10720
Trackerid: 10720 • Fmsid: 846 P-102JCAP • Title: Julio Carballo Fields Playground Reconstruction
Trackerid
10720
Fmsid
846 P-102JCAP
Title
Julio Carballo Fields Playground Reconstruction
Summary
This project will reconstruct the playground at Julio Carballo Fields.
Currentphase
procurement
Designpercentcomplete
100.0
Procurementpercentcomplete
85.0
Constructionpercentcomplete
0.0
Designstart
2024-01-01T00:00:00.000
Designprojectedcompletion
2025-01-01T00:00:00.000
Designactualcompletion
2025-01-01T00:00:00.000
Procurementstart
2026-02-01T00:00:00.000
Procurementprojectedcompletion
2027-02-01T00:00:00.000
Constructionstart
2026-10-01T00:00:00.000
Constructionprojectedcom
2027-10-01T00:00:00.000
Totalfunding
Between $5 million and $10 million
Projectliaison
Katerine Borrome
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
Manida Street between Spofford Avenue and Lafayette Avenue
Parkid
X260
Latitude
40.8157865
Longitude
-73.88908534
Borough
Bronx
VIEW LOCATION
8880
Trackerid: 8880 • Fmsid: 846 P-102MNDA • Title: Julio Carballo Fields Lighting and Scoreboard Construction
Trackerid
8880
Fmsid
846 P-102MNDA
Title
Julio Carballo Fields Lighting and Scoreboard Construction
Summary
This project will construct sports lighting and a scoreboard at Julio Carballo Fields.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2019-01-01T00:00:00.000
Designprojectedcompletion
2020-01-01T00:00:00.000
Designactualcompletion
2020-02-01T00:00:00.000
Procurementstart
2020-02-01T00:00:00.000
Procurementprojectedcompletion
2020-11-01T00:00:00.000
Procurementadjustedcompletion
2022-04-01T00:00:00.000
Procurementactualcompletion
2022-03-01T00:00:00.000
Constructionstart
2022-05-01T00:00:00.000
Constructionprojectedcom
2023-05-01T00:00:00.000
Constructionactualcompletion
2023-04-01T00:00:00.000
Totalfunding
$1,659,000
Projectliaison
Katerine Borrome
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoral
Name
Manida Street between Spofford Avenue and Lafayette Avenue
Parkid
X260
Latitude
40.815536
Longitude
-73.889049
Borough
Bronx
VIEW LOCATION
1352111
Trackerid: 1352111 • Fmsid: 846 P-405JPSS • Title: Juniper Valley Park Water Service Installation
Trackerid
1352111
Fmsid
846 P-405JPSS
Title
Juniper Valley Park Water Service Installation
Summary
This project will provide water service to the spray shower at Juniper Valley Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2021-06-01T00:00:00.000
Designprojectedcompletion
2022-05-01T00:00:00.000
Designactualcompletion
2021-09-01T00:00:00.000
Procurementstart
2021-07-01T00:00:00.000
Procurementprojectedcompletion
2021-12-01T00:00:00.000
Procurementactualcompletion
2022-03-01T00:00:00.000
Constructionstart
2022-04-01T00:00:00.000
Constructionprojectedcom
2022-09-01T00:00:00.000
Constructionactualcompletion
2022-09-01T00:00:00.000
Totalfunding
Less than $1 million
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Parkid
Q102
Latitude
40.720671
Longitude
-73.879727
Borough
Queens
VIEW LOCATION
1545111
Trackerid: 1545111 • Fmsid: 846 P-405JPCS • Title: Juniper Valley Park Field House Reconstruction
Trackerid
1545111
Fmsid
846 P-405JPCS
Title
Juniper Valley Park Field House Reconstruction
Summary
This project will reconstruct the field house in Juniper Valley Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2024-11-01T00:00:00.000
Designprojectedcompletion
2024-04-01T00:00:00.000
Designactualcompletion
2025-08-01T00:00:00.000
Procurementstart
2025-05-01T00:00:00.000
Procurementprojectedcompletion
2025-09-01T00:00:00.000
Procurementactualcompletion
2025-07-01T00:00:00.000
Constructionstart
2025-10-01T00:00:00.000
Constructionprojectedcom
2026-10-01T00:00:00.000
Constructionactualcompletion
2026-06-01T00:00:00.000
Totalfunding
$3,250,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Parkid
Q102
Latitude
40.719936
Longitude
-73.882475
Borough
Queens
VIEW LOCATION
8612
Trackerid: 8612 • Fmsid: 846 P-405JPSS • Title: Juniper Valley Park Spray Shower Reconstruction
Trackerid
8612
Fmsid
846 P-405JPSS
Title
Juniper Valley Park Spray Shower Reconstruction
Summary
This project will reconstruct the spray shower in Juniper Valley Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2016-12-01T00:00:00.000
Designprojectedcompletion
2017-12-01T00:00:00.000
Designactualcompletion
2017-12-01T00:00:00.000
Procurementstart
2017-12-01T00:00:00.000
Procurementprojectedcompletion
2018-09-01T00:00:00.000
Procurementactualcompletion
2018-07-01T00:00:00.000
Constructionstart
2018-10-01T00:00:00.000
Constructionprojectedcom
2019-10-01T00:00:00.000
Constructionactualcompletion
2019-10-01T00:00:00.000
Totalfunding
$2,151,000
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough PresidentMayoral
Name
Between 78th Street and 79th Street
Parkid
Q102
Latitude
40.72063
Longitude
-73.877452
Borough
Queens
VIEW LOCATION
3009
Trackerid: 3009 • Fmsid: 846 P-405JVBC • Title: Juniper Valley Park Bocce Court Construction
Trackerid
3009
Fmsid
846 P-405JVBC
Title
Juniper Valley Park Bocce Court Construction
Summary
This project will reconstruct and expand the bocce court area in Juniper Valley Park with an additional bocce court, shade canopies, a sitting area, benches, and trees.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2011-07-01T00:00:00.000
Designprojectedcompletion
2012-01-01T00:00:00.000
Designactualcompletion
2012-11-01T00:00:00.000
Procurementstart
2012-11-01T00:00:00.000
Procurementprojectedcompletion
2013-08-01T00:00:00.000
Procurementactualcompletion
2013-06-01T00:00:00.000
Constructionstart
2013-09-01T00:00:00.000
Constructionprojectedcom
2014-09-01T00:00:00.000
Constructionadjustedcompletion
2014-09-01T00:00:00.000
Constructionactualcompletion
2014-09-01T00:00:00.000
Totalfunding
$649,000
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough President, City Council
Name
Juniper Boulevard North between 78th Street and 80th Street
Parkid
Q102
Latitude
40.72006722
Longitude
-73.88113528
Borough
Queens
VIEW LOCATION
9268
Trackerid: 9268 • Fmsid: 846 P-405JVBB • Title: Juniper Valley Park Baseball Field Reconstruction
Trackerid
9268
Fmsid
846 P-405JVBB
Title
Juniper Valley Park Baseball Field Reconstruction
Summary
This project will reconstruct Juniper Valley Park ballfield #7 (Cardinal Ballfield) including the conversion of a natural turf infield into a synthetic turf infield.
Currentphase
design
Designpercentcomplete
100.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Designstart
2023-05-01T00:00:00.000
Designprojectedcompletion
2025-03-01T00:00:00.000
Designactualcompletion
2025-03-01T00:00:00.000
Totalfunding
Between $3 million and $5 million
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
Juniper Boulevard North, Lutheran Avenue, 71st Street, Juniper Boulevard South, 80th Street
Parkid
Q102
Latitude
40.7194848
Longitude
-73.8848121
Borough
Queens
VIEW LOCATION
10701
Trackerid: 10701 • Fmsid: 846 P-405JUNP • Title: Juniper Valley Park Multipurpose Play Area Reconstruction
Trackerid
10701
Fmsid
846 P-405JUNP
Title
Juniper Valley Park Multipurpose Play Area Reconstruction
Summary
This project will reconstruct the multipurpose play area at Juniper Park.
Currentphase
design
Designpercentcomplete
50.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Designstart
2024-10-01T00:00:00.000
Designprojectedcompletion
2026-01-01T00:00:00.000
Designadjustedcompletion
2026-11-01T00:00:00.000
Totalfunding
Between $5 million and $10 million
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoral
Name
LOCATED AT 80TH STREET BETWEEN JUNIPER BOULEVARD NORTH AND SOUTH
Parkid
Q102
Latitude
40.7208648
Longitude
-73.8786692
Borough
Queens
VIEW LOCATION
7344
Trackerid: 7344 • Fmsid: 846 P-405JPTK • Title: Juniper Valley Park Track and Field Reconstruction
Trackerid
7344
Fmsid
846 P-405JPTK
Title
Juniper Valley Park Track and Field Reconstruction
Summary
This project will reconstruct the running track and synthetic turf field and construct an adult fitness area at Juniper Valley Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2017-10-01T00:00:00.000
Designprojectedcompletion
2018-10-01T00:00:00.000
Designactualcompletion
2018-10-01T00:00:00.000
Procurementstart
2018-10-01T00:00:00.000
Procurementprojectedcompletion
2019-07-01T00:00:00.000
Procurementadjustedcompletion
2021-05-01T00:00:00.000
Procurementactualcompletion
2021-03-01T00:00:00.000
Constructionstart
2021-04-01T00:00:00.000
Constructionprojectedcom
2022-04-01T00:00:00.000
Constructionadjustedcompletion
2022-12-01T00:00:00.000
Constructionactualcompletion
2022-11-01T00:00:00.000
Totalfunding
$4,980,000
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
Lutheran Avenue between Juniper Boulevard South and Juniper Boulevard North
Parkid
Q102
Latitude
40.719833
Longitude
-73.884433
Borough
Queens
VIEW LOCATION
1388111
Trackerid: 1388111 • Fmsid: 846 P-2DCTKSR • Title: Kaiser Park Telecommunication Lines Reconstruction
Trackerid
1388111
Fmsid
846 P-2DCTKSR
Title
Kaiser Park Telecommunication Lines Reconstruction
Summary
This project will reconstruct the telecommunication lines at Kaiser Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2021-10-01T00:00:00.000
Designprojectedcompletion
2022-05-01T00:00:00.000
Designactualcompletion
2022-05-01T00:00:00.000
Procurementstart
2021-11-01T00:00:00.000
Procurementprojectedcompletion
2022-04-01T00:00:00.000
Procurementactualcompletion
2022-05-01T00:00:00.000
Constructionstart
2022-05-01T00:00:00.000
Constructionprojectedcom
2023-01-01T00:00:00.000
Constructionactualcompletion
2022-11-01T00:00:00.000
Totalfunding
$80,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Parkid
B129
Latitude
40.579309
Longitude
-73.995976
Borough
Brooklyn
VIEW LOCATION
10882
Trackerid: 10882 • Fmsid: 846 P-213KSRP • Title: Kaiser Park Playground Reconstruction
Trackerid
10882
Fmsid
846 P-213KSRP
Title
Kaiser Park Playground Reconstruction
Summary
This project will reconstruct the playground in Kaiser Park.
Currentphase
design
Designpercentcomplete
50.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Designstart
2025-04-01T00:00:00.000
Designprojectedcompletion
2026-04-01T00:00:00.000
Designadjustedcompletion
2027-02-01T00:00:00.000
Totalfunding
Between $3 million and $5 million
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Neptune Avenue between Bayview Avenue and W 23rd Street
Parkid
B129
Latitude
40.57912841
Longitude
-73.99542766
Borough
Brooklyn
VIEW LOCATION
11187
Trackerid: 11187 • Fmsid: 846 P-5CPIKTM • Title: Kaltenmeier Playground Reconstruction
Trackerid
11187
Fmsid
846 P-5CPIKTM
Title
Kaltenmeier Playground Reconstruction
Summary
This project will reconstruct the playground at Kaltenmeier Playground, including the basketball court area, drainage, pavement, fencing, landscaping, drinking fountains, play equipment, spray shower, seating area, security lighting, and electric utilities.
Currentphase
design
Designpercentcomplete
35.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Designstart
2026-08-01T00:00:00.000
Designprojectedcompletion
2027-02-01T00:00:00.000
Totalfunding
Between $5 million and $10 million
Projectliaison
Katrina Toal
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Virginia Avenue and Alderson Street
Parkid
R042
Latitude
40.61471914
Longitude
-74.06852384
Borough
Staten Island
VIEW LOCATION
11136
Trackerid: 11136 • Title: Kelly Park Playground Tennis Courts Reconstruction • Summary: This project will reconstruct the tennis courts in Kelly Park Playground.
Trackerid
11136
Title
Kelly Park Playground Tennis Courts Reconstruction
Summary
This project will reconstruct the tennis courts in Kelly Park Playground.
Currentphase
proposed
Designpercentcomplete
0.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Totalfunding
Between $1 million and $3 million
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
Ave. S bet. E. 14 St. and E. 15 St
Parkid
B051
Latitude
40.60458133
Longitude
-73.95767584
Borough
Brooklyn
VIEW LOCATION
9668
Trackerid: 9668 • Fmsid: 846 P-215KLCS • Title: Kelly Park Public Restroom Building Reconstruction
Trackerid
9668
Fmsid
846 P-215KLCS
Title
Kelly Park Public Restroom Building Reconstruction
Summary
This project will reconstruct the public restroom building at Kelly Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2019-12-01T00:00:00.000
Designprojectedcompletion
2020-12-01T00:00:00.000
Designactualcompletion
2020-12-01T00:00:00.000
Procurementstart
2020-12-01T00:00:00.000
Procurementprojectedcompletion
2021-09-01T00:00:00.000
Procurementadjustedcompletion
2023-07-01T00:00:00.000
Procurementactualcompletion
2023-01-01T00:00:00.000
Constructionstart
2023-04-01T00:00:00.000
Constructionprojectedcom
2024-04-01T00:00:00.000
Constructionactualcompletion
2024-07-01T00:00:00.000
Totalfunding
$2,686,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough PresidentMayoral
Name
Avenue S and East 15th Street
Parkid
B051
Latitude
40.604407
Longitude
-73.957498
Borough
Brooklyn
VIEW LOCATION
8918
Trackerid: 8918 • Fmsid: 846 P-215KELL • Title: Kelly Park Playground Reconstruction
Trackerid
8918
Fmsid
846 P-215KELL
Title
Kelly Park Playground Reconstruction
Summary
This project will reconstruct and expand the playground in Kelly Park, including play equipment, spray shower, swings, seating areas, benches, security lighting, fencing, drainage and water supply, electrical service, and plantings.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2019-11-01T00:00:00.000
Designprojectedcompletion
2020-11-01T00:00:00.000
Designadjustedcompletion
2021-05-01T00:00:00.000
Designactualcompletion
2021-05-01T00:00:00.000
Procurementstart
2021-05-01T00:00:00.000
Procurementprojectedcompletion
2022-01-01T00:00:00.000
Procurementadjustedcompletion
2023-02-01T00:00:00.000
Procurementactualcompletion
2022-11-01T00:00:00.000
Constructionstart
2023-02-01T00:00:00.000
Constructionprojectedcom
2024-04-01T00:00:00.000
Constructionactualcompletion
2024-08-01T00:00:00.000
Totalfunding
$10,530,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral State
Name
Avenue S between East 14th Street and East 15th Street
Parkid
B051
Latitude
40.604108
Longitude
-73.957792
Borough
Brooklyn
VIEW LOCATION
9286
Trackerid: 9286 • Fmsid: 846 P-215KLLY • Title: Kelly Playground Reconstruction
Trackerid
9286
Fmsid
846 P-215KLLY
Title
Kelly Playground Reconstruction
Summary
This project will reconstruct the children's play area in Kelly Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2019-01-01T00:00:00.000
Designprojectedcompletion
2020-01-01T00:00:00.000
Designactualcompletion
2020-01-01T00:00:00.000
Procurementstart
2020-01-01T00:00:00.000
Procurementprojectedcompletion
2020-10-01T00:00:00.000
Procurementadjustedcompletion
2022-04-01T00:00:00.000
Procurementactualcompletion
2022-03-01T00:00:00.000
Constructionstart
2022-05-01T00:00:00.000
Constructionprojectedcom
2023-05-01T00:00:00.000
Constructionactualcompletion
2023-09-01T00:00:00.000
Totalfunding
$2,652,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoral
Name
Moore Place and East 16th Street
Parkid
B157
Latitude
40.604464
Longitude
-73.956428
Borough
Brooklyn
VIEW LOCATION
9822
Trackerid: 9822 • Fmsid: 846 P-303KIML • Title: Kimlau Square Arch Reconstruction
Trackerid
9822
Fmsid
846 P-303KIML
Title
Kimlau Square Arch Reconstruction
Summary
This project will reconstruct the arch in Kimlau Square.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2021-01-01T00:00:00.000
Designprojectedcompletion
2022-08-01T00:00:00.000
Designactualcompletion
2022-09-01T00:00:00.000
Procurementstart
2022-09-01T00:00:00.000
Procurementprojectedcompletion
2023-06-01T00:00:00.000
Procurementadjustedcompletion
2025-07-01T00:00:00.000
Procurementactualcompletion
2025-05-01T00:00:00.000
Constructionstart
2025-07-01T00:00:00.000
Constructionprojectedcom
2026-07-01T00:00:00.000
Constructionactualcompletion
2026-08-01T00:00:00.000
Totalfunding
$1,139,000
Projectliaison
Steve Simon
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
Chatham Sq., Oliver St. and East Broadway
Parkid
M246
Latitude
40.71342299
Longitude
-73.99807233
Borough
Manhattan
VIEW LOCATION
1373111
Trackerid: 1373111 • Fmsid: 846 P-4STFCAR • Currentphase: completed
Trackerid
1373111
Fmsid
846 P-4STFCAR
Title
Kissena Corridor Park Rachel Carson Playground Synthetic Turf Field Reconstruction
Summary
This project will reconstruct the synthetic turf field at Rachel Carson Playground in Kissena Corridor Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2021-07-01T00:00:00.000
Designprojectedcompletion
2022-08-01T00:00:00.000
Designactualcompletion
2022-04-01T00:00:00.000
Procurementstart
2021-09-01T00:00:00.000
Procurementprojectedcompletion
2022-02-01T00:00:00.000
Procurementactualcompletion
2022-04-01T00:00:00.000
Constructionstart
2022-09-01T00:00:00.000
Constructionprojectedcom
2023-01-01T00:00:00.000
Constructionactualcompletion
2022-10-01T00:00:00.000
Totalfunding
$581,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Parkid
Q300
Latitude
40.749293264857
Longitude
-73.822080774473
Borough
Queens
VIEW LOCATION
1100111
Trackerid: 1100111 • Fmsid: 846 P-4PL15A5 • Title: Kissena Corridor Park Path Construction
Trackerid
1100111
Fmsid
846 P-4PL15A5
Title
Kissena Corridor Park Path Construction
Summary
This project will construct a new asphalt path, reconstruct a lawn and remove a chain link fence in Kissena Corridor Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2015-06-01T00:00:00.000
Designprojectedcompletion
2017-06-01T00:00:00.000
Designactualcompletion
2018-01-01T00:00:00.000
Procurementstart
2017-12-01T00:00:00.000
Procurementprojectedcompletion
2018-05-01T00:00:00.000
Procurementactualcompletion
2018-03-01T00:00:00.000
Constructionstart
2018-04-01T00:00:00.000
Constructionprojectedcom
2018-04-01T00:00:00.000
Constructionadjustedcompletion
2018-07-01T00:00:00.000
Constructionactualcompletion
2018-07-01T00:00:00.000
Totalfunding
$105,000
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Parkid
Q300
Latitude
40.74956
Longitude
-73.824514
Borough
Queens
VIEW LOCATION
1729111
Trackerid: 1729111 • Fmsid: 846 P-6CWSTF2 • Title: Kissena Corridor Park Synthetic Turf Soccer Field Reconstruction
Trackerid
1729111
Fmsid
846 P-6CWSTF2
Title
Kissena Corridor Park Synthetic Turf Soccer Field Reconstruction
Summary
This project will reconstruct the synthetic turf soccer field at Kissena Corridor Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2024-04-01T00:00:00.000
Designprojectedcompletion
2025-11-01T00:00:00.000
Designactualcompletion
2025-11-01T00:00:00.000
Procurementstart
2024-06-01T00:00:00.000
Procurementprojectedcompletion
2024-11-01T00:00:00.000
Procurementactualcompletion
2025-10-01T00:00:00.000
Constructionstart
2025-11-01T00:00:00.000
Constructionprojectedcom
2026-05-01T00:00:00.000
Constructionactualcompletion
2025-12-01T00:00:00.000
Totalfunding
$6,770,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Parkid
Q300
Latitude
40.7451484
Longitude
-73.8157062
Borough
Queens
VIEW LOCATION
10073
Trackerid: 10073 • Fmsid: 846 P-4KCPPAV • Title: Kissena Corridor Park Lighting Construction
Trackerid
10073
Fmsid
846 P-4KCPPAV
Title
Kissena Corridor Park Lighting Construction
Summary
This project will construct lighting and a pathway at Kissena Corridor Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2022-06-01T00:00:00.000
Designprojectedcompletion
2023-06-01T00:00:00.000
Designactualcompletion
2023-06-01T00:00:00.000
Procurementstart
2023-06-01T00:00:00.000
Procurementprojectedcompletion
2024-06-01T00:00:00.000
Procurementadjustedcompletion
2025-02-01T00:00:00.000
Procurementactualcompletion
2025-02-01T00:00:00.000
Constructionstart
2025-02-01T00:00:00.000
Constructionprojectedcom
2026-02-01T00:00:00.000
Constructionactualcompletion
2025-12-01T00:00:00.000
Totalfunding
$950,000
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough President, City Council
Name
146th Street, 56th Road and Colden Street
Parkid
Q300
Latitude
40.752081994387
Longitude
-73.831798949434
Borough
Queens
VIEW LOCATION
6862
Trackerid: 6862 • Fmsid: 846 P-4CARSON • Title: Silent Spring Playground Reconstruction
Trackerid
6862
Fmsid
846 P-4CARSON
Title
Silent Spring Playground Reconstruction
Summary
This project will reconstruct Silent Spring Playground in Kissena Corridor Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2016-01-01T00:00:00.000
Designprojectedcompletion
2016-07-01T00:00:00.000
Designadjustedcompletion
2016-08-01T00:00:00.000
Designactualcompletion
2016-09-01T00:00:00.000
Procurementstart
2016-09-01T00:00:00.000
Procurementprojectedcompletion
2017-06-01T00:00:00.000
Procurementadjustedcompletion
2017-11-01T00:00:00.000
Procurementactualcompletion
2017-10-01T00:00:00.000
Constructionstart
2017-12-01T00:00:00.000
Constructionprojectedcom
2018-12-01T00:00:00.000
Constructionactualcompletion
2018-12-01T00:00:00.000
Totalfunding
$1,737,000
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough PresidentMayoral
Name
Colden Street between Juniper Avenue and Geranium Avenue
Parkid
Q300
Latitude
40.74867556
Longitude
-73.82313194
Borough
Queens
VIEW LOCATION
9843
Trackerid: 9843 • Fmsid: 846 P-4MARFAJ • Title: Captain Mario Fajardo Park Playground and Sports Courts Reconstruction
Trackerid
9843
Fmsid
846 P-4MARFAJ
Title
Captain Mario Fajardo Park Playground and Sports Courts Reconstruction
Summary
This project will reconstruct the playground, basketball courts, and handball courts in Captain Mario Fajardo Park.
Currentphase
construction
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
78.47
Designstart
2021-02-01T00:00:00.000
Designprojectedcompletion
2022-02-01T00:00:00.000
Designadjustedcompletion
2022-08-01T00:00:00.000
Designactualcompletion
2022-08-01T00:00:00.000
Procurementstart
2025-08-01T00:00:00.000
Procurementprojectedcompletion
2026-08-01T00:00:00.000
Procurementactualcompletion
2026-03-01T00:00:00.000
Constructionstart
2026-03-01T00:00:00.000
Constructionprojectedcom
2027-03-01T00:00:00.000
Totalfunding
$5,570,000
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough President, City Council
Name
Kissena Boulevard and Booth Memorial Avenue
Parkid
Q300
Latitude
40.74371989
Longitude
-73.81475461
Borough
Queens
VIEW LOCATION
10878
Trackerid: 10878 • Fmsid: 846 P-4DSTG08 • Title: Kissena Corridor Park Greenway Construction
Trackerid
10878
Fmsid
846 P-4DSTG08
Title
Kissena Corridor Park Greenway Construction
Summary
This project will construct a greenway at Kissena Corridor Park as part of the Destination Greenways! initiative.
Currentphase
design
Designpercentcomplete
5.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Designstart
2026-06-01T00:00:00.000
Designprojectedcompletion
2027-07-01T00:00:00.000
Totalfunding
Greater than $10 million
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
Underhill Avenue and Peck Avenue between Fresh Meadow Lane and the Long Island Expressway
Parkid
Q300A
Latitude
40.74095045
Longitude
-73.77543049
Borough
Queens
VIEW LOCATION
3577
Trackerid: 3577 • Fmsid: 846 P-4QMULT2 • Title: Kissena Corridor Park Ballfield 5 Reconstruction
Trackerid
3577
Fmsid
846 P-4QMULT2
Title
Kissena Corridor Park Ballfield 5 Reconstruction
Summary
This project will reconstruct Ballfield 5 at Kissena Corridor Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2021-04-01T00:00:00.000
Designprojectedcompletion
2022-04-01T00:00:00.000
Designadjustedcompletion
2023-02-01T00:00:00.000
Designactualcompletion
2023-02-01T00:00:00.000
Procurementstart
2023-02-01T00:00:00.000
Procurementprojectedcompletion
2024-02-01T00:00:00.000
Procurementadjustedcompletion
2024-10-01T00:00:00.000
Procurementactualcompletion
2024-10-01T00:00:00.000
Constructionstart
2025-04-01T00:00:00.000
Constructionprojectedcom
2026-04-01T00:00:00.000
Constructionactualcompletion
2026-04-01T00:00:00.000
Totalfunding
$3,017,000
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
Underhill Avenue and Peck Avenue between Utopia Parkway and 50th Avenue.
Parkid
Q300A
Latitude
40.74530802
Longitude
-73.78977485
Borough
Queens
VIEW LOCATION
11080
Trackerid: 11080 • Currentphase: proposed • Designpercentcomplete: 0.0
Trackerid
11080
Title
Kissena Corridor Park Ella Fitzgerald Playground Multipurpose Play Area and Sports Courts Reconstruction
Summary
This project will reconstruct the multipurpose play area and sports courts at Ella Fitzgerald Playground in Kissena Corridor Park.
Currentphase
proposed
Designpercentcomplete
0.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Totalfunding
Between $5 million and $10 million
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
Underhill Avenue, Peck Avenue, 188th Street
Parkid
Q300
Latitude
40.7498952
Longitude
-73.82287197
Borough
Queens
VIEW LOCATION
1571111
Trackerid: 1571111 • Fmsid: 846 P-4KSNAPK • Title: Kissena Park Path Reconstruction
Trackerid
1571111
Fmsid
846 P-4KSNAPK
Title
Kissena Park Path Reconstruction
Summary
This project will reconstruct paths in Kissena Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2023-01-01T00:00:00.000
Designprojectedcompletion
2024-10-01T00:00:00.000
Designactualcompletion
2024-08-01T00:00:00.000
Procurementstart
2024-04-01T00:00:00.000
Procurementprojectedcompletion
2024-09-01T00:00:00.000
Procurementactualcompletion
2024-08-01T00:00:00.000
Constructionstart
2026-04-01T00:00:00.000
Constructionprojectedcom
2026-07-01T00:00:00.000
Constructionactualcompletion
2026-05-01T00:00:00.000
Totalfunding
$1,100,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Parkid
Q024
Latitude
40.745939
Longitude
-73.806429
Borough
Queens
VIEW LOCATION
1608111
Trackerid: 1608111 • Fmsid: 846 P-6ROOF22 • Title: Kissena Park Boat House Roof Reconstruction
Trackerid
1608111
Fmsid
846 P-6ROOF22
Title
Kissena Park Boat House Roof Reconstruction
Summary
This project will reconstruct the roof at the Kissena Boat House.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2023-09-01T00:00:00.000
Designprojectedcompletion
2024-08-01T00:00:00.000
Designactualcompletion
2025-01-01T00:00:00.000
Procurementstart
2023-12-01T00:00:00.000
Procurementprojectedcompletion
2024-05-01T00:00:00.000
Procurementactualcompletion
2024-06-01T00:00:00.000
Constructionstart
2025-03-01T00:00:00.000
Constructionprojectedcom
2025-09-01T00:00:00.000
Constructionactualcompletion
2025-08-01T00:00:00.000
Totalfunding
$760,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Parkid
Q024
Latitude
40.746055
Longitude
-73.805986
Borough
Queens
VIEW LOCATION
1823111
Trackerid: 1823111 • Fmsid: 846 P-6RETW23 • Title: Kissena Park Retaining Wall Reconstruction
Trackerid
1823111
Fmsid
846 P-6RETW23
Title
Kissena Park Retaining Wall Reconstruction
Summary
This project will reconstruct retaining walls at the southwest corner of 164th Street and Oak Avenue in Kissena Park.
Currentphase
construction
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
90.0
Designstart
2024-07-01T00:00:00.000
Designprojectedcompletion
2025-09-01T00:00:00.000
Designactualcompletion
2025-03-01T00:00:00.000
Procurementstart
2025-03-01T00:00:00.000
Procurementprojectedcompletion
2025-08-01T00:00:00.000
Procurementactualcompletion
2025-08-01T00:00:00.000
Constructionstart
2025-08-01T00:00:00.000
Constructionprojectedcom
2026-06-01T00:00:00.000
Totalfunding
Less than $1 million
Projectliaison
Contact Us
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Parkid
Q024
Latitude
40.748888
Longitude
-73.803818
Borough
Queens
VIEW LOCATION
9227
Trackerid: 9227 • Fmsid: 846 GQGIKISE • Title: Kissena Park Green Infrastructure Construction
Trackerid
9227
Fmsid
846 GQGIKISE
Title
Kissena Park Green Infrastructure Construction
Summary
This project will construct green infrastructure to capture storm water at Kissena Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2018-12-01T00:00:00.000
Designprojectedcompletion
2020-01-01T00:00:00.000
Designadjustedcompletion
2021-04-01T00:00:00.000
Designactualcompletion
2021-03-01T00:00:00.000
Procurementstart
2021-03-01T00:00:00.000
Procurementprojectedcompletion
2021-12-01T00:00:00.000
Procurementadjustedcompletion
2023-03-01T00:00:00.000
Procurementactualcompletion
2023-04-01T00:00:00.000
Constructionstart
2023-04-01T00:00:00.000
Constructionprojectedcom
2024-09-01T00:00:00.000
Constructionadjustedcompletion
2025-01-01T00:00:00.000
Constructionactualcompletion
2024-12-01T00:00:00.000
Totalfunding
$481,000
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Kissena Boulevard and Booth Memorial Avenue
Parkid
Q024
Latitude
40.743339
Longitude
-73.813735
Borough
Queens
VIEW LOCATION
1175111
Trackerid: 1175111 • Fmsid: 846 P-214KPKP • Title: Kolbert Park Sidewalks Reconstruction
Trackerid
1175111
Fmsid
846 P-214KPKP
Title
Kolbert Park Sidewalks Reconstruction
Summary
This project will reconstruct the sidewalks, curbs, accessible ramps, and pipe rail fencing at Kolbert Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2019-01-01T00:00:00.000
Designprojectedcompletion
2019-05-01T00:00:00.000
Designactualcompletion
2019-05-01T00:00:00.000
Procurementstart
2019-05-01T00:00:00.000
Procurementprojectedcompletion
2019-10-01T00:00:00.000
Procurementactualcompletion
2019-07-01T00:00:00.000
Constructionstart
2019-11-01T00:00:00.000
Constructionprojectedcom
2020-05-01T00:00:00.000
Constructionadjustedcompletion
2020-10-01T00:00:00.000
Constructionactualcompletion
2020-10-01T00:00:00.000
Totalfunding
$364,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Parkid
B150
Latitude
40.620325
Longitude
-73.957996
Borough
Brooklyn
VIEW LOCATION
6643
Trackerid: 6643 • Fmsid: 846 P-214KOLB • Title: Kolbert Playground Reconstruction
Trackerid
6643
Fmsid
846 P-214KOLB
Title
Kolbert Playground Reconstruction
Summary
This project will reconstruct the handball courts and expand the play area to include new basketball courts, new synthetic turf field & walking track, new play equipment, and new adult fitness equipment at Kolbert Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2014-09-01T00:00:00.000
Designprojectedcompletion
2015-11-01T00:00:00.000
Designadjustedcompletion
2016-04-01T00:00:00.000
Designactualcompletion
2016-04-01T00:00:00.000
Procurementstart
2016-04-01T00:00:00.000
Procurementprojectedcompletion
2016-12-01T00:00:00.000
Procurementactualcompletion
2016-12-01T00:00:00.000
Constructionstart
2017-04-01T00:00:00.000
Constructionprojectedcom
2018-04-01T00:00:00.000
Constructionactualcompletion
2018-04-01T00:00:00.000
Totalfunding
$2,851,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
Avenue L, East 17th Street, East 18th Street
Parkid
B150
Latitude
40.62007556
Longitude
-73.9580075
Borough
Brooklyn
VIEW LOCATION
1732111
Trackerid: 1732111 • Fmsid: 846 P-6CWSTF2 • Title: Kwame Ture Recreation Center Synthetic Turf Field Reconstruction
Trackerid
1732111
Fmsid
846 P-6CWSTF2
Title
Kwame Ture Recreation Center Synthetic Turf Field Reconstruction
Summary
This project will reconstruct the synthetic turf field at Kwame Ture Recreation Center.
Currentphase
construction
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
0.0
Designstart
2024-04-01T00:00:00.000
Designprojectedcompletion
2025-11-01T00:00:00.000
Designactualcompletion
2025-10-01T00:00:00.000
Procurementstart
2024-06-01T00:00:00.000
Procurementprojectedcompletion
2024-11-01T00:00:00.000
Procurementactualcompletion
2025-10-01T00:00:00.000
Constructionstart
2026-01-01T00:00:00.000
Constructionprojectedcom
2026-05-01T00:00:00.000
Totalfunding
$472,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Parkid
X261
Latitude
40.844086
Longitude
-73.918767
Borough
Bronx
VIEW LOCATION
1998111
Trackerid: 1998111 • Title: Kwame Ture Recreation Center Roof Reconstruction • Summary: This project will reconstruct the recreation center roof.
Trackerid
1998111
Title
Kwame Ture Recreation Center Roof Reconstruction
Summary
This project will reconstruct the recreation center roof.
Currentphase
proposed
Designpercentcomplete
5.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Designstart
2027-03-01T00:00:00.000
Designprojectedcompletion
2027-12-01T00:00:00.000
Totalfunding
Less than $1 million
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Parkid
X261
Latitude
40.8440305
Longitude
-73.9189814
Borough
Bronx
VIEW LOCATION
7311
Trackerid: 7311 • Fmsid: 846 P-1BWRCTR • Title: West Bronx Recreation Center AC Reconstruction
Trackerid
7311
Fmsid
846 P-1BWRCTR
Title
West Bronx Recreation Center AC Reconstruction
Summary
This project will reconstruct the air conditioning system for the gymnasium at West Bronx Recreation Center.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2015-07-01T00:00:00.000
Designprojectedcompletion
2016-06-01T00:00:00.000
Designadjustedcompletion
2017-02-01T00:00:00.000
Designactualcompletion
2017-02-01T00:00:00.000
Procurementstart
2017-02-01T00:00:00.000
Procurementprojectedcompletion
2017-11-01T00:00:00.000
Procurementadjustedcompletion
2018-09-01T00:00:00.000
Procurementactualcompletion
2018-07-01T00:00:00.000
Constructionstart
2018-10-01T00:00:00.000
Constructionprojectedcom
2019-10-01T00:00:00.000
Constructionadjustedcompletion
2020-01-01T00:00:00.000
Constructionactualcompletion
2020-01-01T00:00:00.000
Totalfunding
$859,000
Projectliaison
Katerine Borrome
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
1527 Jesup Avenue
Parkid
X261
Latitude
40.84434
Longitude
-73.919357
Borough
Bronx
VIEW LOCATION
2953
Trackerid: 2953 • Fmsid: 846 P-402NOON • Title: Noonan Playground Spray Shower and Playground Reconstruction
Trackerid
2953
Fmsid
846 P-402NOON
Title
Noonan Playground Spray Shower and Playground Reconstruction
Summary
This project will reconstruct a portion of the playground, improving safety within the park and providing definitive circulation for park users. A new spray shower and new play equipment will provide recreation for a wide range of children. The project will also extend the green space, mitigate drainage issues and enhance the main entrance of the park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2011-09-01T00:00:00.000
Designprojectedcompletion
2012-12-01T00:00:00.000
Designactualcompletion
2013-01-01T00:00:00.000
Procurementstart
2013-01-01T00:00:00.000
Procurementprojectedcompletion
2013-10-01T00:00:00.000
Procurementactualcompletion
2014-03-01T00:00:00.000
Constructionstart
2014-04-01T00:00:00.000
Constructionprojectedcom
2015-04-01T00:00:00.000
Constructionactualcompletion
2015-03-01T00:00:00.000
Totalfunding
$1,288,000
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
47th Avenue, 43rd Street, Greenpoint Avenue, 42nd Street
Parkid
Q044
Latitude
40.74110028
Longitude
-73.92248056
Borough
Queens
VIEW LOCATION
9261
Trackerid: 9261 • Fmsid: 846 P-4NNANPG • Title: Noonan Playground Dog Run Construction and Seating Area Reconstruction
Trackerid
9261
Fmsid
846 P-4NNANPG
Title
Noonan Playground Dog Run Construction and Seating Area Reconstruction
Summary
This project will construct a dog run and reconstruct the seating area at Noonan Playground, including new plantings, benches, pavement, stairs, fencing, lighting, and drinking fountains.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2019-06-01T00:00:00.000
Designprojectedcompletion
2020-06-01T00:00:00.000
Designactualcompletion
2020-07-01T00:00:00.000
Procurementstart
2020-07-01T00:00:00.000
Procurementprojectedcompletion
2021-03-01T00:00:00.000
Procurementadjustedcompletion
2022-06-01T00:00:00.000
Procurementactualcompletion
2022-06-01T00:00:00.000
Constructionstart
2023-03-01T00:00:00.000
Constructionprojectedcom
2024-03-01T00:00:00.000
Constructionactualcompletion
2024-03-01T00:00:00.000
Totalfunding
$1,421,000
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Greenpoint Avenue and 42nd Street
Parkid
Q044
Latitude
40.741149
Longitude
-73.922466
Borough
Queens
VIEW LOCATION
8626
Trackerid: 8626 • Fmsid: 846 P-2CPILGD • Title: La Guardia Playground Reconstruction Phase 1
Trackerid
8626
Fmsid
846 P-2CPILGD
Title
La Guardia Playground Reconstruction Phase 1
Summary
This project will reconstruct the sports courts and plaza (southern parcel) at La Guardia Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2016-10-01T00:00:00.000
Designprojectedcompletion
2017-10-01T00:00:00.000
Designadjustedcompletion
2018-09-01T00:00:00.000
Designactualcompletion
2018-09-01T00:00:00.000
Procurementstart
2018-09-01T00:00:00.000
Procurementprojectedcompletion
2019-06-01T00:00:00.000
Procurementactualcompletion
2019-06-01T00:00:00.000
Constructionstart
2019-10-01T00:00:00.000
Constructionprojectedcom
2020-10-01T00:00:00.000
Constructionadjustedcompletion
2020-12-01T00:00:00.000
Constructionactualcompletion
2020-10-01T00:00:00.000
Totalfunding
$2,142,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Havemeyer Street, South 5th Street, Brooklyn Queens Expressway
Parkid
B167
Latitude
40.710528
Longitude
-73.959778
Borough
Brooklyn
VIEW LOCATION
9230
Trackerid: 9230 • Fmsid: 846 P-2CPILAG • Title: La Guardia Playground Reconstruction Phase 2
Trackerid
9230
Fmsid
846 P-2CPILAG
Title
La Guardia Playground Reconstruction Phase 2
Summary
This project will reconstruct the children's play area (northern parcel) at La Guardia Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2018-07-01T00:00:00.000
Designprojectedcompletion
2019-04-01T00:00:00.000
Designactualcompletion
2019-05-01T00:00:00.000
Procurementstart
2019-05-01T00:00:00.000
Procurementprojectedcompletion
2020-02-01T00:00:00.000
Procurementadjustedcompletion
2020-11-01T00:00:00.000
Procurementactualcompletion
2021-03-01T00:00:00.000
Constructionstart
2021-06-01T00:00:00.000
Constructionprojectedcom
2022-06-01T00:00:00.000
Constructionactualcompletion
2022-06-01T00:00:00.000
Totalfunding
$3,253,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Roebling Street, South 4th Street, Brooklyn Queens Expressway
Parkid
B167
Latitude
40.710456
Longitude
-73.959658
Borough
Brooklyn
VIEW LOCATION
9980
Trackerid: 9980 • Fmsid: 846 P-203LFGP • Title: Lafayette Gardens Playground Reconstruction
Trackerid
9980
Fmsid
846 P-203LFGP
Title
Lafayette Gardens Playground Reconstruction
Summary
This project will reconstruct the playground at Lafayette Gardens.
Currentphase
construction
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
62.0
Designstart
2021-06-01T00:00:00.000
Designprojectedcompletion
2022-06-01T00:00:00.000
Designadjustedcompletion
2023-03-01T00:00:00.000
Designactualcompletion
2023-03-01T00:00:00.000
Procurementstart
2023-03-01T00:00:00.000
Procurementprojectedcompletion
2024-03-01T00:00:00.000
Procurementadjustedcompletion
2025-09-01T00:00:00.000
Procurementactualcompletion
2025-09-01T00:00:00.000
Constructionstart
2025-10-01T00:00:00.000
Constructionprojectedcom
2026-10-01T00:00:00.000
Totalfunding
$3,500,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
Lafayette Avenue & Franklin Avenue
Parkid
B317
Latitude
40.68965631
Longitude
-73.95744271
Borough
Brooklyn
VIEW LOCATION
7334
Trackerid: 7334 • Fmsid: 846 P-2CPILFT • Title: Lafayette Playground Reconstruction
Trackerid
7334
Fmsid
846 P-2CPILFT
Title
Lafayette Playground Reconstruction
Summary
This project will reconstruct Lafayette Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2016-04-01T00:00:00.000
Designprojectedcompletion
2017-04-01T00:00:00.000
Designactualcompletion
2017-06-01T00:00:00.000
Procurementstart
2017-06-01T00:00:00.000
Procurementprojectedcompletion
2018-03-01T00:00:00.000
Procurementadjustedcompletion
2018-05-01T00:00:00.000
Procurementactualcompletion
2018-05-01T00:00:00.000
Constructionstart
2018-05-01T00:00:00.000
Constructionprojectedcom
2019-08-01T00:00:00.000
Constructionadjustedcompletion
2019-11-01T00:00:00.000
Constructionactualcompletion
2019-07-01T00:00:00.000
Totalfunding
$4,121,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Benson Avenue, Bay 43rd Street, Stillwell Avenue
Parkid
B106B
Latitude
40.594555
Longitude
-73.985305
Borough
Brooklyn
VIEW LOCATION
7076
Trackerid: 7076 • Fmsid: 846 P-414LAN2 • Title: Lanett Playground Sitting Area Reconstruction
Trackerid
7076
Fmsid
846 P-414LAN2
Title
Lanett Playground Sitting Area Reconstruction
Summary
This project will reconstruct the sitting area of Lanett Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2017-10-01T00:00:00.000
Designprojectedcompletion
2018-10-01T00:00:00.000
Designactualcompletion
2018-10-01T00:00:00.000
Procurementstart
2018-10-01T00:00:00.000
Procurementprojectedcompletion
2019-07-01T00:00:00.000
Procurementadjustedcompletion
2019-10-01T00:00:00.000
Procurementactualcompletion
2019-09-01T00:00:00.000
Constructionstart
2020-09-01T00:00:00.000
Constructionprojectedcom
2021-09-01T00:00:00.000
Constructionactualcompletion
2021-09-01T00:00:00.000
Totalfunding
$994,000
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough President
Name
Beach 9th Street between Lanett Avenue and Hicksville Road
Parkid
Q407
Latitude
40.599590370784
Longitude
-73.744531283787
Borough
Queens
VIEW LOCATION
3356
Trackerid: 3356 • Fmsid: 846 P-414LANN • Title: Lanett Playground Reconstruction and Public Restroom Building Construction
Trackerid
3356
Fmsid
846 P-414LANN
Title
Lanett Playground Reconstruction and Public Restroom Building Construction
Summary
This project will reconstruct the playground and construct a new public restroom building at PS 197 (Lanett) Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2009-08-01T00:00:00.000
Designprojectedcompletion
2011-01-01T00:00:00.000
Designadjustedcompletion
2011-01-01T00:00:00.000
Designactualcompletion
2011-01-01T00:00:00.000
Procurementstart
2011-01-01T00:00:00.000
Procurementprojectedcompletion
2011-10-01T00:00:00.000
Procurementactualcompletion
2012-03-01T00:00:00.000
Constructionstart
2012-04-01T00:00:00.000
Constructionprojectedcom
2014-04-01T00:00:00.000
Constructionadjustedcompletion
2014-04-01T00:00:00.000
Constructionactualcompletion
2014-04-01T00:00:00.000
Totalfunding
$2,078,000
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough President, City Council, State
Name
Lanett Ave. bet. Beach 9 St. and Beach 8 St.
Parkid
Q407
Latitude
40.599475
Longitude
-73.743988
Borough
Queens
VIEW LOCATION
2436
Trackerid: 2436 • Fmsid: 846 P-309STNC • Title: Langston Hughes Playground Public Restroom Building Reconstruction
Trackerid
2436
Fmsid
846 P-309STNC
Title
Langston Hughes Playground Public Restroom Building Reconstruction
Summary
This project will reconstruct the public restroom building at Langston Hughes Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2009-08-01T00:00:00.000
Designprojectedcompletion
2012-08-01T00:00:00.000
Designactualcompletion
2015-06-01T00:00:00.000
Procurementstart
2015-06-01T00:00:00.000
Procurementprojectedcompletion
2016-03-01T00:00:00.000
Procurementadjustedcompletion
2016-10-01T00:00:00.000
Procurementactualcompletion
2016-08-01T00:00:00.000
Constructionstart
2016-10-01T00:00:00.000
Constructionprojectedcom
2017-10-01T00:00:00.000
Constructionadjustedcompletion
2018-05-01T00:00:00.000
Constructionactualcompletion
2018-05-01T00:00:00.000
Totalfunding
$876,000
Projectliaison
Steve Simon
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
Adam Clayton Powell Jr. Boulevard and West 130th Street
Parkid
M211B
Latitude
40.812226
Longitude
-73.946356
Borough
Manhattan
VIEW LOCATION
7401
Trackerid: 7401 • Fmsid: 846 P-3CPIBN9 • Title: Playground 103 and Langston Hughes Playground Reconstruction
Trackerid
7401
Fmsid
846 P-3CPIBN9
Title
Playground 103 and Langston Hughes Playground Reconstruction
Summary
This project will reconstruct Playground 103 and Langston Hughes Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2014-12-01T00:00:00.000
Designprojectedcompletion
2015-12-01T00:00:00.000
Designactualcompletion
2015-12-01T00:00:00.000
Procurementstart
2015-12-01T00:00:00.000
Procurementprojectedcompletion
2016-09-01T00:00:00.000
Procurementadjustedcompletion
2016-11-01T00:00:00.000
Procurementactualcompletion
2016-10-01T00:00:00.000
Constructionstart
2016-11-01T00:00:00.000
Constructionprojectedcom
2018-05-01T00:00:00.000
Constructionactualcompletion
2018-05-01T00:00:00.000
Totalfunding
$9,112,000
Projectliaison
Steve Simon
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
FederalMayoral
Name
Adam Clayton Powell, West 129-130 Streets
Parkid
M211B
Latitude
40.812314
Longitude
-73.946486
Borough
Manhattan
VIEW LOCATION
7401
Trackerid: 7401 • Fmsid: 846 P-3CPIBN9 • Title: Playground 103 and Langston Hughes Playground Reconstruction
Trackerid
7401
Fmsid
846 P-3CPIBN9
Title
Playground 103 and Langston Hughes Playground Reconstruction
Summary
This project will reconstruct Playground 103 and Langston Hughes Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2014-12-01T00:00:00.000
Designprojectedcompletion
2015-12-01T00:00:00.000
Designactualcompletion
2015-12-01T00:00:00.000
Procurementstart
2015-12-01T00:00:00.000
Procurementprojectedcompletion
2016-09-01T00:00:00.000
Procurementadjustedcompletion
2016-11-01T00:00:00.000
Procurementactualcompletion
2016-10-01T00:00:00.000
Constructionstart
2016-11-01T00:00:00.000
Constructionprojectedcom
2018-05-01T00:00:00.000
Constructionactualcompletion
2018-05-01T00:00:00.000
Totalfunding
$9,112,000
Projectliaison
Steve Simon
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
FederalMayoral
Name
East 102 Street & FDR Drive
Parkid
M108G
Latitude
40.787209
Longitude
-73.939013
Borough
Manhattan
VIEW LOCATION
4350
Trackerid: 4350 • Fmsid: 846 P-413LPL2 • Title: Laurelton West Playground Reconstruction
Trackerid
4350
Fmsid
846 P-413LPL2
Title
Laurelton West Playground Reconstruction
Summary
This project will reconstruct Laurelton West Playground located on 238th Street between 120th Avenue and 121st Avenue.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2009-07-01T00:00:00.000
Designactualcompletion
2011-08-01T00:00:00.000
Procurementstart
2011-08-01T00:00:00.000
Procurementprojectedcompletion
2012-05-01T00:00:00.000
Procurementactualcompletion
2013-03-01T00:00:00.000
Constructionstart
2013-06-01T00:00:00.000
Constructionprojectedcom
2014-06-01T00:00:00.000
Constructionadjustedcompletion
2014-06-01T00:00:00.000
Constructionactualcompletion
2014-06-01T00:00:00.000
Totalfunding
$1,186,000
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough President
Parkid
Q027
Latitude
40.67540778
Longitude
-73.73237222
Borough
Queens
VIEW LOCATION
10715
Trackerid: 10715 • Fmsid: 846 P-413LAPC • Title: Laurelton Playground Sports Courts Reconstruction
Trackerid
10715
Fmsid
846 P-413LAPC
Title
Laurelton Playground Sports Courts Reconstruction
Summary
This project will reconstruct the sports courts at Laurelton Playground.
Currentphase
design
Designpercentcomplete
100.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Designstart
2024-12-01T00:00:00.000
Designprojectedcompletion
2026-03-01T00:00:00.000
Designactualcompletion
2026-06-01T00:00:00.000
Totalfunding
Between $3 million and $5 million
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
BELT PARKWAY BETWEEN 137TH AVENUE AND 137TH ROAD
Parkid
Q108
Latitude
40.670052
Longitude
-73.736557
Borough
Queens
VIEW LOCATION
9552
Trackerid: 9552 • Fmsid: 846 P-413LPCT • Title: Laurelton Playground Reconstruction
Trackerid
9552
Fmsid
846 P-413LPCT
Title
Laurelton Playground Reconstruction
Summary
This project will reconstruct Laurelton Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2020-10-01T00:00:00.000
Designprojectedcompletion
2022-01-01T00:00:00.000
Designadjustedcompletion
2022-05-01T00:00:00.000
Designactualcompletion
2022-05-01T00:00:00.000
Procurementstart
2022-05-01T00:00:00.000
Procurementprojectedcompletion
2023-02-01T00:00:00.000
Procurementadjustedcompletion
2024-01-01T00:00:00.000
Procurementactualcompletion
2024-01-01T00:00:00.000
Constructionstart
2024-03-01T00:00:00.000
Constructionprojectedcom
2025-03-01T00:00:00.000
Constructionactualcompletion
2025-03-01T00:00:00.000
Totalfunding
$4,014,000
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoral
Name
Brookville Blvd between 136th and 138th Avenues
Parkid
Q108
Latitude
40.670539791013
Longitude
-73.736140854252
Borough
Queens
VIEW LOCATION
10361
Trackerid: 10361 • Fmsid: 846 P-4LLVIRG • Title: Lawrence Virgilio Playground and Mini Pool Reconstruction
Trackerid
10361
Fmsid
846 P-4LLVIRG
Title
Lawrence Virgilio Playground and Mini Pool Reconstruction
Summary
This project will reconstruct Lawrence Virgilio Playground and the mini pool.
Currentphase
design
Designpercentcomplete
100.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Designstart
2024-07-01T00:00:00.000
Designprojectedcompletion
2025-10-01T00:00:00.000
Designadjustedcompletion
2026-01-01T00:00:00.000
Designactualcompletion
2026-02-01T00:00:00.000
Totalfunding
Greater than $10 million
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough PresidentCity CouncilMayoral
Name
52nd Street and Woodside Avenue between 39th Road and 39th Drive
Parkid
Q031
Latitude
40.74752203
Longitude
-73.91054569
Borough
Queens
VIEW LOCATION