Title
McKinley Playground Play Area Reconstruction
Summary
This project will reconstruct the playground and spray shower, including fencing, paving, curbs, safety surfacing, benches, lighting, play equipment, plantings, and trees at McKinley Playground.
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2017-06-01T00:00:00.000
Designprojectedcompletion
2018-06-01T00:00:00.000
Designadjustedcompletion
2018-11-01T00:00:00.000
Designactualcompletion
2018-11-01T00:00:00.000
Procurementstart
2018-11-01T00:00:00.000
Procurementprojectedcompletion
2019-08-01T00:00:00.000
Procurementadjustedcompletion
2020-02-01T00:00:00.000
Procurementactualcompletion
2020-01-01T00:00:00.000
Constructionstart
2020-09-01T00:00:00.000
Constructionprojectedcom
2021-09-01T00:00:00.000
Constructionactualcompletion
2021-09-01T00:00:00.000
Projectliaison
Steve Simon
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough President, City Council, Private
Name
East 3rd Street, East 4th Street, Avenue A, 1st Avenue