Capital Project Schedules and Budgets

List of capital projects with managing organization, phase status and project costs.

Housing & Development School Construction Authority (SCA) Dataset 2xh6-psuq 14 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
15
Project Geographic District : 15 • Project Building Identifier: K656 • Project School Name: BROOKLYN HS OF THE ARTS - BROOKLYN
Project Geographic District
15
Project Building Identifier
K656
Project School Name
BROOKLYN HS OF THE ARTS - BROOKLYN
Project Type
SCA CIP
Project Description
PLANYC BOILER CONVERSION / PLANYC CLIMATE CONTROL
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
7/20/2017
Project Phase Planned End Date
12/21/2017
Project Phase Actual End Date
1/19/2018
Project Budget Amount
426177
Final Estimate Of Actual Costs Through End Of Phase Amount
594294
Total Phase Actual Spending Amount
571008
Dsf Number S
DSF0000798263, DSF0000784013
15
Project Geographic District : 15 • Project Building Identifier: K656 • Project School Name: BROOKLYN HS OF THE ARTS - BROOKLYN
Project Geographic District
15
Project Building Identifier
K656
Project School Name
BROOKLYN HS OF THE ARTS - BROOKLYN
Project Type
SCA CIP
Project Description
FLOOD ELIMINATION / WINDOWS / EXTERIOR MASONRY / ROOFS / COVID VENTILATION
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
11/10/2021
Project Phase Planned End Date
4/15/2022
Project Phase Actual End Date
5/11/2022
Project Budget Amount
639043
Final Estimate Of Actual Costs Through End Of Phase Amount
561671
Total Phase Actual Spending Amount
537857
Dsf Number S
DSF0000942271, DSF0000942274, DSF0000942275, DSF0000942273, DSF0000990972
15
Project Geographic District : 15 • Project Building Identifier: K656 • Project School Name: BROOKLYN HS OF THE ARTS - BROOKLYN
Project Geographic District
15
Project Building Identifier
K656
Project School Name
BROOKLYN HS OF THE ARTS - BROOKLYN
Project Type
SCA CIP
Project Description
FLOOD ELIMINATION / WINDOWS / EXTERIOR MASONRY / ROOFS / COVID VENTILATION
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
1/26/2021
Project Phase Planned End Date
7/12/2021
Project Phase Actual End Date
11/3/2021
Project Budget Amount
129522
Final Estimate Of Actual Costs Through End Of Phase Amount
242032
Total Phase Actual Spending Amount
236317
Dsf Number S
DSF0000942271, DSF0000942274, DSF0000942275, DSF0000942273, DSF0000990972
15
Project Geographic District : 15 • Project Building Identifier: K656 • Project School Name: BROOKLYN HS OF THE ARTS - BROOKLYN
Project Geographic District
15
Project Building Identifier
K656
Project School Name
BROOKLYN HS OF THE ARTS - BROOKLYN
Project Type
SCA CIP
Project Description
PLANYC BOILER CONVERSION / PLANYC CLIMATE CONTROL
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
5/18/2017
Project Phase Planned End Date
10/19/2017
Project Phase Actual End Date
7/18/2017
Project Budget Amount
109022
Final Estimate Of Actual Costs Through End Of Phase Amount
185911
Total Phase Actual Spending Amount
185911
Dsf Number S
DSF0000798263, DSF0000784013
19
Project Geographic District : 19 • Project Building Identifier: K660 • Project School Name: WILLIAM MAXWELL VOC HS - K
Project Geographic District
19
Project Building Identifier
K660
Project School Name
WILLIAM MAXWELL VOC HS - K
Project Type
DOE - Skilled Trades
Project Description
FIRE PUMP SYSTEM REPLACEMENT
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
1/3/2024
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
98631
Dsf Number S
DSF0001094470
19
Project Geographic District : 19 • Project Building Identifier: K660 • Project School Name: WILLIAM MAXWELL VOC HS - K
Project Geographic District
19
Project Building Identifier
K660
Project School Name
WILLIAM MAXWELL VOC HS - K
Project Type
SCA CIP RESOA
Project Description
FY25 RESO A GYMNASIUM UPGRADE
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
4/29/2026
Project Phase Planned End Date
3/24/2027
Project Budget Amount
54000
Final Estimate Of Actual Costs Through End Of Phase Amount
66041
Total Phase Actual Spending Amount
27695
Dsf Number S
DSF0001112732
19
Project Geographic District : 19 • Project Building Identifier: K660 • Project School Name: WILLIAM MAXWELL VOC HS - K
Project Geographic District
19
Project Building Identifier
K660
Project School Name
WILLIAM MAXWELL VOC HS - K
Project Type
SCA CIP RESOA
Project Description
FY25 RESO A GYMNASIUM UPGRADE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
4/29/2026
Project Phase Planned End Date
3/24/2027
Project Budget Amount
792000
Final Estimate Of Actual Costs Through End Of Phase Amount
508729
Total Phase Actual Spending Amount
5034
Dsf Number S
DSF0001112732
19
Project Geographic District : 19 • Project Building Identifier: K660 • Project School Name: WILLIAM MAXWELL VOC HS - K
Project Geographic District
19
Project Building Identifier
K660
Project School Name
WILLIAM MAXWELL VOC HS - K
Project Type
SCA CIP RESOA
Project Description
FY25 RESO A GYMNASIUM UPGRADE
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
7/8/2025
Project Phase Planned End Date
11/21/2025
Project Phase Actual End Date
11/5/2025
Project Budget Amount
54000
Final Estimate Of Actual Costs Through End Of Phase Amount
66747
Total Phase Actual Spending Amount
53134
Dsf Number S
DSF0001112732
19
Project Geographic District : 19 • Project Building Identifier: K660 • Project School Name: WILLIAM MAXWELL VOC HS - K
Project Geographic District
19
Project Building Identifier
K660
Project School Name
WILLIAM MAXWELL VOC HS - K
Project Type
SCA CIP RESOA
Project Description
FY25 RESO A GYMNASIUM UPGRADE
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
2/11/2025
Project Phase Planned End Date
6/12/2025
Project Phase Actual End Date
6/30/2025
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
17218
Total Phase Actual Spending Amount
17218
Dsf Number S
DSF0001112732
21
Project Geographic District : 21 • Project Building Identifier: K662 • Project School Name: BROOKLYN DAILY DISCOVERY PRE-K CENTER
Project Geographic District
21
Project Building Identifier
K662
Project School Name
BROOKLYN DAILY DISCOVERY PRE-K CENTER
Project Type
SCA IEH
Project Description
PO18-AHERA P.S RESPONSE ACTION ABATEMENT SOFT CONCRETE FILLER FLOORING MATERIAL LVL 3 -SLOP SINK - 3
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
5/26/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
6/26/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
801
Total Phase Actual Spending Amount
51
Dsf Number S
SCA0000076043
19
Project Geographic District : 19 • Project Building Identifier: K667 • Project School Name: M.S. 935 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K667
Project School Name
M.S. 935 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY22 RESO A STEM LAB
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
371000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001033138
19
Project Geographic District : 19 • Project Building Identifier: K667 • Project School Name: P.S. 938 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K667
Project School Name
P.S. 938 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY25 RESO A DIGITAL SIGN
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
100000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001112733
20
Project Geographic District : 20 • Project Building Identifier: K668 • Project School Name: PRE-K CENTER @ 412 63 STREET - BROOKLYN
Project Geographic District
20
Project Building Identifier
K668
Project School Name
PRE-K CENTER @ 412 63 STREET - BROOKLYN
Project Type
PRE-K
Project Description
LEASE
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
8/11/2025
Project Phase Planned End Date
9/3/2026
Project Budget Amount
1403200
Final Estimate Of Actual Costs Through End Of Phase Amount
464810
Total Phase Actual Spending Amount
657371
Dsf Number S
DSF0000866170
20
Project Geographic District : 20 • Project Building Identifier: K668 • Project School Name: PRE-K CENTER @ 412 63 STREET - BROOKLYN
Project Geographic District
20
Project Building Identifier
K668
Project School Name
PRE-K CENTER @ 412 63 STREET - BROOKLYN
Project Type
PRE-K
Project Description
LEASE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
8/11/2025
Project Phase Planned End Date
9/3/2026
Project Budget Amount
9953950
Final Estimate Of Actual Costs Through End Of Phase Amount
9614144
Total Phase Actual Spending Amount
5051227
Dsf Number S
DSF0000866170
20
Project Geographic District : 20 • Project Building Identifier: K668 • Project School Name: PRE-K CENTER @ 412 63 STREET - BROOKLYN
Project Geographic District
20
Project Building Identifier
K668
Project School Name
PRE-K CENTER @ 412 63 STREET - BROOKLYN
Project Type
PRE-K
Project Description
LEASE
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
8/8/2017
Project Phase Planned End Date
11/22/2017
Project Phase Actual End Date
8/8/2024
Project Budget Amount
789300
Final Estimate Of Actual Costs Through End Of Phase Amount
952511
Total Phase Actual Spending Amount
799341
Dsf Number S
DSF0000866170
20
Project Geographic District : 20 • Project Building Identifier: K668 • Project School Name: PRE-K CENTER @ 412 63 STREET - BROOKLYN
Project Geographic District
20
Project Building Identifier
K668
Project School Name
PRE-K CENTER @ 412 63 STREET - BROOKLYN
Project Type
PRE-K
Project Description
LEASE
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
11/10/2016
Project Phase Planned End Date
2/22/2017
Project Phase Actual End Date
2/22/2017
Project Budget Amount
175400
Final Estimate Of Actual Costs Through End Of Phase Amount
74734
Total Phase Actual Spending Amount
74734
Dsf Number S
DSF0000866170
15
Project Geographic District : 15 • Project Building Identifier: K671 • Project School Name: P.S. 958
Project Geographic District
15
Project Building Identifier
K671
Project School Name
P.S. 958
Project Type
DOE - RESOA
Project Description
FY25 RESO A GYMNASIUM UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
75000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001112734
20
Project Geographic District : 20 • Project Building Identifier: K676 • Project School Name: THE DETECTIVE WENJIAN LIU SCHOOL OF CIVICS AND ENTREPRENEURSHIP
Project Geographic District
20
Project Building Identifier
K676
Project School Name
THE DETECTIVE WENJIAN LIU SCHOOL OF CIVICS AND ENTREPRENEURSHIP
Project Type
DIIT - RESOA
Project Description
FY26 RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
75000
Total Phase Actual Spending Amount
75000
Dsf Number S
DSF0001163363
20
Project Geographic District : 20 • Project Building Identifier: K676 • Project School Name: K372 SPED - BROOKLYN
Project Geographic District
20
Project Building Identifier
K676
Project School Name
K372 SPED - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY26 RESO A ROOM CONVERSION
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
250000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001163364
20
Project Geographic District : 20 • Project Building Identifier: K676 • Project School Name: THE DETECTIVE WENJIAN LIU SCHOOL OF CIVICS AND ENTREPRENEURSHIP
Project Geographic District
20
Project Building Identifier
K676
Project School Name
THE DETECTIVE WENJIAN LIU SCHOOL OF CIVICS AND ENTREPRENEURSHIP
Project Type
DOE - RESOA
Project Description
RESO A DIGITAL SIGN
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
100000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001114931
20
Project Geographic District : 20 • Project Building Identifier: K676 • Project School Name: THE DETECTIVE WENJIAN LIU SCHOOL OF CIVICS AND ENTREPRENEURSHIP
Project Geographic District
20
Project Building Identifier
K676
Project School Name
THE DETECTIVE WENJIAN LIU SCHOOL OF CIVICS AND ENTREPRENEURSHIP
Project Type
Fast Track Projects
Project Description
LSP RESO A AUDITORIUM UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
FTK
Project Phase Planned End Date
FTK
Project Phase Actual End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
100000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001114930
15
Project Geographic District : 15 • Project Building Identifier: K680 • Project School Name: I.S. @ 46 VERONA STREET - BROOKLYN
Project Geographic District
15
Project Building Identifier
K680
Project School Name
I.S. @ 46 VERONA STREET - BROOKLYN
Project Type
SCA Capacity
Project Description
NEW SCHOOL
Project Phase Name
CM,Art,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
2/9/2026
Project Phase Planned End Date
9/3/2027
Project Budget Amount
15545595
Final Estimate Of Actual Costs Through End Of Phase Amount
6809224
Total Phase Actual Spending Amount
725156
Dsf Number S
DSF0000843826
15
Project Geographic District : 15 • Project Building Identifier: K680 • Project School Name: I.S. @ 46 VERONA STREET - BROOKLYN
Project Geographic District
15
Project Building Identifier
K680
Project School Name
I.S. @ 46 VERONA STREET - BROOKLYN
Project Type
SCA Capacity
Project Description
NEW SCHOOL
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
2/9/2026
Project Phase Planned End Date
9/3/2027
Project Budget Amount
118468155
Final Estimate Of Actual Costs Through End Of Phase Amount
109315344
Total Phase Actual Spending Amount
1781595
Dsf Number S
DSF0000843826
15
Project Geographic District : 15 • Project Building Identifier: K680 • Project School Name: I.S. @ 46 VERONA STREET - BROOKLYN
Project Geographic District
15
Project Building Identifier
K680
Project School Name
I.S. @ 46 VERONA STREET - BROOKLYN
Project Type
SCA Capacity
Project Description
NEW SCHOOL
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
11/17/2021
Project Phase Planned End Date
5/5/2022
Project Phase Actual End Date
10/8/2024
Project Budget Amount
8576880
Final Estimate Of Actual Costs Through End Of Phase Amount
3197980
Total Phase Actual Spending Amount
2364015
Dsf Number S
DSF0000843826
15
Project Geographic District : 15 • Project Building Identifier: K680 • Project School Name: I.S. @ 46 VERONA STREET - BROOKLYN
Project Geographic District
15
Project Building Identifier
K680
Project School Name
I.S. @ 46 VERONA STREET - BROOKLYN
Project Type
SCA Capacity
Project Description
NEW SCHOOL
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
5/6/2021
Project Phase Planned End Date
9/30/2021
Project Phase Actual End Date
11/16/2021
Project Budget Amount
2144220
Final Estimate Of Actual Costs Through End Of Phase Amount
1155901
Total Phase Actual Spending Amount
1155901
Dsf Number S
DSF0000843826
15
Project Geographic District : 15 • Project Building Identifier: K680 • Project School Name: I.S. @ 46 VERONA STREET - BROOKLYN
Project Geographic District
15
Project Building Identifier
K680
Project School Name
I.S. @ 46 VERONA STREET - BROOKLYN
Project Type
SCA CIP
Project Description
DEMOLITION
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
9/23/2024
Project Phase Planned End Date
9/22/2025
Project Budget Amount
738850
Final Estimate Of Actual Costs Through End Of Phase Amount
1472326
Total Phase Actual Spending Amount
619813
Dsf Number S
DSF0000843826
15
Project Geographic District : 15 • Project Building Identifier: K680 • Project School Name: I.S. @ 46 VERONA STREET - BROOKLYN
Project Geographic District
15
Project Building Identifier
K680
Project School Name
I.S. @ 46 VERONA STREET - BROOKLYN
Project Type
SCA CIP
Project Description
DEMOLITION
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
476521
Final Estimate Of Actual Costs Through End Of Phase Amount
476521
Total Phase Actual Spending Amount
296996
Dsf Number S
DSF0000843826
15
Project Geographic District : 15 • Project Building Identifier: K680 • Project School Name: I.S. @ 46 VERONA STREET - BROOKLYN
Project Geographic District
15
Project Building Identifier
K680
Project School Name
I.S. @ 46 VERONA STREET - BROOKLYN
Project Type
SCA CIP
Project Description
DEMOLITION
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
7658377
Final Estimate Of Actual Costs Through End Of Phase Amount
7658377
Total Phase Actual Spending Amount
368466
Dsf Number S
DSF0000843826
15
Project Geographic District : 15 • Project Building Identifier: K680 • Project School Name: I.S. @ 46 VERONA STREET - BROOKLYN
Project Geographic District
15
Project Building Identifier
K680
Project School Name
I.S. @ 46 VERONA STREET - BROOKLYN
Project Type
SCA CIP
Project Description
DEMOLITION
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
9/23/2024
Project Phase Planned End Date
9/22/2025
Project Budget Amount
11874375
Final Estimate Of Actual Costs Through End Of Phase Amount
22808076
Total Phase Actual Spending Amount
2728789
Dsf Number S
DSF0000843826
15
Project Geographic District : 15 • Project Building Identifier: K680 • Project School Name: I.S. @ 46 VERONA STREET - BROOKLYN
Project Geographic District
15
Project Building Identifier
K680
Project School Name
I.S. @ 46 VERONA STREET - BROOKLYN
Project Type
SCA CIP
Project Description
DEMOLITION
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
9/13/2022
Project Phase Planned End Date
4/18/2023
Project Phase Actual End Date
7/14/2023
Project Budget Amount
340372
Final Estimate Of Actual Costs Through End Of Phase Amount
160984
Total Phase Actual Spending Amount
160984
Dsf Number S
DSF0000843826
15
Project Geographic District : 15 • Project Building Identifier: K680 • Project School Name: I.S. @ 46 VERONA STREET - BROOKLYN
Project Geographic District
15
Project Building Identifier
K680
Project School Name
I.S. @ 46 VERONA STREET - BROOKLYN
Project Type
SCA CIP
Project Description
DEMOLITION
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
7/1/2022
Project Phase Planned End Date
11/30/2022
Project Phase Actual End Date
12/19/2022
Project Budget Amount
527750
Final Estimate Of Actual Costs Through End Of Phase Amount
335178
Total Phase Actual Spending Amount
232868
Dsf Number S
DSF0000843826
15
Project Geographic District : 15 • Project Building Identifier: K680 • Project School Name: I.S. @ 46 VERONA STREET - BROOKLYN
Project Geographic District
15
Project Building Identifier
K680
Project School Name
I.S. @ 46 VERONA STREET - BROOKLYN
Project Type
SCA CIP
Project Description
DEMOLITION
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
7/1/2022
Project Phase Planned End Date
8/29/2022
Project Phase Actual End Date
7/1/2022
Project Budget Amount
105550
Final Estimate Of Actual Costs Through End Of Phase Amount
62238
Total Phase Actual Spending Amount
62238
Dsf Number S
DSF0000843826
15
Project Geographic District : 15 • Project Building Identifier: K680 • Project School Name: I.S. @ 46 VERONA STREET - BROOKLYN
Project Geographic District
15
Project Building Identifier
K680
Project School Name
I.S. @ 46 VERONA STREET - BROOKLYN
Project Type
SCA CIP
Project Description
DEMOLITION
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
9/13/2022
Project Phase Planned End Date
9/13/2022
Project Phase Actual End Date
9/13/2022
Project Budget Amount
68074
Final Estimate Of Actual Costs Through End Of Phase Amount
61425
Total Phase Actual Spending Amount
61425
Dsf Number S
DSF0000843826
15
Project Geographic District : 15 • Project Building Identifier: K682 • Project School Name: P.S. 896 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K682
Project School Name
P.S. 896 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY21 RESO A HYDROPONICS LAB
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
111480
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001008257
22
Project Geographic District : 22 • Project Building Identifier: K705 • Project School Name: MIDWOOD HS - BROOKLYN
Project Geographic District
22
Project Building Identifier
K705
Project School Name
MIDWOOD HS - BROOKLYN
Project Type
SCA CIP
Project Description
ROOFS
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
22437
Final Estimate Of Actual Costs Through End Of Phase Amount
22437
Total Phase Actual Spending Amount
22437
Dsf Number S
DSF0001066857
22
Project Geographic District : 22 • Project Building Identifier: K705 • Project School Name: MIDWOOD HS - BROOKLYN
Project Geographic District
22
Project Building Identifier
K705
Project School Name
MIDWOOD HS - BROOKLYN
Project Type
SCA CIP
Project Description
ROOFS
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
4803
Final Estimate Of Actual Costs Through End Of Phase Amount
4803
Total Phase Actual Spending Amount
4303
Dsf Number S
DSF0001066857
22
Project Geographic District : 22 • Project Building Identifier: K705 • Project School Name: MIDWOOD HS - BROOKLYN
Project Geographic District
22
Project Building Identifier
K705
Project School Name
MIDWOOD HS - BROOKLYN
Project Type
SCA CIP
Project Description
ROOFS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
1/8/2025
Project Phase Planned End Date
6/10/2025
Project Phase Actual End Date
4/11/2025
Project Budget Amount
107612
Final Estimate Of Actual Costs Through End Of Phase Amount
107612
Total Phase Actual Spending Amount
104774
Dsf Number S
DSF0001066857
22
Project Geographic District : 22 • Project Building Identifier: K705 • Project School Name: MIDWOOD HS - BROOKLYN
Project Geographic District
22
Project Building Identifier
K705
Project School Name
MIDWOOD HS - BROOKLYN
Project Type
SCA CIP
Project Description
ROOFS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
8/20/2024
Project Phase Planned End Date
1/8/2025
Project Phase Actual End Date
12/13/2024
Project Budget Amount
44256
Final Estimate Of Actual Costs Through End Of Phase Amount
44256
Total Phase Actual Spending Amount
40599
Dsf Number S
DSF0001066857
21
Project Geographic District : 21 • Project Building Identifier: K721 • Project School Name: BKLYN STUDIO SEC. SCL - BROOKLYN
Project Geographic District
21
Project Building Identifier
K721
Project School Name
BKLYN STUDIO SEC. SCL - BROOKLYN
Project Type
DIIT - RESOA
Project Description
FY26 RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
250000
Total Phase Actual Spending Amount
250000
Dsf Number S
DSF0001163365
21
Project Geographic District : 21 • Project Building Identifier: K721 • Project School Name: BKLYN STUDIO SEC. SCL - BROOKLYN
Project Geographic District
21
Project Building Identifier
K721
Project School Name
BKLYN STUDIO SEC. SCL - BROOKLYN
Project Type
Fast Track Projects
Project Description
FY23 RESO A LSP GYMNASIUM UPGRADE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
11/12/2025
Project Phase Planned End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
205475
Total Phase Actual Spending Amount
8564
Dsf Number S
DSF0001035586
21
Project Geographic District : 21 • Project Building Identifier: K721 • Project School Name: BKLYN STUDIO SEC. SCL - BROOKLYN
Project Geographic District
21
Project Building Identifier
K721
Project School Name
BKLYN STUDIO SEC. SCL - BROOKLYN
Project Type
Fast Track Projects
Project Description
FY25 RESO A LSP ROOM CONVERSION
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
11/12/2025
Project Phase Planned End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
72935
Total Phase Actual Spending Amount
1712
Dsf Number S
DSF0001112735
21
Project Geographic District : 21 • Project Building Identifier: K721 • Project School Name: BKLYN STUDIO SEC. SCL - BROOKLYN
Project Geographic District
21
Project Building Identifier
K721
Project School Name
BKLYN STUDIO SEC. SCL - BROOKLYN
Project Type
Fast Track Projects
Project Description
FY25 RESO A ROOM CONVERSION
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
FTK
Project Phase Planned End Date
FTK
Project Phase Actual End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
150
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001112736
21
Project Geographic District : 21 • Project Building Identifier: K721 • Project School Name: BKLYN STUDIO SEC. SCL - BROOKLYN
Project Geographic District
21
Project Building Identifier
K721
Project School Name
BKLYN STUDIO SEC. SCL - BROOKLYN
Project Type
SCA CIP
Project Description
FLOOD ELIMINATION / EXTERIOR MASONRY / PATH OF TRAVEL FLOOD ELIMINATION / PARAPETS
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
886771
Final Estimate Of Actual Costs Through End Of Phase Amount
886771
Total Phase Actual Spending Amount
60459
Dsf Number S
DSF0001094567, DSF0001094570, DSF0001114179, DSF0001146322
21
Project Geographic District : 21 • Project Building Identifier: K721 • Project School Name: BKLYN STUDIO SEC. SCL - BROOKLYN
Project Geographic District
21
Project Building Identifier
K721
Project School Name
BKLYN STUDIO SEC. SCL - BROOKLYN
Project Type
SCA CIP
Project Description
FLOOD ELIMINATION / EXTERIOR MASONRY / PATH OF TRAVEL FLOOD ELIMINATION / PARAPETS
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
8001554
Final Estimate Of Actual Costs Through End Of Phase Amount
8001554
Total Phase Actual Spending Amount
24590
Dsf Number S
DSF0001094567, DSF0001094570, DSF0001114179, DSF0001146322
21
Project Geographic District : 21 • Project Building Identifier: K721 • Project School Name: BKLYN STUDIO SEC. SCL - BROOKLYN
Project Geographic District
21
Project Building Identifier
K721
Project School Name
BKLYN STUDIO SEC. SCL - BROOKLYN
Project Type
SCA CIP
Project Description
FLOOD ELIMINATION / EXTERIOR MASONRY / PATH OF TRAVEL FLOOD ELIMINATION / PARAPETS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
1/5/2026
Project Phase Planned End Date
6/5/2026
Project Phase Actual End Date
4/15/2026
Project Budget Amount
508478
Final Estimate Of Actual Costs Through End Of Phase Amount
292655
Total Phase Actual Spending Amount
274941
Dsf Number S
DSF0001094567, DSF0001094570, DSF0001114179, DSF0001146322
21
Project Geographic District : 21 • Project Building Identifier: K721 • Project School Name: BKLYN STUDIO SEC. SCL - BROOKLYN
Project Geographic District
21
Project Building Identifier
K721
Project School Name
BKLYN STUDIO SEC. SCL - BROOKLYN
Project Type
SCA CIP
Project Description
FLOOD ELIMINATION / EXTERIOR MASONRY / PATH OF TRAVEL FLOOD ELIMINATION / PARAPETS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
5/15/2024
Project Phase Planned End Date
9/3/2025
Project Phase Actual End Date
7/9/2025
Project Budget Amount
110440
Final Estimate Of Actual Costs Through End Of Phase Amount
190117
Total Phase Actual Spending Amount
180242
Dsf Number S
DSF0001094567, DSF0001094570, DSF0001114179, DSF0001146322
21
Project Geographic District : 21 • Project Building Identifier: K722 • Project School Name: K721 SPED - BROOKLYN
Project Geographic District
21
Project Building Identifier
K722
Project School Name
K721 SPED - BROOKLYN
Project Type
DIIT - RESOA
Project Description
FY22 RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
75000
Total Phase Actual Spending Amount
75000
Dsf Number S
DSF0001033604
21
Project Geographic District : 21 • Project Building Identifier: K722 • Project School Name: K721 SPED - BROOKLYN
Project Geographic District
21
Project Building Identifier
K722
Project School Name
K721 SPED - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY20 RESO A HYDROPONICS LAB
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
4/26/2021
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
170519
Total Phase Actual Spending Amount
164786
Dsf Number S
DSF0000913290
21
Project Geographic District : 21 • Project Building Identifier: K722 • Project School Name: K721 SPED - BROOKLYN
Project Geographic District
21
Project Building Identifier
K722
Project School Name
K721 SPED - BROOKLYN
Project Type
Fast Track Projects
Project Description
FY26 RESO A STEM LAB
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
FTK
Project Phase Planned End Date
FTK
Project Phase Actual End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
160000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001163366
21
Project Geographic District : 21 • Project Building Identifier: K722 • Project School Name: K721 SPED - BROOKLYN
Project Geographic District
21
Project Building Identifier
K722
Project School Name
K721 SPED - BROOKLYN
Project Type
SCA CIP
Project Description
EXTERIOR MASONRY / FLOOD ELIMINATION / ROOFS
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
10/4/2023
Project Phase Planned End Date
10/2/2025
Project Budget Amount
387585
Final Estimate Of Actual Costs Through End Of Phase Amount
833998
Total Phase Actual Spending Amount
822553
Dsf Number S
DSF0000874161, DSF0001032952, DSF0001032951