Capital Project Tracker

A listing of all capital projects managed by NYC Parks, and a timeline for their completion.

Supporting documentation can be found at the following link (http://www.nycgovparks.org/bigapps/desc/DPR_CapitalProjectTracker_001.txt).

See JSON and XML feeds here https://data.cityofnewyork.us/Recreation/Capital-Project-Tracker/qiwj-i2jk

Recreation Department of Parks and Recreation (DPR) Dataset 4hcv-tc5r 29 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
9276
Trackerid: 9276 • Fmsid: 846 P-104GBLE • Title: Goble Playground Reconstruction
Trackerid
9276
Fmsid
846 P-104GBLE
Title
Goble Playground Reconstruction
Summary
This project will reconstruct Goble Playground, including the play equipment, swings, basketball and handball courts, drainage and water systems, landscaping and park security lighting.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2021-03-01T00:00:00.000
Designprojectedcompletion
2022-03-01T00:00:00.000
Designadjustedcompletion
2022-08-01T00:00:00.000
Designactualcompletion
2022-08-01T00:00:00.000
Procurementstart
2022-08-01T00:00:00.000
Procurementprojectedcompletion
2023-05-01T00:00:00.000
Procurementadjustedcompletion
2024-03-01T00:00:00.000
Procurementactualcompletion
2024-03-01T00:00:00.000
Constructionstart
2024-06-01T00:00:00.000
Constructionprojectedcom
2025-06-01T00:00:00.000
Constructionactualcompletion
2025-06-01T00:00:00.000
Totalfunding
$3,793,000
Projectliaison
Katerine Borrome
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
Goble Place between Inwood Avenue and Macombs Road
Parkid
X114
Latitude
40.843809
Longitude
-73.91693
Borough
Bronx
VIEW LOCATION
10625
Trackerid: 10625 • Fmsid: 846 P-2CPIGPP • Title: Gonzalo Plasencia Playground Reconstruction
Trackerid
10625
Fmsid
846 P-2CPIGPP
Title
Gonzalo Plasencia Playground Reconstruction
Summary
This project will reconstruct the playground, natural turf field, basketball courts, handball courts, and sitting area in Gonzalo Plasencia Playground.
Currentphase
design
Designpercentcomplete
100.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Designstart
2024-09-01T00:00:00.000
Designprojectedcompletion
2025-12-01T00:00:00.000
Designactualcompletion
2025-12-01T00:00:00.000
Totalfunding
Between $5 million and $10 million
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
41st Street between 3rd and 4th Avenues
Parkid
B210I
Latitude
40.6522359
Longitude
-74.00810381
Borough
Brooklyn
VIEW LOCATION
9283
Trackerid: 9283 • Fmsid: 846 P-205GRPG • Title: Grace Playground Reconstruction
Trackerid
9283
Fmsid
846 P-205GRPG
Title
Grace Playground Reconstruction
Summary
This project will reconstruct the playground area in Grace Playground, including the play equipment, safety surfacing, spray shower, fencing, and utilities.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2019-05-01T00:00:00.000
Designprojectedcompletion
2020-05-01T00:00:00.000
Designactualcompletion
2020-05-01T00:00:00.000
Procurementstart
2020-05-01T00:00:00.000
Procurementprojectedcompletion
2021-02-01T00:00:00.000
Procurementadjustedcompletion
2022-02-01T00:00:00.000
Procurementactualcompletion
2022-01-01T00:00:00.000
Constructionstart
2022-04-01T00:00:00.000
Constructionprojectedcom
2023-04-01T00:00:00.000
Constructionactualcompletion
2023-03-01T00:00:00.000
Totalfunding
$1,798,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
Vermont Street between Pitkin Avenue and Belmont Avenue
Parkid
B078
Latitude
40.671767
Longitude
-73.894477
Borough
Brooklyn
VIEW LOCATION
1212
Trackerid: 1212 • Fmsid: 846 P-105GAPL • Title: Grand Playground Construction
Trackerid
1212
Fmsid
846 P-105GAPL
Title
Grand Playground Construction
Summary
This project will construct Grand Playground, including a new play area, sitting area, spray shower, and basketball court.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2011-05-01T00:00:00.000
Designprojectedcompletion
2014-05-01T00:00:00.000
Designadjustedcompletion
2015-04-01T00:00:00.000
Designactualcompletion
2015-04-01T00:00:00.000
Procurementstart
2015-04-01T00:00:00.000
Procurementprojectedcompletion
2016-01-01T00:00:00.000
Procurementadjustedcompletion
2016-05-01T00:00:00.000
Procurementactualcompletion
2016-05-01T00:00:00.000
Constructionstart
2016-05-01T00:00:00.000
Constructionprojectedcom
2017-08-01T00:00:00.000
Constructionactualcompletion
2017-06-01T00:00:00.000
Totalfunding
$2,349,000
Projectliaison
Katerine Borrome
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
Grand Avenue and West 181st Street
Parkid
X244
Latitude
40.85603167
Longitude
-73.90722944
Borough
Bronx
VIEW LOCATION
10061
Trackerid: 10061 • Fmsid: 846 P-404GSPS • Title: Grand Slope Staircase Reconstruction
Trackerid
10061
Fmsid
846 P-404GSPS
Title
Grand Slope Staircase Reconstruction
Summary
This project will reconstruct the staircase at Grand Slope.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2021-11-01T00:00:00.000
Designprojectedcompletion
2022-11-01T00:00:00.000
Designactualcompletion
2022-11-01T00:00:00.000
Procurementstart
2022-11-01T00:00:00.000
Procurementprojectedcompletion
2023-08-01T00:00:00.000
Procurementadjustedcompletion
2024-06-01T00:00:00.000
Procurementactualcompletion
2024-08-01T00:00:00.000
Constructionstart
2024-09-01T00:00:00.000
Constructionprojectedcom
2025-09-01T00:00:00.000
Constructionactualcompletion
2025-02-01T00:00:00.000
Totalfunding
$347,000
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoral
Name
Grand Avenue and Kneeland Avenue at Haspel Street
Parkid
Q151
Latitude
40.734583
Longitude
-73.882779
Borough
Queens
VIEW LOCATION
1186
Trackerid: 1186 • Fmsid: 846 P-104GPPV • Title: Grant Park Playground and Basketball Court Reconstruction
Trackerid
1186
Fmsid
846 P-104GPPV
Title
Grant Park Playground and Basketball Court Reconstruction
Summary
This project will reconstruct the playground and basketball court at Grant Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2015-03-01T00:00:00.000
Designprojectedcompletion
2016-12-01T00:00:00.000
Designadjustedcompletion
2017-08-01T00:00:00.000
Designactualcompletion
2017-08-01T00:00:00.000
Procurementstart
2017-08-01T00:00:00.000
Procurementprojectedcompletion
2018-05-01T00:00:00.000
Procurementadjustedcompletion
2018-09-01T00:00:00.000
Procurementactualcompletion
2018-07-01T00:00:00.000
Constructionstart
2018-08-01T00:00:00.000
Constructionprojectedcom
2020-02-01T00:00:00.000
Constructionactualcompletion
2020-03-01T00:00:00.000
Totalfunding
$3,250,000
Projectliaison
Katerine Borrome
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough PresidentCity CouncilMayoral
Name
Grant Avenue and East 169th Street
Parkid
X271
Latitude
40.8376625
Longitude
-73.91207028
Borough
Bronx
VIEW LOCATION
9153
Trackerid: 9153 • Fmsid: 846 NDF-GRANT • Title: Grant Park Construction
Trackerid
9153
Fmsid
846 NDF-GRANT
Title
Grant Park Construction
Summary
This project will construct Grant Park, including converting the roadbed to recreational space.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2019-05-01T00:00:00.000
Designprojectedcompletion
2020-11-01T00:00:00.000
Designadjustedcompletion
2021-03-01T00:00:00.000
Designactualcompletion
2021-03-01T00:00:00.000
Procurementstart
2021-03-01T00:00:00.000
Procurementprojectedcompletion
2021-12-01T00:00:00.000
Procurementadjustedcompletion
2023-10-01T00:00:00.000
Procurementactualcompletion
2023-09-01T00:00:00.000
Constructionstart
2023-10-01T00:00:00.000
Constructionprojectedcom
2025-10-01T00:00:00.000
Constructionadjustedcompletion
2026-02-01T00:00:00.000
Constructionactualcompletion
2026-03-01T00:00:00.000
Totalfunding
$17,001,000
Projectliaison
Katerine Borrome
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough PresidentMayoral
Name
Grant Avenue between East 169th Street and East 170th Street
Parkid
X271
Latitude
40.836755
Longitude
-73.913112
Borough
Bronx
VIEW LOCATION
10805
Trackerid: 10805 • Title: Grant Park Public Restroom Building Construction • Currentphase: proposed
Trackerid
10805
Title
Grant Park Public Restroom Building Construction
Summary
This project will construct a prefabricated modular public restroom building in Grant Park.
Currentphase
proposed
Designpercentcomplete
0.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Totalfunding
Between $3 million and $5 million
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Grant Avenue between East 169th Street and East 170th Street
Parkid
X271
Latitude
40.83621151
Longitude
-73.91313394
Borough
Bronx
VIEW LOCATION
7036
Trackerid: 7036 • Fmsid: 846 P-4CPIGRS • Title: Grassmere Playground Reconstruction
Trackerid
7036
Fmsid
846 P-4CPIGRS
Title
Grassmere Playground Reconstruction
Summary
This project will reconstruct the play equipment, swings, landscaping, and sitting areas in Grassmere Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2015-02-01T00:00:00.000
Designprojectedcompletion
2015-12-01T00:00:00.000
Designactualcompletion
2016-01-01T00:00:00.000
Procurementstart
2016-01-01T00:00:00.000
Procurementprojectedcompletion
2016-10-01T00:00:00.000
Procurementactualcompletion
2016-07-01T00:00:00.000
Constructionstart
2016-11-01T00:00:00.000
Constructionprojectedcom
2018-05-01T00:00:00.000
Constructionactualcompletion
2017-11-01T00:00:00.000
Totalfunding
$3,724,000
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Hanson Court between Grassmere Terrace and Briar Place
Parkid
Q353
Latitude
40.59927694
Longitude
-73.75891
Borough
Queens
VIEW LOCATION
1721
Trackerid: 1721 • Fmsid: 846 P-212GRVD • Title: Gravesend Park Public Restroom Building Construction
Trackerid
1721
Fmsid
846 P-212GRVD
Title
Gravesend Park Public Restroom Building Construction
Summary
This project will construct a new public restroom building at Gravesend Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2012-01-01T00:00:00.000
Designprojectedcompletion
2013-07-01T00:00:00.000
Designadjustedcompletion
2014-09-01T00:00:00.000
Designactualcompletion
2014-09-01T00:00:00.000
Procurementstart
2014-09-01T00:00:00.000
Procurementprojectedcompletion
2015-06-01T00:00:00.000
Procurementadjustedcompletion
2015-08-01T00:00:00.000
Procurementactualcompletion
2015-08-01T00:00:00.000
Constructionstart
2015-11-01T00:00:00.000
Constructionprojectedcom
2017-04-01T00:00:00.000
Constructionadjustedcompletion
2017-06-01T00:00:00.000
Constructionactualcompletion
2017-06-01T00:00:00.000
Totalfunding
$1,855,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough PresidentCity CouncilMayoral
Name
18th Avenue between 56th Street and 57th Street
Parkid
B042
Latitude
40.624007
Longitude
-73.984896
Borough
Brooklyn
VIEW LOCATION
11384
Trackerid: 11384 • Title: Gravesend Park Playground Reconstruction • Summary: This project will reconstruct the playground at Gravesend Park.
Trackerid
11384
Title
Gravesend Park Playground Reconstruction
Summary
This project will reconstruct the playground at Gravesend Park.
Currentphase
proposed
Designpercentcomplete
0.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Totalfunding
Less than $1 million
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
18th Avenue, 19th Avenue, 55th Street, 58th Street
Parkid
B042
Latitude
40.6235732
Longitude
-73.9850353
Borough
Brooklyn
VIEW LOCATION
1615
Trackerid: 1615 • Fmsid: 846 P-212C17F • Title: Gravesend Park Playground and Court Area Reconstruction
Trackerid
1615
Fmsid
846 P-212C17F
Title
Gravesend Park Playground and Court Area Reconstruction
Summary
This project will demolish the hockey rink and expand the playground and reconstruct the court area and ballfields in Gravesend Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2009-09-01T00:00:00.000
Designprojectedcompletion
2012-11-01T00:00:00.000
Designadjustedcompletion
2013-04-01T00:00:00.000
Designactualcompletion
2014-04-01T00:00:00.000
Procurementstart
2014-04-01T00:00:00.000
Procurementprojectedcompletion
2015-01-01T00:00:00.000
Procurementactualcompletion
2014-12-01T00:00:00.000
Constructionstart
2015-05-01T00:00:00.000
Constructionprojectedcom
2016-11-01T00:00:00.000
Constructionadjustedcompletion
2017-03-01T00:00:00.000
Constructionactualcompletion
2016-10-01T00:00:00.000
Totalfunding
$5,176,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough PresidentCity CouncilMayoral
Name
18th Avenue, 55th Street, 19th Avenue, 58th Street
Parkid
B042
Latitude
40.623538
Longitude
-73.985007
Borough
Brooklyn
VIEW LOCATION
1062111
Trackerid: 1062111 • Fmsid: 846 EXPENSE • Title: New Dorp Beach Temporary Berm Reconstruction
Trackerid
1062111
Fmsid
846 EXPENSE
Title
New Dorp Beach Temporary Berm Reconstruction
Summary
This project will reconstruct and maintain temporary berms installed after Hurricane Sandy at New Dorp Beach in Staten Island.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2014-11-01T00:00:00.000
Designprojectedcompletion
2015-06-01T00:00:00.000
Designactualcompletion
2016-02-01T00:00:00.000
Procurementstart
2016-03-01T00:00:00.000
Procurementprojectedcompletion
2016-08-01T00:00:00.000
Procurementactualcompletion
2016-02-01T00:00:00.000
Constructionstart
2016-05-01T00:00:00.000
Constructionprojectedcom
2016-06-01T00:00:00.000
Constructionactualcompletion
2016-06-01T00:00:00.000
Totalfunding
$53,000
Projectliaison
Katrina Toal
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Parkid
R016
Latitude
40.55554
Longitude
-74.109621
Borough
Staten Island
VIEW LOCATION
6318
Trackerid: 6318 • Fmsid: 846 SANDY5-23 • Title: New Dorp Center Interior Reconstruction (Hurricane Sandy)
Trackerid
6318
Fmsid
846 SANDY5-23
Title
New Dorp Center Interior Reconstruction (Hurricane Sandy)
Summary
This project will reconstruct the first floor of the New Dorp Center in Staten Island due to damage from Hurricane Sandy.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2014-04-01T00:00:00.000
Designprojectedcompletion
2014-11-01T00:00:00.000
Designadjustedcompletion
2015-09-01T00:00:00.000
Designactualcompletion
2016-07-01T00:00:00.000
Procurementstart
2016-07-01T00:00:00.000
Procurementprojectedcompletion
2017-04-01T00:00:00.000
Procurementadjustedcompletion
2017-11-01T00:00:00.000
Procurementactualcompletion
2017-11-01T00:00:00.000
Constructionstart
2018-03-01T00:00:00.000
Constructionprojectedcom
2019-09-01T00:00:00.000
Constructionactualcompletion
2019-08-01T00:00:00.000
Totalfunding
$2,435,000
Projectliaison
Katrina Toal
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough PresidentCity CouncilFederalMayoral
Name
128 Cedar Grove Avenue
Parkid
R016
Latitude
40.561401413259
Longitude
-74.099997762258
Borough
Staten Island
VIEW LOCATION
5921
Trackerid: 5921 • Fmsid: 846 P-5OAKBRM • Title: Cedar Grove Beach Access Improvements
Trackerid
5921
Fmsid
846 P-5OAKBRM
Title
Cedar Grove Beach Access Improvements
Summary
This project will reconstruct the roads and paths at Cedar Grove Beach in Great Kills Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2011-10-01T00:00:00.000
Designprojectedcompletion
2012-06-01T00:00:00.000
Designactualcompletion
2012-09-01T00:00:00.000
Procurementstart
2012-09-01T00:00:00.000
Procurementprojectedcompletion
2013-06-01T00:00:00.000
Procurementactualcompletion
2013-05-01T00:00:00.000
Constructionstart
2014-06-01T00:00:00.000
Constructionprojectedcom
2015-06-01T00:00:00.000
Constructionactualcompletion
2015-05-01T00:00:00.000
Totalfunding
$343,000
Projectliaison
Katrina Toal
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
Cedar Grove Beach Place
Parkid
R016
Latitude
40.557379
Longitude
-74.101816
Borough
Staten Island
VIEW LOCATION
7066
Trackerid: 7066 • Fmsid: 846 SANDY5-30 • Title: New Dorp Beach Site Restoration in Great Kills Park (Hurricane Sandy)
Trackerid
7066
Fmsid
846 SANDY5-30
Title
New Dorp Beach Site Restoration in Great Kills Park (Hurricane Sandy)
Summary
This project will reconstruct Hurricane Sandy-damaged site amenities, a spray shower and paths at New Dorp Beach in Great Kills Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2015-04-01T00:00:00.000
Designprojectedcompletion
2016-05-01T00:00:00.000
Designadjustedcompletion
2017-02-01T00:00:00.000
Designactualcompletion
2017-02-01T00:00:00.000
Procurementstart
2017-02-01T00:00:00.000
Procurementprojectedcompletion
2017-11-01T00:00:00.000
Procurementadjustedcompletion
2018-03-01T00:00:00.000
Procurementactualcompletion
2018-03-01T00:00:00.000
Constructionstart
2018-04-01T00:00:00.000
Constructionprojectedcom
2019-04-01T00:00:00.000
Constructionactualcompletion
2019-02-01T00:00:00.000
Totalfunding
$371,000
Projectliaison
Katrina Toal
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
FederalMayoral
Name
Ebbits Avenue and New Dorp Lane along Cedar Grove Avenue
Parkid
R016
Latitude
40.557726
Longitude
-74.101228
Borough
Staten Island
VIEW LOCATION
6205
Trackerid: 6205 • Fmsid: 846 P-501CEDG • Title: Cedar Grove Beach Freshwater Wetlands Reconstruction and Planting
Trackerid
6205
Fmsid
846 P-501CEDG
Title
Cedar Grove Beach Freshwater Wetlands Reconstruction and Planting
Summary
This project will reconstruct the freshwater wetlands, plantings and site work at Cedar Grove Beach in Great Kills Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2013-11-01T00:00:00.000
Designprojectedcompletion
2014-06-01T00:00:00.000
Designactualcompletion
2014-07-01T00:00:00.000
Procurementstart
2014-07-01T00:00:00.000
Procurementprojectedcompletion
2015-03-01T00:00:00.000
Procurementadjustedcompletion
2015-08-01T00:00:00.000
Procurementactualcompletion
2015-07-01T00:00:00.000
Constructionstart
2015-09-01T00:00:00.000
Constructionprojectedcom
2017-09-01T00:00:00.000
Constructionactualcompletion
2017-01-01T00:00:00.000
Totalfunding
$799,000
Projectliaison
Katrina Toal
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoral
Name
Ebbitts Street and Cedar Grove Avenue
Parkid
R016
Latitude
40.550913
Longitude
-74.11102
Borough
Staten Island
VIEW LOCATION
7087
Trackerid: 7087 • Fmsid: 846 P-204GRCK • Title: Green Central Knoll Public Restroom Building Construction
Trackerid
7087
Fmsid
846 P-204GRCK
Title
Green Central Knoll Public Restroom Building Construction
Summary
This project will construct a new public restroom building and an accessible ramp in Green Central Knoll.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2014-09-01T00:00:00.000
Designprojectedcompletion
2015-10-01T00:00:00.000
Designactualcompletion
2016-09-01T00:00:00.000
Procurementstart
2016-09-01T00:00:00.000
Procurementprojectedcompletion
2017-06-01T00:00:00.000
Procurementactualcompletion
2017-05-01T00:00:00.000
Constructionstart
2017-06-01T00:00:00.000
Constructionprojectedcom
2018-06-01T00:00:00.000
Constructionadjustedcompletion
2019-07-01T00:00:00.000
Constructionactualcompletion
2019-08-01T00:00:00.000
Totalfunding
$3,793,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoralPrivate
Name
Evergreen Avenue, Noll Street, Central Avenue, Flushing Avenue
Parkid
B395
Latitude
40.70193361
Longitude
-73.93303472
Borough
Brooklyn
VIEW LOCATION
6277
Trackerid: 6277 • Fmsid: 846 P-503GCPL • Title: Greencroft Playground Public Restroom Building Construction
Trackerid
6277
Fmsid
846 P-503GCPL
Title
Greencroft Playground Public Restroom Building Construction
Summary
This project will demolish the existing public restroom building and construct a new public restroom building at Greencroft Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2015-05-01T00:00:00.000
Designprojectedcompletion
2016-06-01T00:00:00.000
Designadjustedcompletion
2017-07-01T00:00:00.000
Designactualcompletion
2017-07-01T00:00:00.000
Procurementstart
2017-07-01T00:00:00.000
Procurementprojectedcompletion
2018-04-01T00:00:00.000
Procurementadjustedcompletion
2019-10-01T00:00:00.000
Procurementactualcompletion
2019-10-01T00:00:00.000
Constructionstart
2019-12-01T00:00:00.000
Constructionprojectedcom
2021-06-01T00:00:00.000
Constructionadjustedcompletion
2022-08-01T00:00:00.000
Constructionactualcompletion
2022-10-01T00:00:00.000
Totalfunding
$3,301,000
Projectliaison
Katrina Toal
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough President, City Council
Name
Greencroft Avenue Between Redgrave Avenue and Ainsworth Avenue
Parkid
R089
Latitude
40.55177917
Longitude
-74.13643444
Borough
Staten Island
VIEW LOCATION
9970
Trackerid: 9970 • Fmsid: 846 P-503GCPG • Title: Greencroft Playground Reconstruction
Trackerid
9970
Fmsid
846 P-503GCPG
Title
Greencroft Playground Reconstruction
Summary
This project will reconstruct the playground area at Greencroft Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2021-11-01T00:00:00.000
Designprojectedcompletion
2022-11-01T00:00:00.000
Designadjustedcompletion
2023-10-01T00:00:00.000
Designactualcompletion
2023-09-01T00:00:00.000
Procurementstart
2023-09-01T00:00:00.000
Procurementprojectedcompletion
2024-09-01T00:00:00.000
Procurementadjustedcompletion
2025-04-01T00:00:00.000
Procurementactualcompletion
2025-04-01T00:00:00.000
Constructionstart
2025-06-01T00:00:00.000
Constructionprojectedcom
2026-06-01T00:00:00.000
Constructionactualcompletion
2026-06-01T00:00:00.000
Totalfunding
$8,262,000
Projectliaison
Katrina Toal
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoral
Name
Redgrave Avenue and Greencroft Avenue
Parkid
R089
Latitude
40.55220317
Longitude
-74.13635566
Borough
Staten Island
VIEW LOCATION
9820
Trackerid: 9820 • Fmsid: 846 P-202GRPL • Title: Greene Playground Reconstruction
Trackerid
9820
Fmsid
846 P-202GRPL
Title
Greene Playground Reconstruction
Summary
This project will reconstruct the playground at Greene Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2021-01-01T00:00:00.000
Designprojectedcompletion
2022-01-01T00:00:00.000
Designadjustedcompletion
2022-05-01T00:00:00.000
Designactualcompletion
2022-05-01T00:00:00.000
Procurementstart
2022-05-01T00:00:00.000
Procurementprojectedcompletion
2023-02-01T00:00:00.000
Procurementadjustedcompletion
2023-12-01T00:00:00.000
Procurementactualcompletion
2023-12-01T00:00:00.000
Constructionstart
2024-04-01T00:00:00.000
Constructionprojectedcom
2025-04-01T00:00:00.000
Constructionadjustedcompletion
2025-06-01T00:00:00.000
Constructionactualcompletion
2025-06-01T00:00:00.000
Totalfunding
$3,000,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
Greene & Washington Avenues
Parkid
B301
Latitude
40.686323
Longitude
-73.965791
Borough
Brooklyn
VIEW LOCATION
10082
Trackerid: 10082 • Title: Greene Playground Multipurpose Play Area and Sports Courts Reconstruction • Currentphase: proposed
Trackerid
10082
Title
Greene Playground Multipurpose Play Area and Sports Courts Reconstruction
Summary
This project will reconstruct the multipurpose play area, basketball courts, and handball courts at Greene Playground.
Currentphase
proposed
Designpercentcomplete
0.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Totalfunding
Between $1 million and $3 million
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
Greene Avenue & Waverly Avenue
Parkid
B301
Latitude
40.68640207
Longitude
-73.96593871
Borough
Brooklyn
VIEW LOCATION
11375
Trackerid: 11375 • Title: Greenpoint Playground Reconstruction • Summary: This project will reconstruct Greenpoint Playground.
Trackerid
11375
Title
Greenpoint Playground Reconstruction
Summary
This project will reconstruct Greenpoint Playground.
Currentphase
proposed
Designpercentcomplete
0.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Totalfunding
Between $1 million and $3 million
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough President, City Council
Name
Franklin Street, Commerical Street, Dupont Street
Parkid
B043
Latitude
40.7357101
Longitude
-73.9587977
Borough
Brooklyn
VIEW LOCATION
10394
Trackerid: 10394 • Fmsid: 846 P-207GWHB • Currentphase: completed
Trackerid
10394
Fmsid
846 P-207GWHB
Title
Greenwood Playground Handball Courts Reconstruction and Pickleball Court Construction
Summary
This project will reconstruct the handball courts and construct pickleball courts at Greenwood Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2022-11-01T00:00:00.000
Designprojectedcompletion
2023-11-01T00:00:00.000
Designactualcompletion
2023-10-01T00:00:00.000
Procurementstart
2023-10-01T00:00:00.000
Procurementprojectedcompletion
2024-10-01T00:00:00.000
Procurementadjustedcompletion
2025-02-01T00:00:00.000
Procurementactualcompletion
2025-03-01T00:00:00.000
Constructionstart
2025-03-01T00:00:00.000
Constructionprojectedcom
2026-03-01T00:00:00.000
Constructionactualcompletion
2026-04-01T00:00:00.000
Totalfunding
$999,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
Fort Hamilton Parkway, Greenwood Avenue, East 5th Street
Parkid
B130
Latitude
40.650354
Longitude
-73.976298
Borough
Brooklyn
VIEW LOCATION
1614111
Trackerid: 1614111 • Fmsid: 846 P-1PAVBRX • Title: Grove Hill Playground Multipurpose Play Area Pavement Reconstruction
Trackerid
1614111
Fmsid
846 P-1PAVBRX
Title
Grove Hill Playground Multipurpose Play Area Pavement Reconstruction
Summary
This project will reconstruct pavements at the multipurpose play area in Grove Hill Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2023-06-01T00:00:00.000
Designprojectedcompletion
2024-05-01T00:00:00.000
Designactualcompletion
2024-04-01T00:00:00.000
Procurementstart
2023-07-01T00:00:00.000
Procurementprojectedcompletion
2023-12-01T00:00:00.000
Procurementactualcompletion
2024-04-01T00:00:00.000
Constructionstart
2024-09-01T00:00:00.000
Constructionprojectedcom
2025-05-01T00:00:00.000
Constructionactualcompletion
2025-02-01T00:00:00.000
Totalfunding
$550,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Parkid
X235
Latitude
40.819897
Longitude
-73.908801
Borough
Bronx
VIEW LOCATION
8997
Trackerid: 8997 • Fmsid: 846 P-1GHPCSR • Title: Grove Hill Playground Public Restroom Building Reconstruction
Trackerid
8997
Fmsid
846 P-1GHPCSR
Title
Grove Hill Playground Public Restroom Building Reconstruction
Summary
This project will reconstruct the public restroom building in Grove Hill Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2018-01-01T00:00:00.000
Designprojectedcompletion
2019-01-01T00:00:00.000
Designactualcompletion
2019-01-01T00:00:00.000
Procurementstart
2019-01-01T00:00:00.000
Procurementprojectedcompletion
2019-10-01T00:00:00.000
Procurementadjustedcompletion
2020-04-01T00:00:00.000
Procurementactualcompletion
2020-03-01T00:00:00.000
Constructionstart
2020-10-01T00:00:00.000
Constructionprojectedcom
2022-04-01T00:00:00.000
Constructionactualcompletion
2023-04-01T00:00:00.000
Totalfunding
$1,366,000
Projectliaison
Katerine Borrome
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
East 158th Street between Eagle Avenue and Cauldwell Avenue
Parkid
X235
Latitude
40.819976
Longitude
-73.908997
Borough
Bronx
VIEW LOCATION
9345
Trackerid: 9345 • Fmsid: 846 P-4BWSTF1 • Title: Grover Cleveland Playground and Pals Oval Synthetic Turf Fields Reconstruction
Trackerid
9345
Fmsid
846 P-4BWSTF1
Title
Grover Cleveland Playground and Pals Oval Synthetic Turf Fields Reconstruction
Summary
This project will reconstruct the synthetic turf fields at Grover Cleveland Playground and Pals Oval.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2018-10-01T00:00:00.000
Designprojectedcompletion
2019-01-01T00:00:00.000
Designactualcompletion
2019-01-01T00:00:00.000
Procurementstart
2019-01-01T00:00:00.000
Procurementprojectedcompletion
2019-10-01T00:00:00.000
Procurementadjustedcompletion
2020-04-01T00:00:00.000
Procurementactualcompletion
2020-04-01T00:00:00.000
Constructionstart
2020-09-01T00:00:00.000
Constructionprojectedcom
2021-06-01T00:00:00.000
Constructionactualcompletion
2020-11-01T00:00:00.000
Totalfunding
$1,418,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Rene Court, Grandview Avenue, Stanhope Street & Fairview Avenue
Parkid
Q002
Latitude
40.710285
Longitude
-73.911492
Borough
Queens
VIEW LOCATION
9345
Trackerid: 9345 • Fmsid: 846 P-4BWSTF1 • Title: Grover Cleveland Playground and Pals Oval Synthetic Turf Fields Reconstruction
Trackerid
9345
Fmsid
846 P-4BWSTF1
Title
Grover Cleveland Playground and Pals Oval Synthetic Turf Fields Reconstruction
Summary
This project will reconstruct the synthetic turf fields at Grover Cleveland Playground and Pals Oval.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2018-10-01T00:00:00.000
Designprojectedcompletion
2019-01-01T00:00:00.000
Designactualcompletion
2019-01-01T00:00:00.000
Procurementstart
2019-01-01T00:00:00.000
Procurementprojectedcompletion
2019-10-01T00:00:00.000
Procurementadjustedcompletion
2020-04-01T00:00:00.000
Procurementactualcompletion
2020-04-01T00:00:00.000
Constructionstart
2020-09-01T00:00:00.000
Constructionprojectedcom
2021-06-01T00:00:00.000
Constructionactualcompletion
2020-11-01T00:00:00.000
Totalfunding
$1,418,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
North Conduit Avenue, between 80 and 88 Streets, 133 Avenue
Parkid
Q094
Latitude
40.671696
Longitude
-73.848657
Borough
Queens
VIEW LOCATION
10078
Trackerid: 10078 • Fmsid: 846 P-4RRDPK • Title: Gwen Ifill Park and Public Restroom Building Construction
Trackerid
10078
Fmsid
846 P-4RRDPK
Title
Gwen Ifill Park and Public Restroom Building Construction
Summary
This project will construct a playground, basketball courts, adult fitness equipment, entry plazas, public restroom and pathways at Gwen Ifill Park.
Currentphase
design
Designpercentcomplete
100.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Designstart
2021-09-01T00:00:00.000
Designprojectedcompletion
2023-09-01T00:00:00.000
Designadjustedcompletion
2025-12-01T00:00:00.000
Designactualcompletion
2025-12-01T00:00:00.000
Totalfunding
Greater than $10 million
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
129th Avenue between 172nd Street and 176th Street
Parkid
Q412
Latitude
40.67936275
Longitude
-73.76883853
Borough
Queens
VIEW LOCATION
10158
Trackerid: 10158 • Fmsid: 846 P-1HAFFPL • Title: Haffen Park Pool Complex Reconstruction
Trackerid
10158
Fmsid
846 P-1HAFFPL
Title
Haffen Park Pool Complex Reconstruction
Summary
This project will reconstruct the pool complex at Haffen Park.
Currentphase
construction
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
11.0
Designstart
2021-08-01T00:00:00.000
Designprojectedcompletion
2022-10-01T00:00:00.000
Designadjustedcompletion
2023-01-01T00:00:00.000
Designactualcompletion
2023-02-01T00:00:00.000
Procurementstart
2023-02-01T00:00:00.000
Procurementprojectedcompletion
2026-04-01T00:00:00.000
Procurementactualcompletion
2025-10-01T00:00:00.000
Constructionstart
2025-12-01T00:00:00.000
Constructionprojectedcom
2027-08-01T00:00:00.000
Totalfunding
$13,402,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral State
Name
1814 Burke Avenue
Parkid
X196
Latitude
40.87431436
Longitude
-73.83889704
Borough
Bronx
VIEW LOCATION
10119
Trackerid: 10119 • Fmsid: 846 P-1HAFFP1 • Currentphase: design
Trackerid
10119
Fmsid
846 P-1HAFFP1
Title
Haffen Park Courts, Synthetic Turf Field, Playground, Adult Fitness, and Landscape Reconstruction
Summary
This project will reconstruct the playground, landscape, tennis courts, basketball courts, synthetic turf ballfield, pavements, water and drainage systems, park lighting, plantings, and construct an adult fitness area at Haffen Park.
Currentphase
design
Designpercentcomplete
100.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Designstart
2022-03-01T00:00:00.000
Designprojectedcompletion
2023-04-01T00:00:00.000
Designadjustedcompletion
2024-08-01T00:00:00.000
Designactualcompletion
2024-08-01T00:00:00.000
Totalfunding
Greater than $10 million
Projectliaison
Katerine Borrome
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough PresidentCity CouncilMayoral
Name
Burke and Hammersley Avenues between Gunther and Ely Avenues
Parkid
X196
Latitude
40.87373737
Longitude
-73.8400404
Borough
Bronx
VIEW LOCATION
10118
Trackerid: 10118 • Fmsid: 846 P-1HAFFP3 • Title: Haffen Amphitheater and Public Restroom Building Reconstruction
Trackerid
10118
Fmsid
846 P-1HAFFP3
Title
Haffen Amphitheater and Public Restroom Building Reconstruction
Summary
This project will reconstruct the public restroom building and amphitheater in Haffen Park.
Currentphase
design
Designpercentcomplete
100.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Designstart
2023-01-01T00:00:00.000
Designprojectedcompletion
2025-01-01T00:00:00.000
Designadjustedcompletion
2026-09-01T00:00:00.000
Designactualcompletion
2026-09-01T00:00:00.000
Totalfunding
Between $5 million and $10 million
Projectliaison
Katerine Borrome
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Gunther Avenue and Hammersley Avenue
Parkid
X196
Latitude
40.8735557
Longitude
-73.839281
Borough
Bronx
VIEW LOCATION
10834
Trackerid: 10834 • Fmsid: 846 P-1HAFFP4 • Title: Haffen Park Field House Construction
Trackerid
10834
Fmsid
846 P-1HAFFP4
Title
Haffen Park Field House Construction
Summary
This project will construct a field house in Haffen Park.
Currentphase
design
Designpercentcomplete
30.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Designstart
2025-07-01T00:00:00.000
Designprojectedcompletion
2026-12-01T00:00:00.000
Totalfunding
Greater than $10 million
Projectliaison
Katerine Borrome
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Hammersley, Ely, Avenues
Parkid
X196
Latitude
40.87378467
Longitude
-73.83916295
Borough
Bronx
VIEW LOCATION
11373
Trackerid: 11373 • Title: Haggerty Park Playground Reconstruction • Summary: This project will reconstruct the playground at Haggerty Park.
Trackerid
11373
Title
Haggerty Park Playground Reconstruction
Summary
This project will reconstruct the playground at Haggerty Park.
Currentphase
proposed
Designpercentcomplete
0.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Totalfunding
Between $5 million and $10 million
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
Jamaica Avenue & 202nd Street
Parkid
Q359
Latitude
40.7131675
Longitude
-73.7585807
Borough
Queens
VIEW LOCATION
1945111
Trackerid: 1945111 • Fmsid: 846 P-105HNBC • Title: Half Nelson Playground Pavement Reconstruction
Trackerid
1945111
Fmsid
846 P-105HNBC
Title
Half Nelson Playground Pavement Reconstruction
Summary
This project will reconstruct the basketball court paved surfaces and color seal.
Currentphase
construction
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
0.0
Designstart
2026-03-01T00:00:00.000
Designprojectedcompletion
2026-05-01T00:00:00.000
Designactualcompletion
2026-08-01T00:00:00.000
Procurementstart
2026-03-01T00:00:00.000
Procurementprojectedcompletion
2026-08-01T00:00:00.000
Procurementactualcompletion
2026-08-01T00:00:00.000
Constructionstart
2026-08-01T00:00:00.000
Constructionprojectedcom
2026-10-01T00:00:00.000
Totalfunding
$325,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Parkid
X295
Latitude
40.8468002
Longitude
-73.9192162
Borough
Bronx
VIEW LOCATION
9549
Trackerid: 9549 • Fmsid: 846 P-4HCHAND • Title: Hallets Cove Playground Handball Court Reconstruction
Trackerid
9549
Fmsid
846 P-4HCHAND
Title
Hallets Cove Playground Handball Court Reconstruction
Summary
This project will reconstruct the handball courts at Hallets Cove Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2020-02-01T00:00:00.000
Designprojectedcompletion
2020-11-01T00:00:00.000
Designactualcompletion
2020-09-01T00:00:00.000
Procurementstart
2020-09-01T00:00:00.000
Procurementprojectedcompletion
2021-05-01T00:00:00.000
Procurementadjustedcompletion
2023-05-01T00:00:00.000
Procurementactualcompletion
2023-05-01T00:00:00.000
Constructionstart
2023-05-01T00:00:00.000
Constructionprojectedcom
2023-11-01T00:00:00.000
Constructionactualcompletion
2023-10-01T00:00:00.000
Totalfunding
$450,000
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough President
Name
Along East River, 1st Street, Astoria Blvd, and Vernon Blvd.
Parkid
Q226
Latitude
40.771845252988
Longitude
-73.934263103335
Borough
Queens
VIEW LOCATION
8894
Trackerid: 8894 • Fmsid: 846 P-401HCSW • Title: Hallets Cove Seawall Reconstruction
Trackerid
8894
Fmsid
846 P-401HCSW
Title
Hallets Cove Seawall Reconstruction
Summary
This project will reconstruct damaged portions of the seawall and railing at Hallets Cove.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2017-09-01T00:00:00.000
Designprojectedcompletion
2018-04-01T00:00:00.000
Designadjustedcompletion
2018-06-01T00:00:00.000
Designactualcompletion
2018-06-01T00:00:00.000
Procurementstart
2018-06-01T00:00:00.000
Procurementprojectedcompletion
2019-03-01T00:00:00.000
Procurementadjustedcompletion
2020-04-01T00:00:00.000
Procurementactualcompletion
2020-04-01T00:00:00.000
Constructionstart
2020-09-01T00:00:00.000
Constructionprojectedcom
2021-09-01T00:00:00.000
Constructionadjustedcompletion
2022-04-01T00:00:00.000
Constructionactualcompletion
2022-09-01T00:00:00.000
Totalfunding
$6,549,000
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Along the East River from Hallets Cove Playground at Vernon Blvd to Hallets Point Playground at Astoria Blvd and 1st Street.
Parkid
Q226
Latitude
40.772227260986
Longitude
-73.936314933849
Borough
Queens
VIEW LOCATION
10668
Trackerid: 10668 • Fmsid: 846 P-4CPIHPP • Title: Hallets Point Playground Reconstruction
Trackerid
10668
Fmsid
846 P-4CPIHPP
Title
Hallets Point Playground Reconstruction
Summary
This project will reconstruct Hallets Point Playground.
Currentphase
procurement
Designpercentcomplete
100.0
Procurementpercentcomplete
5.0
Constructionpercentcomplete
0.0
Designstart
2024-11-01T00:00:00.000
Designprojectedcompletion
2025-05-01T00:00:00.000
Designactualcompletion
2025-06-01T00:00:00.000
Procurementstart
2026-08-01T00:00:00.000
Procurementprojectedcompletion
2027-08-01T00:00:00.000
Totalfunding
Between $3 million and $5 million
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral, Private
Name
Astoria Boulevard between 1st Street and the East River
Parkid
Q226
Latitude
40.77427335
Longitude
-73.93747083
Borough
Queens
VIEW LOCATION
7244
Trackerid: 7244 • Fmsid: 846 P-4HCOVPG • Title: Hallets Cove Playground Reconstruction
Trackerid
7244
Fmsid
846 P-4HCOVPG
Title
Hallets Cove Playground Reconstruction
Summary
This project will reconstruct Hallets Cove Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2016-10-01T00:00:00.000
Designprojectedcompletion
2017-10-01T00:00:00.000
Designactualcompletion
2017-11-01T00:00:00.000
Procurementstart
2017-11-01T00:00:00.000
Procurementprojectedcompletion
2018-08-01T00:00:00.000
Procurementadjustedcompletion
2018-11-01T00:00:00.000
Procurementactualcompletion
2018-11-01T00:00:00.000
Constructionstart
2019-02-01T00:00:00.000
Constructionprojectedcom
2020-02-01T00:00:00.000
Constructionactualcompletion
2019-12-01T00:00:00.000
Totalfunding
$1,866,000
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough PresidentCity CouncilMayoral
Name
Vernon Boulevard between Main Avenue and Astoria Boulevard
Parkid
Q226
Latitude
40.772385
Longitude
-73.934067
Borough
Queens
VIEW LOCATION
8833
Trackerid: 8833 • Fmsid: 846 P-4HCOVP2 • Title: Hallets Cove Playground Multi Purpose Play Area Reconstruction
Trackerid
8833
Fmsid
846 P-4HCOVP2
Title
Hallets Cove Playground Multi Purpose Play Area Reconstruction
Summary
This project will reconstruct the multi-purpose play area at Hallets Cove Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2018-08-01T00:00:00.000
Designprojectedcompletion
2019-08-01T00:00:00.000
Designactualcompletion
2019-08-01T00:00:00.000
Procurementstart
2019-08-01T00:00:00.000
Procurementprojectedcompletion
2020-05-01T00:00:00.000
Procurementadjustedcompletion
2021-07-01T00:00:00.000
Procurementactualcompletion
2021-06-01T00:00:00.000
Constructionstart
2022-04-01T00:00:00.000
Constructionprojectedcom
2023-04-01T00:00:00.000
Constructionactualcompletion
2023-02-01T00:00:00.000
Totalfunding
$2,523,000
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
Vernon Boulevard, Main Avenue, and 8th Street
Parkid
Q226
Latitude
40.772252762233
Longitude
-73.934072391123
Borough
Queens
VIEW LOCATION
1138111
Trackerid: 1138111 • Fmsid: 846 P-3HMFISH • Title: Hamilton Fish Park Basketball Courts and Adult Fitness Equipment Reconstruction
Trackerid
1138111
Fmsid
846 P-3HMFISH
Title
Hamilton Fish Park Basketball Courts and Adult Fitness Equipment Reconstruction
Summary
This project will reconstruct the basketball courts and adult fitness equipment at Hamilton Fish Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2018-11-01T00:00:00.000
Designprojectedcompletion
2019-10-01T00:00:00.000
Designactualcompletion
2020-03-01T00:00:00.000
Procurementstart
2019-09-01T00:00:00.000
Procurementprojectedcompletion
2020-02-01T00:00:00.000
Procurementactualcompletion
2020-02-01T00:00:00.000
Constructionstart
2020-09-01T00:00:00.000
Constructionprojectedcom
2020-12-01T00:00:00.000
Constructionadjustedcompletion
2021-06-01T00:00:00.000
Constructionactualcompletion
2021-05-01T00:00:00.000
Totalfunding
$537,000
Projectliaison
Steve Simon
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough President, City Council
Parkid
M033
Latitude
40.719893
Longitude
-73.981165
Borough
Manhattan
VIEW LOCATION
1591111
Trackerid: 1591111 • Fmsid: 846 EXPENSE • Title: Hamilton Fish Park Pool Filter Plant FaÇade Stabilization
Trackerid
1591111
Fmsid
846 EXPENSE
Title
Hamilton Fish Park Pool Filter Plant FaÇade Stabilization
Summary
This project will stabilize the faÇade of the pool filter plant in Hamilton Fish Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2023-03-01T00:00:00.000
Designprojectedcompletion
2023-01-01T00:00:00.000
Designactualcompletion
2022-05-01T00:00:00.000
Procurementstart
2023-03-01T00:00:00.000
Procurementprojectedcompletion
2023-08-01T00:00:00.000
Procurementactualcompletion
2023-07-01T00:00:00.000
Constructionstart
2022-06-01T00:00:00.000
Constructionprojectedcom
2024-06-01T00:00:00.000
Constructionactualcompletion
2023-06-01T00:00:00.000
Totalfunding
$180,000
Projectliaison
Contact Us
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Parkid
M033
Latitude
40.719827
Longitude
-73.980511
Borough
Manhattan
VIEW LOCATION
9856
Trackerid: 9856 • Fmsid: 846 P-303HMFS • Title: Hamilton Fish Park Playground Reconstruction
Trackerid
9856
Fmsid
846 P-303HMFS
Title
Hamilton Fish Park Playground Reconstruction
Summary
This project will reconstruct the playground at Hamilton Fish Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2021-06-01T00:00:00.000
Designprojectedcompletion
2022-06-01T00:00:00.000
Designadjustedcompletion
2022-11-01T00:00:00.000
Designactualcompletion
2022-11-01T00:00:00.000
Procurementstart
2022-11-01T00:00:00.000
Procurementprojectedcompletion
2023-08-01T00:00:00.000
Procurementadjustedcompletion
2024-12-01T00:00:00.000
Procurementactualcompletion
2024-12-01T00:00:00.000
Constructionstart
2025-01-01T00:00:00.000
Constructionprojectedcom
2026-01-01T00:00:00.000
Constructionactualcompletion
2026-01-01T00:00:00.000
Totalfunding
$3,644,000
Projectliaison
Steve Simon
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
East Houston Street between Sheriff Street and Pitt Street
Parkid
M033
Latitude
40.720120931487
Longitude
-73.980483915228
Borough
Manhattan
VIEW LOCATION
7120
Trackerid: 7120 • Fmsid: 846 P-303HFRC • Title: Hamilton Fish Recreation Center and Pool Reconstruction
Trackerid
7120
Fmsid
846 P-303HFRC
Title
Hamilton Fish Recreation Center and Pool Reconstruction
Summary
This project will reconstruct Hamilton Fish Recreation Center and Pool.
Currentphase
design
Designpercentcomplete
5.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Designstart
2024-05-01T00:00:00.000
Designprojectedcompletion
2026-05-01T00:00:00.000
Totalfunding
Greater than $10 million
Projectliaison
Steve Simon
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoralState
Name
Pitt Street between Stanton Street and East Houston Street
Parkid
M033
Latitude
40.71996159
Longitude
-73.98143707
Borough
Manhattan
VIEW LOCATION
8737
Trackerid: 8737 • Fmsid: 846 P-2STFHM • Title: Hamilton-Metz Field Synthetic Turf Field Reconstruction
Trackerid
8737
Fmsid
846 P-2STFHM
Title
Hamilton-Metz Field Synthetic Turf Field Reconstruction
Summary
This project will reconstruct the existing synthetic turf field at Hamilton-Metz Field.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2017-11-01T00:00:00.000
Designprojectedcompletion
2018-11-01T00:00:00.000
Designactualcompletion
2018-11-01T00:00:00.000
Procurementstart
2018-11-01T00:00:00.000
Procurementprojectedcompletion
2019-08-01T00:00:00.000
Procurementadjustedcompletion
2019-10-01T00:00:00.000
Procurementactualcompletion
2019-10-01T00:00:00.000
Constructionstart
2019-11-01T00:00:00.000
Constructionprojectedcom
2020-11-01T00:00:00.000
Constructionadjustedcompletion
2021-01-01T00:00:00.000
Constructionactualcompletion
2021-01-01T00:00:00.000
Totalfunding
$1,478,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
East New York Avenue and Albany Avenue
Parkid
B193
Latitude
40.66249
Longitude
-73.941272
Borough
Brooklyn
VIEW LOCATION
6220
Trackerid: 6220 • Fmsid: 846 P-310HRFT • Title: Hansborough Recreation Center Gym Floor and Window Reconstruction
Trackerid
6220
Fmsid
846 P-310HRFT
Title
Hansborough Recreation Center Gym Floor and Window Reconstruction
Summary
This project will reconstruct the gymnasium floor and natatorium windows at the Hansborough Recreation Center.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2013-12-01T00:00:00.000
Designprojectedcompletion
2015-03-01T00:00:00.000
Designadjustedcompletion
2015-06-01T00:00:00.000
Designactualcompletion
2015-06-01T00:00:00.000
Procurementstart
2015-06-01T00:00:00.000
Procurementprojectedcompletion
2016-03-01T00:00:00.000
Procurementadjustedcompletion
2016-09-01T00:00:00.000
Procurementactualcompletion
2016-07-01T00:00:00.000
Constructionstart
2016-10-01T00:00:00.000
Constructionprojectedcom
2017-10-01T00:00:00.000
Constructionadjustedcompletion
2017-11-01T00:00:00.000
Constructionactualcompletion
2017-11-01T00:00:00.000
Totalfunding
$435,000
Projectliaison
Steve Simon
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
35 West 134th Street
Parkid
M131
Latitude
40.812823
Longitude
-73.939234
Borough
Manhattan
VIEW LOCATION
6326
Trackerid: 6326 • Fmsid: 846 P-3PDHBRC • Title: Hansborough Recreation Center Reconstruction
Trackerid
6326
Fmsid
846 P-3PDHBRC
Title
Hansborough Recreation Center Reconstruction
Summary
This project will reconstruct the pool, entrance and interior spaces of the Hansborough Recreation Center.
Currentphase
construction
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
63.2
Designstart
2020-03-01T00:00:00.000
Designprojectedcompletion
2021-03-01T00:00:00.000
Designadjustedcompletion
2022-05-01T00:00:00.000
Designactualcompletion
2022-03-01T00:00:00.000
Procurementstart
2022-03-01T00:00:00.000
Procurementprojectedcompletion
2022-12-01T00:00:00.000
Procurementadjustedcompletion
2024-02-01T00:00:00.000
Procurementactualcompletion
2024-01-01T00:00:00.000
Constructionstart
2024-03-01T00:00:00.000
Constructionprojectedcom
2026-03-01T00:00:00.000
Constructionadjustedcompletion
2027-08-01T00:00:00.000
Totalfunding
$70,155,000
Projectliaison
Steve Simon
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoralState
Name
35 West 134th Street between Lenox Terrace and 5th Avenue.
Parkid
M131
Latitude
40.81283112
Longitude
-73.93928228
Borough
Manhattan
VIEW LOCATION
10851
Trackerid: 10851 • Currentphase: proposed • Designpercentcomplete: 0.0
Trackerid
10851
Title
Happy Warrior Playground Basketball Courts and Multipurpose Play Area Reconstruction
Summary
This project will reconstruct the multipurpose play area and basketball courts of Happy Warrior Playground.
Currentphase
proposed
Designpercentcomplete
0.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Totalfunding
Between $3 million and $5 million
Projectliaison
Steve Simon
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
Amsterdam Avenue between West 98th Street and West 99th Street
Parkid
M229
Latitude
40.79555276
Longitude
-73.96855547
Borough
Manhattan
VIEW LOCATION
10672
Trackerid: 10672 • Fmsid: 846 P-1CPIHAP • Title: Harding Park Playground Reconstruction
Trackerid
10672
Fmsid
846 P-1CPIHAP
Title
Harding Park Playground Reconstruction
Summary
This project will reconstruct the playground at the north parcel of Harding Park and construct a pump track and passive areas at the undeveloped south parcel.
Currentphase
design
Designpercentcomplete
100.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Designstart
2024-08-01T00:00:00.000
Designprojectedcompletion
2025-11-01T00:00:00.000
Designactualcompletion
2025-12-01T00:00:00.000
Totalfunding
Greater than $10 million
Projectliaison
Katerine Borrome
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoral
Name
Bolton Avenue between O’Brien and Cornell Avenues
Parkid
X262
Latitude
40.80959146
Longitude
-73.85663606
Borough
Bronx
VIEW LOCATION
9246
Trackerid: 9246 • Fmsid: 846 P-311TURF • Title: Harlem River Park Synthetic Turf Field Reconstruction
Trackerid
9246
Fmsid
846 P-311TURF
Title
Harlem River Park Synthetic Turf Field Reconstruction
Summary
This contract will reconstruct the synthetic turf field in Harlem River Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2019-02-01T00:00:00.000
Designprojectedcompletion
2020-02-01T00:00:00.000
Designactualcompletion
2020-02-01T00:00:00.000
Procurementstart
2020-02-01T00:00:00.000
Procurementprojectedcompletion
2020-11-01T00:00:00.000
Procurementadjustedcompletion
2022-05-01T00:00:00.000
Procurementactualcompletion
2022-04-01T00:00:00.000
Constructionstart
2022-05-01T00:00:00.000
Constructionprojectedcom
2023-05-01T00:00:00.000
Constructionactualcompletion
2022-09-01T00:00:00.000
Totalfunding
$2,386,000
Projectliaison
Steve Simon
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
East 128th Street, Third Avenue Bridge, Harlem River Drive
Parkid
M208D
Latitude
40.805939
Longitude
-73.933758
Borough
Manhattan
VIEW LOCATION