Project Geographic District
20
Project Building Identifier
K490
Project School Name
FORT HAMILTON HS - K
Project Description
IDA FLOOD ELIMINATION / IDA HEATING PLANT UPGRADE / IDA CLIMATE CONTROL / NON-IDA CLIMATE CONTROL / IDA INTERIOR SPACES / IDA POOL BOILER / IDA ELECTRICAL SYSTEMS / PATH OF TRAVEL IDA INTERIOR SPACES
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
3/12/2024
Project Phase Planned End Date
7/11/2024
Project Phase Actual End Date
12/3/2024
Project Budget Amount
1315153
Final Estimate Of Actual Costs Through End Of Phase Amount
1049781
Total Phase Actual Spending Amount
786689
Dsf Number S
DSF0001112070, DSF0001035203, DSF0001035204, DSF0001035205, DSF0001085125, DSF0001085126, DSF0001066333, DSF0001111805