Project Geographic District
18
Project Building Identifier
K415
Project School Name
KURT HAHN EXPED LEARNING SCH - K
Project Type
SCA CIP RESOA
Project Description
FY24 RESO A ROOM CONVERSION / PATH OF TRAVEL RESO A ROOM CONVERSION
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
7/1/2024
Project Phase Planned End Date
11/1/2024
Project Phase Actual End Date
11/13/2024
Project Budget Amount
60456
Final Estimate Of Actual Costs Through End Of Phase Amount
77149
Total Phase Actual Spending Amount
54090
Dsf Number S
DSF0001086114, DSF0001086115, DSF0001087029, DSF0001087030