Project Geographic District
2
Project Building Identifier
M040
Project School Name
P.S. 40 - MANHATTAN
Project Description
FLOOD ELIMINATION / PARAPETS / EXTERIOR MASONRY / WINDOWS / ROOFS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
1/25/2022
Project Phase Planned End Date
6/24/2022
Project Phase Actual End Date
5/10/2022
Project Budget Amount
1597150
Final Estimate Of Actual Costs Through End Of Phase Amount
1186911
Total Phase Actual Spending Amount
1177720
Dsf Number S
DSF0000943382, DSF0000943384, DSF0000943386, DSF0000943385, DSF0001034496