Title
Tompkins Square Playground Reconstruction
Summary
This project will reconstruct two playgrounds in Tompkins Square Park with new play equipment, safety surfacing, spray showers, seating, and fencing.
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2015-11-01T00:00:00.000
Designprojectedcompletion
2016-12-01T00:00:00.000
Designadjustedcompletion
2017-05-01T00:00:00.000
Designactualcompletion
2017-06-01T00:00:00.000
Procurementstart
2017-06-01T00:00:00.000
Procurementprojectedcompletion
2018-02-01T00:00:00.000
Procurementadjustedcompletion
2018-07-01T00:00:00.000
Procurementactualcompletion
2018-07-01T00:00:00.000
Constructionstart
2018-09-01T00:00:00.000
Constructionprojectedcom
2019-09-01T00:00:00.000
Constructionactualcompletion
2019-09-01T00:00:00.000
Projectliaison
Steve Simon
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Borough PresidentCity CouncilMayoral
Name
East 7th Street and Avenue B