Title
Gateway Estates Phase II Park Construction
Summary
This project will construct a new park, including a multi-purpose synthetic turf field, skate park, basketball courts, adult fitness equipment, and seating areas at Gateway Estates.
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2018-06-01T00:00:00.000
Designprojectedcompletion
2020-05-01T00:00:00.000
Designadjustedcompletion
2020-12-01T00:00:00.000
Designactualcompletion
2020-11-01T00:00:00.000
Procurementstart
2020-11-01T00:00:00.000
Procurementprojectedcompletion
2021-08-01T00:00:00.000
Procurementadjustedcompletion
2022-08-01T00:00:00.000
Procurementactualcompletion
2022-06-01T00:00:00.000
Constructionstart
2022-10-01T00:00:00.000
Constructionprojectedcom
2023-12-01T00:00:00.000
Constructionactualcompletion
2023-09-01T00:00:00.000
Projectliaison
James Morris
Lastupdated
2026-10-02T00:00:00.000
Name
Vandalia Avenue, Schroeders Avenue, Walker Street, Ashford Street