Capital Project Tracker

A listing of all capital projects managed by NYC Parks, and a timeline for their completion.

Supporting documentation can be found at the following link (http://www.nycgovparks.org/bigapps/desc/DPR_CapitalProjectTracker_001.txt).

See JSON and XML feeds here https://data.cityofnewyork.us/Recreation/Capital-Project-Tracker/qiwj-i2jk

Recreation Department of Parks and Recreation (DPR) Dataset 4hcv-tc5r 29 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
1256111
Trackerid: 1256111 • Fmsid: 846 P-3GARVRF • Title: Marcus Garvey Park POP Office Roof Reconstruction
Trackerid
1256111
Fmsid
846 P-3GARVRF
Title
Marcus Garvey Park POP Office Roof Reconstruction
Summary
This project will reconstruct the roof of the Manhattan Parks Opportunity Program (POP) Office in Marcus Garvey Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2019-10-01T00:00:00.000
Designprojectedcompletion
2020-08-01T00:00:00.000
Designadjustedcompletion
2021-09-01T00:00:00.000
Designactualcompletion
2021-08-01T00:00:00.000
Procurementstart
2020-03-01T00:00:00.000
Procurementprojectedcompletion
2020-08-01T00:00:00.000
Procurementactualcompletion
2021-06-01T00:00:00.000
Constructionstart
2023-03-01T00:00:00.000
Constructionprojectedcom
2023-08-01T00:00:00.000
Constructionactualcompletion
2023-08-01T00:00:00.000
Totalfunding
$363,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Parkid
M058
Latitude
40.805179
Longitude
-73.943143
Borough
Manhattan
VIEW LOCATION
1528111
Trackerid: 1528111 • Fmsid: 846 P-3MCRPAV • Title: Marcus Garvey Park Path Reconstruction and Ramps Construction
Trackerid
1528111
Fmsid
846 P-3MCRPAV
Title
Marcus Garvey Park Path Reconstruction and Ramps Construction
Summary
This project will reconstruct a portion of the path and construct ramps in Marcus Garvey Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2023-06-01T00:00:00.000
Designprojectedcompletion
2024-06-01T00:00:00.000
Designactualcompletion
2024-05-01T00:00:00.000
Procurementstart
2023-07-01T00:00:00.000
Procurementprojectedcompletion
2023-12-01T00:00:00.000
Procurementactualcompletion
2023-10-01T00:00:00.000
Constructionstart
2024-04-01T00:00:00.000
Constructionprojectedcom
2025-04-01T00:00:00.000
Constructionactualcompletion
2025-04-01T00:00:00.000
Totalfunding
$4,400,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Parkid
M058
Latitude
40.804752
Longitude
-73.943704
Borough
Manhattan
VIEW LOCATION
10318
Trackerid: 10318 • Fmsid: 846 P-311PFRC • Title: Marcus Garvey Park Pelham Fritz Recreation Center Roof Reconstruction
Trackerid
10318
Fmsid
846 P-311PFRC
Title
Marcus Garvey Park Pelham Fritz Recreation Center Roof Reconstruction
Summary
This project will reconstruct the roof at Pelham Fritz Recreation Center in Marcus Garvey Park.
Currentphase
design
Designpercentcomplete
50.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Designstart
2022-10-01T00:00:00.000
Designprojectedcompletion
2023-12-01T00:00:00.000
Designadjustedcompletion
2026-12-01T00:00:00.000
Totalfunding
Between $3 million and $5 million
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
18 Mount Morris Park West
Parkid
M058
Latitude
40.8049193
Longitude
-73.94479584
Borough
Manhattan
VIEW LOCATION
2492
Trackerid: 2492 • Fmsid: 846 P-311MGLL • Title: Marcus Garvey Park Public Restroom Building Construction
Trackerid
2492
Fmsid
846 P-311MGLL
Title
Marcus Garvey Park Public Restroom Building Construction
Summary
This project will construct a new public restroom building and Little League building in Marcus Garvey Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2015-03-01T00:00:00.000
Designprojectedcompletion
2016-02-01T00:00:00.000
Designadjustedcompletion
2016-04-01T00:00:00.000
Designactualcompletion
2016-04-01T00:00:00.000
Procurementstart
2016-04-01T00:00:00.000
Procurementprojectedcompletion
2016-12-01T00:00:00.000
Procurementadjustedcompletion
2017-08-01T00:00:00.000
Procurementactualcompletion
2017-06-01T00:00:00.000
Constructionstart
2017-07-01T00:00:00.000
Constructionprojectedcom
2019-01-01T00:00:00.000
Constructionadjustedcompletion
2021-05-01T00:00:00.000
Constructionactualcompletion
2021-07-01T00:00:00.000
Totalfunding
$4,250,000
Projectliaison
Steve Simon
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
MayoralPrivateState
Name
18 Mount Morris Park West, between West 121st Street and West 122nd Street
Parkid
M058
Latitude
40.804632132622
Longitude
-73.944815356489
Borough
Manhattan
VIEW LOCATION
8658
Trackerid: 8658 • Fmsid: 846 P-311PFRI • Title: Marcus Garvey Park Pelham Fritz Recreation Center Reconstruction
Trackerid
8658
Fmsid
846 P-311PFRI
Title
Marcus Garvey Park Pelham Fritz Recreation Center Reconstruction
Summary
This project will reconstruct the entrance lobby and retaining walls at Pelham Fritz Recreation Center in Marcus Garvey Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2017-09-01T00:00:00.000
Designprojectedcompletion
2018-09-01T00:00:00.000
Designadjustedcompletion
2018-12-01T00:00:00.000
Designactualcompletion
2018-12-01T00:00:00.000
Procurementstart
2018-12-01T00:00:00.000
Procurementprojectedcompletion
2019-09-01T00:00:00.000
Procurementadjustedcompletion
2020-04-01T00:00:00.000
Procurementactualcompletion
2020-03-01T00:00:00.000
Constructionstart
2020-11-01T00:00:00.000
Constructionprojectedcom
2022-05-01T00:00:00.000
Constructionactualcompletion
2022-04-01T00:00:00.000
Totalfunding
$923,000
Projectliaison
Steve Simon
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoral
Name
18 Mt. Morris Park West at West 122nd Street
Parkid
M058
Latitude
40.805015
Longitude
-73.94485
Borough
Manhattan
VIEW LOCATION
10849
Trackerid: 10849 • Currentphase: proposed • Designpercentcomplete: 0.0
Trackerid
10849
Title
Marcus Garvey Park Northwest and Northeast Playgrounds and Southern Amphitheatre Plaza Reconstruction
Summary
This project will reconstruct the Northwest and Northeast Playgrounds and the Southern Amphitheatre Plaza area at Marcus Garvey Park.
Currentphase
proposed
Designpercentcomplete
0.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Totalfunding
Between $5 million and $10 million
Projectliaison
Steve Simon
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoralState
Name
East 124th Street between Mt. Morris Park West and Madison Avenue
Parkid
M058
Latitude
40.8034597
Longitude
-73.94317886
Borough
Manhattan
VIEW LOCATION
10578
Trackerid: 10578 • Fmsid: 846 P-311MGAP • Title: Marcus Garvey Park Acropolis Reconstruction
Trackerid
10578
Fmsid
846 P-311MGAP
Title
Marcus Garvey Park Acropolis Reconstruction
Summary
This project will reconstruct the Marcus Garvey Park Acropolis.
Currentphase
design
Designpercentcomplete
30.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Designstart
2026-01-01T00:00:00.000
Designprojectedcompletion
2026-12-01T00:00:00.000
Totalfunding
Greater than $10 million
Projectliaison
Steve Simon
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral, Private
Name
Madison Ave, E. 120 St. to E. 124 St., New York, NY
Parkid
M058
Latitude
40.80482594
Longitude
-73.94339803
Borough
Manhattan
VIEW LOCATION
6351
Trackerid: 6351 • Fmsid: 846 P-311MGFI • Title: Marcus Garvey Park Fire Watchtower Restoration
Trackerid
6351
Fmsid
846 P-311MGFI
Title
Marcus Garvey Park Fire Watchtower Restoration
Summary
This project will reconstruct the fire watchtower and surrounding plaza in Marcus Garvey Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2015-03-01T00:00:00.000
Designprojectedcompletion
2015-10-01T00:00:00.000
Designadjustedcompletion
2016-02-01T00:00:00.000
Designactualcompletion
2016-02-01T00:00:00.000
Procurementstart
2016-02-01T00:00:00.000
Procurementprojectedcompletion
2016-11-01T00:00:00.000
Procurementadjustedcompletion
2017-07-01T00:00:00.000
Procurementactualcompletion
2017-06-01T00:00:00.000
Constructionstart
2017-07-01T00:00:00.000
Constructionprojectedcom
2018-07-01T00:00:00.000
Constructionadjustedcompletion
2019-10-01T00:00:00.000
Constructionactualcompletion
2019-12-01T00:00:00.000
Totalfunding
$7,971,000
Projectliaison
Steve Simon
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough PresidentCity CouncilMayoral
Name
Madison Avenue at East 122nd Street
Parkid
M058
Latitude
40.804489
Longitude
-73.94363
Borough
Manhattan
VIEW LOCATION
5221
Trackerid: 5221 • Fmsid: 846 P-311HFWT • Title: Marcus Garvey Park Fire Watchtower Dismantling
Trackerid
5221
Fmsid
846 P-311HFWT
Title
Marcus Garvey Park Fire Watchtower Dismantling
Summary
This project will dismantle the Marcus Garvey Park Fire Watchtower in preparation for its reconstruction.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2013-07-01T00:00:00.000
Designprojectedcompletion
2014-01-01T00:00:00.000
Designactualcompletion
2014-06-01T00:00:00.000
Procurementstart
2014-06-01T00:00:00.000
Procurementprojectedcompletion
2015-03-01T00:00:00.000
Procurementactualcompletion
2014-11-01T00:00:00.000
Constructionstart
2014-08-01T00:00:00.000
Constructionprojectedcom
2015-02-01T00:00:00.000
Constructionadjustedcompletion
2015-07-01T00:00:00.000
Constructionactualcompletion
2015-06-01T00:00:00.000
Totalfunding
$1,927,000
Projectliaison
Steve Simon
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough President, City Council, Private
Name
Madison Avenue, East 124th Street, Mount Morris Park West, West 120th Street
Parkid
M058
Latitude
40.804135
Longitude
-73.943581
Borough
Manhattan
VIEW LOCATION
9224
Trackerid: 9224 • Fmsid: 846 P-201MRCY • Title: Marcy Green Park Reconstruction
Trackerid
9224
Fmsid
846 P-201MRCY
Title
Marcy Green Park Reconstruction
Summary
This project will reconstruct Marcy Green Park. Marcy Green North will include a spray shower, lawn, and seating areas. Marcy Green Center will include seating areas and ping pong tables, and Marcy Green South will include a new dog run.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2019-06-01T00:00:00.000
Designprojectedcompletion
2020-06-01T00:00:00.000
Designactualcompletion
2020-06-01T00:00:00.000
Procurementstart
2020-06-01T00:00:00.000
Procurementprojectedcompletion
2021-03-01T00:00:00.000
Procurementadjustedcompletion
2022-03-01T00:00:00.000
Procurementactualcompletion
2022-03-01T00:00:00.000
Constructionstart
2022-05-01T00:00:00.000
Constructionprojectedcom
2023-05-01T00:00:00.000
Constructionactualcompletion
2023-04-01T00:00:00.000
Totalfunding
$3,409,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Marcy Avenue, South 4 and South 5 Streets
Parkid
B223QB
Latitude
40.7088549
Longitude
-73.957525
Borough
Brooklyn
VIEW LOCATION
9224
Trackerid: 9224 • Fmsid: 846 P-201MRCY • Title: Marcy Green Park Reconstruction
Trackerid
9224
Fmsid
846 P-201MRCY
Title
Marcy Green Park Reconstruction
Summary
This project will reconstruct Marcy Green Park. Marcy Green North will include a spray shower, lawn, and seating areas. Marcy Green Center will include seating areas and ping pong tables, and Marcy Green South will include a new dog run.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2019-06-01T00:00:00.000
Designprojectedcompletion
2020-06-01T00:00:00.000
Designactualcompletion
2020-06-01T00:00:00.000
Procurementstart
2020-06-01T00:00:00.000
Procurementprojectedcompletion
2021-03-01T00:00:00.000
Procurementadjustedcompletion
2022-03-01T00:00:00.000
Procurementactualcompletion
2022-03-01T00:00:00.000
Constructionstart
2022-05-01T00:00:00.000
Constructionprojectedcom
2023-05-01T00:00:00.000
Constructionactualcompletion
2023-04-01T00:00:00.000
Totalfunding
$3,409,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Marcy Avenue, South 3 and South 4 Streets
Parkid
B223QC
Latitude
40.7095524
Longitude
-73.9565461
Borough
Brooklyn
VIEW LOCATION
9224
Trackerid: 9224 • Fmsid: 846 P-201MRCY • Title: Marcy Green Park Reconstruction
Trackerid
9224
Fmsid
846 P-201MRCY
Title
Marcy Green Park Reconstruction
Summary
This project will reconstruct Marcy Green Park. Marcy Green North will include a spray shower, lawn, and seating areas. Marcy Green Center will include seating areas and ping pong tables, and Marcy Green South will include a new dog run.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2019-06-01T00:00:00.000
Designprojectedcompletion
2020-06-01T00:00:00.000
Designactualcompletion
2020-06-01T00:00:00.000
Procurementstart
2020-06-01T00:00:00.000
Procurementprojectedcompletion
2021-03-01T00:00:00.000
Procurementadjustedcompletion
2022-03-01T00:00:00.000
Procurementactualcompletion
2022-03-01T00:00:00.000
Constructionstart
2022-05-01T00:00:00.000
Constructionprojectedcom
2023-05-01T00:00:00.000
Constructionactualcompletion
2023-04-01T00:00:00.000
Totalfunding
$3,409,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Broadway, Marcy Avenue and South 5 Street
Parkid
B223QA
Latitude
40.7088549
Longitude
-73.957525
Borough
Brooklyn
VIEW LOCATION
10068
Trackerid: 10068 • Fmsid: 846 P-407WBPK • Title: Weeping Beech Park Multipurpose Play Area Reconstruction
Trackerid
10068
Fmsid
846 P-407WBPK
Title
Weeping Beech Park Multipurpose Play Area Reconstruction
Summary
This project will reconstruct the multipurpose play area and the paths in Margaret Carman Green at Weeping Beech Park.
Currentphase
design
Designpercentcomplete
100.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Designstart
2023-11-01T00:00:00.000
Designprojectedcompletion
2025-02-01T00:00:00.000
Designadjustedcompletion
2025-06-01T00:00:00.000
Designactualcompletion
2025-06-01T00:00:00.000
Totalfunding
Between $5 million and $10 million
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoral
Name
Bowne Street and 37th Avenue
Parkid
Q022
Latitude
40.76343334
Longitude
-73.82471228
Borough
Queens
VIEW LOCATION
3086
Trackerid: 3086 • Fmsid: 846 P-407BHRE • Title: Bowne House Restoration
Trackerid
3086
Fmsid
846 P-407BHRE
Title
Bowne House Restoration
Summary
This project will restore the exterior and address interior structural issues of the Bowne House in Margaret I. Carmen Green – Weeping Beech.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2010-05-01T00:00:00.000
Designactualcompletion
2011-10-01T00:00:00.000
Procurementstart
2011-10-01T00:00:00.000
Procurementprojectedcompletion
2012-07-01T00:00:00.000
Procurementadjustedcompletion
2012-11-01T00:00:00.000
Procurementactualcompletion
2012-11-01T00:00:00.000
Constructionstart
2013-04-01T00:00:00.000
Constructionprojectedcom
2014-05-01T00:00:00.000
Constructionadjustedcompletion
2014-11-01T00:00:00.000
Constructionactualcompletion
2014-11-01T00:00:00.000
Totalfunding
$2,743,000
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough President, State
Name
Bowne Street between 37th and 38th Avenues, Weeping Beech Park, Queens
Parkid
Q022
Latitude
40.76315194
Longitude
-73.82498639
Borough
Queens
VIEW LOCATION
10457
Trackerid: 10457 • Fmsid: 846 P-204MHPG • Title: Maria Hernandez Park Playground and Dog Run Reconstruction
Trackerid
10457
Fmsid
846 P-204MHPG
Title
Maria Hernandez Park Playground and Dog Run Reconstruction
Summary
This project will reconstruct the playground and dog run in Maria Hernandez Park.
Currentphase
design
Designpercentcomplete
100.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Designstart
2023-06-01T00:00:00.000
Designprojectedcompletion
2025-01-01T00:00:00.000
Designactualcompletion
2024-12-01T00:00:00.000
Totalfunding
Between $5 million and $10 million
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
Irving Avenue, Knickerbocker Avenue between Starr Street and Suydam Street
Parkid
B016
Latitude
40.70328
Longitude
-73.923725
Borough
Brooklyn
VIEW LOCATION
8889
Trackerid: 8889 • Fmsid: 846 P-2STFMH • Title: Maria Hernandez Park Synthetic Turf Field Construction
Trackerid
8889
Fmsid
846 P-2STFMH
Title
Maria Hernandez Park Synthetic Turf Field Construction
Summary
This project will construct a new synthetic turf field and adult fitness at Maria Hernandez Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2017-10-01T00:00:00.000
Designprojectedcompletion
2018-10-01T00:00:00.000
Designactualcompletion
2018-10-01T00:00:00.000
Procurementstart
2018-10-01T00:00:00.000
Procurementprojectedcompletion
2019-07-01T00:00:00.000
Procurementadjustedcompletion
2021-04-01T00:00:00.000
Procurementactualcompletion
2021-04-01T00:00:00.000
Constructionstart
2021-08-01T00:00:00.000
Constructionprojectedcom
2022-08-01T00:00:00.000
Constructionactualcompletion
2022-06-01T00:00:00.000
Totalfunding
$3,196,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Knickerbocker Avenue between Starr Street and Suydam Street
Parkid
B016
Latitude
40.703618
Longitude
-73.923453
Borough
Brooklyn
VIEW LOCATION
1007111
Trackerid: 1007111 • Fmsid: 846 P-218BRGM • Title: Marine Park Bike Path Restoration
Trackerid
1007111
Fmsid
846 P-218BRGM
Title
Marine Park Bike Path Restoration
Summary
This project will restore damaged portions of the Plumb Beach bike path in Marine Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2013-09-01T00:00:00.000
Designprojectedcompletion
2014-05-01T00:00:00.000
Designactualcompletion
2014-05-01T00:00:00.000
Procurementstart
2015-06-01T00:00:00.000
Procurementprojectedcompletion
2015-11-01T00:00:00.000
Procurementactualcompletion
2014-09-01T00:00:00.000
Constructionstart
2014-10-01T00:00:00.000
Constructionprojectedcom
2014-11-01T00:00:00.000
Constructionactualcompletion
2014-12-01T00:00:00.000
Totalfunding
$275,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Parkid
B057
Latitude
40.597864
Longitude
-73.919567
Borough
Brooklyn
VIEW LOCATION
1093111
Trackerid: 1093111 • Fmsid: 846 P-218MPVT • Title: Marine Park Veterans Memorial Reconstruction
Trackerid
1093111
Fmsid
846 P-218MPVT
Title
Marine Park Veterans Memorial Reconstruction
Summary
This project will reconstruct the veterans' memorial in Marine Park with new seating, a planting bed around the memorial, and asphalt paving.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2017-03-01T00:00:00.000
Designprojectedcompletion
2018-06-01T00:00:00.000
Designactualcompletion
2018-03-01T00:00:00.000
Procurementstart
2017-06-01T00:00:00.000
Procurementprojectedcompletion
2017-11-01T00:00:00.000
Procurementactualcompletion
2018-03-01T00:00:00.000
Constructionstart
2018-09-01T00:00:00.000
Constructionprojectedcom
2018-11-01T00:00:00.000
Constructionactualcompletion
2018-10-01T00:00:00.000
Totalfunding
$49,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Parkid
B057
Latitude
40.59949
Longitude
-73.929798
Borough
Brooklyn
VIEW LOCATION
1655111
Trackerid: 1655111 • Fmsid: 846 P-6CWPAV1 • Title: Marine Park Avenue S Parking Lot Reconstruction
Trackerid
1655111
Fmsid
846 P-6CWPAV1
Title
Marine Park Avenue S Parking Lot Reconstruction
Summary
This project will reconstruct the parking lot at Avenue S in Marine Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2023-12-01T00:00:00.000
Designprojectedcompletion
2024-11-01T00:00:00.000
Designactualcompletion
2024-10-01T00:00:00.000
Procurementstart
2024-03-01T00:00:00.000
Procurementprojectedcompletion
2024-08-01T00:00:00.000
Procurementactualcompletion
2024-10-01T00:00:00.000
Constructionstart
2025-09-01T00:00:00.000
Constructionprojectedcom
2026-06-01T00:00:00.000
Constructionactualcompletion
2025-11-01T00:00:00.000
Totalfunding
$1,834,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Parkid
B057
Latitude
40.60649
Longitude
-73.938572
Borough
Brooklyn
VIEW LOCATION
1824
Trackerid: 1824 • Fmsid: 846 P-218SEBA • Title: Marine Park Seba Playground Expansion
Trackerid
1824
Fmsid
846 P-218SEBA
Title
Marine Park Seba Playground Expansion
Summary
This project will expand Seba Playground in Marine Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2011-03-01T00:00:00.000
Designactualcompletion
2012-01-01T00:00:00.000
Procurementstart
2012-01-01T00:00:00.000
Procurementprojectedcompletion
2012-10-01T00:00:00.000
Procurementactualcompletion
2012-07-01T00:00:00.000
Constructionstart
2013-05-01T00:00:00.000
Constructionprojectedcom
2014-05-01T00:00:00.000
Constructionadjustedcompletion
2014-05-01T00:00:00.000
Constructionactualcompletion
2014-05-01T00:00:00.000
Totalfunding
$1,531,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council, State
Parkid
B057
Latitude
40.589312
Longitude
-73.9206
Borough
Brooklyn
VIEW LOCATION
6630
Trackerid: 6630 • Fmsid: 846 P-218GOLF • Title: Marine Park Golf Course Path Reconstruction
Trackerid
6630
Fmsid
846 P-218GOLF
Title
Marine Park Golf Course Path Reconstruction
Summary
This project will reconstruct the pavement, curbs, and drainage at the main entrance and areas adjacent to the clubhouse within Marine Park Golf Course.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2018-09-01T00:00:00.000
Designprojectedcompletion
2019-09-01T00:00:00.000
Designadjustedcompletion
2020-10-01T00:00:00.000
Designactualcompletion
2020-10-01T00:00:00.000
Procurementstart
2020-10-01T00:00:00.000
Procurementprojectedcompletion
2021-07-01T00:00:00.000
Procurementadjustedcompletion
2022-10-01T00:00:00.000
Procurementactualcompletion
2022-10-01T00:00:00.000
Constructionstart
2023-02-01T00:00:00.000
Constructionprojectedcom
2024-02-01T00:00:00.000
Constructionactualcompletion
2023-10-01T00:00:00.000
Totalfunding
$1,319,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough President, City Council
Name
2880 Flatbush Avenue
Parkid
B057
Latitude
40.600653
Longitude
-73.913811
Borough
Brooklyn
VIEW LOCATION
7016
Trackerid: 7016 • Fmsid: 846 P-218MPNC • Title: Marine Park Salt Marsh Nature Center Reconstruction
Trackerid
7016
Fmsid
846 P-218MPNC
Title
Marine Park Salt Marsh Nature Center Reconstruction
Summary
This project will reconstruct the Salt Marsh Nature Center to provide additional office and exhibition space and ADA access outside the building, around the bluff perimeter.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2017-08-01T00:00:00.000
Designprojectedcompletion
2018-08-01T00:00:00.000
Designadjustedcompletion
2019-09-01T00:00:00.000
Designactualcompletion
2019-08-01T00:00:00.000
Procurementstart
2019-08-01T00:00:00.000
Procurementprojectedcompletion
2020-04-01T00:00:00.000
Procurementadjustedcompletion
2020-12-01T00:00:00.000
Procurementactualcompletion
2021-04-01T00:00:00.000
Constructionstart
2021-09-01T00:00:00.000
Constructionprojectedcom
2023-03-01T00:00:00.000
Constructionactualcompletion
2023-03-01T00:00:00.000
Totalfunding
$2,000,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Avenue U and East 33rd Street
Parkid
B057
Latitude
40.604119
Longitude
-73.930525
Borough
Brooklyn
VIEW LOCATION
11293
Trackerid: 11293 • Title: Marine Park Salt Marsh Nature Trail Bridge Reconstruction • Currentphase: proposed
Trackerid
11293
Title
Marine Park Salt Marsh Nature Trail Bridge Reconstruction
Summary
This project will reconstruct the existing bridge on the Salt Marsh Nature Trail and restore the adjacent wetlands in Marine Park.
Currentphase
proposed
Designpercentcomplete
0.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Totalfunding
Between $3 million and $5 million
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough PresidentFederal
Name
Avenue U near East 33rd Street
Parkid
B057
Latitude
40.59571938
Longitude
-73.9173092
Borough
Brooklyn
VIEW LOCATION
9555
Trackerid: 9555 • Fmsid: 846 P-218MPOV • Title: Marine Park Oval Path Reconstruction
Trackerid
9555
Fmsid
846 P-218MPOV
Title
Marine Park Oval Path Reconstruction
Summary
This project will reconstruct the inner and outer walking paths of the oval as well as several connecting paths at Marine Park, including new asphalt pavement, bottle fillers and benches.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2019-11-01T00:00:00.000
Designprojectedcompletion
2020-11-01T00:00:00.000
Designadjustedcompletion
2021-12-01T00:00:00.000
Designactualcompletion
2021-12-01T00:00:00.000
Procurementstart
2021-12-01T00:00:00.000
Procurementprojectedcompletion
2022-09-01T00:00:00.000
Procurementadjustedcompletion
2023-04-01T00:00:00.000
Procurementactualcompletion
2023-04-01T00:00:00.000
Constructionstart
2023-06-01T00:00:00.000
Constructionprojectedcom
2024-09-01T00:00:00.000
Constructionactualcompletion
2024-10-01T00:00:00.000
Totalfunding
$5,746,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoral
Name
Avenue U, Stuart Street, Fillmore Avenue, East 33rd Street
Parkid
B057
Latitude
40.605814
Longitude
-73.93517
Borough
Brooklyn
VIEW LOCATION
9988
Trackerid: 9988 • Fmsid: 846 P-2SPC21A • Title: Marine Park Forest Restoration
Trackerid
9988
Fmsid
846 P-2SPC21A
Title
Marine Park Forest Restoration
Summary
This project will restore native species habitat within forested natural areas in Marine Park.
Currentphase
construction
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
88.25
Designstart
2021-01-01T00:00:00.000
Designprojectedcompletion
2021-10-01T00:00:00.000
Designactualcompletion
2021-10-01T00:00:00.000
Procurementstart
2021-10-01T00:00:00.000
Procurementprojectedcompletion
2022-07-01T00:00:00.000
Procurementadjustedcompletion
2023-06-01T00:00:00.000
Procurementactualcompletion
2023-06-01T00:00:00.000
Constructionstart
2023-11-01T00:00:00.000
Constructionprojectedcom
2026-11-01T00:00:00.000
Totalfunding
$1,207,000
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
East of Gerritsen Avenue between Bartlett Place and Lois Avenue
Parkid
B057
Latitude
40.59087981
Longitude
-73.91806919
Borough
Brooklyn
VIEW LOCATION
1036
Trackerid: 1036 • Fmsid: 846 P-218MPRK • Title: Marine Park Bocce Courts and Sport Courts Reconstruction
Trackerid
1036
Fmsid
846 P-218MPRK
Title
Marine Park Bocce Courts and Sport Courts Reconstruction
Summary
This project will reconstruct the bocce courts, sports courts and landscaping at Marine Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2012-03-01T00:00:00.000
Designprojectedcompletion
2014-01-01T00:00:00.000
Designadjustedcompletion
2015-01-01T00:00:00.000
Designactualcompletion
2015-01-01T00:00:00.000
Procurementstart
2015-01-01T00:00:00.000
Procurementprojectedcompletion
2015-10-01T00:00:00.000
Procurementactualcompletion
2015-07-01T00:00:00.000
Constructionstart
2015-10-01T00:00:00.000
Constructionprojectedcom
2017-03-01T00:00:00.000
Constructionactualcompletion
2016-12-01T00:00:00.000
Totalfunding
$5,642,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
Fillmore Avenue and East 32nd Street
Parkid
B057
Latitude
40.593264
Longitude
-73.923829
Borough
Brooklyn
VIEW LOCATION
9662
Trackerid: 9662 • Fmsid: 846 P-218MPPG • Title: Marine Park PS 278 Playground Reconstruction
Trackerid
9662
Fmsid
846 P-218MPPG
Title
Marine Park PS 278 Playground Reconstruction
Summary
This project will reconstruct the play area and sport courts at PS 278 Playground in Marine Park.
Currentphase
design
Designpercentcomplete
100.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Designstart
2020-01-01T00:00:00.000
Designprojectedcompletion
2021-01-01T00:00:00.000
Designadjustedcompletion
2024-12-01T00:00:00.000
Designactualcompletion
2025-03-01T00:00:00.000
Totalfunding
Greater than $10 million
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough President, City Council, State
Name
Fillmore Avenue and Madison Place
Parkid
B057
Latitude
40.60730729
Longitude
-73.93826042
Borough
Brooklyn
VIEW LOCATION
6210
Trackerid: 6210 • Fmsid: 846 P-218D17S • Title: Dr. John's Playground Paths, Water Supply & Drainage System Reconstruction
Trackerid
6210
Fmsid
846 P-218D17S
Title
Dr. John's Playground Paths, Water Supply & Drainage System Reconstruction
Summary
This project will reconstruct the paths, water supply and drainage systems at Dr. John's Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2011-07-01T00:00:00.000
Designprojectedcompletion
2014-10-01T00:00:00.000
Designadjustedcompletion
2015-12-01T00:00:00.000
Designactualcompletion
2016-01-01T00:00:00.000
Procurementstart
2016-01-01T00:00:00.000
Procurementprojectedcompletion
2016-10-01T00:00:00.000
Procurementadjustedcompletion
2016-12-01T00:00:00.000
Procurementactualcompletion
2016-12-01T00:00:00.000
Constructionstart
2017-04-01T00:00:00.000
Constructionprojectedcom
2018-04-01T00:00:00.000
Constructionactualcompletion
2018-04-01T00:00:00.000
Totalfunding
$2,527,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
Gerritsen Avenue and Avenue X
Parkid
B057
Latitude
40.596621
Longitude
-73.927353
Borough
Brooklyn
VIEW LOCATION
6094
Trackerid: 6094 • Fmsid: 846 P-218GERI • Title: Marine Park Gerritsen Avenue Pedestrian Path Construction Phase 1
Trackerid
6094
Fmsid
846 P-218GERI
Title
Marine Park Gerritsen Avenue Pedestrian Path Construction Phase 1
Summary
This project will construct new asphalt paths along Gerritsen Avenue and provide improved accessibility to the existing baseball fields in Marine Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2015-03-01T00:00:00.000
Designprojectedcompletion
2015-06-01T00:00:00.000
Designadjustedcompletion
2015-09-01T00:00:00.000
Designactualcompletion
2015-09-01T00:00:00.000
Procurementstart
2015-09-01T00:00:00.000
Procurementprojectedcompletion
2016-06-01T00:00:00.000
Procurementactualcompletion
2016-06-01T00:00:00.000
Constructionstart
2016-08-01T00:00:00.000
Constructionprojectedcom
2017-08-01T00:00:00.000
Constructionactualcompletion
2017-04-01T00:00:00.000
Totalfunding
$480,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoral
Name
Gerritsen Avenue between Seba Avenue and Florence Avenue
Parkid
B057
Latitude
40.586711
Longitude
-73.910525
Borough
Brooklyn
VIEW LOCATION
8578
Trackerid: 8578 • Fmsid: 846 P-218GERT • Title: Marine Park Gerritsen Avenue Pedestrian Path Construction Phase 2
Trackerid
8578
Fmsid
846 P-218GERT
Title
Marine Park Gerritsen Avenue Pedestrian Path Construction Phase 2
Summary
This project will construct a new asphalt path, benches and accessible entrances adjacent to the Gerritsen Avenue ballfields in Marine Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2016-09-01T00:00:00.000
Designprojectedcompletion
2017-06-01T00:00:00.000
Designactualcompletion
2017-06-01T00:00:00.000
Procurementstart
2017-06-01T00:00:00.000
Procurementprojectedcompletion
2018-02-01T00:00:00.000
Procurementadjustedcompletion
2019-03-01T00:00:00.000
Procurementactualcompletion
2019-03-01T00:00:00.000
Constructionstart
2019-06-01T00:00:00.000
Constructionprojectedcom
2020-06-01T00:00:00.000
Constructionactualcompletion
2019-10-01T00:00:00.000
Totalfunding
$1,196,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoralState
Name
Gerritsen Avenue near Florence Avenue and Channel Avenue
Parkid
B057
Latitude
40.59358
Longitude
-73.925612
Borough
Brooklyn
VIEW LOCATION
1035
Trackerid: 1035 • Fmsid: 846 P-2BRIGHM • Title: Lew Fidler Park Construction
Trackerid
1035
Fmsid
846 P-2BRIGHM
Title
Lew Fidler Park Construction
Summary
This project will construct Lew Fidler Park, including a new playground with play equipment, swings, spray shower area, hillside slide and a picnic area in Marine Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2011-07-01T00:00:00.000
Designprojectedcompletion
2014-12-01T00:00:00.000
Designadjustedcompletion
2016-10-01T00:00:00.000
Designactualcompletion
2017-08-01T00:00:00.000
Procurementstart
2017-08-01T00:00:00.000
Procurementprojectedcompletion
2018-05-01T00:00:00.000
Procurementadjustedcompletion
2018-09-01T00:00:00.000
Procurementactualcompletion
2018-07-01T00:00:00.000
Constructionstart
2018-11-01T00:00:00.000
Constructionprojectedcom
2020-05-01T00:00:00.000
Constructionadjustedcompletion
2021-01-01T00:00:00.000
Constructionactualcompletion
2021-03-01T00:00:00.000
Totalfunding
$5,624,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoral
Name
Southeast corner of Brigham Street and Emmons Avenue
Parkid
B057
Latitude
40.5837645
Longitude
-73.9315991
Borough
Brooklyn
VIEW LOCATION
10881
Trackerid: 10881 • Fmsid: 846 P-213MRLB • Title: Marlboro Playground Reconstruction
Trackerid
10881
Fmsid
846 P-213MRLB
Title
Marlboro Playground Reconstruction
Summary
This project will reconstruct Marlboro Playground.
Currentphase
design
Designpercentcomplete
5.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Designstart
2026-06-01T00:00:00.000
Designprojectedcompletion
2027-07-01T00:00:00.000
Totalfunding
Between $5 million and $10 million
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
W 11th Street between Avenue W and Avenue X
Parkid
B272
Latitude
40.59095239
Longitude
-73.98086011
Borough
Brooklyn
VIEW LOCATION
6883
Trackerid: 6883 • Fmsid: 846 P-213MBRO • Title: Marlboro Playground Security Lighting Installation
Trackerid
6883
Fmsid
846 P-213MBRO
Title
Marlboro Playground Security Lighting Installation
Summary
This project will install a park security lighting system in Marlboro Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2015-06-01T00:00:00.000
Designprojectedcompletion
2015-09-01T00:00:00.000
Designactualcompletion
2016-02-01T00:00:00.000
Procurementstart
2016-02-01T00:00:00.000
Procurementprojectedcompletion
2016-11-01T00:00:00.000
Procurementactualcompletion
2016-07-01T00:00:00.000
Constructionstart
2016-10-01T00:00:00.000
Constructionprojectedcom
2016-12-01T00:00:00.000
Constructionadjustedcompletion
2017-03-01T00:00:00.000
Constructionactualcompletion
2017-03-01T00:00:00.000
Totalfunding
$89,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
West 11th Street and Avenue W
Parkid
B272
Latitude
40.59121917
Longitude
-73.98084361
Borough
Brooklyn
VIEW LOCATION
6097
Trackerid: 6097 • Fmsid: 846 P-2PLAY13 • Currentphase: completed
Trackerid
6097
Fmsid
846 P-2PLAY13
Title
Martin Luther King Jr. Playground Spray Shower, Ocean Hill Playground, and Wingate Park Playground Reconstruction
Summary
This project will reconstruct the spray shower at Martin Luther King Jr. Playground, and the playgrounds at Ocean Hill Playground and Wingate Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2012-04-01T00:00:00.000
Designprojectedcompletion
2013-08-01T00:00:00.000
Designactualcompletion
2013-12-01T00:00:00.000
Procurementstart
2013-12-01T00:00:00.000
Procurementprojectedcompletion
2014-08-01T00:00:00.000
Procurementadjustedcompletion
2015-11-01T00:00:00.000
Procurementactualcompletion
2015-10-01T00:00:00.000
Constructionstart
2016-04-01T00:00:00.000
Constructionprojectedcom
2017-07-01T00:00:00.000
Constructionadjustedcompletion
2017-09-01T00:00:00.000
Constructionactualcompletion
2017-08-01T00:00:00.000
Totalfunding
$1,558,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough PresidentMayoral
Name
Dumont Ave., Blake Ave. bet. Bradford St. and Miller Ave.
Parkid
B056
Latitude
40.667409
Longitude
-73.890395
Borough
Brooklyn
VIEW LOCATION
6097
Trackerid: 6097 • Fmsid: 846 P-2PLAY13 • Currentphase: completed
Trackerid
6097
Fmsid
846 P-2PLAY13
Title
Martin Luther King Jr. Playground Spray Shower, Ocean Hill Playground, and Wingate Park Playground Reconstruction
Summary
This project will reconstruct the spray shower at Martin Luther King Jr. Playground, and the playgrounds at Ocean Hill Playground and Wingate Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2012-04-01T00:00:00.000
Designprojectedcompletion
2013-08-01T00:00:00.000
Designactualcompletion
2013-12-01T00:00:00.000
Procurementstart
2013-12-01T00:00:00.000
Procurementprojectedcompletion
2014-08-01T00:00:00.000
Procurementadjustedcompletion
2015-11-01T00:00:00.000
Procurementactualcompletion
2015-10-01T00:00:00.000
Constructionstart
2016-04-01T00:00:00.000
Constructionprojectedcom
2017-07-01T00:00:00.000
Constructionadjustedcompletion
2017-09-01T00:00:00.000
Constructionactualcompletion
2017-08-01T00:00:00.000
Totalfunding
$1,558,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough PresidentMayoral
Name
Dean St., Bergen St. bet. Rockaway Ave.and Hopkinson Ave.
Parkid
B144
Latitude
40.674601
Longitude
-73.912148
Borough
Brooklyn
VIEW LOCATION
6097
Trackerid: 6097 • Fmsid: 846 P-2PLAY13 • Currentphase: completed
Trackerid
6097
Fmsid
846 P-2PLAY13
Title
Martin Luther King Jr. Playground Spray Shower, Ocean Hill Playground, and Wingate Park Playground Reconstruction
Summary
This project will reconstruct the spray shower at Martin Luther King Jr. Playground, and the playgrounds at Ocean Hill Playground and Wingate Park.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2012-04-01T00:00:00.000
Designprojectedcompletion
2013-08-01T00:00:00.000
Designactualcompletion
2013-12-01T00:00:00.000
Procurementstart
2013-12-01T00:00:00.000
Procurementprojectedcompletion
2014-08-01T00:00:00.000
Procurementadjustedcompletion
2015-11-01T00:00:00.000
Procurementactualcompletion
2015-10-01T00:00:00.000
Constructionstart
2016-04-01T00:00:00.000
Constructionprojectedcom
2017-07-01T00:00:00.000
Constructionadjustedcompletion
2017-09-01T00:00:00.000
Constructionactualcompletion
2017-08-01T00:00:00.000
Totalfunding
$1,558,000
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough PresidentMayoral
Name
S E Corner Brooklyn Av and Rutl& Rd
Parkid
B254
Latitude
40.659512
Longitude
-73.944876
Borough
Brooklyn
VIEW LOCATION
11398
Trackerid: 11398 • Title: Merriam Playground Pathway Reconstruction • Currentphase: proposed
Trackerid
11398
Title
Merriam Playground Pathway Reconstruction
Summary
This project will reconstruct the paths, stairs, and sitting area in Merriam Playground.
Currentphase
proposed
Designpercentcomplete
0.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Totalfunding
Between $3 million and $5 million
Projectliaison
Katerine Borrome
Lastupdated
2026-10-01T00:00:00.000
Name
Ogden Ave. bet. W. 168 St. and Merriam Ave. Bronx
Parkid
X153
Latitude
40.8404309
Longitude
-3.9268863
Borough
Bronx
VIEW LOCATION
7419
Trackerid: 7419 • Fmsid: 846 P-3CPIMLK • Title: Martin Luther King Jr. Playground Reconstruction
Trackerid
7419
Fmsid
846 P-3CPIMLK
Title
Martin Luther King Jr. Playground Reconstruction
Summary
This project will reconstruct Martin Luther King Jr. Playground with new play equipment, a spray shower, synthetic turf area, basketball courts, lighting, fencing, pavements, plantings and site furnishings.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2015-01-01T00:00:00.000
Designprojectedcompletion
2015-12-01T00:00:00.000
Designactualcompletion
2016-01-01T00:00:00.000
Procurementstart
2016-01-01T00:00:00.000
Procurementprojectedcompletion
2016-10-01T00:00:00.000
Procurementactualcompletion
2016-08-01T00:00:00.000
Constructionstart
2016-09-01T00:00:00.000
Constructionprojectedcom
2017-12-01T00:00:00.000
Constructionactualcompletion
2018-01-01T00:00:00.000
Totalfunding
$3,864,000
Projectliaison
Steve Simon
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Name
Malcolm X Boulevard (Lenox Avenue) between West 113th Street and West 114th Street
Parkid
M198
Latitude
40.80019
Longitude
-73.950434
Borough
Manhattan
VIEW LOCATION
10885
Trackerid: 10885 • Fmsid: 846 P-207MLPG • Title: Martin Luther Playground Reconstruction
Trackerid
10885
Fmsid
846 P-207MLPG
Title
Martin Luther Playground Reconstruction
Summary
This project will reconstruct Martin Luther Playground.
Currentphase
design
Designpercentcomplete
5.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Designstart
2026-03-01T00:00:00.000
Designprojectedcompletion
2027-03-01T00:00:00.000
Totalfunding
Between $3 million and $5 million
Projectliaison
James Morris
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
2nd Avenue between 55th Street and 56th Street.
Parkid
B098
Latitude
40.66723183
Longitude
-73.89044033
Borough
Brooklyn
VIEW LOCATION
9327
Trackerid: 9327 • Fmsid: 846 P-306TUDO • Title: Mary O'Connor and Tudor Grove Playground Reconstruction
Trackerid
9327
Fmsid
846 P-306TUDO
Title
Mary O'Connor and Tudor Grove Playground Reconstruction
Summary
This project will reconstruct the play equipment and safety surfacing at Mary O'Connor and Tudor Grove playgrounds.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2019-02-01T00:00:00.000
Designprojectedcompletion
2020-02-01T00:00:00.000
Designactualcompletion
2020-02-01T00:00:00.000
Procurementstart
2020-02-01T00:00:00.000
Procurementprojectedcompletion
2020-11-01T00:00:00.000
Procurementadjustedcompletion
2022-08-01T00:00:00.000
Procurementactualcompletion
2022-08-01T00:00:00.000
Constructionstart
2022-11-01T00:00:00.000
Constructionprojectedcom
2023-11-01T00:00:00.000
Constructionactualcompletion
2023-08-01T00:00:00.000
Totalfunding
$1,000,000
Projectliaison
Steve Simon
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoral
Name
N/S East 42 Street & Tudor Place
Parkid
M203D
Latitude
40.7496
Longitude
-73.970812
Borough
Manhattan
VIEW LOCATION
9327
Trackerid: 9327 • Fmsid: 846 P-306TUDO • Title: Mary O'Connor and Tudor Grove Playground Reconstruction
Trackerid
9327
Fmsid
846 P-306TUDO
Title
Mary O'Connor and Tudor Grove Playground Reconstruction
Summary
This project will reconstruct the play equipment and safety surfacing at Mary O'Connor and Tudor Grove playgrounds.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2019-02-01T00:00:00.000
Designprojectedcompletion
2020-02-01T00:00:00.000
Designactualcompletion
2020-02-01T00:00:00.000
Procurementstart
2020-02-01T00:00:00.000
Procurementprojectedcompletion
2020-11-01T00:00:00.000
Procurementadjustedcompletion
2022-08-01T00:00:00.000
Procurementactualcompletion
2022-08-01T00:00:00.000
Constructionstart
2022-11-01T00:00:00.000
Constructionprojectedcom
2023-11-01T00:00:00.000
Constructionactualcompletion
2023-08-01T00:00:00.000
Totalfunding
$1,000,000
Projectliaison
Steve Simon
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoral
Name
S/S East 42 Street, 1 to 2 Avenues
Parkid
M203E
Latitude
40.749063
Longitude
-73.9711
Borough
Manhattan
VIEW LOCATION
10723
Trackerid: 10723 • Fmsid: 846 P-304MPRC • Title: Mathews-Palmer Playground Public Restroom Building Reconstruction
Trackerid
10723
Fmsid
846 P-304MPRC
Title
Mathews-Palmer Playground Public Restroom Building Reconstruction
Summary
This project will reconstruct the public restroom building at Mathews-Palmer Playground.
Currentphase
design
Designpercentcomplete
100.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Designstart
2025-05-01T00:00:00.000
Designprojectedcompletion
2026-05-01T00:00:00.000
Designadjustedcompletion
2026-09-01T00:00:00.000
Designactualcompletion
2026-09-01T00:00:00.000
Totalfunding
Between $1 million and $3 million
Projectliaison
Steve Simon
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City CouncilMayoral
Name
437 West 45th Street
Parkid
M154
Latitude
40.76119691
Longitude
-73.99289132
Borough
Manhattan
VIEW LOCATION
5996
Trackerid: 5996 • Fmsid: 846 P-304MPPR • Title: Mathews-Palmer Playground Reconstruction
Trackerid
5996
Fmsid
846 P-304MPPR
Title
Mathews-Palmer Playground Reconstruction
Summary
This project will reconstruct Mathews-Palmer Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2013-03-01T00:00:00.000
Designprojectedcompletion
2014-09-01T00:00:00.000
Designadjustedcompletion
2015-11-01T00:00:00.000
Designactualcompletion
2016-07-01T00:00:00.000
Procurementstart
2016-07-01T00:00:00.000
Procurementprojectedcompletion
2017-04-01T00:00:00.000
Procurementactualcompletion
2017-02-01T00:00:00.000
Constructionstart
2017-04-01T00:00:00.000
Constructionprojectedcom
2018-04-01T00:00:00.000
Constructionactualcompletion
2018-04-01T00:00:00.000
Totalfunding
$2,385,000
Projectliaison
Steve Simon
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
West 45th Street between 9th and 10th Avenues, Manhattan
Parkid
M154
Latitude
40.76139583
Longitude
-73.99273556
Borough
Manhattan
VIEW LOCATION
1740111
Trackerid: 1740111 • Fmsid: 846 P-307SAPO • Title: Matthew P. Sapolin Playground Sewer Service Reconstruction
Trackerid
1740111
Fmsid
846 P-307SAPO
Title
Matthew P. Sapolin Playground Sewer Service Reconstruction
Summary
This project will reconstruct the Sewer Service at Matthew P. Sapolin Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2024-04-01T00:00:00.000
Designprojectedcompletion
2024-08-01T00:00:00.000
Designactualcompletion
2024-08-01T00:00:00.000
Procurementstart
2024-06-01T00:00:00.000
Procurementprojectedcompletion
2024-11-01T00:00:00.000
Procurementactualcompletion
2024-08-01T00:00:00.000
Constructionstart
2024-08-01T00:00:00.000
Constructionprojectedcom
2024-11-01T00:00:00.000
Constructionactualcompletion
2024-08-01T00:00:00.000
Totalfunding
$200,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Parkid
M233
Latitude
40.77746
Longitude
-73.984045
Borough
Manhattan
VIEW LOCATION
10688
Trackerid: 10688 • Title: Matthew P. Sapolin Playground Reconstruction • Summary: This project will reconstruct Matthew P. Sapolin Playground.
Trackerid
10688
Title
Matthew P. Sapolin Playground Reconstruction
Summary
This project will reconstruct Matthew P. Sapolin Playground.
Currentphase
proposed
Designpercentcomplete
0.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Totalfunding
Between $3 million and $5 million
Projectliaison
Steve Simon
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
West 70 Street between West End & Amsterdam Avenues
Parkid
M233
Latitude
40.77734544
Longitude
-73.98384067
Borough
Manhattan
VIEW LOCATION
8959
Trackerid: 8959 • Fmsid: 846 P-307SAPO • Title: Matthew P. Sapolin Playground Multipurpose Play Area Reconstruction
Trackerid
8959
Fmsid
846 P-307SAPO
Title
Matthew P. Sapolin Playground Multipurpose Play Area Reconstruction
Summary
The project will reconstruct the multipurpose field at Matthew P. Sapolin Playground.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2020-01-01T00:00:00.000
Designprojectedcompletion
2021-01-01T00:00:00.000
Designactualcompletion
2021-01-01T00:00:00.000
Procurementstart
2021-01-01T00:00:00.000
Procurementprojectedcompletion
2021-10-01T00:00:00.000
Procurementadjustedcompletion
2022-12-01T00:00:00.000
Procurementactualcompletion
2022-12-01T00:00:00.000
Constructionstart
2023-06-01T00:00:00.000
Constructionprojectedcom
2024-06-01T00:00:00.000
Constructionactualcompletion
2024-06-01T00:00:00.000
Totalfunding
$1,437,000
Projectliaison
Steve Simon
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough President, City Council
Name
West 70th Street between Amsterdam and West End Avenues.
Parkid
M233
Latitude
40.777573
Longitude
-73.984031
Borough
Manhattan
VIEW LOCATION
11351
Trackerid: 11351 • Title: Matthews Muliner Playground Reconstruction • Summary: This project will reconstruct Matthews Muliner Playground.
Trackerid
11351
Title
Matthews Muliner Playground Reconstruction
Summary
This project will reconstruct Matthews Muliner Playground.
Currentphase
proposed
Designpercentcomplete
0.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Totalfunding
Between $3 million and $5 million
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
State
Name
Matthews Avenue and Muliner Avenue between Morris Park Avenue and Rhinelander Avenue
Parkid
X178
Latitude
40.8469961
Longitude
-73.8612718
Borough
Bronx
VIEW LOCATION
1379111
Trackerid: 1379111 • Fmsid: 846 P-6SUSTN1 • Title: Maurice A. Fitzgerald Playground Ballfield Lighting Reconstruction
Trackerid
1379111
Fmsid
846 P-6SUSTN1
Title
Maurice A. Fitzgerald Playground Ballfield Lighting Reconstruction
Summary
This project will reconstruct the ballfield lighting at Maurice A. Fitzgerald Playground with energy-efficient LED fixtures.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2021-10-01T00:00:00.000
Designprojectedcompletion
2022-06-01T00:00:00.000
Designactualcompletion
2022-12-01T00:00:00.000
Procurementstart
2021-12-01T00:00:00.000
Procurementprojectedcompletion
2022-05-01T00:00:00.000
Procurementactualcompletion
2022-10-01T00:00:00.000
Constructionstart
2023-10-01T00:00:00.000
Constructionprojectedcom
2023-12-01T00:00:00.000
Constructionactualcompletion
2023-12-01T00:00:00.000
Totalfunding
$250,000
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Mayoral
Parkid
Q337
Latitude
40.690339
Longitude
-73.839779
Borough
Queens
VIEW LOCATION
11138
Trackerid: 11138 • Title: Maurice A. Fitzgerald Playground Basketball Half-Court Reconstruction • Currentphase: proposed
Trackerid
11138
Title
Maurice A. Fitzgerald Playground Basketball Half-Court Reconstruction
Summary
This project will reconstruct a half court basketball court in Maurice A. Fitzgerald Playground.
Currentphase
proposed
Designpercentcomplete
0.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Totalfunding
Less than $1 million
Projectliaison
Cristin Leoutsakos
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
City Council
Name
106 St. bet. Atlantic Ave. and 94 Ave.
Parkid
Q337
Latitude
40.69038068
Longitude
-73.83950002
Borough
Queens
VIEW LOCATION
9961
Trackerid: 9961 • Fmsid: 846 P-4FITZPG • Title: Maurice A. FitzGerald Playground Reconstruction
Trackerid
9961
Fmsid
846 P-4FITZPG
Title
Maurice A. FitzGerald Playground Reconstruction
Summary
This project will reconstruct Maurice A. FitzGerald Playground.
Currentphase
design
Designpercentcomplete
100.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Designstart
2024-02-01T00:00:00.000
Designprojectedcompletion
2025-05-01T00:00:00.000
Designactualcompletion
2025-05-01T00:00:00.000
Totalfunding
Between $5 million and $10 million
Projectliaison
Meira Berkower
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough President, City Council
Name
106th Street between Atlantic and 94th Avenues
Parkid
Q337
Latitude
40.69037963
Longitude
-73.83965159
Borough
Queens
VIEW LOCATION