Capital Project Schedules and Budgets

List of capital projects with managing organization, phase status and project costs.

Housing & Development School Construction Authority (SCA) Dataset 2xh6-psuq 14 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
17
Project Geographic District : 17 • Project Building Identifier: K600 • Project School Name: CLARA BARTON HS - K
Project Geographic District
17
Project Building Identifier
K600
Project School Name
CLARA BARTON HS - K
Project Type
DOE - Skilled Trades
Project Description
EMERGENCY POWER FOR QUICK CONNECT PROGRAM
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
7/24/2025
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
750069
Dsf Number S
DSF0001083751
17
Project Geographic District : 17 • Project Building Identifier: K600 • Project School Name: CLARA BARTON HS - K
Project Geographic District
17
Project Building Identifier
K600
Project School Name
CLARA BARTON HS - K
Project Type
DOE - Skilled Trades
Project Description
WATER HEATERS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
5/13/2016
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
352056
Total Phase Actual Spending Amount
352055
Dsf Number S
DSF0000783858
17
Project Geographic District : 17 • Project Building Identifier: K600 • Project School Name: CLARA BARTON HS - K
Project Geographic District
17
Project Building Identifier
K600
Project School Name
CLARA BARTON HS - K
Project Type
Fast Track Projects
Project Description
CTF ROOM CONVERSION / PATH OF TRAVEL CTF ROOM CONVERSION
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
6/30/2023
Project Phase Planned End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
1742311
Total Phase Actual Spending Amount
1707318
Dsf Number S
DSF0001034944, DSF0001034967
17
Project Geographic District : 17 • Project Building Identifier: K600 • Project School Name: CLARA BARTON HS - K
Project Geographic District
17
Project Building Identifier
K600
Project School Name
CLARA BARTON HS - K
Project Type
SCA CIP
Project Description
ROOFS / WINDOWS / PARAPETS / EXTERIOR MASONRY
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
2660240
Final Estimate Of Actual Costs Through End Of Phase Amount
2660240
Total Phase Actual Spending Amount
75721
Dsf Number S
DSF0001122097, DSF0001114441, DSF0001146049, DSF0001146050
17
Project Geographic District : 17 • Project Building Identifier: K600 • Project School Name: CLARA BARTON HS - K
Project Geographic District
17
Project Building Identifier
K600
Project School Name
CLARA BARTON HS - K
Project Type
SCA CIP
Project Description
ROOFS / WINDOWS / PARAPETS / EXTERIOR MASONRY
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
26844240
Final Estimate Of Actual Costs Through End Of Phase Amount
26844240
Total Phase Actual Spending Amount
11142
Dsf Number S
DSF0001122097, DSF0001114441, DSF0001146049, DSF0001146050
17
Project Geographic District : 17 • Project Building Identifier: K600 • Project School Name: CLARA BARTON HS - K
Project Geographic District
17
Project Building Identifier
K600
Project School Name
CLARA BARTON HS - K
Project Type
SCA CIP
Project Description
ROOFS / WINDOWS / PARAPETS / EXTERIOR MASONRY
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
11/12/2025
Project Phase Planned End Date
4/16/2026
Project Phase Actual End Date
4/15/2026
Project Budget Amount
1692880
Final Estimate Of Actual Costs Through End Of Phase Amount
375229
Total Phase Actual Spending Amount
375229
Dsf Number S
DSF0001122097, DSF0001114441, DSF0001146049, DSF0001146050
17
Project Geographic District : 17 • Project Building Identifier: K600 • Project School Name: CLARA BARTON HS - K
Project Geographic District
17
Project Building Identifier
K600
Project School Name
CLARA BARTON HS - K
Project Type
SCA CIP
Project Description
ROOFS / WINDOWS / PARAPETS / EXTERIOR MASONRY
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
6/30/2025
Project Phase Planned End Date
11/14/2025
Project Phase Actual End Date
10/16/2025
Project Budget Amount
362761
Final Estimate Of Actual Costs Through End Of Phase Amount
174238
Total Phase Actual Spending Amount
144238
Dsf Number S
DSF0001122097, DSF0001114441, DSF0001146049, DSF0001146050
17
Project Geographic District : 17 • Project Building Identifier: K600 • Project School Name: CLARA BARTON HS - K
Project Geographic District
17
Project Building Identifier
K600
Project School Name
CLARA BARTON HS - K
Project Type
SCA IEH
Project Description
PO18-ABATE APPROX. 4 LFT MARKED RED ON THE TOP PIPE INSULATION AT LOCATION LOCATION: FAN 1, REHEAT V
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
2/10/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
3/29/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
17023
Total Phase Actual Spending Amount
12273
Dsf Number S
SCA0000075417
17
Project Geographic District : 17 • Project Building Identifier: K600 • Project School Name: CLARA BARTON HS - K
Project Geographic District
17
Project Building Identifier
K600
Project School Name
CLARA BARTON HS - K
Project Type
SCA IEH
Project Description
PO18-ABATE FLOORS AT LOCATION LOCATION: ROOM 105 (SPACE ID 2105) (10+) 12 X 12 TILES WERE RIPPED WHE
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
3/3/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
4/18/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
23804
Total Phase Actual Spending Amount
2669
Dsf Number S
SCA0000075517
17
Project Geographic District : 17 • Project Building Identifier: K600 • Project School Name: CLARA BARTON HS - K
Project Geographic District
17
Project Building Identifier
K600
Project School Name
CLARA BARTON HS - K
Project Type
SCA IEH
Project Description
PO18-ABATE AND REPLACE 9X9 FLOOR TILES IN CLASSROOM B50. LOCATED IN THE BASEMENT, SPACE ID 10050A
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
6/9/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
6/25/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
6856
Total Phase Actual Spending Amount
406
Dsf Number S
SCA0000076092
14
Project Geographic District : 14 • Project Building Identifier: K610 • Project School Name: A-TECH HIGH SCHOOL - K
Project Geographic District
14
Project Building Identifier
K610
Project School Name
A-TECH HIGH SCHOOL - K
Project Type
DOE - Skilled Trades
Project Description
BATHROOM UPGRADES
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
9/20/2023
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
245705
Total Phase Actual Spending Amount
8724
Dsf Number S
DSF0001034233
14
Project Geographic District : 14 • Project Building Identifier: K610 • Project School Name: A-TECH HIGH SCHOOL - K
Project Geographic District
14
Project Building Identifier
K610
Project School Name
A-TECH HIGH SCHOOL - K
Project Type
DOE - Skilled Trades
Project Description
ACE STEAM SYSTEM OPTIMIZATION
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
10/1/2022
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
279434
Dsf Number S
DSF0001034416
14
Project Geographic District : 14 • Project Building Identifier: K610 • Project School Name: A-TECH HIGH SCHOOL - K
Project Geographic District
14
Project Building Identifier
K610
Project School Name
A-TECH HIGH SCHOOL - K
Project Type
SCA IEH
Project Description
PO18-AHERA P.S RESPONSE ACTION ABATEMENT DETAILED SCOPE
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
3/2/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
6/20/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
48935
Total Phase Actual Spending Amount
3295
Dsf Number S
SCA0000075502
13
Project Geographic District : 13 • Project Building Identifier: K611 • Project School Name: THE DOCK STREET SCHOOL FOR STEAM STUDIES - BROOKLYN
Project Geographic District
13
Project Building Identifier
K611
Project School Name
THE DOCK STREET SCHOOL FOR STEAM STUDIES - BROOKLYN
Project Type
DIIT - RESOA
Project Description
RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
175000
Total Phase Actual Spending Amount
175000
Dsf Number S
DSF0001114256
13
Project Geographic District : 13 • Project Building Identifier: K611 • Project School Name: THE DOCK STREET SCHOOL FOR STEAM STUDIES - BROOKLYN
Project Geographic District
13
Project Building Identifier
K611
Project School Name
THE DOCK STREET SCHOOL FOR STEAM STUDIES - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY24 RESO A HYDROPONICS LAB
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
8/15/2025
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
241280
Total Phase Actual Spending Amount
220514
Dsf Number S
DSF0001086143
19
Project Geographic District : 19 • Project Building Identifier: K615 • Project School Name: E NY VOC HS OF TRANSIT TECH.-K
Project Geographic District
19
Project Building Identifier
K615
Project School Name
E NY VOC HS OF TRANSIT TECH.-K
Project Type
DOE - Skilled Trades
Project Description
DEP GREEN INFRASTRUCTURE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
3/4/2022
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
631884
Total Phase Actual Spending Amount
586255
Dsf Number S
DSF0000911946
19
Project Geographic District : 19 • Project Building Identifier: K615 • Project School Name: E NY VOC HS OF TRANSIT TECH.-K
Project Geographic District
19
Project Building Identifier
K615
Project School Name
E NY VOC HS OF TRANSIT TECH.-K
Project Type
SCA CIP RESOA
Project Description
PATH OF TRAVEL RESO A ROOM CONVERSION
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
0
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001114859
19
Project Geographic District : 19 • Project Building Identifier: K615 • Project School Name: E NY VOC HS OF TRANSIT TECH.-K
Project Geographic District
19
Project Building Identifier
K615
Project School Name
E NY VOC HS OF TRANSIT TECH.-K
Project Type
SCA CIP RESOA
Project Description
FY26 RESO A ROOM CONVERSION
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
60000
Final Estimate Of Actual Costs Through End Of Phase Amount
60000
Total Phase Actual Spending Amount
1064
Dsf Number S
DSF0001163360
19
Project Geographic District : 19 • Project Building Identifier: K615 • Project School Name: E NY VOC HS OF TRANSIT TECH.-K
Project Geographic District
19
Project Building Identifier
K615
Project School Name
E NY VOC HS OF TRANSIT TECH.-K
Project Type
SCA CIP RESOA
Project Description
PATH OF TRAVEL RESO A ROOM CONVERSION
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
0
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001114859
19
Project Geographic District : 19 • Project Building Identifier: K615 • Project School Name: E NY VOC HS OF TRANSIT TECH.-K
Project Geographic District
19
Project Building Identifier
K615
Project School Name
E NY VOC HS OF TRANSIT TECH.-K
Project Type
SCA CIP RESOA
Project Description
FY26 RESO A ROOM CONVERSION
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
880000
Final Estimate Of Actual Costs Through End Of Phase Amount
880000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001163360
19
Project Geographic District : 19 • Project Building Identifier: K615 • Project School Name: E NY VOC HS OF TRANSIT TECH.-K
Project Geographic District
19
Project Building Identifier
K615
Project School Name
E NY VOC HS OF TRANSIT TECH.-K
Project Type
SCA CIP RESOA
Project Description
PATH OF TRAVEL RESO A ROOM CONVERSION
Project Phase Name
Design
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
876
Total Phase Actual Spending Amount
876
Dsf Number S
DSF0001114859
19
Project Geographic District : 19 • Project Building Identifier: K615 • Project School Name: E NY VOC HS OF TRANSIT TECH.-K
Project Geographic District
19
Project Building Identifier
K615
Project School Name
E NY VOC HS OF TRANSIT TECH.-K
Project Type
SCA CIP RESOA
Project Description
FY26 RESO A ROOM CONVERSION
Project Phase Name
Design
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
60000
Final Estimate Of Actual Costs Through End Of Phase Amount
58795
Total Phase Actual Spending Amount
4820
Dsf Number S
DSF0001163360
19
Project Geographic District : 19 • Project Building Identifier: K615 • Project School Name: E NY VOC HS OF TRANSIT TECH.-K
Project Geographic District
19
Project Building Identifier
K615
Project School Name
E NY VOC HS OF TRANSIT TECH.-K
Project Type
SCA CIP RESOA
Project Description
FY26 RESO A ROOM CONVERSION
Project Phase Name
Scope
Project Status Name
In-Progress
Project Phase Actual Start Date
4/29/2026
Project Phase Planned End Date
7/31/2026
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
1205
Total Phase Actual Spending Amount
1205
Dsf Number S
DSF0001163360
19
Project Geographic District : 19 • Project Building Identifier: K615 • Project School Name: E NY VOC HS OF TRANSIT TECH.-K
Project Geographic District
19
Project Building Identifier
K615
Project School Name
E NY VOC HS OF TRANSIT TECH.-K
Project Type
SCA CIP RESOA
Project Description
PATH OF TRAVEL RESO A ROOM CONVERSION
Project Phase Name
Scope
Project Status Name
In-Progress
Project Phase Actual Start Date
6/10/2026
Project Phase Planned End Date
9/11/2026
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
219
Total Phase Actual Spending Amount
219
Dsf Number S
DSF0001114859
19
Project Geographic District : 19 • Project Building Identifier: K615 • Project School Name: E NY VOC HS OF TRANSIT TECH.-K
Project Geographic District
19
Project Building Identifier
K615
Project School Name
E NY VOC HS OF TRANSIT TECH.-K
Project Type
SCA IEH
Project Description
PO18-ABATE PIPE INSULATION ON 4' WASTE LINE LOC: BOILER ROOM SPACE ID 1033
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
1/9/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
1/10/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
15363
Total Phase Actual Spending Amount
15363
Dsf Number S
SCA0000075279
21
Project Geographic District : 21 • Project Building Identifier: K620 • Project School Name: WILLIAM E. GRADY VOC HS - K
Project Geographic District
21
Project Building Identifier
K620
Project School Name
WILLIAM E. GRADY VOC HS - K
Project Type
DIIT - RESOA
Project Description
FY21 RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
In-Progress
Project Phase Actual Start Date
3/14/2021
Project Phase Planned End Date
DIIR
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
50000
Total Phase Actual Spending Amount
50000
Dsf Number S
DSF0001008447
21
Project Geographic District : 21 • Project Building Identifier: K620 • Project School Name: WILLIAM E. GRADY VOC HS - K
Project Geographic District
21
Project Building Identifier
K620
Project School Name
WILLIAM E. GRADY VOC HS - K
Project Type
DOE - RESOA
Project Description
FY20 RESO A ROOM RENOVATION
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
3/2/2022
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
155645
Total Phase Actual Spending Amount
40839
Dsf Number S
DSF0000913288
21
Project Geographic District : 21 • Project Building Identifier: K620 • Project School Name: WILLIAM E. GRADY VOC HS - K
Project Geographic District
21
Project Building Identifier
K620
Project School Name
WILLIAM E. GRADY VOC HS - K
Project Type
Fast Track Projects
Project Description
FY21 RESO A CTF ROOM CONVERSION
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
5/14/2024
Project Phase Planned End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
1658365
Total Phase Actual Spending Amount
1572027
Dsf Number S
DSF0001008550
21
Project Geographic District : 21 • Project Building Identifier: K620 • Project School Name: WILLIAM E. GRADY VOC HS - K
Project Geographic District
21
Project Building Identifier
K620
Project School Name
WILLIAM E. GRADY VOC HS - K
Project Type
SCA CIP
Project Description
ANSUL SYSTEM DUCTWORK
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
8/14/2023
Project Phase Planned End Date
8/12/2024
Project Budget Amount
159530
Final Estimate Of Actual Costs Through End Of Phase Amount
374266
Total Phase Actual Spending Amount
374266
Dsf Number S
DSF0000890994
21
Project Geographic District : 21 • Project Building Identifier: K620 • Project School Name: WILLIAM E. GRADY VOC HS - K
Project Geographic District
21
Project Building Identifier
K620
Project School Name
WILLIAM E. GRADY VOC HS - K
Project Type
SCA CIP
Project Description
ANSUL SYSTEM DUCTWORK
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
8/14/2023
Project Phase Planned End Date
8/12/2024
Project Budget Amount
2563875
Final Estimate Of Actual Costs Through End Of Phase Amount
2476859
Total Phase Actual Spending Amount
2237678
Dsf Number S
DSF0000890994
21
Project Geographic District : 21 • Project Building Identifier: K620 • Project School Name: WILLIAM E. GRADY VOC HS - K
Project Geographic District
21
Project Building Identifier
K620
Project School Name
WILLIAM E. GRADY VOC HS - K
Project Type
SCA CIP
Project Description
ANSUL SYSTEM DUCTWORK
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
2/4/2020
Project Phase Planned End Date
6/24/2020
Project Phase Actual End Date
8/12/2022
Project Budget Amount
113950
Final Estimate Of Actual Costs Through End Of Phase Amount
150235
Total Phase Actual Spending Amount
148574
Dsf Number S
DSF0000890994
21
Project Geographic District : 21 • Project Building Identifier: K620 • Project School Name: WILLIAM E. GRADY VOC HS - K
Project Geographic District
21
Project Building Identifier
K620
Project School Name
WILLIAM E. GRADY VOC HS - K
Project Type
SCA CIP
Project Description
ANSUL SYSTEM DUCTWORK
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
9/10/2018
Project Phase Planned End Date
1/10/2019
Project Phase Actual End Date
2/4/2020
Project Budget Amount
22790
Final Estimate Of Actual Costs Through End Of Phase Amount
26266
Total Phase Actual Spending Amount
26266
Dsf Number S
DSF0000890994
17
Project Geographic District : 17 • Project Building Identifier: K625 • Project School Name: PATHWAYS IN TECHNOLOGY EARLY COLLEGE HS - K
Project Geographic District
17
Project Building Identifier
K625
Project School Name
PATHWAYS IN TECHNOLOGY EARLY COLLEGE HS - K
Project Type
Fast Track Projects
Project Description
FY26 LSP RESO A GYMNASIUM UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
FTK
Project Phase Planned End Date
FTK
Project Phase Actual End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
360000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001163361
14
Project Geographic District : 14 • Project Building Identifier: K650 • Project School Name: WIILIAMSBURG PREP- BROOKLYN
Project Geographic District
14
Project Building Identifier
K650
Project School Name
WIILIAMSBURG PREP- BROOKLYN
Project Type
DOE - RESOA
Project Description
FY24 RESO A GYMNASIUM UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
512708
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001086144
14
Project Geographic District : 14 • Project Building Identifier: K650 • Project School Name: WILLIAMSBURG HS FOR ARCH & DES-K
Project Geographic District
14
Project Building Identifier
K650
Project School Name
WILLIAMSBURG HS FOR ARCH & DES-K
Project Type
DOE - RESOA
Project Description
FY22 RESO A ROOM CONVERSION
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
100000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001033582
14
Project Geographic District : 14 • Project Building Identifier: K650 • Project School Name: WILLIAMSBURG HS FOR ARCH & DES-K
Project Geographic District
14
Project Building Identifier
K650
Project School Name
WILLIAMSBURG HS FOR ARCH & DES-K
Project Type
DOE - RESOA
Project Description
FY21 RESO A BATHROOM UPGRADE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
11/30/2023
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
995756
Total Phase Actual Spending Amount
471205
Dsf Number S
DSF0001008216
14
Project Geographic District : 14 • Project Building Identifier: K650 • Project School Name: WILLIAMSBURG HS FOR ARCH & DES-K
Project Geographic District
14
Project Building Identifier
K650
Project School Name
WILLIAMSBURG HS FOR ARCH & DES-K
Project Type
Fast Track Projects
Project Description
FY26 LSP RESO A AUDITORIUM UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
FTK
Project Phase Planned End Date
FTK
Project Phase Actual End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
12625
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001163362
14
Project Geographic District : 14 • Project Building Identifier: K650 • Project School Name: WIILIAMSBURG PREP- BROOKLYN
Project Geographic District
14
Project Building Identifier
K650
Project School Name
WIILIAMSBURG PREP- BROOKLYN
Project Type
SCA CIP
Project Description
PARAPETS / EXTERIOR MASONRY / FLOOD ELIMINATION / WINDOWS
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
2603083
Final Estimate Of Actual Costs Through End Of Phase Amount
2603083
Total Phase Actual Spending Amount
36599
Dsf Number S
DSF0001122211, DSF0001122212, DSF0001146163, DSF0001114395
14
Project Geographic District : 14 • Project Building Identifier: K650 • Project School Name: WIILIAMSBURG PREP- BROOKLYN
Project Geographic District
14
Project Building Identifier
K650
Project School Name
WIILIAMSBURG PREP- BROOKLYN
Project Type
SCA CIP
Project Description
FIRE ALARM SYSTEM
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
7/14/2025
Project Phase Planned End Date
1/4/2027
Project Budget Amount
132213
Final Estimate Of Actual Costs Through End Of Phase Amount
266285
Total Phase Actual Spending Amount
242211
Dsf Number S
DSF0000990915
14
Project Geographic District : 14 • Project Building Identifier: K650 • Project School Name: WIILIAMSBURG PREP- BROOKLYN
Project Geographic District
14
Project Building Identifier
K650
Project School Name
WIILIAMSBURG PREP- BROOKLYN
Project Type
SCA CIP
Project Description
PARAPETS / EXTERIOR MASONRY / FLOOD ELIMINATION / WINDOWS
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
26267472
Final Estimate Of Actual Costs Through End Of Phase Amount
26267472
Total Phase Actual Spending Amount
20277
Dsf Number S
DSF0001122211, DSF0001122212, DSF0001146163, DSF0001114395
14
Project Geographic District : 14 • Project Building Identifier: K650 • Project School Name: WIILIAMSBURG PREP- BROOKLYN
Project Geographic District
14
Project Building Identifier
K650
Project School Name
WIILIAMSBURG PREP- BROOKLYN
Project Type
SCA CIP
Project Description
FIRE ALARM SYSTEM
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
7/14/2025
Project Phase Planned End Date
1/4/2027
Project Budget Amount
2124855
Final Estimate Of Actual Costs Through End Of Phase Amount
2715593
Total Phase Actual Spending Amount
1228647
Dsf Number S
DSF0000990915
14
Project Geographic District : 14 • Project Building Identifier: K650 • Project School Name: WIILIAMSBURG PREP- BROOKLYN
Project Geographic District
14
Project Building Identifier
K650
Project School Name
WIILIAMSBURG PREP- BROOKLYN
Project Type
SCA CIP
Project Description
PARAPETS / EXTERIOR MASONRY / FLOOD ELIMINATION / WINDOWS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
10/31/2025
Project Phase Planned End Date
4/7/2026
Project Phase Actual End Date
4/7/2026
Project Budget Amount
1656508
Final Estimate Of Actual Costs Through End Of Phase Amount
486957
Total Phase Actual Spending Amount
472158
Dsf Number S
DSF0001122211, DSF0001122212, DSF0001146163, DSF0001114395
14
Project Geographic District : 14 • Project Building Identifier: K650 • Project School Name: WIILIAMSBURG PREP- BROOKLYN
Project Geographic District
14
Project Building Identifier
K650
Project School Name
WIILIAMSBURG PREP- BROOKLYN
Project Type
SCA CIP
Project Description
FIRE ALARM SYSTEM
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
10/20/2022
Project Phase Planned End Date
4/26/2023
Project Phase Actual End Date
5/8/2023
Project Budget Amount
94438
Final Estimate Of Actual Costs Through End Of Phase Amount
322376
Total Phase Actual Spending Amount
174156
Dsf Number S
DSF0000990915
14
Project Geographic District : 14 • Project Building Identifier: K650 • Project School Name: WIILIAMSBURG PREP- BROOKLYN
Project Geographic District
14
Project Building Identifier
K650
Project School Name
WIILIAMSBURG PREP- BROOKLYN
Project Type
SCA CIP
Project Description
PARAPETS / EXTERIOR MASONRY / FLOOD ELIMINATION / WINDOWS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
5/20/2025
Project Phase Planned End Date
10/6/2025
Project Phase Actual End Date
9/29/2025
Project Budget Amount
354967
Final Estimate Of Actual Costs Through End Of Phase Amount
177689
Total Phase Actual Spending Amount
150651
Dsf Number S
DSF0001122211, DSF0001122212, DSF0001146163, DSF0001114395
14
Project Geographic District : 14 • Project Building Identifier: K650 • Project School Name: WIILIAMSBURG PREP- BROOKLYN
Project Geographic District
14
Project Building Identifier
K650
Project School Name
WIILIAMSBURG PREP- BROOKLYN
Project Type
SCA CIP
Project Description
FIRE ALARM SYSTEM
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
7/22/2021
Project Phase Planned End Date
10/21/2021
Project Phase Actual End Date
10/4/2022
Project Budget Amount
18888
Final Estimate Of Actual Costs Through End Of Phase Amount
64063
Total Phase Actual Spending Amount
64063
Dsf Number S
DSF0000990915
14
Project Geographic District : 14 • Project Building Identifier: K650 • Project School Name: WIILIAMSBURG PREP- BROOKLYN
Project Geographic District
14
Project Building Identifier
K650
Project School Name
WIILIAMSBURG PREP- BROOKLYN
Project Type
SCA Furniture & Equipment
Project Description
FY21 RESO A MOBILE SCIENCE LABS
Project Phase Name
F&E
Project Status Name
Complete
Project Phase Actual Start Date
12/21/2021
Project Phase Actual End Date
8/30/2022
Project Budget Amount
425000
Final Estimate Of Actual Costs Through End Of Phase Amount
425000
Total Phase Actual Spending Amount
401664
Dsf Number S
DSF0000961256
15
Project Geographic District : 15 • Project Building Identifier: K656 • Project School Name: BROOKLYN HS OF THE ARTS - BROOKLYN
Project Geographic District
15
Project Building Identifier
K656
Project School Name
BROOKLYN HS OF THE ARTS - BROOKLYN
Project Type
SCA CIP
Project Description
FLOOD ELIMINATION / WINDOWS / EXTERIOR MASONRY / ROOFS / COVID VENTILATION
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
9/12/2022
Project Phase Planned End Date
9/10/2024
Project Budget Amount
970878
Final Estimate Of Actual Costs Through End Of Phase Amount
530141
Total Phase Actual Spending Amount
516764
Dsf Number S
DSF0000942271, DSF0000942274, DSF0000942275, DSF0000942273, DSF0000990972
15
Project Geographic District : 15 • Project Building Identifier: K656 • Project School Name: BROOKLYN HS OF THE ARTS - BROOKLYN
Project Geographic District
15
Project Building Identifier
K656
Project School Name
BROOKLYN HS OF THE ARTS - BROOKLYN
Project Type
SCA CIP
Project Description
PLANYC BOILER CONVERSION / PLANYC CLIMATE CONTROL
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
6/11/2018
Project Phase Planned End Date
3/1/2020
Project Budget Amount
637617
Final Estimate Of Actual Costs Through End Of Phase Amount
1213411
Total Phase Actual Spending Amount
1183287
Dsf Number S
DSF0000798263, DSF0000784013
15
Project Geographic District : 15 • Project Building Identifier: K656 • Project School Name: BROOKLYN HS OF THE ARTS - BROOKLYN
Project Geographic District
15
Project Building Identifier
K656
Project School Name
BROOKLYN HS OF THE ARTS - BROOKLYN
Project Type
SCA CIP
Project Description
PLANYC BOILER CONVERSION / PLANYC CLIMATE CONTROL
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
6/11/2018
Project Phase Planned End Date
3/1/2020
Project Budget Amount
7101271
Final Estimate Of Actual Costs Through End Of Phase Amount
7019164
Total Phase Actual Spending Amount
5481795
Dsf Number S
DSF0000798263, DSF0000784013
15
Project Geographic District : 15 • Project Building Identifier: K656 • Project School Name: BROOKLYN HS OF THE ARTS - BROOKLYN
Project Geographic District
15
Project Building Identifier
K656
Project School Name
BROOKLYN HS OF THE ARTS - BROOKLYN
Project Type
SCA CIP
Project Description
FLOOD ELIMINATION / WINDOWS / EXTERIOR MASONRY / ROOFS / COVID VENTILATION
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
9/12/2022
Project Phase Planned End Date
9/10/2024
Project Budget Amount
13637703
Final Estimate Of Actual Costs Through End Of Phase Amount
13550051
Total Phase Actual Spending Amount
10907773
Dsf Number S
DSF0000942271, DSF0000942274, DSF0000942275, DSF0000942273, DSF0000990972