amount
150589
Total Phase Actual Spending Amount
150589
Dsf Number S
DSF0000912347
14
Project Geographic District : 14 • Project Building Identifier: K031 • Project School Name: P.S. 31 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K031
Project School Name
P.S. 31 - BROOKLYN
Project Type
SCA Furniture & Equipment
Project Description
FY21 RESO A MOBILE SCIENCE LABS
Project Phase Name
F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
75000
Final Estimate Of Actual Costs Through End Of Phase Amount
75000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001008210
14
Project Geographic District : 14 • Project Building Identifier: K031 • Project School Name: P.S. 31 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K031
Project School Name
P.S. 31 - BROOKLYN
Project Type
SCA Furniture & Equipment
Project Description
FY25 RESO A MOBILE SCIENCE LABS
Project Phase Name
F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
5/7/2026
Project Budget Amount
60000
Final Estimate Of Actual Costs Through End Of Phase Amount
60000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001112534
14
Project Geographic District : 14 • Project Building Identifier: K031 • Project School Name: P.S. 31 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K031
Project School Name
P.S. 31 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-ABATE AND REPAIR CEILING IN BATHROOM 107A MEN'S BATHROOM IS SHUT DOWN AND COLLASPED CEILING
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
5/7/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
5/24/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
27280
Total Phase Actual Spending Amount
304
Dsf Number S
SCA0000075935
15
Project Geographic District : 15 • Project Building Identifier: K032 • Project School Name: P.S. 32 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K032
Project School Name
P.S. 32 - BROOKLYN
Project Type
SCA CIP
Project Description
FLOOD ELIMINATION / PARAPETS / ROOFS
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
587950
Final Estimate Of Actual Costs Through End Of Phase Amount
587950
Total Phase Actual Spending Amount
102748
Dsf Number S
DSF0001088395, DSF0001088397, DSF0001113800
15
Project Geographic District : 15 • Project Building Identifier: K032 • Project School Name: P.S. 32 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K032
Project School Name
P.S. 32 - BROOKLYN
Project Type
SCA CIP
Project Description
FLOOD ELIMINATION / PARAPETS / ROOFS
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
5932950
Final Estimate Of Actual Costs Through End Of Phase Amount
5932950
Total Phase Actual Spending Amount
132080
Dsf Number S
DSF0001088395, DSF0001088397, DSF0001113800
15
Project Geographic District : 15 • Project Building Identifier: K032 • Project School Name: P.S. 32 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K032
Project School Name
P.S. 32 - BROOKLYN
Project Type
SCA CIP
Project Description
FLOOD ELIMINATION / PARAPETS / ROOFS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
12/10/2025
Project Phase Planned End Date
5/13/2026
Project Phase Actual End Date
4/16/2026
Project Budget Amount
374151
Final Estimate Of Actual Costs Through End Of Phase Amount
323534
Total Phase Actual Spending Amount
293099
Dsf Number S
DSF0001088395, DSF0001088397, DSF0001113800
15
Project Geographic District : 15 • Project Building Identifier: K032 • Project School Name: P.S. 32 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K032
Project School Name
P.S. 32 - BROOKLYN
Project Type
SCA CIP
Project Description
FLOOD ELIMINATION / PARAPETS / ROOFS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
6/7/2024
Project Phase Planned End Date
10/24/2024
Project Phase Actual End Date
7/7/2025
Project Budget Amount
80175
Final Estimate Of Actual Costs Through End Of Phase Amount
86756
Total Phase Actual Spending Amount
86756
Dsf Number S
DSF0001088395, DSF0001088397, DSF0001113800
15
Project Geographic District : 15 • Project Building Identifier: K032 • Project School Name: P.S. 32 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K032
Project School Name
P.S. 32 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-RESPONSE ACTION NEEDED DUE TO OBSERVED DAMAGE AT LOCATIONS (3208A) PIPE SPACE IN FAN ROOM 208 -
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
8/6/2025
Project Phase Planned End Date
IEH
Project Phase Actual End Date
3/12/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
49074
Total Phase Actual Spending Amount
3090
Dsf Number S
SCA0000074600
14
Project Geographic District : 14 • Project Building Identifier: K033 • Project School Name: BROOKLYN COMMUNITY ARTS & MEDIA HIGH SCHOOL (BCAM) - K
Project Geographic District
14
Project Building Identifier
K033
Project School Name
BROOKLYN COMMUNITY ARTS & MEDIA HIGH SCHOOL (BCAM) - K
Project Type
DOE - RESOA
Project Description
FY21 RESO A BATHROOM UPGRADES
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
5/6/2022
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
185779
Total Phase Actual Spending Amount
185779
Dsf Number S
DSF0000961205
14
Project Geographic District : 14 • Project Building Identifier: K033 • Project School Name: K368 SPED - BROOKLYN
Project Geographic District
14
Project Building Identifier
K033
Project School Name
K368 SPED - BROOKLYN
Project Type
SCA CIP
Project Description
ROOFS / PARAPETS / EXTERIOR MASONRY / WINDOWS
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
12/4/2023
Project Phase Planned End Date
4/6/2027
Project Budget Amount
1428001
Final Estimate Of Actual Costs Through End Of Phase Amount
634113
Total Phase Actual Spending Amount
610046
Dsf Number S
DSF0001009995, DSF0001009996, DSF0001009997, DSF0001036324
14
Project Geographic District : 14 • Project Building Identifier: K033 • Project School Name: K368 SPED - BROOKLYN
Project Geographic District
14
Project Building Identifier
K033
Project School Name
K368 SPED - BROOKLYN
Project Type
SCA CIP
Project Description
ROOFS / PARAPETS / EXTERIOR MASONRY / WINDOWS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
12/4/2023
Project Phase Planned End Date
4/6/2027
Project Budget Amount
22950000
Final Estimate Of Actual Costs Through End Of Phase Amount
21699951
Total Phase Actual Spending Amount
17901330
Dsf Number S
DSF0001009995, DSF0001009996, DSF0001009997, DSF0001036324
14
Project Geographic District : 14 • Project Building Identifier: K033 • Project School Name: K368 SPED - BROOKLYN
Project Geographic District
14
Project Building Identifier
K033
Project School Name
K368 SPED - BROOKLYN
Project Type
SCA CIP
Project Description
ROOFS / PARAPETS / EXTERIOR MASONRY / WINDOWS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
9/28/2022
Project Phase Planned End Date
6/12/2023
Project Phase Actual End Date
4/13/2023
Project Budget Amount
1020000
Final Estimate Of Actual Costs Through End Of Phase Amount
593741
Total Phase Actual Spending Amount
593562
Dsf Number S
DSF0001009995, DSF0001009996, DSF0001009997, DSF0001036324
14
Project Geographic District : 14 • Project Building Identifier: K033 • Project School Name: K368 SPED - BROOKLYN
Project Geographic District
14
Project Building Identifier
K033
Project School Name
K368 SPED - BROOKLYN
Project Type
SCA CIP
Project Description
ROOFS / PARAPETS / EXTERIOR MASONRY / WINDOWS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
5/26/2022
Project Phase Planned End Date
11/21/2022
Project Phase Actual End Date
9/26/2022
Project Budget Amount
203999
Final Estimate Of Actual Costs Through End Of Phase Amount
290579
Total Phase Actual Spending Amount
264011
Dsf Number S
DSF0001009995, DSF0001009996, DSF0001009997, DSF0001036324
14
Project Geographic District : 14 • Project Building Identifier: K033 • Project School Name: K368 SPED - BROOKLYN
Project Geographic District
14
Project Building Identifier
K033
Project School Name
K368 SPED - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY22 RESO A GYMNASIUM UPGRADE
Project Phase Name
CM,F&E
Project Status Name
Complete
Project Phase Actual Start Date
12/5/2023
Project Phase Planned End Date
10/29/2024
Project Phase Actual End Date
1/22/2026
Project Budget Amount
44520
Final Estimate Of Actual Costs Through End Of Phase Amount
92419
Total Phase Actual Spending Amount
91662
Dsf Number S
DSF0001033076
14
Project Geographic District : 14 • Project Building Identifier: K033 • Project School Name: K368 SPED - BROOKLYN
Project Geographic District
14
Project Building Identifier
K033
Project School Name
K368 SPED - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY22 RESO A GYMNASIUM UPGRADE
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
12/5/2023
Project Phase Planned End Date
10/29/2024
Project Phase Actual End Date
1/22/2026
Project Budget Amount
652960
Final Estimate Of Actual Costs Through End Of Phase Amount
395007
Total Phase Actual Spending Amount
336976
Dsf Number S
DSF0001033076
14
Project Geographic District : 14 • Project Building Identifier: K033 • Project School Name: K368 SPED - BROOKLYN
Project Geographic District
14
Project Building Identifier
K033
Project School Name
K368 SPED - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY22 RESO A GYMNASIUM UPGRADE
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
10/17/2022
Project Phase Planned End Date
3/7/2023
Project Phase Actual End Date
3/20/2023
Project Budget Amount
44520
Final Estimate Of Actual Costs Through End Of Phase Amount
71378
Total Phase Actual Spending Amount
71378
Dsf Number S
DSF0001033076
14
Project Geographic District : 14 • Project Building Identifier: K033 • Project School Name: K368 SPED - BROOKLYN
Project Geographic District
14
Project Building Identifier
K033
Project School Name
K368 SPED - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY22 RESO A GYMNASIUM UPGRADE
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
6/10/2022
Project Phase Planned End Date
10/12/2022
Project Phase Actual End Date
10/12/2022
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
18445
Total Phase Actual Spending Amount
18445
Dsf Number S
DSF0001033076
14
Project Geographic District : 14 • Project Building Identifier: K033 • Project School Name: K368 SPED - BROOKLYN
Project Geographic District
14
Project Building Identifier
K033
Project School Name
K368 SPED - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-LOCATION 1: B2 CLASSROOM ABATE AND OPEN CEILING, REMOVE ACM PIPE IN SOFFIT, AND REMOVE FILL BET
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
3/17/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
5/9/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
8131
Total Phase Actual Spending Amount
1436
Dsf Number S
SCA0000075609
14
Project Geographic District : 14 • Project Building Identifier: K033 • Project School Name: K368 SPED - BROOKLYN
Project Geographic District
14
Project Building Identifier
K033
Project School Name
K368 SPED - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-ABATE PIPE AND FITTING INSULATION APPROX 15LFT LOCATION - BASEMENT RM#B4 & B6 AHERA 1002 & 1004
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
3/20/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
4/25/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
9999
Total Phase Actual Spending Amount
1349
Dsf Number S
SCA0000075634
14
Project Geographic District : 14 • Project Building Identifier: K034 • Project School Name: P.S. 34 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K034
Project School Name
P.S. 34 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY23 RESO A CAFETERIA UPGRADE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
4/1/2024
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
706455
Total Phase Actual Spending Amount
706455
Dsf Number S
DSF0001035385
14
Project Geographic District : 14 • Project Building Identifier: K034 • Project School Name: P.S. 34 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K034
Project School Name
P.S. 34 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY25 RESO A BATHROOM UPGRADES
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
3/2/2026
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
125000
Dsf Number S
DSF0001112535
14
Project Geographic District : 14 • Project Building Identifier: K034 • Project School Name: P.S. 34 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K034
Project School Name
P.S. 34 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
6/19/2026
Project Phase Planned End Date
5/14/2027
Project Budget Amount
43917
Final Estimate Of Actual Costs Through End Of Phase Amount
20493
Total Phase Actual Spending Amount
4312
Dsf Number S
DSF0001087374
14
Project Geographic District : 14 • Project Building Identifier: K034 • Project School Name: P.S. 34 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K034
Project School Name
P.S. 34 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
6/19/2026
Project Phase Planned End Date
5/14/2027
Project Budget Amount
171203
Final Estimate Of Actual Costs Through End Of Phase Amount
167216
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001087374
14
Project Geographic District : 14 • Project Building Identifier: K034 • Project School Name: P.S. 34 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K034
Project School Name
P.S. 34 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
10/27/2025
Project Phase Planned End Date
4/24/2026
Project Phase Actual End Date
4/15/2026
Project Budget Amount
11910
Final Estimate Of Actual Costs Through End Of Phase Amount
6781
Total Phase Actual Spending Amount
6781
Dsf Number S
DSF0001087374
14
Project Geographic District : 14 • Project Building Identifier: K034 • Project School Name: P.S. 34 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K034
Project School Name
P.S. 34 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
10/7/2025
Project Phase Planned End Date
2/10/2026
Project Phase Actual End Date
10/27/2025
Project Budget Amount
2977
Final Estimate Of Actual Costs Through End Of Phase Amount
1695
Total Phase Actual Spending Amount
1695
Dsf Number S
DSF0001087374
14
Project Geographic District : 14 • Project Building Identifier: K034 • Project School Name: P.S. 34 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K034
Project School Name
P.S. 34 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
PATH OF TRAVEL RESO A PLAYGROUND UPGRADE
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
0
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001114875
14
Project Geographic District : 14 • Project Building Identifier: K034 • Project School Name: P.S. 34 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K034
Project School Name
P.S. 34 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY26 RESO A PLAYGROUND UPGRADE
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
76200
Final Estimate Of Actual Costs Through End Of Phase Amount
76200
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001163537
14
Project Geographic District : 14 • Project Building Identifier: K034 • Project School Name: P.S. 34 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K034
Project School Name
P.S. 34 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY26 RESO A PLAYGROUND UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
1117600
Final Estimate Of Actual Costs Through End Of Phase Amount
1117600
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001163537
14
Project Geographic District : 14 • Project Building Identifier: K034 • Project School Name: P.S. 34 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K034
Project School Name
P.S. 34 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
PATH OF TRAVEL RESO A PLAYGROUND UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
0
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001114875
14
Project Geographic District : 14 • Project Building Identifier: K034 • Project School Name: P.S. 34 - BROOKLYN
Project Geographic District
14
Project Building Identifier
K034
Project School Name
P.S. 34 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY26 RESO A PLAYGROUND UPGRADE
Project Phase Name
Design
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
76200
Final Estimate Of Actual Costs Through End Of Phase Amount
75510
Total Phase Actual Spending Amount
2761
Dsf Number S
DSF0001163537