Capital Project Tracker

A listing of all capital projects managed by NYC Parks, and a timeline for their completion.

Supporting documentation can be found at the following link (http://www.nycgovparks.org/bigapps/desc/DPR_CapitalProjectTracker_001.txt).

See JSON and XML feeds here https://data.cityofnewyork.us/Recreation/Capital-Project-Tracker/qiwj-i2jk

Recreation Department of Parks and Recreation (DPR) Dataset 4hcv-tc5r 29 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
5073
Trackerid: 5073 • Fmsid: 846 P-6ROOF9B • Title: Brooklyn and Staten Island Roofing Systems Reconstruction (CNYG-3109M)
Trackerid
5073
Fmsid
846 P-6ROOF9B
Title
Brooklyn and Staten Island Roofing Systems Reconstruction (CNYG-3109M)
Summary
This project will reconstruct the roofing systems at various parks facilities in Brooklyn and Staten Island.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2006-12-01T00:00:00.000
Designactualcompletion
2009-03-01T00:00:00.000
Procurementstart
2009-03-01T00:00:00.000
Procurementprojectedcompletion
2009-12-01T00:00:00.000
Procurementactualcompletion
2010-01-01T00:00:00.000
Constructionstart
2010-03-01T00:00:00.000
Constructionprojectedcom
2013-02-01T00:00:00.000
Constructionadjustedcompletion
2014-06-01T00:00:00.000
Constructionactualcompletion
2014-06-01T00:00:00.000
Totalfunding
$3,325,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Parkinson Avenue, Kramer Street
Parkid
R063
Latitude
40.595395
Longitude
-74.081361
Borough
Brooklyn, Staten Island
VIEW LOCATION
5073
Trackerid: 5073 • Fmsid: 846 P-6ROOF9B • Title: Brooklyn and Staten Island Roofing Systems Reconstruction (CNYG-3109M)
Trackerid
5073
Fmsid
846 P-6ROOF9B
Title
Brooklyn and Staten Island Roofing Systems Reconstruction (CNYG-3109M)
Summary
This project will reconstruct the roofing systems at various parks facilities in Brooklyn and Staten Island.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2006-12-01T00:00:00.000
Designactualcompletion
2009-03-01T00:00:00.000
Procurementstart
2009-03-01T00:00:00.000
Procurementprojectedcompletion
2009-12-01T00:00:00.000
Procurementactualcompletion
2010-01-01T00:00:00.000
Constructionstart
2010-03-01T00:00:00.000
Constructionprojectedcom
2013-02-01T00:00:00.000
Constructionadjustedcompletion
2014-06-01T00:00:00.000
Constructionactualcompletion
2014-06-01T00:00:00.000
Totalfunding
$3,325,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Stanley Avenue & Eldert Lane
Parkid
B309
Latitude
40.666546
Longitude
-73.862668
Borough
Brooklyn, Staten Island
VIEW LOCATION
5073
Trackerid: 5073 • Fmsid: 846 P-6ROOF9B • Title: Brooklyn and Staten Island Roofing Systems Reconstruction (CNYG-3109M)
Trackerid
5073
Fmsid
846 P-6ROOF9B
Title
Brooklyn and Staten Island Roofing Systems Reconstruction (CNYG-3109M)
Summary
This project will reconstruct the roofing systems at various parks facilities in Brooklyn and Staten Island.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2006-12-01T00:00:00.000
Designactualcompletion
2009-03-01T00:00:00.000
Procurementstart
2009-03-01T00:00:00.000
Procurementprojectedcompletion
2009-12-01T00:00:00.000
Procurementactualcompletion
2010-01-01T00:00:00.000
Constructionstart
2010-03-01T00:00:00.000
Constructionprojectedcom
2013-02-01T00:00:00.000
Constructionadjustedcompletion
2014-06-01T00:00:00.000
Constructionactualcompletion
2014-06-01T00:00:00.000
Totalfunding
$3,325,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Victory Boulevard, Signs Road, Travis Avenue & Arthur Kill
Parkid
R017A
Latitude
40.591403
Longitude
-74.133932
Borough
Brooklyn, Staten Island
VIEW LOCATION
5073
Trackerid: 5073 • Fmsid: 846 P-6ROOF9B • Title: Brooklyn and Staten Island Roofing Systems Reconstruction (CNYG-3109M)
Trackerid
5073
Fmsid
846 P-6ROOF9B
Title
Brooklyn and Staten Island Roofing Systems Reconstruction (CNYG-3109M)
Summary
This project will reconstruct the roofing systems at various parks facilities in Brooklyn and Staten Island.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2006-12-01T00:00:00.000
Designactualcompletion
2009-03-01T00:00:00.000
Procurementstart
2009-03-01T00:00:00.000
Procurementprojectedcompletion
2009-12-01T00:00:00.000
Procurementactualcompletion
2010-01-01T00:00:00.000
Constructionstart
2010-03-01T00:00:00.000
Constructionprojectedcom
2013-02-01T00:00:00.000
Constructionadjustedcompletion
2014-06-01T00:00:00.000
Constructionactualcompletion
2014-06-01T00:00:00.000
Totalfunding
$3,325,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Prospect Park Southwest between Prospect Park West & 16 Street
Parkid
B073
Latitude
40.661353
Longitude
-73.969682
Borough
Brooklyn, Staten Island
VIEW LOCATION
5073
Trackerid: 5073 • Fmsid: 846 P-6ROOF9B • Title: Brooklyn and Staten Island Roofing Systems Reconstruction (CNYG-3109M)
Trackerid
5073
Fmsid
846 P-6ROOF9B
Title
Brooklyn and Staten Island Roofing Systems Reconstruction (CNYG-3109M)
Summary
This project will reconstruct the roofing systems at various parks facilities in Brooklyn and Staten Island.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2006-12-01T00:00:00.000
Designactualcompletion
2009-03-01T00:00:00.000
Procurementstart
2009-03-01T00:00:00.000
Procurementprojectedcompletion
2009-12-01T00:00:00.000
Procurementactualcompletion
2010-01-01T00:00:00.000
Constructionstart
2010-03-01T00:00:00.000
Constructionprojectedcom
2013-02-01T00:00:00.000
Constructionadjustedcompletion
2014-06-01T00:00:00.000
Constructionactualcompletion
2014-06-01T00:00:00.000
Totalfunding
$3,325,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Tompkins Avenue & Broad Street
Parkid
R061
Latitude
40.623247
Longitude
-74.079651
Borough
Brooklyn, Staten Island
VIEW LOCATION
5073
Trackerid: 5073 • Fmsid: 846 P-6ROOF9B • Title: Brooklyn and Staten Island Roofing Systems Reconstruction (CNYG-3109M)
Trackerid
5073
Fmsid
846 P-6ROOF9B
Title
Brooklyn and Staten Island Roofing Systems Reconstruction (CNYG-3109M)
Summary
This project will reconstruct the roofing systems at various parks facilities in Brooklyn and Staten Island.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2006-12-01T00:00:00.000
Designactualcompletion
2009-03-01T00:00:00.000
Procurementstart
2009-03-01T00:00:00.000
Procurementprojectedcompletion
2009-12-01T00:00:00.000
Procurementactualcompletion
2010-01-01T00:00:00.000
Constructionstart
2010-03-01T00:00:00.000
Constructionprojectedcom
2013-02-01T00:00:00.000
Constructionadjustedcompletion
2014-06-01T00:00:00.000
Constructionactualcompletion
2014-06-01T00:00:00.000
Totalfunding
$3,325,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Victory Boulevard, Clove Road, Forest Avenue
Parkid
R022
Latitude
40.625947
Longitude
-74.097441
Borough
Brooklyn, Staten Island
VIEW LOCATION
6245
Trackerid: 6245 • Fmsid: 846 P-216BRWN • Title: Brownsville Recreation Center Pool Roof Reconstruction
Trackerid
6245
Fmsid
846 P-216BRWN
Title
Brownsville Recreation Center Pool Roof Reconstruction
Summary
This project will reconstruct the roof at Brownsville Recreation Center.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2014-01-01T00:00:00.000
Designprojectedcompletion
2014-01-01T00:00:00.000
Designactualcompletion
2014-03-01T00:00:00.000
Procurementstart
2014-03-01T00:00:00.000
Procurementprojectedcompletion
2014-12-01T00:00:00.000
Procurementadjustedcompletion
2015-08-01T00:00:00.000
Procurementactualcompletion
2015-07-01T00:00:00.000
Constructionstart
2015-08-01T00:00:00.000
Constructionprojectedcom
2017-08-01T00:00:00.000
Constructionactualcompletion
2017-06-01T00:00:00.000
Totalfunding
$4,199,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoral
Name
Linden Boulevard and Mother Gaston Boulevard
Parkid
B270
Latitude
40.65673
Longitude
-73.902826
Borough
Brooklyn
VIEW LOCATION
10999
Trackerid: 10999 • Fmsid: 846 SEED-BFNO • Title: Bufano Park Reconstruction and Public Restroom Building Construction
Trackerid
10999
Fmsid
846 SEED-BFNO
Title
Bufano Park Reconstruction and Public Restroom Building Construction
Summary
This project will reconstruct the playground, basketball courts, handball courts and construct a new public restroom building at Bufano Park.
Currentphase
design
Designpercentcomplete
5.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Designstart
2026-06-01T00:00:00.000
Designprojectedcompletion
2027-09-01T00:00:00.000
Totalfunding
Greater than $10 million
Projectliaison
Katerine Borrome
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Bradford Avenue between La Salle Avenue and Waterbury Avenue
Parkid
X121
Latitude
40.83799935
Longitude
-73.83101137
Borough
Bronx
VIEW LOCATION
1971111
Trackerid: 1971111 • Fmsid: 846 EXPENSE • Title: Burns Playground Plumbing Reconstruction
Trackerid
1971111
Fmsid
846 EXPENSE
Title
Burns Playground Plumbing Reconstruction
Summary
This project will reconstruct plumbing connections at Burns Playground.
Currentphase
construction
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
0.0
Designstart
2026-08-01T00:00:00.000
Designprojectedcompletion
2026-07-01T00:00:00.000
Designactualcompletion
2026-09-01T00:00:00.000
Procurementstart
2026-08-01T00:00:00.000
Procurementprojectedcompletion
2027-01-01T00:00:00.000
Procurementactualcompletion
2026-09-01T00:00:00.000
Constructionstart
2026-09-01T00:00:00.000
Constructionprojectedcom
2026-12-01T00:00:00.000
Totalfunding
$130,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Parkid
X232
Latitude
40.8629407
Longitude
-73.8367335
Borough
Bronx
VIEW LOCATION
1357111
Trackerid: 1357111 • Fmsid: 846 P-2STFBSH • Title: Bushwick Inlet Park Synthetic Turf Field Reconstruction
Trackerid
1357111
Fmsid
846 P-2STFBSH
Title
Bushwick Inlet Park Synthetic Turf Field Reconstruction
Summary
This project will reconstruct the synthetic turf field at Bushwick Inlet Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2021-05-01T00:00:00.000
Designprojectedcompletion
2022-04-01T00:00:00.000
Designactualcompletion
2022-04-01T00:00:00.000
Procurementstart
2021-09-01T00:00:00.000
Procurementprojectedcompletion
2022-02-01T00:00:00.000
Procurementactualcompletion
2022-04-01T00:00:00.000
Constructionstart
2022-05-01T00:00:00.000
Constructionprojectedcom
2022-08-01T00:00:00.000
Constructionactualcompletion
2022-07-01T00:00:00.000
Totalfunding
$3,193,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral, City Council
Parkid
B529
Latitude
40.724259
Longitude
-73.959935
Borough
Brooklyn
VIEW LOCATION
8919
Trackerid: 8919 • Fmsid: 846 P-2GPWB25 • Summary: This project will construct a new passive seating area in Bushwick Inlet Park.
Trackerid
8919
Fmsid
846 P-2GPWB25
Title
Bushwick Inlet Park Motiva Parcel Remediation and Passive Seating Area Construction
Summary
This project will construct a new passive seating area in Bushwick Inlet Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2019-01-01T00:00:00.000
Designprojectedcompletion
2020-07-01T00:00:00.000
Designadjustedcompletion
2023-04-01T00:00:00.000
Designactualcompletion
2023-01-01T00:00:00.000
Procurementstart
2023-01-01T00:00:00.000
Procurementprojectedcompletion
2023-10-01T00:00:00.000
Procurementadjustedcompletion
2024-04-01T00:00:00.000
Procurementactualcompletion
2024-04-01T00:00:00.000
Constructionstart
2024-03-01T00:00:00.000
Constructionprojectedcom
2025-09-01T00:00:00.000
Constructionadjustedcompletion
2026-04-01T00:00:00.000
Constructionactualcompletion
2026-04-01T00:00:00.000
Totalfunding
$9,818,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Franklin Street, Kent Avenue, East River, Quay Street
Parkid
B529
Latitude
40.725314
Longitude
-73.958008
Borough
Brooklyn
VIEW LOCATION
10567
Trackerid: 10567 • Fmsid: 846 P-2GPWB12 • Title: Bushwick Inlet Park Sewer Connection Construction
Trackerid
10567
Fmsid
846 P-2GPWB12
Title
Bushwick Inlet Park Sewer Connection Construction
Summary
This project will install a sewer connection in Bushwick Inlet Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2023-02-01T00:00:00.000
Designprojectedcompletion
2024-02-01T00:00:00.000
Designactualcompletion
2023-07-01T00:00:00.000
Procurementstart
2023-07-01T00:00:00.000
Procurementprojectedcompletion
2024-07-01T00:00:00.000
Procurementadjustedcompletion
2024-11-01T00:00:00.000
Procurementactualcompletion
2025-01-01T00:00:00.000
Constructionstart
2025-05-01T00:00:00.000
Constructionprojectedcom
2025-11-01T00:00:00.000
Constructionactualcompletion
2025-08-01T00:00:00.000
Totalfunding
$1,176,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Kent Avenue between N.12th and N.11th Streets
Parkid
B529
Latitude
40.724138
Longitude
-73.960001
Borough
Brooklyn
VIEW LOCATION
8955
Trackerid: 8955 • Fmsid: 846 P-2GPWBKT • Title: Bushwick Inlet Park (50 Kent Avenue) New Park Construction
Trackerid
8955
Fmsid
846 P-2GPWBKT
Title
Bushwick Inlet Park (50 Kent Avenue) New Park Construction
Summary
This project will construct a portion of Bushwick Inlet Park at 50 Kent Avenue.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2018-06-01T00:00:00.000
Designprojectedcompletion
2019-07-01T00:00:00.000
Designactualcompletion
2019-08-01T00:00:00.000
Procurementstart
2019-08-01T00:00:00.000
Procurementprojectedcompletion
2020-05-01T00:00:00.000
Procurementadjustedcompletion
2021-04-01T00:00:00.000
Procurementactualcompletion
2021-03-01T00:00:00.000
Constructionstart
2021-04-01T00:00:00.000
Constructionprojectedcom
2022-04-01T00:00:00.000
Constructionadjustedcompletion
2022-12-01T00:00:00.000
Constructionactualcompletion
2022-12-01T00:00:00.000
Totalfunding
$6,391,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Kent Avenue between North 11th Street and North 12th Street
Parkid
B529
Latitude
40.723190133422
Longitude
-73.959681855993
Borough
Brooklyn
VIEW LOCATION
11071
Trackerid: 11071 • Title: Bushwick Inlet Park CitiStorage North Parcel Construction • Currentphase: proposed
Trackerid
11071
Title
Bushwick Inlet Park CitiStorage North Parcel Construction
Summary
This project will construct a portion of Bushwick Inlet Park at the CitiStorage north parcel.
Currentphase
proposed
Designpercentcomplete
0.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Totalfunding
Greater than $10 million
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
North 11th Street and North 12th Street between the East River and Kent Avenue
Parkid
B529
Latitude
40.7241037
Longitude
-73.9596878
Borough
Brooklyn
VIEW LOCATION
1761111
Trackerid: 1761111 • Fmsid: 846 P-204BPST • Title: Bushwick Playground Synthetic Turf Field Reconstruction
Trackerid
1761111
Fmsid
846 P-204BPST
Title
Bushwick Playground Synthetic Turf Field Reconstruction
Summary
This project will reconstruct the synthetic turf field at Bushwick Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2024-05-01T00:00:00.000
Designprojectedcompletion
2024-12-01T00:00:00.000
Designactualcompletion
2024-11-01T00:00:00.000
Procurementstart
2024-08-01T00:00:00.000
Procurementprojectedcompletion
2025-01-01T00:00:00.000
Procurementactualcompletion
2024-11-01T00:00:00.000
Constructionstart
2025-07-01T00:00:00.000
Constructionprojectedcom
2026-01-01T00:00:00.000
Constructionactualcompletion
2025-09-01T00:00:00.000
Totalfunding
$800,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Parkid
B017
Latitude
40.6960561
Longitude
-73.9127088
Borough
Brooklyn
VIEW LOCATION
3898
Trackerid: 3898 • Fmsid: 846 P-6BLDG9A • Title: Citywide Buildings Reconstruction (CNYG-209M)
Trackerid
3898
Fmsid
846 P-6BLDG9A
Title
Citywide Buildings Reconstruction (CNYG-209M)
Summary
This project will reconstruct buildings and public restroom buildings in various parks citywide.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2009-08-01T00:00:00.000
Designactualcompletion
2009-09-01T00:00:00.000
Procurementstart
2009-09-01T00:00:00.000
Procurementprojectedcompletion
2010-06-01T00:00:00.000
Procurementactualcompletion
2010-07-01T00:00:00.000
Constructionstart
2010-07-01T00:00:00.000
Constructionprojectedcom
2013-07-01T00:00:00.000
Constructionadjustedcompletion
2015-02-01T00:00:00.000
Constructionactualcompletion
2015-02-01T00:00:00.000
Totalfunding
$2,171,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoral
Name
Knickerbocker Avenue between Woodbine Street and Putnam Avenue
Parkid
B017
Latitude
40.696004
Longitude
-73.912137
Borough
Brooklyn, Queens, Manhattan, Bronx
VIEW LOCATION
3898
Trackerid: 3898 • Fmsid: 846 P-6BLDG9A • Title: Citywide Buildings Reconstruction (CNYG-209M)
Trackerid
3898
Fmsid
846 P-6BLDG9A
Title
Citywide Buildings Reconstruction (CNYG-209M)
Summary
This project will reconstruct buildings and public restroom buildings in various parks citywide.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2009-08-01T00:00:00.000
Designactualcompletion
2009-09-01T00:00:00.000
Procurementstart
2009-09-01T00:00:00.000
Procurementprojectedcompletion
2010-06-01T00:00:00.000
Procurementactualcompletion
2010-07-01T00:00:00.000
Constructionstart
2010-07-01T00:00:00.000
Constructionprojectedcom
2013-07-01T00:00:00.000
Constructionadjustedcompletion
2015-02-01T00:00:00.000
Constructionactualcompletion
2015-02-01T00:00:00.000
Totalfunding
$2,171,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoral
Name
Grand Central Parkway, Van Wyck Expressway
Parkid
Q099
Latitude
40.751399
Longitude
-73.833783
Borough
Brooklyn, Queens, Manhattan, Bronx
VIEW LOCATION
3898
Trackerid: 3898 • Fmsid: 846 P-6BLDG9A • Title: Citywide Buildings Reconstruction (CNYG-209M)
Trackerid
3898
Fmsid
846 P-6BLDG9A
Title
Citywide Buildings Reconstruction (CNYG-209M)
Summary
This project will reconstruct buildings and public restroom buildings in various parks citywide.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2009-08-01T00:00:00.000
Designactualcompletion
2009-09-01T00:00:00.000
Procurementstart
2009-09-01T00:00:00.000
Procurementprojectedcompletion
2010-06-01T00:00:00.000
Procurementactualcompletion
2010-07-01T00:00:00.000
Constructionstart
2010-07-01T00:00:00.000
Constructionprojectedcom
2013-07-01T00:00:00.000
Constructionadjustedcompletion
2015-02-01T00:00:00.000
Constructionactualcompletion
2015-02-01T00:00:00.000
Totalfunding
$2,171,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoral
Name
West 59 Street, West 60 Street between Amsterdam Avenue and West End Avenue
Parkid
M063
Latitude
40.771294
Longitude
-73.988729
Borough
Brooklyn, Queens, Manhattan, Bronx
VIEW LOCATION
3898
Trackerid: 3898 • Fmsid: 846 P-6BLDG9A • Title: Citywide Buildings Reconstruction (CNYG-209M)
Trackerid
3898
Fmsid
846 P-6BLDG9A
Title
Citywide Buildings Reconstruction (CNYG-209M)
Summary
This project will reconstruct buildings and public restroom buildings in various parks citywide.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2009-08-01T00:00:00.000
Designactualcompletion
2009-09-01T00:00:00.000
Procurementstart
2009-09-01T00:00:00.000
Procurementprojectedcompletion
2010-06-01T00:00:00.000
Procurementactualcompletion
2010-07-01T00:00:00.000
Constructionstart
2010-07-01T00:00:00.000
Constructionprojectedcom
2013-07-01T00:00:00.000
Constructionadjustedcompletion
2015-02-01T00:00:00.000
Constructionactualcompletion
2015-02-01T00:00:00.000
Totalfunding
$2,171,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoral
Name
Hammersley, Ely, Burke, Gunther Avenues
Parkid
X196
Latitude
40.873683
Longitude
-73.839166
Borough
Brooklyn, Queens, Manhattan, Bronx
VIEW LOCATION
3898
Trackerid: 3898 • Fmsid: 846 P-6BLDG9A • Title: Citywide Buildings Reconstruction (CNYG-209M)
Trackerid
3898
Fmsid
846 P-6BLDG9A
Title
Citywide Buildings Reconstruction (CNYG-209M)
Summary
This project will reconstruct buildings and public restroom buildings in various parks citywide.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2009-08-01T00:00:00.000
Designactualcompletion
2009-09-01T00:00:00.000
Procurementstart
2009-09-01T00:00:00.000
Procurementprojectedcompletion
2010-06-01T00:00:00.000
Procurementactualcompletion
2010-07-01T00:00:00.000
Constructionstart
2010-07-01T00:00:00.000
Constructionprojectedcom
2013-07-01T00:00:00.000
Constructionadjustedcompletion
2015-02-01T00:00:00.000
Constructionactualcompletion
2015-02-01T00:00:00.000
Totalfunding
$2,171,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoral
Name
Beach 83rd Street & Rockaway Beach Boulevard
Parkid
Q367
Latitude
40.588203
Longitude
-73.809374
Borough
Brooklyn, Queens, Manhattan, Bronx
VIEW LOCATION
3898
Trackerid: 3898 • Fmsid: 846 P-6BLDG9A • Title: Citywide Buildings Reconstruction (CNYG-209M)
Trackerid
3898
Fmsid
846 P-6BLDG9A
Title
Citywide Buildings Reconstruction (CNYG-209M)
Summary
This project will reconstruct buildings and public restroom buildings in various parks citywide.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2009-08-01T00:00:00.000
Designactualcompletion
2009-09-01T00:00:00.000
Procurementstart
2009-09-01T00:00:00.000
Procurementprojectedcompletion
2010-06-01T00:00:00.000
Procurementactualcompletion
2010-07-01T00:00:00.000
Constructionstart
2010-07-01T00:00:00.000
Constructionprojectedcom
2013-07-01T00:00:00.000
Constructionadjustedcompletion
2015-02-01T00:00:00.000
Constructionactualcompletion
2015-02-01T00:00:00.000
Totalfunding
$2,171,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoral
Name
Goulden Avenue, West 205 Street, Paul Avenue, Bedford Park Boulevard
Parkid
X136
Latitude
40.876281
Longitude
-73.891882
Borough
Brooklyn, Queens, Manhattan, Bronx
VIEW LOCATION
3898
Trackerid: 3898 • Fmsid: 846 P-6BLDG9A • Title: Citywide Buildings Reconstruction (CNYG-209M)
Trackerid
3898
Fmsid
846 P-6BLDG9A
Title
Citywide Buildings Reconstruction (CNYG-209M)
Summary
This project will reconstruct buildings and public restroom buildings in various parks citywide.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2009-08-01T00:00:00.000
Designactualcompletion
2009-09-01T00:00:00.000
Procurementstart
2009-09-01T00:00:00.000
Procurementprojectedcompletion
2010-06-01T00:00:00.000
Procurementactualcompletion
2010-07-01T00:00:00.000
Constructionstart
2010-07-01T00:00:00.000
Constructionprojectedcom
2013-07-01T00:00:00.000
Constructionadjustedcompletion
2015-02-01T00:00:00.000
Constructionactualcompletion
2015-02-01T00:00:00.000
Totalfunding
$2,171,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoral
Name
West 155th & Dyckman Streets, Edgecombe & Amsterdam Avenues
Parkid
M037
Latitude
40.842759
Longitude
-73.93429
Borough
Brooklyn, Queens, Manhattan, Bronx
VIEW LOCATION
3898
Trackerid: 3898 • Fmsid: 846 P-6BLDG9A • Title: Citywide Buildings Reconstruction (CNYG-209M)
Trackerid
3898
Fmsid
846 P-6BLDG9A
Title
Citywide Buildings Reconstruction (CNYG-209M)
Summary
This project will reconstruct buildings and public restroom buildings in various parks citywide.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2009-08-01T00:00:00.000
Designactualcompletion
2009-09-01T00:00:00.000
Procurementstart
2009-09-01T00:00:00.000
Procurementprojectedcompletion
2010-06-01T00:00:00.000
Procurementactualcompletion
2010-07-01T00:00:00.000
Constructionstart
2010-07-01T00:00:00.000
Constructionprojectedcom
2013-07-01T00:00:00.000
Constructionadjustedcompletion
2015-02-01T00:00:00.000
Constructionactualcompletion
2015-02-01T00:00:00.000
Totalfunding
$2,171,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoral
Name
Dyckman Street, Hudson River, Harlem River Ship Canal
Parkid
M042
Latitude
40.874044
Longitude
-73.920126
Borough
Brooklyn, Queens, Manhattan, Bronx
VIEW LOCATION
3898
Trackerid: 3898 • Fmsid: 846 P-6BLDG9A • Title: Citywide Buildings Reconstruction (CNYG-209M)
Trackerid
3898
Fmsid
846 P-6BLDG9A
Title
Citywide Buildings Reconstruction (CNYG-209M)
Summary
This project will reconstruct buildings and public restroom buildings in various parks citywide.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2009-08-01T00:00:00.000
Designactualcompletion
2009-09-01T00:00:00.000
Procurementstart
2009-09-01T00:00:00.000
Procurementprojectedcompletion
2010-06-01T00:00:00.000
Procurementactualcompletion
2010-07-01T00:00:00.000
Constructionstart
2010-07-01T00:00:00.000
Constructionprojectedcom
2013-07-01T00:00:00.000
Constructionadjustedcompletion
2015-02-01T00:00:00.000
Constructionactualcompletion
2015-02-01T00:00:00.000
Totalfunding
$2,171,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoral
Name
Schermerhorn & Nevins Street
Parkid
B137
Latitude
40.686792
Longitude
-73.981006
Borough
Brooklyn, Queens, Manhattan, Bronx
VIEW LOCATION
7327
Trackerid: 7327 • Fmsid: 846 P-207BTFY • Title: Butterfly Gardens Pavement Reconstruction and Planted Area Expansion
Trackerid
7327
Fmsid
846 P-207BTFY
Title
Butterfly Gardens Pavement Reconstruction and Planted Area Expansion
Summary
This project will reconstruct Butterfly Gardens including new pavements, fencing, benches, and trash receptacles and expanded planted areas.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2015-09-01T00:00:00.000
Designprojectedcompletion
2016-06-01T00:00:00.000
Designadjustedcompletion
2016-08-01T00:00:00.000
Designactualcompletion
2016-07-01T00:00:00.000
Procurementstart
2016-07-01T00:00:00.000
Procurementprojectedcompletion
2017-03-01T00:00:00.000
Procurementadjustedcompletion
2017-09-01T00:00:00.000
Procurementactualcompletion
2017-08-01T00:00:00.000
Constructionstart
2017-09-01T00:00:00.000
Constructionprojectedcom
2018-09-01T00:00:00.000
Constructionactualcompletion
2018-09-01T00:00:00.000
Totalfunding
$637,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough PresidentMayoral
Name
7th Avenue and 18th Street
Parkid
B255G
Latitude
40.66032
Longitude
-73.986475
Borough
Brooklyn
VIEW LOCATION
1506111
Trackerid: 1506111 • Fmsid: 846 P-202CPST • Title: Cadman Plaza Park Synthetic Turf Reconstruction
Trackerid
1506111
Fmsid
846 P-202CPST
Title
Cadman Plaza Park Synthetic Turf Reconstruction
Summary
This project will reconstruct the synthetic turf at Cadman Plaza Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2022-08-01T00:00:00.000
Designprojectedcompletion
2023-10-01T00:00:00.000
Designactualcompletion
2023-06-01T00:00:00.000
Procurementstart
2022-10-01T00:00:00.000
Procurementprojectedcompletion
2023-03-01T00:00:00.000
Procurementactualcompletion
2023-06-01T00:00:00.000
Constructionstart
2023-08-01T00:00:00.000
Constructionprojectedcom
2024-02-01T00:00:00.000
Constructionactualcompletion
2023-09-01T00:00:00.000
Totalfunding
$660,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Parkid
B113A
Latitude
40.697693
Longitude
-73.990675
Borough
Brooklyn
VIEW LOCATION
9215
Trackerid: 9215 • Fmsid: 846 P-202CAD2 • Title: Cadman Plaza Park Oval Reconstruction
Trackerid
9215
Fmsid
846 P-202CAD2
Title
Cadman Plaza Park Oval Reconstruction
Summary
This project will reconstruct the oval at Cadman Plaza Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2019-06-01T00:00:00.000
Designprojectedcompletion
2020-06-01T00:00:00.000
Designactualcompletion
2020-07-01T00:00:00.000
Procurementstart
2020-07-01T00:00:00.000
Procurementprojectedcompletion
2021-04-01T00:00:00.000
Procurementadjustedcompletion
2022-11-01T00:00:00.000
Procurementactualcompletion
2022-10-01T00:00:00.000
Constructionstart
2023-01-01T00:00:00.000
Constructionprojectedcom
2024-01-01T00:00:00.000
Constructionadjustedcompletion
2024-05-01T00:00:00.000
Constructionactualcompletion
2024-04-01T00:00:00.000
Totalfunding
$4,227,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Between Cadman Plaza East, Cadman Plaza West, the Brooklyn Bridge, and the Brooklyn War Memorial
Parkid
B113A
Latitude
40.698828
Longitude
-73.990337
Borough
Brooklyn
VIEW LOCATION
1044
Trackerid: 1044 • Fmsid: 846 P-202CADM • Title: Cadman Plaza Park Brooklyn War Memorial ADA Ramp and Elevator Construction
Trackerid
1044
Fmsid
846 P-202CADM
Title
Cadman Plaza Park Brooklyn War Memorial ADA Ramp and Elevator Construction
Summary
This project will install an accessible ramp and elevator at the Brooklyn War Memorial in Cadman Plaza Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2016-06-01T00:00:00.000
Designprojectedcompletion
2017-06-01T00:00:00.000
Designadjustedcompletion
2017-07-01T00:00:00.000
Designactualcompletion
2017-08-01T00:00:00.000
Procurementstart
2017-08-01T00:00:00.000
Procurementprojectedcompletion
2018-05-01T00:00:00.000
Procurementadjustedcompletion
2019-07-01T00:00:00.000
Procurementactualcompletion
2019-07-01T00:00:00.000
Constructionstart
2020-01-01T00:00:00.000
Constructionprojectedcom
2021-01-01T00:00:00.000
Constructionadjustedcompletion
2022-04-01T00:00:00.000
Constructionactualcompletion
2021-10-01T00:00:00.000
Totalfunding
$3,889,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough PresidentCity CouncilFederalMayoral
Name
Cadman Plaza West, Tillary Street, Cadman Plaza East, Tillary Street, Brooklyn Bridge
Parkid
B113A
Latitude
40.698459966852
Longitude
-73.990859575848
Borough
Brooklyn
VIEW LOCATION
8985
Trackerid: 8985 • Fmsid: 846 P-6CADMAR • Currentphase: construction
Trackerid
8985
Fmsid
846 P-6CADMAR
Title
Marlboro Playground and Cadman Plaza Park Public Restroom Building Reconstruction
Summary
This project will reconstruct the public restroom buildings at Marlboro Playground and Cadman Plaza Park.
Currentphase
construction
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
16.0
Designstart
2017-12-01T00:00:00.000
Designprojectedcompletion
2019-08-01T00:00:00.000
Designadjustedcompletion
2022-12-01T00:00:00.000
Designactualcompletion
2023-01-01T00:00:00.000
Procurementstart
2023-01-01T00:00:00.000
Procurementprojectedcompletion
2021-09-01T00:00:00.000
Procurementadjustedcompletion
2025-08-01T00:00:00.000
Procurementactualcompletion
2025-09-01T00:00:00.000
Constructionstart
2025-10-01T00:00:00.000
Constructionprojectedcom
2028-10-01T00:00:00.000
Totalfunding
$4,439,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough PresidentMayoralState
Name
Tillary, Cadman Plaza East, Prospect Streets
Parkid
B113A
Latitude
40.696824
Longitude
-73.991014
Borough
Brooklyn
VIEW LOCATION
8985
Trackerid: 8985 • Fmsid: 846 P-6CADMAR • Currentphase: construction
Trackerid
8985
Fmsid
846 P-6CADMAR
Title
Marlboro Playground and Cadman Plaza Park Public Restroom Building Reconstruction
Summary
This project will reconstruct the public restroom buildings at Marlboro Playground and Cadman Plaza Park.
Currentphase
construction
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
16.0
Designstart
2017-12-01T00:00:00.000
Designprojectedcompletion
2019-08-01T00:00:00.000
Designadjustedcompletion
2022-12-01T00:00:00.000
Designactualcompletion
2023-01-01T00:00:00.000
Procurementstart
2023-01-01T00:00:00.000
Procurementprojectedcompletion
2021-09-01T00:00:00.000
Procurementadjustedcompletion
2025-08-01T00:00:00.000
Procurementactualcompletion
2025-09-01T00:00:00.000
Constructionstart
2025-10-01T00:00:00.000
Constructionprojectedcom
2028-10-01T00:00:00.000
Totalfunding
$4,439,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough PresidentMayoralState
Name
West 11th Street & Avenue W
Parkid
B272
Latitude
40.591348
Longitude
-73.981062
Borough
Brooklyn
VIEW LOCATION
1951111
Trackerid: 1951111 • Fmsid: 846 P-501CLP1 • Title: Clove Lakes Park Path Pavement Reconstruction
Trackerid
1951111
Fmsid
846 P-501CLP1
Title
Clove Lakes Park Path Pavement Reconstruction
Summary
This project will reconstruct paved pathways in Clove Lakes Park.
Currentphase
design-procurement
Designpercentcomplete
30.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
0.0
Designstart
2026-03-01T00:00:00.000
Designprojectedcompletion
2026-12-01T00:00:00.000
Procurementstart
2026-05-01T00:00:00.000
Procurementprojectedcompletion
2026-10-01T00:00:00.000
Procurementactualcompletion
2026-08-01T00:00:00.000
Totalfunding
$2,500,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Parkid
R005
Latitude
40.620499
Longitude
-74.115084
Borough
Staten Island
VIEW LOCATION
8986
Trackerid: 8986 • Fmsid: 846 P-6WPEBCS • Currentphase: completed
Trackerid
8986
Fmsid
846 P-6WPEBCS
Title
Brooklyn War Memorial Restroom and Eleanor Roosevelt Playground Public Restroom Building Reconstruction
Summary
This project will reconstruct Brooklyn War Memorial Restroom and Eleanor Roosevelt Playground public restroom building.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2017-12-01T00:00:00.000
Designprojectedcompletion
2018-11-01T00:00:00.000
Designactualcompletion
2019-07-01T00:00:00.000
Procurementstart
2019-07-01T00:00:00.000
Procurementprojectedcompletion
2020-04-01T00:00:00.000
Procurementadjustedcompletion
2020-12-01T00:00:00.000
Procurementactualcompletion
2021-05-01T00:00:00.000
Constructionstart
2021-06-01T00:00:00.000
Constructionprojectedcom
2023-06-01T00:00:00.000
Constructionactualcompletion
2023-04-01T00:00:00.000
Totalfunding
$1,697,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoral
Name
Tillary, Cadman Plaza East, Prospect Streets
Parkid
B113A
Latitude
40.698452173293
Longitude
-73.990622476275
Borough
Brooklyn
VIEW LOCATION
8986
Trackerid: 8986 • Fmsid: 846 P-6WPEBCS • Currentphase: completed
Trackerid
8986
Fmsid
846 P-6WPEBCS
Title
Brooklyn War Memorial Restroom and Eleanor Roosevelt Playground Public Restroom Building Reconstruction
Summary
This project will reconstruct Brooklyn War Memorial Restroom and Eleanor Roosevelt Playground public restroom building.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2017-12-01T00:00:00.000
Designprojectedcompletion
2018-11-01T00:00:00.000
Designactualcompletion
2019-07-01T00:00:00.000
Procurementstart
2019-07-01T00:00:00.000
Procurementprojectedcompletion
2020-04-01T00:00:00.000
Procurementadjustedcompletion
2020-12-01T00:00:00.000
Procurementactualcompletion
2021-05-01T00:00:00.000
Constructionstart
2021-06-01T00:00:00.000
Constructionprojectedcom
2023-06-01T00:00:00.000
Constructionactualcompletion
2023-04-01T00:00:00.000
Totalfunding
$1,697,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoral
Name
Dekalb Avenue / Kosciusko Street between Lewis & Stuyvesant Avenues
Parkid
B359
Latitude
40.692749193586
Longitude
-73.935811548213
Borough
Brooklyn
VIEW LOCATION
8549
Trackerid: 8549 • Fmsid: 846 NDF-CLNKY • Title: Callahan-Kelly Playground Reconstruction
Trackerid
8549
Fmsid
846 NDF-CLNKY
Title
Callahan-Kelly Playground Reconstruction
Summary
This project will reconstruct the playground, spray shower, perimeter sidewalks and walls, basketball courts, adult fitness equipment and sitting areas in Callahan-Kelly Playground. In addition, this project will construct a new skate park and park entrances.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2016-09-01T00:00:00.000
Designprojectedcompletion
2018-01-01T00:00:00.000
Designadjustedcompletion
2018-06-01T00:00:00.000
Designactualcompletion
2018-06-01T00:00:00.000
Procurementstart
2018-06-01T00:00:00.000
Procurementprojectedcompletion
2019-03-01T00:00:00.000
Procurementadjustedcompletion
2020-10-01T00:00:00.000
Procurementactualcompletion
2021-03-01T00:00:00.000
Constructionstart
2021-04-01T00:00:00.000
Constructionprojectedcom
2023-04-01T00:00:00.000
Constructionadjustedcompletion
2023-06-01T00:00:00.000
Constructionactualcompletion
2023-08-01T00:00:00.000
Totalfunding
$19,744,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Fulton Street, Truxton Street, Van Sinderen Avenue
Parkid
B219
Latitude
40.678334
Longitude
-73.90518
Borough
Brooklyn
VIEW LOCATION
1376111
Trackerid: 1376111 • Fmsid: 846 P-6SUSTN1 • Title: Calvert Vaux Park Ballfield Lighting Reconstruction
Trackerid
1376111
Fmsid
846 P-6SUSTN1
Title
Calvert Vaux Park Ballfield Lighting Reconstruction
Summary
This project will reconstruct the ballfield lighting at Calvert Vaux Park with energy-efficient LED fixtures.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2021-10-01T00:00:00.000
Designprojectedcompletion
2022-11-01T00:00:00.000
Designactualcompletion
2022-11-01T00:00:00.000
Procurementstart
2021-12-01T00:00:00.000
Procurementprojectedcompletion
2022-05-01T00:00:00.000
Procurementactualcompletion
2022-10-01T00:00:00.000
Constructionstart
2023-10-01T00:00:00.000
Constructionprojectedcom
2023-12-01T00:00:00.000
Constructionactualcompletion
2023-09-01T00:00:00.000
Totalfunding
$389,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Parkid
B125
Latitude
40.585401
Longitude
-73.994368
Borough
Brooklyn
VIEW LOCATION
1759111
Trackerid: 1759111 • Fmsid: 846 P-213CVPK • Title: Calvert Vaux Park Synthetic Turf Fields Reconstruction
Trackerid
1759111
Fmsid
846 P-213CVPK
Title
Calvert Vaux Park Synthetic Turf Fields Reconstruction
Summary
This project will reconstruct the synthetic turf fields at Calvert Vaux Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2024-05-01T00:00:00.000
Designprojectedcompletion
2024-12-01T00:00:00.000
Designactualcompletion
2024-11-01T00:00:00.000
Procurementstart
2024-08-01T00:00:00.000
Procurementprojectedcompletion
2025-01-01T00:00:00.000
Procurementactualcompletion
2024-11-01T00:00:00.000
Constructionstart
2025-01-01T00:00:00.000
Constructionprojectedcom
2025-05-01T00:00:00.000
Constructionactualcompletion
2025-04-01T00:00:00.000
Totalfunding
$2,960,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Parkid
B125
Latitude
40.5865432
Longitude
-73.9939169
Borough
Brooklyn
VIEW LOCATION
2063
Trackerid: 2063 • Fmsid: 846 P-2PNYC03 • Title: Calvert Vaux Park Soccer Fields Construction
Trackerid
2063
Fmsid
846 P-2PNYC03
Title
Calvert Vaux Park Soccer Fields Construction
Summary
This project will construct two soccer fields in Calvert Vaux Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2007-04-01T00:00:00.000
Designprojectedcompletion
2007-09-01T00:00:00.000
Designadjustedcompletion
2007-12-01T00:00:00.000
Designactualcompletion
2007-12-01T00:00:00.000
Procurementstart
2007-12-01T00:00:00.000
Procurementprojectedcompletion
2008-09-01T00:00:00.000
Procurementactualcompletion
2008-06-01T00:00:00.000
Constructionstart
2009-02-01T00:00:00.000
Constructionprojectedcom
2010-02-01T00:00:00.000
Constructionadjustedcompletion
2013-10-01T00:00:00.000
Constructionactualcompletion
2013-10-01T00:00:00.000
Totalfunding
$17,155,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Shore Parkway between Bay 44th & Bay 49th Streets.
Parkid
B125
Latitude
40.585752
Longitude
-73.992571
Borough
Brooklyn
VIEW LOCATION
1038
Trackerid: 1038 • Fmsid: 846 P-2PNYC05 • Title: Calvert Vaux Park Public Restroom Building and Maintenance Facility Construction
Trackerid
1038
Fmsid
846 P-2PNYC05
Title
Calvert Vaux Park Public Restroom Building and Maintenance Facility Construction
Summary
This project will construct a public restroom building and maintenance facility in Calvert Vaux Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2011-07-01T00:00:00.000
Designprojectedcompletion
2014-08-01T00:00:00.000
Designadjustedcompletion
2017-11-01T00:00:00.000
Designactualcompletion
2018-01-01T00:00:00.000
Procurementstart
2018-01-01T00:00:00.000
Procurementprojectedcompletion
2018-10-01T00:00:00.000
Procurementadjustedcompletion
2019-08-01T00:00:00.000
Procurementactualcompletion
2019-07-01T00:00:00.000
Constructionstart
2019-12-01T00:00:00.000
Constructionprojectedcom
2021-05-01T00:00:00.000
Constructionadjustedcompletion
2022-10-01T00:00:00.000
Constructionactualcompletion
2023-03-01T00:00:00.000
Totalfunding
$10,163,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoral
Name
Shore Parkway near Bay 48th Street
Parkid
B125
Latitude
40.585108
Longitude
-73.992288
Borough
Brooklyn
VIEW LOCATION
1732
Trackerid: 1732 • Fmsid: 846 P-213018A • Title: Calvert Vaux Park Aquatic and Coastal Upland Habitat Restoration
Trackerid
1732
Fmsid
846 P-213018A
Title
Calvert Vaux Park Aquatic and Coastal Upland Habitat Restoration
Summary
This project will construct a 3.5-acre natural habitat for waterfowl by excavating existing fill material, re-grading steep slopes and creating inter-tidal zones. It will also include a new boat launch ramp, fencing, and plantings.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2001-11-01T00:00:00.000
Designprojectedcompletion
2002-10-01T00:00:00.000
Designadjustedcompletion
2009-01-01T00:00:00.000
Designactualcompletion
2009-01-01T00:00:00.000
Procurementstart
2009-01-01T00:00:00.000
Procurementprojectedcompletion
2009-10-01T00:00:00.000
Procurementactualcompletion
2011-07-01T00:00:00.000
Constructionstart
2011-09-01T00:00:00.000
Constructionprojectedcom
2012-08-01T00:00:00.000
Constructionadjustedcompletion
2013-08-01T00:00:00.000
Constructionactualcompletion
2013-08-01T00:00:00.000
Totalfunding
$3,152,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoralState
Name
Shore Parkway near Bay 49th Street
Parkid
B125
Latitude
40.584074
Longitude
-73.992157
Borough
Brooklyn
VIEW LOCATION
6608
Trackerid: 6608 • Fmsid: 846 P-4PLG15D • Currentphase: completed
Trackerid
6608
Fmsid
846 P-4PLG15D
Title
Nautilus, Walter Ward, and Cambria Playgrounds Basketball and Handball Courts Reconstruction
Summary
This project will reconstruct basketball and handball courts at Nautilus Playground and Cambria Playground, and the basketball courts at Walter Ward Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2014-07-01T00:00:00.000
Designprojectedcompletion
2015-03-01T00:00:00.000
Designadjustedcompletion
2015-04-01T00:00:00.000
Designactualcompletion
2015-05-01T00:00:00.000
Procurementstart
2015-05-01T00:00:00.000
Procurementprojectedcompletion
2016-02-01T00:00:00.000
Procurementadjustedcompletion
2016-05-01T00:00:00.000
Procurementactualcompletion
2016-04-01T00:00:00.000
Constructionstart
2016-06-01T00:00:00.000
Constructionprojectedcom
2017-12-01T00:00:00.000
Constructionactualcompletion
2017-03-01T00:00:00.000
Totalfunding
$983,000
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
121 Avenue & 220 Street
Parkid
Q339
Latitude
40.689116
Longitude
-73.742872
Borough
Queens
VIEW LOCATION
6608
Trackerid: 6608 • Fmsid: 846 P-4PLG15D • Currentphase: completed
Trackerid
6608
Fmsid
846 P-4PLG15D
Title
Nautilus, Walter Ward, and Cambria Playgrounds Basketball and Handball Courts Reconstruction
Summary
This project will reconstruct basketball and handball courts at Nautilus Playground and Cambria Playground, and the basketball courts at Walter Ward Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2014-07-01T00:00:00.000
Designprojectedcompletion
2015-03-01T00:00:00.000
Designadjustedcompletion
2015-04-01T00:00:00.000
Designactualcompletion
2015-05-01T00:00:00.000
Procurementstart
2015-05-01T00:00:00.000
Procurementprojectedcompletion
2016-02-01T00:00:00.000
Procurementadjustedcompletion
2016-05-01T00:00:00.000
Procurementactualcompletion
2016-04-01T00:00:00.000
Constructionstart
2016-06-01T00:00:00.000
Constructionprojectedcom
2017-12-01T00:00:00.000
Constructionactualcompletion
2017-03-01T00:00:00.000
Totalfunding
$983,000
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Baisley & Merrick Boulevards, 115 Avenue
Parkid
Q448
Latitude
40.685093
Longitude
-73.770738
Borough
Queens
VIEW LOCATION
6608
Trackerid: 6608 • Fmsid: 846 P-4PLG15D • Currentphase: completed
Trackerid
6608
Fmsid
846 P-4PLG15D
Title
Nautilus, Walter Ward, and Cambria Playgrounds Basketball and Handball Courts Reconstruction
Summary
This project will reconstruct basketball and handball courts at Nautilus Playground and Cambria Playground, and the basketball courts at Walter Ward Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2014-07-01T00:00:00.000
Designprojectedcompletion
2015-03-01T00:00:00.000
Designadjustedcompletion
2015-04-01T00:00:00.000
Designactualcompletion
2015-05-01T00:00:00.000
Procurementstart
2015-05-01T00:00:00.000
Procurementprojectedcompletion
2016-02-01T00:00:00.000
Procurementadjustedcompletion
2016-05-01T00:00:00.000
Procurementactualcompletion
2016-04-01T00:00:00.000
Constructionstart
2016-06-01T00:00:00.000
Constructionprojectedcom
2017-12-01T00:00:00.000
Constructionactualcompletion
2017-03-01T00:00:00.000
Totalfunding
$983,000
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
89 St and 160 Av
Parkid
Q421
Latitude
40.657667
Longitude
-73.843636
Borough
Queens
VIEW LOCATION
8861
Trackerid: 8861 • Fmsid: 846 P-4BWIDER • Title: Queens Adult Fitness Equipment Construction (QG-618M)
Trackerid
8861
Fmsid
846 P-4BWIDER
Title
Queens Adult Fitness Equipment Construction (QG-618M)
Summary
This project will install adult fitness equipment at Cambria Playground, Haggerty Park, and Montbellier Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2017-09-01T00:00:00.000
Designprojectedcompletion
2018-09-01T00:00:00.000
Designactualcompletion
2018-10-01T00:00:00.000
Procurementstart
2018-10-01T00:00:00.000
Procurementprojectedcompletion
2019-07-01T00:00:00.000
Procurementactualcompletion
2019-06-01T00:00:00.000
Constructionstart
2019-07-01T00:00:00.000
Constructionprojectedcom
2020-07-01T00:00:00.000
Constructionactualcompletion
2020-03-01T00:00:00.000
Totalfunding
$614,000
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
121 Avenue & 220 Street
Parkid
Q339
Latitude
40.689682
Longitude
-73.743084
Borough
Queens
VIEW LOCATION
8861
Trackerid: 8861 • Fmsid: 846 P-4BWIDER • Title: Queens Adult Fitness Equipment Construction (QG-618M)
Trackerid
8861
Fmsid
846 P-4BWIDER
Title
Queens Adult Fitness Equipment Construction (QG-618M)
Summary
This project will install adult fitness equipment at Cambria Playground, Haggerty Park, and Montbellier Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2017-09-01T00:00:00.000
Designprojectedcompletion
2018-09-01T00:00:00.000
Designactualcompletion
2018-10-01T00:00:00.000
Procurementstart
2018-10-01T00:00:00.000
Procurementprojectedcompletion
2019-07-01T00:00:00.000
Procurementactualcompletion
2019-06-01T00:00:00.000
Constructionstart
2019-07-01T00:00:00.000
Constructionprojectedcom
2020-07-01T00:00:00.000
Constructionactualcompletion
2020-03-01T00:00:00.000
Totalfunding
$614,000
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
202 Street & Jamaica Avenue S/S
Parkid
Q359
Latitude
40.712995
Longitude
-73.757964
Borough
Queens
VIEW LOCATION
8861
Trackerid: 8861 • Fmsid: 846 P-4BWIDER • Title: Queens Adult Fitness Equipment Construction (QG-618M)
Trackerid
8861
Fmsid
846 P-4BWIDER
Title
Queens Adult Fitness Equipment Construction (QG-618M)
Summary
This project will install adult fitness equipment at Cambria Playground, Haggerty Park, and Montbellier Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2017-09-01T00:00:00.000
Designprojectedcompletion
2018-09-01T00:00:00.000
Designactualcompletion
2018-10-01T00:00:00.000
Procurementstart
2018-10-01T00:00:00.000
Procurementprojectedcompletion
2019-07-01T00:00:00.000
Procurementactualcompletion
2019-06-01T00:00:00.000
Constructionstart
2019-07-01T00:00:00.000
Constructionprojectedcom
2020-07-01T00:00:00.000
Constructionactualcompletion
2020-03-01T00:00:00.000
Totalfunding
$614,000
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
Springfield Boulevard & 139 Avenue
Parkid
Q396
Latitude
40.673958
Longitude
-73.756596
Borough
Queens
VIEW LOCATION
9842
Trackerid: 9842 • Fmsid: 846 P-413CAMB • Title: Cambria Playground Reconstruction
Trackerid
9842
Fmsid
846 P-413CAMB
Title
Cambria Playground Reconstruction
Summary
This project will reconstruct Cambria Playground.
Currentphase
procurement
Designpercentcomplete
100.0
Procurementpercentcomplete
60.0
Constructionpercentcomplete
0.0
Designstart
2021-04-01T00:00:00.000
Designprojectedcompletion
2022-04-01T00:00:00.000
Designadjustedcompletion
2024-11-01T00:00:00.000
Designactualcompletion
2024-11-01T00:00:00.000
Procurementstart
2026-04-01T00:00:00.000
Procurementprojectedcompletion
2027-04-01T00:00:00.000
Totalfunding
Between $3 million and $5 million
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough President, City Council
Name
121st Avenue and Francis Lewis Boulevard near 222nd Street
Parkid
Q339
Latitude
40.68863882
Longitude
-73.74230727
Borough
Queens
VIEW LOCATION
1944111
Trackerid: 1944111 • Fmsid: 846 P-218CPMC • Title: Monroe Cohen Park Path Reconstruction
Trackerid
1944111
Fmsid
846 P-218CPMC
Title
Monroe Cohen Park Path Reconstruction
Summary
This project will reconstruct paved surfaces at Monroe Cohen Park.
Currentphase
construction
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
0.0
Designstart
2026-05-01T00:00:00.000
Designprojectedcompletion
2026-02-01T00:00:00.000
Designactualcompletion
2026-09-01T00:00:00.000
Procurementstart
2026-05-01T00:00:00.000
Procurementprojectedcompletion
2026-10-01T00:00:00.000
Procurementactualcompletion
2026-08-01T00:00:00.000
Totalfunding
$2,000,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
State
Parkid
B018
Latitude
40.6299267
Longitude
-73.8931327
Borough
Brooklyn
VIEW LOCATION
6424
Trackerid: 6424 • Fmsid: 846 P-2BELTPD • Title: Canarsie West Trail Connector Construction
Trackerid
6424
Fmsid
846 P-2BELTPD
Title
Canarsie West Trail Connector Construction
Summary
This project will construct a multi-use greenway path connecting the on-street path along Paerdegat Avenue North to the Shore Parkway Greenway along the southwestern edge of Canarsie Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2014-09-01T00:00:00.000
Designprojectedcompletion
2015-10-01T00:00:00.000
Designactualcompletion
2016-01-01T00:00:00.000
Procurementstart
2016-01-01T00:00:00.000
Procurementprojectedcompletion
2016-10-01T00:00:00.000
Procurementadjustedcompletion
2017-05-01T00:00:00.000
Procurementactualcompletion
2017-04-01T00:00:00.000
Constructionstart
2017-05-01T00:00:00.000
Constructionprojectedcom
2018-05-01T00:00:00.000
Constructionactualcompletion
2018-05-01T00:00:00.000
Totalfunding
$1,230,000
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Federal
Name
Paerdegat Avenue North & Seaview Avenue to Shore Parkway
Parkid
B018
Latitude
40.624239
Longitude
-73.897798
Borough
Brooklyn
VIEW LOCATION
1931
Trackerid: 1931 • Fmsid: 846 P-218CANR • Title: Canarsie Park Playground Construction
Trackerid
1931
Fmsid
846 P-218CANR
Title
Canarsie Park Playground Construction
Summary
This project will construct a playground in Canarsie Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2011-03-01T00:00:00.000
Designprojectedcompletion
2011-10-01T00:00:00.000
Designadjustedcompletion
2011-12-01T00:00:00.000
Designactualcompletion
2011-12-01T00:00:00.000
Procurementstart
2011-12-01T00:00:00.000
Procurementprojectedcompletion
2012-09-01T00:00:00.000
Procurementadjustedcompletion
2011-05-01T00:00:00.000
Procurementactualcompletion
2012-10-01T00:00:00.000
Constructionstart
2012-10-01T00:00:00.000
Constructionprojectedcom
2013-10-01T00:00:00.000
Constructionadjustedcompletion
2012-04-01T00:00:00.000
Constructionactualcompletion
2013-10-01T00:00:00.000
Totalfunding
$2,225,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough President, City Council
Name
Seaview Avenue and East 80th Street.
Parkid
B018
Latitude
40.626846
Longitude
-73.899487
Borough
Brooklyn
VIEW LOCATION
9666
Trackerid: 9666 • Fmsid: 846 P-218CCMF • Title: Canarsie Park Public Restroom Building Construction
Trackerid
9666
Fmsid
846 P-218CCMF
Title
Canarsie Park Public Restroom Building Construction
Summary
This project will construct a public restroom building in Canarsie Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2015-01-01T00:00:00.000
Designprojectedcompletion
2015-09-01T00:00:00.000
Designadjustedcompletion
2017-05-01T00:00:00.000
Designactualcompletion
2017-05-01T00:00:00.000
Procurementstart
2017-05-01T00:00:00.000
Procurementprojectedcompletion
2018-01-01T00:00:00.000
Procurementadjustedcompletion
2021-12-01T00:00:00.000
Procurementactualcompletion
2022-01-01T00:00:00.000
Constructionstart
2022-05-01T00:00:00.000
Constructionprojectedcom
2023-10-01T00:00:00.000
Constructionadjustedcompletion
2024-09-01T00:00:00.000
Constructionactualcompletion
2024-10-01T00:00:00.000
Totalfunding
$4,385,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough PresidentCity CouncilMayoralPrivate
Name
Seaview Avenue and Paerdegat Avenue North
Parkid
B018
Latitude
40.626217
Longitude
-73.900409
Borough
Brooklyn
VIEW LOCATION