Project Geographic District
13
Project Building Identifier
K743
Project School Name
ADULT AND CONTINUING EDUCATION
Project Description
EXTERIOR MASONRY / LOW VOLTAGE ELECTRICAL SYSTEMS / VENTILATION / ROOFS / WINDOWS / PARAPETS / FLOOD ELIMINATION
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
3/13/2017
Project Phase Planned End Date
8/10/2017
Project Phase Actual End Date
5/18/2018
Project Budget Amount
698119
Final Estimate Of Actual Costs Through End Of Phase Amount
828544
Total Phase Actual Spending Amount
804855
Dsf Number S
DSF0000843680, DSF0000851506, DSF0000851523, DSF0000851509, DSF0000851510, DSF0000866095, DSF0000851507