Capital Project Schedules and Budgets

List of capital projects with managing organization, phase status and project costs.

Housing & Development School Construction Authority (SCA) Dataset 2xh6-psuq 14 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
2
Project Geographic District : 2 • Project Building Identifier: M017 • Project School Name: P.S. 212 - MANHATTAN
Project Geographic District
2
Project Building Identifier
M017
Project School Name
P.S. 212 - MANHATTAN
Project Type
SCA IEH
Project Description
PO18-AHERA P.S RESPONSE ACTION ABATEMENT 4312A - CLOSET IN CLASSROOM #312 - CEILING PLASTER LVL 4 RO
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
4/21/2026
Project Phase Planned End Date
IEH
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
851
Total Phase Actual Spending Amount
101
Dsf Number S
SCA0000075824
2
Project Geographic District : 2 • Project Building Identifier: M017 • Project School Name: P.S. 212 - MANHATTAN
Project Geographic District
2
Project Building Identifier
M017
Project School Name
P.S. 212 - MANHATTAN
Project Type
SCA IEH
Project Description
PO18-/ABATE WALL PLASTER RM 470A (TEACHERS BATHROOM) (SPACE ID# 5470A)
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
5/29/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
6/7/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
19248
Total Phase Actual Spending Amount
1309
Dsf Number S
SCA0000076063
2
Project Geographic District : 2 • Project Building Identifier: M017 • Project School Name: P.S. 212 - MANHATTAN
Project Geographic District
2
Project Building Identifier
M017
Project School Name
P.S. 212 - MANHATTAN
Project Type
SCA IEH
Project Description
PO18-ABATE AND REPLACE FLOOR TILES 5TH FL HALLWAY (SPACE ID# 6000B) REPLACE APPROXIMATELY 100 SQ FT
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
2/13/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
3/23/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
14853
Total Phase Actual Spending Amount
83
Dsf Number S
SCA0000075432
2
Project Geographic District : 2 • Project Building Identifier: M017 • Project School Name: P.S. 212 - MANHATTAN
Project Geographic District
2
Project Building Identifier
M017
Project School Name
P.S. 212 - MANHATTAN
Project Type
SCA IEH
Project Description
PO18-ABATE AND REPLACE 9X9 FLOOR TILES IN THE LIBRARY LOCATED IN THE 3RD FLOOR. IT IS 1320 SQUARE
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
2/5/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
3/19/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
70062
Total Phase Actual Spending Amount
0
Dsf Number S
SCA0000075385
2
Project Geographic District : 2 • Project Building Identifier: M017 • Project School Name: P.S. 212 - MANHATTAN
Project Geographic District
2
Project Building Identifier
M017
Project School Name
P.S. 212 - MANHATTAN
Project Type
SCA IEH
Project Description
PO18-ABATE PIPE INSULATION IN BASEMENT HALLWAY & STORAGE RM TO REPAIR A LEAKING PIPE IN RADIATOR BAS
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
2/4/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
2/14/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
15776
Total Phase Actual Spending Amount
15776
Dsf Number S
SCA0000075379
2
Project Geographic District : 2 • Project Building Identifier: M017 • Project School Name: P.S. 212 - MANHATTAN
Project Geographic District
2
Project Building Identifier
M017
Project School Name
P.S. 212 - MANHATTAN
Project Type
SCA IEH
Project Description
PO18-ABATE WALL IN WEST SIDE HALLWAY ( BASEMENT) TO DRILL HOLES TO REPLACED THE COMMUNICATION CABLE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
10/6/2025
Project Phase Planned End Date
IEH
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
859
Total Phase Actual Spending Amount
109
Dsf Number S
SCA0000075013
2
Project Geographic District : 2 • Project Building Identifier: M017 • Project School Name: P.S. 212 - MANHATTAN
Project Geographic District
2
Project Building Identifier
M017
Project School Name
P.S. 212 - MANHATTAN
Project Type
SCA IEH
Project Description
PO18-ABATE PIPE INSULATION THAT IS DAMAGE ON THE WEST END OF BASEMENT HALLWAY. SPACE ID# 1000A
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
9/11/2025
Project Phase Planned End Date
IEH
Project Phase Actual End Date
3/23/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
12286
Total Phase Actual Spending Amount
0
Dsf Number S
SCA0000074911
1
Project Geographic District : 1 • Project Building Identifier: M019 • Project School Name: P.S. 315 - MANHATTAN
Project Geographic District
1
Project Building Identifier
M019
Project School Name
P.S. 315 - MANHATTAN
Project Type
DOE - RESOA
Project Description
FY24 RESO A GYMNASIUM UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
65000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001086175
1
Project Geographic District : 1 • Project Building Identifier: M019 • Project School Name: P.S. 19 - MANHATTAN
Project Geographic District
1
Project Building Identifier
M019
Project School Name
P.S. 19 - MANHATTAN
Project Type
SCA CIP
Project Description
PLANYC BOILER CONVERSION / PLANYC CLIMATE CONTROL
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
7/18/2022
Project Phase Planned End Date
7/16/2024
Project Budget Amount
480620
Final Estimate Of Actual Costs Through End Of Phase Amount
390306
Total Phase Actual Spending Amount
385807
Dsf Number S
DSF0001008800, DSF0000991942
1
Project Geographic District : 1 • Project Building Identifier: M019 • Project School Name: P.S. 19 - MANHATTAN
Project Geographic District
1
Project Building Identifier
M019
Project School Name
P.S. 19 - MANHATTAN
Project Type
SCA CIP
Project Description
PLANYC BOILER CONVERSION / PLANYC CLIMATE CONTROL
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
7/18/2022
Project Phase Planned End Date
7/16/2024
Project Budget Amount
7724250
Final Estimate Of Actual Costs Through End Of Phase Amount
7306626
Total Phase Actual Spending Amount
6312537
Dsf Number S
DSF0001008800, DSF0000991942
1
Project Geographic District : 1 • Project Building Identifier: M019 • Project School Name: P.S. 19 - MANHATTAN
Project Geographic District
1
Project Building Identifier
M019
Project School Name
P.S. 19 - MANHATTAN
Project Type
SCA CIP
Project Description
PLANYC BOILER CONVERSION / PLANYC CLIMATE CONTROL
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
7/6/2021
Project Phase Planned End Date
12/7/2021
Project Phase Actual End Date
11/29/2021
Project Budget Amount
343300
Final Estimate Of Actual Costs Through End Of Phase Amount
425635
Total Phase Actual Spending Amount
399181
Dsf Number S
DSF0001008800, DSF0000991942
1
Project Geographic District : 1 • Project Building Identifier: M019 • Project School Name: P.S. 19 - MANHATTAN
Project Geographic District
1
Project Building Identifier
M019
Project School Name
P.S. 19 - MANHATTAN
Project Type
SCA CIP
Project Description
PLANYC BOILER CONVERSION / PLANYC CLIMATE CONTROL
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
4/13/2021
Project Phase Planned End Date
9/13/2021
Project Phase Actual End Date
7/1/2021
Project Budget Amount
68660
Final Estimate Of Actual Costs Through End Of Phase Amount
86612
Total Phase Actual Spending Amount
86612
Dsf Number S
DSF0001008800, DSF0000991942
1
Project Geographic District : 1 • Project Building Identifier: M020 • Project School Name: P.S. 20 - MANHATTAN
Project Geographic District
1
Project Building Identifier
M020
Project School Name
P.S. 20 - MANHATTAN
Project Type
DOE - Skilled Trades
Project Description
BATHROOM UPGRADES
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
7/7/2021
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
195021
Total Phase Actual Spending Amount
6911
Dsf Number S
DSF0001008690
1
Project Geographic District : 1 • Project Building Identifier: M020 • Project School Name: P.S. 20 - MANHATTAN
Project Geographic District
1
Project Building Identifier
M020
Project School Name
P.S. 20 - MANHATTAN
Project Type
Fast Track Projects
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
12/27/2024
Project Phase Planned End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
415233
Total Phase Actual Spending Amount
350059
Dsf Number S
DSF0001087468
1
Project Geographic District : 1 • Project Building Identifier: M020 • Project School Name: P.S. 20 - MANHATTAN
Project Geographic District
1
Project Building Identifier
M020
Project School Name
P.S. 20 - MANHATTAN
Project Type
SCA IEH
Project Description
PO18-AHERA P.S RESPONSE ACTION ABATEMENT BROWM LAYERED PAPER PIPE INSULATION - 1023 - B23 STORAGE RO
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
4/21/2026
Project Phase Planned End Date
IEH
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
750
Total Phase Actual Spending Amount
0
Dsf Number S
SCA0000075825
1
Project Geographic District : 1 • Project Building Identifier: M022 • Project School Name: NEW EXPLORATIONS - M
Project Geographic District
1
Project Building Identifier
M022
Project School Name
NEW EXPLORATIONS - M
Project Type
DIIT - RESOA
Project Description
FY22 RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
In-Progress
Project Phase Actual Start Date
4/14/2023
Project Phase Planned End Date
DIIR
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
50000
Total Phase Actual Spending Amount
50000
Dsf Number S
DSF0001033717
1
Project Geographic District : 1 • Project Building Identifier: M022 • Project School Name: NEW EXPLORATIONS - M
Project Geographic District
1
Project Building Identifier
M022
Project School Name
NEW EXPLORATIONS - M
Project Type
DOE - RESOA
Project Description
FY24 RESO A PLAYGROUND UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
200000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001086176
1
Project Geographic District : 1 • Project Building Identifier: M022 • Project School Name: NEW EXPLORATIONS - M
Project Geographic District
1
Project Building Identifier
M022
Project School Name
NEW EXPLORATIONS - M
Project Type
DOE - RESOA
Project Description
FY25 RESO A SUPPLEMENTAL COOLING
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
442622
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001112760
1
Project Geographic District : 1 • Project Building Identifier: M022 • Project School Name: NEW EXPLORATIONS - M
Project Geographic District
1
Project Building Identifier
M022
Project School Name
NEW EXPLORATIONS - M
Project Type
DOE - RESOA
Project Description
FY21 RESO A BATHROOM UPGRADES
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
8/6/2021
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
87851
Total Phase Actual Spending Amount
87851
Dsf Number S
DSF0000961298
1
Project Geographic District : 1 • Project Building Identifier: M022 • Project School Name: NEW EXPLORATIONS - M
Project Geographic District
1
Project Building Identifier
M022
Project School Name
NEW EXPLORATIONS - M
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / LOW VOLTAGE ELECTRICAL SYSTEMS
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
8/7/2023
Project Phase Planned End Date
8/5/2025
Project Budget Amount
1427780
Final Estimate Of Actual Costs Through End Of Phase Amount
1347784
Total Phase Actual Spending Amount
1291143
Dsf Number S
DSF0000961144, DSF0001017428
1
Project Geographic District : 1 • Project Building Identifier: M022 • Project School Name: NEW EXPLORATIONS - M
Project Geographic District
1
Project Building Identifier
M022
Project School Name
NEW EXPLORATIONS - M
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / LOW VOLTAGE ELECTRICAL SYSTEMS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
8/7/2023
Project Phase Planned End Date
8/5/2025
Project Budget Amount
21999375
Final Estimate Of Actual Costs Through End Of Phase Amount
22340812
Total Phase Actual Spending Amount
19300800
Dsf Number S
DSF0000961144, DSF0001017428
1
Project Geographic District : 1 • Project Building Identifier: M022 • Project School Name: NEW EXPLORATIONS - M
Project Geographic District
1
Project Building Identifier
M022
Project School Name
NEW EXPLORATIONS - M
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / LOW VOLTAGE ELECTRICAL SYSTEMS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
12/22/2021
Project Phase Planned End Date
6/10/2022
Project Phase Actual End Date
9/16/2022
Project Budget Amount
977750
Final Estimate Of Actual Costs Through End Of Phase Amount
692323
Total Phase Actual Spending Amount
608011
Dsf Number S
DSF0000961144, DSF0001017428
1
Project Geographic District : 1 • Project Building Identifier: M022 • Project School Name: NEW EXPLORATIONS - M
Project Geographic District
1
Project Building Identifier
M022
Project School Name
NEW EXPLORATIONS - M
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / LOW VOLTAGE ELECTRICAL SYSTEMS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
4/22/2021
Project Phase Planned End Date
9/7/2021
Project Phase Actual End Date
12/21/2021
Project Budget Amount
195550
Final Estimate Of Actual Costs Through End Of Phase Amount
195047
Total Phase Actual Spending Amount
192452
Dsf Number S
DSF0000961144, DSF0001017428
1
Project Geographic District : 1 • Project Building Identifier: M022 • Project School Name: NEW EXPLORATIONS - M
Project Geographic District
1
Project Building Identifier
M022
Project School Name
NEW EXPLORATIONS - M
Project Type
SCA IEH
Project Description
PO18-AHERA P.S RESPONSE ACTION ABATEMENT PIPE JOINT TO FIBERGLASS PIPE INSULATION LVL 1 - 1700 - GIR
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
5/14/2026
Project Phase Planned End Date
IEH
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
750
Total Phase Actual Spending Amount
0
Dsf Number S
SCA0000075973
1
Project Geographic District : 1 • Project Building Identifier: M022 • Project School Name: NEW EXPLORATIONS - M
Project Geographic District
1
Project Building Identifier
M022
Project School Name
NEW EXPLORATIONS - M
Project Type
SCA IEH
Project Description
PO18-AREAS WERE INDENTIFIED DURING THE AHERA PERIODIC SURVEILLANCE AS RESPONSE ACTIONS DUE TO OBSERV
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
10/15/2025
Project Phase Planned End Date
IEH
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
750
Total Phase Actual Spending Amount
0
Dsf Number S
SCA0000075033
1
Project Geographic District : 1 • Project Building Identifier: M022 • Project School Name: NEW EXPLORATIONS - M
Project Geographic District
1
Project Building Identifier
M022
Project School Name
NEW EXPLORATIONS - M
Project Type
SCA IEH
Project Description
PO18-ABATE PIPE INSULATION IN VARIOUS AREAS DUE TO DAMAGE PIPES C82 (SPACE ID: 1600) APPROX. 20 LINE
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
6/17/2025
Project Phase Planned End Date
IEH
Project Phase Actual End Date
2/22/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
47842
Total Phase Actual Spending Amount
47842
Dsf Number S
SCA0000074369
1
Project Geographic District : 1 • Project Building Identifier: M025 • Project School Name: LOWER EAST SIDE PREP HS - M
Project Geographic District
1
Project Building Identifier
M025
Project School Name
LOWER EAST SIDE PREP HS - M
Project Type
SCA CIP
Project Description
IPDVS CAMERA INSTALLATION
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
5/24/2022
Project Phase Planned End Date
3/19/2023
Project Budget Amount
234139
Final Estimate Of Actual Costs Through End Of Phase Amount
293192
Total Phase Actual Spending Amount
270391
Dsf Number S
DSF0000960787
1
Project Geographic District : 1 • Project Building Identifier: M025 • Project School Name: LOWER EAST SIDE PREP HS - M
Project Geographic District
1
Project Building Identifier
M025
Project School Name
LOWER EAST SIDE PREP HS - M
Project Type
SCA CIP
Project Description
IPDVS CAMERA INSTALLATION
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
5/24/2022
Project Phase Planned End Date
3/19/2023
Project Budget Amount
201929
Final Estimate Of Actual Costs Through End Of Phase Amount
188076
Total Phase Actual Spending Amount
161379
Dsf Number S
DSF0000960787
1
Project Geographic District : 1 • Project Building Identifier: M025 • Project School Name: LOWER EAST SIDE PREP HS - M
Project Geographic District
1
Project Building Identifier
M025
Project School Name
LOWER EAST SIDE PREP HS - M
Project Type
SCA CIP
Project Description
IPDVS CAMERA INSTALLATION
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
7/21/2020
Project Phase Planned End Date
1/15/2021
Project Phase Actual End Date
3/30/2021
Project Budget Amount
15667
Final Estimate Of Actual Costs Through End Of Phase Amount
19420
Total Phase Actual Spending Amount
19420
Dsf Number S
DSF0000960787
1
Project Geographic District : 1 • Project Building Identifier: M025 • Project School Name: LOWER EAST SIDE PREP HS - M
Project Geographic District
1
Project Building Identifier
M025
Project School Name
LOWER EAST SIDE PREP HS - M
Project Type
SCA CIP
Project Description
IPDVS CAMERA INSTALLATION
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
6/25/2020
Project Phase Planned End Date
10/26/2020
Project Phase Actual End Date
7/21/2020
Project Budget Amount
3482
Final Estimate Of Actual Costs Through End Of Phase Amount
4855
Total Phase Actual Spending Amount
4855
Dsf Number S
DSF0000960787
1
Project Geographic District : 1 • Project Building Identifier: M025 • Project School Name: LOWER EAST SIDE PREP HS - M
Project Geographic District
1
Project Building Identifier
M025
Project School Name
LOWER EAST SIDE PREP HS - M
Project Type
SCA IEH
Project Description
PO18-ABATE FLOOR TILES IN ROOM 242 ( SPACE ID# 3242) TO REPAIR STEAM LEAKS
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
2/26/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
3/1/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
15331
Total Phase Actual Spending Amount
7448
Dsf Number S
SCA0000075481
1
Project Geographic District : 1 • Project Building Identifier: M025 • Project School Name: LOWER EAST SIDE PREP HS - M
Project Geographic District
1
Project Building Identifier
M025
Project School Name
LOWER EAST SIDE PREP HS - M
Project Type
SCA IEH
Project Description
PO18-ABATE FLOOR TILES IN ROOM 326 (SPACE ID# 4326) DUE TO STEAM LEAKS
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
3/25/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
5/26/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
14351
Total Phase Actual Spending Amount
655
Dsf Number S
SCA0000075665
1
Project Geographic District : 1 • Project Building Identifier: M025 • Project School Name: LOWER EAST SIDE PREP HS - M
Project Geographic District
1
Project Building Identifier
M025
Project School Name
LOWER EAST SIDE PREP HS - M
Project Type
SCA IEH
Project Description
PO18-AHERA P.S RESPONSE ACTION ABATEMENT SOFT CONCRETE FILLER FLOORING MATERIAL - 2158, 5404P, 3244P
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
5/14/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
6/9/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
1250
Total Phase Actual Spending Amount
101
Dsf Number S
SCA0000075970
1
Project Geographic District : 1 • Project Building Identifier: M025 • Project School Name: LOWER EAST SIDE PREP HS - M
Project Geographic District
1
Project Building Identifier
M025
Project School Name
LOWER EAST SIDE PREP HS - M
Project Type
SCA IEH
Project Description
PO18-CORE DRILLING THROUGH THE FLOOR(ROOM 332 FLOOR TO ROOM 232 CEILING). ROOM 332 (SPACE ID# 4332)
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
3/3/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
4/21/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
11918
Total Phase Actual Spending Amount
946
Dsf Number S
SCA0000075516
1
Project Geographic District : 1 • Project Building Identifier: M025 • Project School Name: LOWER EAST SIDE PREP HS - M
Project Geographic District
1
Project Building Identifier
M025
Project School Name
LOWER EAST SIDE PREP HS - M
Project Type
SCA IEH
Project Description
PO18-ABATEMENT IN THE FOLLOWING LOCATIONS: ROOM 232- FLOOR (SPACE ID# 3232), ROOM 243 - FLOOR (SPA
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
9/2/2025
Project Phase Planned End Date
IEH
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
1352
Total Phase Actual Spending Amount
602
Dsf Number S
SCA0000074868
6
Project Geographic District : 6 • Project Building Identifier: M028 • Project School Name: P.S. 28 - MANHATTAN
Project Geographic District
6
Project Building Identifier
M028
Project School Name
P.S. 28 - MANHATTAN
Project Type
DIIT - RESOA
Project Description
FY26 RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
100000
Total Phase Actual Spending Amount
100000
Dsf Number S
DSF0001163475
6
Project Geographic District : 6 • Project Building Identifier: M028 • Project School Name: P.S. 28 - MANHATTAN
Project Geographic District
6
Project Building Identifier
M028
Project School Name
P.S. 28 - MANHATTAN
Project Type
DOE - RESOA
Project Description
FY26 RESO A AUDITORIUM UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
100000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001163474
6
Project Geographic District : 6 • Project Building Identifier: M028 • Project School Name: P.S. 28 - MANHATTAN
Project Geographic District
6
Project Building Identifier
M028
Project School Name
P.S. 28 - MANHATTAN
Project Type
DOE - RESOA
Project Description
FY23 RESO A AUDITORIUM UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
150000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001035622
6
Project Geographic District : 6 • Project Building Identifier: M028 • Project School Name: P.S. 28 - MANHATTAN
Project Geographic District
6
Project Building Identifier
M028
Project School Name
P.S. 28 - MANHATTAN
Project Type
SCA CIP
Project Description
WATER INFILTRATION INTO ELECTRCIAL EQUIPMENT / FIRE ALARM SYSTEM REPLACEMENT
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
8/11/2025
Project Phase Planned End Date
2/1/2027
Project Budget Amount
210485
Final Estimate Of Actual Costs Through End Of Phase Amount
36631
Total Phase Actual Spending Amount
36631
Dsf Number S
DSF0001083877, DSF0001085604
6
Project Geographic District : 6 • Project Building Identifier: M028 • Project School Name: P.S. 28 - MANHATTAN
Project Geographic District
6
Project Building Identifier
M028
Project School Name
P.S. 28 - MANHATTAN
Project Type
SCA CIP
Project Description
WATER INFILTRATION INTO ELECTRCIAL EQUIPMENT / FIRE ALARM SYSTEM REPLACEMENT
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
8/11/2025
Project Phase Planned End Date
2/1/2027
Project Budget Amount
1135640
Final Estimate Of Actual Costs Through End Of Phase Amount
1004172
Total Phase Actual Spending Amount
401605
Dsf Number S
DSF0001083877, DSF0001085604
6
Project Geographic District : 6 • Project Building Identifier: M028 • Project School Name: P.S. 28 - MANHATTAN
Project Geographic District
6
Project Building Identifier
M028
Project School Name
P.S. 28 - MANHATTAN
Project Type
SCA CIP
Project Description
WATER INFILTRATION INTO ELECTRCIAL EQUIPMENT / FIRE ALARM SYSTEM REPLACEMENT
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
7/17/2023
Project Phase Planned End Date
12/18/2023
Project Phase Actual End Date
12/15/2023
Project Budget Amount
88110
Final Estimate Of Actual Costs Through End Of Phase Amount
100737
Total Phase Actual Spending Amount
89277
Dsf Number S
DSF0001083877, DSF0001085604
6
Project Geographic District : 6 • Project Building Identifier: M028 • Project School Name: P.S. 28 - MANHATTAN
Project Geographic District
6
Project Building Identifier
M028
Project School Name
P.S. 28 - MANHATTAN
Project Type
SCA CIP
Project Description
WATER INFILTRATION INTO ELECTRCIAL EQUIPMENT / FIRE ALARM SYSTEM REPLACEMENT
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
3/7/2023
Project Phase Planned End Date
7/21/2023
Project Phase Actual End Date
6/26/2023
Project Budget Amount
19580
Final Estimate Of Actual Costs Through End Of Phase Amount
15682
Total Phase Actual Spending Amount
15682
Dsf Number S
DSF0001083877, DSF0001085604
6
Project Geographic District : 6 • Project Building Identifier: M028 • Project School Name: P.S. 28 - MANHATTAN
Project Geographic District
6
Project Building Identifier
M028
Project School Name
P.S. 28 - MANHATTAN
Project Type
SCA CIP RESOA
Project Description
PATH OF TRAVEL RESO A PLAYGROUND UPGRADE
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
0
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001113601
6
Project Geographic District : 6 • Project Building Identifier: M028 • Project School Name: P.S. 28 - MANHATTAN
Project Geographic District
6
Project Building Identifier
M028
Project School Name
P.S. 28 - MANHATTAN
Project Type
SCA CIP RESOA
Project Description
FY25 RESO A PLAYGROUND UPGRADE
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
30000
Final Estimate Of Actual Costs Through End Of Phase Amount
30000
Total Phase Actual Spending Amount
13254
Dsf Number S
DSF0001112761
6
Project Geographic District : 6 • Project Building Identifier: M028 • Project School Name: P.S. 28 - MANHATTAN
Project Geographic District
6
Project Building Identifier
M028
Project School Name
P.S. 28 - MANHATTAN
Project Type
SCA CIP RESOA
Project Description
FY25 RESO A PLAYGROUND UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
440000
Final Estimate Of Actual Costs Through End Of Phase Amount
440000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001112761
6
Project Geographic District : 6 • Project Building Identifier: M028 • Project School Name: P.S. 28 - MANHATTAN
Project Geographic District
6
Project Building Identifier
M028
Project School Name
P.S. 28 - MANHATTAN
Project Type
SCA CIP RESOA
Project Description
PATH OF TRAVEL RESO A PLAYGROUND UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
0
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001113601
6
Project Geographic District : 6 • Project Building Identifier: M028 • Project School Name: P.S. 28 - MANHATTAN
Project Geographic District
6
Project Building Identifier
M028
Project School Name
P.S. 28 - MANHATTAN
Project Type
SCA CIP RESOA
Project Description
FY25 RESO A PLAYGROUND UPGRADE
Project Phase Name
Design
Project Status Name
In-Progress
Project Phase Actual Start Date
1/21/2026
Project Phase Planned End Date
6/5/2026
Project Budget Amount
60556
Final Estimate Of Actual Costs Through End Of Phase Amount
60556
Total Phase Actual Spending Amount
42323
Dsf Number S
DSF0001112761
6
Project Geographic District : 6 • Project Building Identifier: M028 • Project School Name: P.S. 28 - MANHATTAN
Project Geographic District
6
Project Building Identifier
M028
Project School Name
P.S. 28 - MANHATTAN
Project Type
SCA CIP RESOA
Project Description
PATH OF TRAVEL RESO A PLAYGROUND UPGRADE
Project Phase Name
Design
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
1123
Total Phase Actual Spending Amount
1123
Dsf Number S
DSF0001113601
6
Project Geographic District : 6 • Project Building Identifier: M028 • Project School Name: P.S. 28 - MANHATTAN
Project Geographic District
6
Project Building Identifier
M028
Project School Name
P.S. 28 - MANHATTAN
Project Type
SCA CIP RESOA
Project Description
PATH OF TRAVEL RESO A PLAYGROUND UPGRADE
Project Phase Name
Scope
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
281
Total Phase Actual Spending Amount
281
Dsf Number S
DSF0001113601
6
Project Geographic District : 6 • Project Building Identifier: M028 • Project School Name: P.S. 28 - MANHATTAN
Project Geographic District
6
Project Building Identifier
M028
Project School Name
P.S. 28 - MANHATTAN
Project Type
SCA CIP RESOA
Project Description
FY25 RESO A PLAYGROUND UPGRADE
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
2/12/2025
Project Phase Planned End Date
5/13/2025
Project Phase Actual End Date
1/14/2026
Project Budget Amount
81384
Final Estimate Of Actual Costs Through End Of Phase Amount
81384
Total Phase Actual Spending Amount
49427
Dsf Number S
DSF0001112761