Project Geographic District
1
Project Building Identifier
M110
Project School Name
P.S. 110 - MANHATTAN
Project Description
FACADE REMEDIATION @M110 / PARAPETS / ROOFS / FLOOD ELIMINATION
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
6/1/2022
Project Phase Planned End Date
11/22/2022
Project Phase Actual End Date
5/12/2023
Project Budget Amount
616310
Final Estimate Of Actual Costs Through End Of Phase Amount
422524
Total Phase Actual Spending Amount
315839
Dsf Number S
DSF0001085128, DSF0001018329, DSF0001018328, DSF0001018326