17
Project Geographic District : 17 • Project Building Identifier: K465 • Project School Name: I.S. 382 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K465
Project School Name
I.S. 382 - BROOKLYN
Project Type
SCA CIP
Project Description
PARAPET AND SIDE OF BUILDING DAMAGE @ K465 / EXTERIOR MASONRY / ROOFS / FLOOD ELIMINATION / WINDOWS / ROOFTOP MECHANICAL EQUIPMENT UPGRADE
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
1/26/2022
Project Phase Planned End Date
6/27/2022
Project Phase Actual End Date
5/11/2022
Project Budget Amount
4156723
Final Estimate Of Actual Costs Through End Of Phase Amount
2278283
Total Phase Actual Spending Amount
2106266
Dsf Number S
DSF0001015453, DSF0001015455, DSF0001015452, DSF0001015450, DSF0001087242, DSF0001121709
17
Project Geographic District : 17 • Project Building Identifier: K465 • Project School Name: I.S. 382 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K465
Project School Name
I.S. 382 - BROOKLYN
Project Type
SCA CIP
Project Description
PARAPET AND SIDE OF BUILDING DAMAGE @ K465 / EXTERIOR MASONRY / ROOFS / FLOOD ELIMINATION / WINDOWS / ROOFTOP MECHANICAL EQUIPMENT UPGRADE
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
6/25/2021
Project Phase Planned End Date
11/24/2021
Project Phase Actual End Date
1/25/2022
Project Budget Amount
832241
Final Estimate Of Actual Costs Through End Of Phase Amount
487795
Total Phase Actual Spending Amount
475635
Dsf Number S
DSF0001015453, DSF0001015455, DSF0001015452, DSF0001015450, DSF0001087242, DSF0001121709
17
Project Geographic District : 17 • Project Building Identifier: K465 • Project School Name: SCIENCE TECH & RESEARCH - K
Project Geographic District
17
Project Building Identifier
K465
Project School Name
SCIENCE TECH & RESEARCH - K
Project Type
SCA CIP RESOA
Project Description
PATH OF TRAVEL RESO A CTE ROOM UPGRADE
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
0
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001113592
17
Project Geographic District : 17 • Project Building Identifier: K465 • Project School Name: SCIENCE TECH & RESEARCH - K
Project Geographic District
17
Project Building Identifier
K465
Project School Name
SCIENCE TECH & RESEARCH - K
Project Type
SCA CIP RESOA
Project Description
PATH OF TRAVEL RESO A CTE ROOM UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
0
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001113592
17
Project Geographic District : 17 • Project Building Identifier: K465 • Project School Name: SCIENCE TECH & RESEARCH - K
Project Geographic District
17
Project Building Identifier
K465
Project School Name
SCIENCE TECH & RESEARCH - K
Project Type
SCA CIP RESOA
Project Description
PATH OF TRAVEL RESO A CTE ROOM UPGRADE
Project Phase Name
Design
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
0
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001113592
17
Project Geographic District : 17 • Project Building Identifier: K465 • Project School Name: SCIENCE TECH & RESEARCH - K
Project Geographic District
17
Project Building Identifier
K465
Project School Name
SCIENCE TECH & RESEARCH - K
Project Type
SCA CIP RESOA
Project Description
PATH OF TRAVEL RESO A CTE ROOM UPGRADE
Project Phase Name
Scope
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
0
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001113592
17
Project Geographic District : 17 • Project Building Identifier: K465 • Project School Name: I.S. 382 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K465
Project School Name
I.S. 382 - BROOKLYN
Project Type
SCA Emergency Response
Project Description
EMERGENCY STABILIZATION
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
12/1/2020
Project Phase Planned End Date
EMER
Project Budget Amount
EMER
Final Estimate Of Actual Costs Through End Of Phase Amount
1756049
Total Phase Actual Spending Amount
1585128
Dsf Number S
SCA0000068027
17
Project Geographic District : 17 • Project Building Identifier: K465 • Project School Name: HS FOR YOUTH & COMMUNITY DEV. - K
Project Geographic District
17
Project Building Identifier
K465
Project School Name
HS FOR YOUTH & COMMUNITY DEV. - K
Project Type
SCA Furniture & Equipment
Project Description
FY26 RESO A MOBILE SCIENCE LABS
Project Phase Name
F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
6/2/2026
Project Budget Amount
256000
Final Estimate Of Actual Costs Through End Of Phase Amount
256000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001163231
17
Project Geographic District : 17 • Project Building Identifier: K465 • Project School Name: I.S. 382 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K465
Project School Name
I.S. 382 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-ABATE & REPAIR CIELING PLASTER APPROX 100 SFT DAMAGED LOCATION STAIRCASE M 1ST THROUGH 4TH FLR
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
3/20/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
5/18/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
56199
Total Phase Actual Spending Amount
3131
Dsf Number S
SCA0000075635
17
Project Geographic District : 17 • Project Building Identifier: K470 • Project School Name: H.S. 745 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K470
Project School Name
H.S. 745 - BROOKLYN
Project Type
DOE - Skilled Trades
Project Description
EMERGENCY POWER FOR QUICK CONNECT PROGRAM
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
10/31/2023
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
769284
Dsf Number S
DSF0001083762
17
Project Geographic District : 17 • Project Building Identifier: K470 • Project School Name: INTERNATIONAL ARTS BUSINESS HS - K
Project Geographic District
17
Project Building Identifier
K470
Project School Name
INTERNATIONAL ARTS BUSINESS HS - K
Project Type
DOE - Skilled Trades
Project Description
STAGE RIGGING & DRAPERY
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
1/27/2020
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
407498
Total Phase Actual Spending Amount
204142
Dsf Number S
DSF0000821588
17
Project Geographic District : 17 • Project Building Identifier: K470 • Project School Name: H.S. 745 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K470
Project School Name
H.S. 745 - BROOKLYN
Project Type
DOE - Skilled Trades
Project Description
CAFETERIA SERVING LINE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
1/27/2023
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
716512
Total Phase Actual Spending Amount
625686
Dsf Number S
DSF0000960843
17
Project Geographic District : 17 • Project Building Identifier: K470 • Project School Name: H.S. 745 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K470
Project School Name
H.S. 745 - BROOKLYN
Project Type
SCA CIP
Project Description
SCIENCE LAB UPGRADES
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
588669
Final Estimate Of Actual Costs Through End Of Phase Amount
588669
Total Phase Actual Spending Amount
40499
Dsf Number S
DSF0001121753
17
Project Geographic District : 17 • Project Building Identifier: K470 • Project School Name: H.S. 745 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K470
Project School Name
H.S. 745 - BROOKLYN
Project Type
SCA CIP
Project Description
PATH OF TRAVEL SCIENCE LAB UPGRADE
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
148479
Final Estimate Of Actual Costs Through End Of Phase Amount
148479
Total Phase Actual Spending Amount
4612
Dsf Number S
DSF0001114363
17
Project Geographic District : 17 • Project Building Identifier: K470 • Project School Name: HS FOR PUBLIC SERVICE - K
Project Geographic District
17
Project Building Identifier
K470
Project School Name
HS FOR PUBLIC SERVICE - K
Project Type
SCA CIP
Project Description
FLOOD ELIMINATION
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
215194
Final Estimate Of Actual Costs Through End Of Phase Amount
215194
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001145682
17
Project Geographic District : 17 • Project Building Identifier: K470 • Project School Name: H.S. 745 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K470
Project School Name
H.S. 745 - BROOKLYN
Project Type
SCA CIP
Project Description
GYM UPGRADE
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
358291
Final Estimate Of Actual Costs Through End Of Phase Amount
358291
Total Phase Actual Spending Amount
75285
Dsf Number S
DSF0001121751
17
Project Geographic District : 17 • Project Building Identifier: K470 • Project School Name: H.S. 745 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K470
Project School Name
H.S. 745 - BROOKLYN
Project Type
SCA CIP
Project Description
GYM UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
3615483
Final Estimate Of Actual Costs Through End Of Phase Amount
3615483
Total Phase Actual Spending Amount
158902
Dsf Number S
DSF0001121751
17
Project Geographic District : 17 • Project Building Identifier: K470 • Project School Name: H.S. 745 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K470
Project School Name
H.S. 745 - BROOKLYN
Project Type
SCA CIP
Project Description
SCIENCE LAB UPGRADES
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
5940201
Final Estimate Of Actual Costs Through End Of Phase Amount
5940201
Total Phase Actual Spending Amount
5408
Dsf Number S
DSF0001121753
17
Project Geographic District : 17 • Project Building Identifier: K470 • Project School Name: H.S. 745 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K470
Project School Name
H.S. 745 - BROOKLYN
Project Type
SCA CIP
Project Description
PATH OF TRAVEL SCIENCE LAB UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
578817
Final Estimate Of Actual Costs Through End Of Phase Amount
578817
Total Phase Actual Spending Amount
417
Dsf Number S
DSF0001114363
17
Project Geographic District : 17 • Project Building Identifier: K470 • Project School Name: HS FOR PUBLIC SERVICE - K
Project Geographic District
17
Project Building Identifier
K470
Project School Name
HS FOR PUBLIC SERVICE - K
Project Type
SCA CIP
Project Description
FLOOD ELIMINATION
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
2171501
Final Estimate Of Actual Costs Through End Of Phase Amount
2171501
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001145682
17
Project Geographic District : 17 • Project Building Identifier: K470 • Project School Name: H.S. 745 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K470
Project School Name
H.S. 745 - BROOKLYN
Project Type
SCA CIP
Project Description
SCIENCE LAB UPGRADES
Project Phase Name
Design
Project Status Name
In-Progress
Project Phase Actual Start Date
11/5/2025
Project Phase Planned End Date
4/10/2026
Project Budget Amount
374607
Final Estimate Of Actual Costs Through End Of Phase Amount
374607
Total Phase Actual Spending Amount
110590
Dsf Number S
DSF0001121753
17
Project Geographic District : 17 • Project Building Identifier: K470 • Project School Name: H.S. 745 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K470
Project School Name
H.S. 745 - BROOKLYN
Project Type
SCA CIP
Project Description
GYM UPGRADE
Project Phase Name
Design
Project Status Name
In-Progress
Project Phase Actual Start Date
11/4/2025
Project Phase Planned End Date
3/25/2026
Project Budget Amount
228003
Final Estimate Of Actual Costs Through End Of Phase Amount
277286
Total Phase Actual Spending Amount
49562
Dsf Number S
DSF0001121751
17
Project Geographic District : 17 • Project Building Identifier: K470 • Project School Name: H.S. 745 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K470
Project School Name
H.S. 745 - BROOKLYN
Project Type
SCA CIP
Project Description
PATH OF TRAVEL SCIENCE LAB UPGRADE
Project Phase Name
Design
Project Status Name
In-Progress
Project Phase Actual Start Date
1/16/2026
Project Phase Planned End Date
5/26/2026
Project Budget Amount
40266
Final Estimate Of Actual Costs Through End Of Phase Amount
40266
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001114363
17
Project Geographic District : 17 • Project Building Identifier: K470 • Project School Name: HS FOR PUBLIC SERVICE - K
Project Geographic District
17
Project Building Identifier
K470
Project School Name
HS FOR PUBLIC SERVICE - K
Project Type
SCA CIP
Project Description
FLOOD ELIMINATION
Project Phase Name
Design
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
136941
Final Estimate Of Actual Costs Through End Of Phase Amount
136941
Total Phase Actual Spending Amount
3974
Dsf Number S
DSF0001145682
17
Project Geographic District : 17 • Project Building Identifier: K470 • Project School Name: H.S. 745 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K470
Project School Name
H.S. 745 - BROOKLYN
Project Type
SCA CIP
Project Description
PATH OF TRAVEL SCIENCE LAB UPGRADE
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
11/18/2025
Project Phase Planned End Date
2/23/2026
Project Phase Actual End Date
1/16/2026
Project Budget Amount
10066
Final Estimate Of Actual Costs Through End Of Phase Amount
0
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001114363
17
Project Geographic District : 17 • Project Building Identifier: K470 • Project School Name: HS FOR PUBLIC SERVICE - K
Project Geographic District
17
Project Building Identifier
K470
Project School Name
HS FOR PUBLIC SERVICE - K
Project Type
SCA CIP
Project Description
FLOOD ELIMINATION
Project Phase Name
Scope
Project Status Name
In-Progress
Project Phase Actual Start Date
5/28/2026
Project Phase Planned End Date
10/14/2026
Project Budget Amount
29345
Final Estimate Of Actual Costs Through End Of Phase Amount
52104
Total Phase Actual Spending Amount
994
Dsf Number S
DSF0001145682
17
Project Geographic District : 17 • Project Building Identifier: K470 • Project School Name: H.S. 745 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K470
Project School Name
H.S. 745 - BROOKLYN
Project Type
SCA CIP
Project Description
SCIENCE LAB UPGRADES
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
7/10/2025
Project Phase Planned End Date
10/24/2025
Project Phase Actual End Date
10/31/2025
Project Budget Amount
80273
Final Estimate Of Actual Costs Through End Of Phase Amount
76703
Total Phase Actual Spending Amount
76703
Dsf Number S
DSF0001121753
17
Project Geographic District : 17 • Project Building Identifier: K470 • Project School Name: H.S. 745 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K470
Project School Name
H.S. 745 - BROOKLYN
Project Type
SCA CIP
Project Description
GYM UPGRADE
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
5/28/2025
Project Phase Planned End Date
9/29/2025
Project Phase Actual End Date
9/19/2025
Project Budget Amount
48858
Final Estimate Of Actual Costs Through End Of Phase Amount
96959
Total Phase Actual Spending Amount
11983
Dsf Number S
DSF0001121751
17
Project Geographic District : 17 • Project Building Identifier: K470 • Project School Name: H.S. 745 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K470
Project School Name
H.S. 745 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-AHERA P.S RESPONSE ACTION DETAILED SCOPE PROVIDED IN EMAIL
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
3/2/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
5/11/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
67145
Total Phase Actual Spending Amount
1477
Dsf Number S
SCA0000075499
17
Project Geographic District : 17 • Project Building Identifier: K470 • Project School Name: H.S. 745 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K470
Project School Name
H.S. 745 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-ABATE/REPAIR PIPE INSULATIONS IN MULTIPLE LOCATIONS P.S. RESPONSE ACTION - PRIORITY 04
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
9/2/2025
Project Phase Planned End Date
IEH
Project Phase Actual End Date
3/8/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
26777
Total Phase Actual Spending Amount
26777
Dsf Number S
SCA0000074866
32
Project Geographic District : 32 • Project Building Identifier: K480 • Project School Name: THE BROOKLYN SCHOOL FOR SOCIAL JUSTICE - K
Project Geographic District
32
Project Building Identifier
K480
Project School Name
THE BROOKLYN SCHOOL FOR SOCIAL JUSTICE - K
Project Type
DIIT - RESOA
Project Description
FY20 RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
In-Progress
Project Phase Actual Start Date
3/14/2021
Project Phase Planned End Date
DIIR
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
80000
Total Phase Actual Spending Amount
80000
Dsf Number S
DSF0000913547
32
Project Geographic District : 32 • Project Building Identifier: K480 • Project School Name: THE ACADEMY OF URBAN PLANNING AND ENGINEERING - K
Project Geographic District
32
Project Building Identifier
K480
Project School Name
THE ACADEMY OF URBAN PLANNING AND ENGINEERING - K
Project Type
DOE - RESOA
Project Description
FY22 RESO A BATHROOM UPGRADE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
6/30/2023
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
178767
Total Phase Actual Spending Amount
1000
Dsf Number S
DSF0001033104
32
Project Geographic District : 32 • Project Building Identifier: K480 • Project School Name: THE ACADEMY OF URBAN PLANNING AND ENGINEERING - K
Project Geographic District
32
Project Building Identifier
K480
Project School Name
THE ACADEMY OF URBAN PLANNING AND ENGINEERING - K
Project Type
Fast Track Projects
Project Description
FY24 RESO A LSP AUDITORIUM UPGRADE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
4/20/2026
Project Phase Planned End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
349375
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001086131
32
Project Geographic District : 32 • Project Building Identifier: K480 • Project School Name: THE BROOKLYN SCHOOL FOR SOCIAL JUSTICE - K
Project Geographic District
32
Project Building Identifier
K480
Project School Name
THE BROOKLYN SCHOOL FOR SOCIAL JUSTICE - K
Project Type
SCA CIP
Project Description
WATER HEATER REPLACEMENT
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
8/11/2025
Project Phase Planned End Date
2/1/2027
Project Budget Amount
181650
Final Estimate Of Actual Costs Through End Of Phase Amount
113380
Total Phase Actual Spending Amount
113147
Dsf Number S
DSF0001066264
32
Project Geographic District : 32 • Project Building Identifier: K480 • Project School Name: THE BROOKLYN SCHOOL FOR SOCIAL JUSTICE - K
Project Geographic District
32
Project Building Identifier
K480
Project School Name
THE BROOKLYN SCHOOL FOR SOCIAL JUSTICE - K
Project Type
SCA CIP
Project Description
WATER HEATER REPLACEMENT
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
8/11/2025
Project Phase Planned End Date
2/1/2027
Project Budget Amount
2919375
Final Estimate Of Actual Costs Through End Of Phase Amount
2675143
Total Phase Actual Spending Amount
1297040
Dsf Number S
DSF0001066264
32
Project Geographic District : 32 • Project Building Identifier: K480 • Project School Name: THE BROOKLYN SCHOOL FOR SOCIAL JUSTICE - K
Project Geographic District
32
Project Building Identifier
K480
Project School Name
THE BROOKLYN SCHOOL FOR SOCIAL JUSTICE - K
Project Type
SCA CIP
Project Description
WATER HEATER REPLACEMENT
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
12/9/2024
Project Phase Planned End Date
5/12/2025
Project Phase Actual End Date
4/14/2025
Project Budget Amount
129750
Final Estimate Of Actual Costs Through End Of Phase Amount
100892
Total Phase Actual Spending Amount
73916
Dsf Number S
DSF0001066264
32
Project Geographic District : 32 • Project Building Identifier: K480 • Project School Name: THE BROOKLYN SCHOOL FOR SOCIAL JUSTICE - K
Project Geographic District
32
Project Building Identifier
K480
Project School Name
THE BROOKLYN SCHOOL FOR SOCIAL JUSTICE - K
Project Type
SCA CIP
Project Description
WATER HEATER REPLACEMENT
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
6/20/2023
Project Phase Planned End Date
9/20/2023
Project Phase Actual End Date
8/29/2023
Project Budget Amount
25950
Final Estimate Of Actual Costs Through End Of Phase Amount
21980
Total Phase Actual Spending Amount
21980
Dsf Number S
DSF0001066264
20
Project Geographic District : 20 • Project Building Identifier: K485 • Project School Name: TELECOM. ARTS & TECH. HS - K
Project Geographic District
20
Project Building Identifier
K485
Project School Name
TELECOM. ARTS & TECH. HS - K
Project Type
DOE - RESOA
Project Description
FY21 RESO A GYMNASIUM UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
1140782
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001008297
20
Project Geographic District : 20 • Project Building Identifier: K485 • Project School Name: TELECOM. ARTS & TECH. HS - K
Project Geographic District
20
Project Building Identifier
K485
Project School Name
TELECOM. ARTS & TECH. HS - K
Project Type
Fast Track Projects
Project Description
LSP REPLACE BURNER CONTROLS
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
8/15/2019
Project Phase Planned End Date
FTK
Project Phase Actual End Date
2/19/2026
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
314302
Total Phase Actual Spending Amount
299844
Dsf Number S
DSF0000896594
20
Project Geographic District : 20 • Project Building Identifier: K485 • Project School Name: TELECOM. ARTS & TECH. HS - K
Project Geographic District
20
Project Building Identifier
K485
Project School Name
TELECOM. ARTS & TECH. HS - K
Project Type
SCA CIP
Project Description
EXTERIOR MASONRY / ROOFS
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
4/20/2026
Project Phase Planned End Date
1/9/2028
Project Budget Amount
378000
Final Estimate Of Actual Costs Through End Of Phase Amount
51699
Total Phase Actual Spending Amount
47891
Dsf Number S
DSF0000896588, DSF0000960684
20
Project Geographic District : 20 • Project Building Identifier: K485 • Project School Name: TELECOM. ARTS & TECH. HS - K
Project Geographic District
20
Project Building Identifier
K485
Project School Name
TELECOM. ARTS & TECH. HS - K
Project Type
SCA CIP
Project Description
EXTERIOR MASONRY / ROOFS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
4/20/2026
Project Phase Planned End Date
1/9/2028
Project Budget Amount
6075000
Final Estimate Of Actual Costs Through End Of Phase Amount
5499499
Total Phase Actual Spending Amount
9355
Dsf Number S
DSF0000896588, DSF0000960684
20
Project Geographic District : 20 • Project Building Identifier: K485 • Project School Name: TELECOM. ARTS & TECH. HS - K
Project Geographic District
20
Project Building Identifier
K485
Project School Name
TELECOM. ARTS & TECH. HS - K
Project Type
SCA CIP
Project Description
EXTERIOR MASONRY / ROOFS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
1/14/2020
Project Phase Planned End Date
6/15/2020
Project Phase Actual End Date
5/11/2021
Project Budget Amount
270000
Final Estimate Of Actual Costs Through End Of Phase Amount
339947
Total Phase Actual Spending Amount
251254
Dsf Number S
DSF0000896588, DSF0000960684
20
Project Geographic District : 20 • Project Building Identifier: K485 • Project School Name: TELECOM. ARTS & TECH. HS - K
Project Geographic District
20
Project Building Identifier
K485
Project School Name
TELECOM. ARTS & TECH. HS - K
Project Type
SCA CIP
Project Description
EXTERIOR MASONRY / ROOFS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
5/31/2019
Project Phase Planned End Date
10/15/2019
Project Phase Actual End Date
12/13/2019
Project Budget Amount
54000
Final Estimate Of Actual Costs Through End Of Phase Amount
46139
Total Phase Actual Spending Amount
46139
Dsf Number S
DSF0000896588, DSF0000960684
20
Project Geographic District : 20 • Project Building Identifier: K485 • Project School Name: TELECOM. ARTS & TECH. HS - K
Project Geographic District
20
Project Building Identifier
K485
Project School Name
TELECOM. ARTS & TECH. HS - K
Project Type
SCA CIP RESOA
Project Description
PATH OF TRAVEL RESO A GYMNASIUM UPGRADE
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
0
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001007769
20
Project Geographic District : 20 • Project Building Identifier: K485 • Project School Name: TELECOM. ARTS & TECH. HS - K
Project Geographic District
20
Project Building Identifier
K485
Project School Name
TELECOM. ARTS & TECH. HS - K
Project Type
SCA CIP RESOA
Project Description
PATH OF TRAVEL RESO A GYMNASIUM UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
0
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001007769
20
Project Geographic District : 20 • Project Building Identifier: K485 • Project School Name: TELECOM. ARTS & TECH. HS - K
Project Geographic District
20
Project Building Identifier
K485
Project School Name
TELECOM. ARTS & TECH. HS - K
Project Type
SCA CIP RESOA
Project Description
PATH OF TRAVEL RESO A GYMNASIUM UPGRADE
Project Phase Name
Design
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
0
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001007769
20
Project Geographic District : 20 • Project Building Identifier: K485 • Project School Name: TELECOM. ARTS & TECH. HS - K
Project Geographic District
20
Project Building Identifier
K485
Project School Name
TELECOM. ARTS & TECH. HS - K
Project Type
SCA CIP RESOA
Project Description
PATH OF TRAVEL RESO A GYMNASIUM UPGRADE
Project Phase Name
Scope
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
0
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001007769
20
Project Geographic District : 20 • Project Building Identifier: K485 • Project School Name: TELECOM. ARTS & TECH. HS - K
Project Geographic District
20
Project Building Identifier
K485
Project School Name
TELECOM. ARTS & TECH. HS - K
Project Type
SCA IEH
Project Description
PO18-PERFORM ACM ABATEMENT (WALL PLASTER) 1ST FLOOR HALLWAY WALLS (SPACE ID 4000) - APPROX 20 SSQ FT
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
10/1/2025
Project Phase Planned End Date
IEH
Project Phase Actual End Date
2/14/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
28891
Total Phase Actual Spending Amount
28891
Dsf Number S
SCA0000074958
20
Project Geographic District : 20 • Project Building Identifier: K485 • Project School Name: TELECOM. ARTS & TECH. HS - K
Project Geographic District
20
Project Building Identifier
K485
Project School Name
TELECOM. ARTS & TECH. HS - K
Project Type
SCA IEH
Project Description
PO18-ABATE AND REPAIR WALL PLASTER STAIRCASES ON MULTIPLE LOCATIONS
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
8/11/2025
Project Phase Planned End Date
IEH
Project Phase Actual End Date
1/11/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
109977
Total Phase Actual Spending Amount
5458
Dsf Number S
SCA0000074645
20
Project Geographic District : 20 • Project Building Identifier: K485 • Project School Name: TELECOM. ARTS & TECH. HS - K
Project Geographic District
20
Project Building Identifier
K485
Project School Name
TELECOM. ARTS & TECH. HS - K
Project Type
SCA IEH
Project Description
PO18-AHERA P.S RESPONSE ACTION ABATE DAMAGED 3000C WALL PLASTER STAIRCASES & DAMAGED 4000A PIPE INSU
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
3/2/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
4/1/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
1185
Total Phase Actual Spending Amount
435
Dsf Number S
SCA0000075504