Title
Coney Island Greenstreets and Green Infrastructure Construction
Summary
This project will construct green infrastructure to capture storm water at Greenstreets at various locations near Coney Island Beach and Boardwalk.
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2015-02-01T00:00:00.000
Designprojectedcompletion
2016-02-01T00:00:00.000
Designadjustedcompletion
2017-09-01T00:00:00.000
Designactualcompletion
2017-12-01T00:00:00.000
Procurementstart
2017-12-01T00:00:00.000
Procurementprojectedcompletion
2018-08-01T00:00:00.000
Procurementadjustedcompletion
2019-11-01T00:00:00.000
Procurementactualcompletion
2019-08-01T00:00:00.000
Constructionstart
2019-09-01T00:00:00.000
Constructionprojectedcom
2020-09-01T00:00:00.000
Constructionadjustedcompletion
2020-11-01T00:00:00.000
Constructionactualcompletion
2020-11-01T00:00:00.000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
FederalMayoral
Name
Between Brighton 1st Street, Neptune Avenue, West End Avenue, and the Coney Island Boardwalk