Title
Sol Lain Playground Reconstruction
Summary
This project will reconstruct the entire playground including play equipment, spray shower, basketball court, multi-purpose play area, benches, fences, drainage, water supply, security lighting, sports lighting and landscaping.
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2014-12-01T00:00:00.000
Designprojectedcompletion
2015-12-01T00:00:00.000
Designactualcompletion
2015-12-01T00:00:00.000
Procurementstart
2015-12-01T00:00:00.000
Procurementprojectedcompletion
2016-09-01T00:00:00.000
Procurementactualcompletion
2016-07-01T00:00:00.000
Constructionstart
2016-08-01T00:00:00.000
Constructionprojectedcom
2017-10-01T00:00:00.000
Constructionactualcompletion
2017-09-01T00:00:00.000
Projectliaison
Steve Simon
Lastupdated
2026-10-02T00:00:00.000
Name
Adjacent to P.S. 134 between Henry Street and East Broadway