Project Geographic District
17
Project Building Identifier
K390
Project School Name
M.S. 354 - BROOKLYN
Project Description
ROOFS / PARAPETS / SECURITY LIGHTING / EXTERIOR MASONRY / FLOOD ELIMINATION / WINDOWS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
6/12/2024
Project Phase Planned End Date
11/14/2024
Project Phase Actual End Date
3/4/2025
Project Budget Amount
1715956
Final Estimate Of Actual Costs Through End Of Phase Amount
1219785
Total Phase Actual Spending Amount
921432
Dsf Number S
DSF0001065766, DSF0001065767, DSF0001111912, DSF0001093419, DSF0001093415, DSF0001112308