Capital Project Tracker

A listing of all capital projects managed by NYC Parks, and a timeline for their completion.

Supporting documentation can be found at the following link (http://www.nycgovparks.org/bigapps/desc/DPR_CapitalProjectTracker_001.txt).

See JSON and XML feeds here https://data.cityofnewyork.us/Recreation/Capital-Project-Tracker/qiwj-i2jk

Recreation Department of Parks and Recreation (DPR) Dataset 4hcv-tc5r 29 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
10195
Trackerid: 10195 • Fmsid: 846 P-1TREP22 • Title: Bronx Park Tree Planting FY22
Trackerid
10195
Fmsid
846 P-1TREP22
Title
Bronx Park Tree Planting FY22
Summary
This project will plant new and replacement park trees in the Bronx.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2021-09-01T00:00:00.000
Designprojectedcompletion
2022-01-01T00:00:00.000
Designadjustedcompletion
2023-05-01T00:00:00.000
Designactualcompletion
2023-03-01T00:00:00.000
Procurementstart
2023-03-01T00:00:00.000
Procurementprojectedcompletion
2022-10-01T00:00:00.000
Procurementadjustedcompletion
2024-03-01T00:00:00.000
Procurementactualcompletion
2024-03-01T00:00:00.000
Constructionstart
2024-03-01T00:00:00.000
Constructionprojectedcom
2025-09-01T00:00:00.000
Constructionactualcompletion
2025-09-01T00:00:00.000
Totalfunding
$4,882,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
City CouncilMayoralPrivate
Name
Various locations in The Bronx
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Bronx
VIEW LOCATION
6142
Trackerid: 6142 • Fmsid: 846 P-1PNYT18 • Title: Bronx Street Tree Planting FY14 - Community Boards 7-12
Trackerid
6142
Fmsid
846 P-1PNYT18
Title
Bronx Street Tree Planting FY14 - Community Boards 7-12
Summary
This project will plant new street trees in Community Boards 7-12 in the Bronx.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2013-04-01T00:00:00.000
Designprojectedcompletion
2013-05-01T00:00:00.000
Designactualcompletion
2013-06-01T00:00:00.000
Procurementstart
2013-06-01T00:00:00.000
Procurementprojectedcompletion
2014-03-01T00:00:00.000
Procurementactualcompletion
2014-01-01T00:00:00.000
Constructionstart
2014-02-01T00:00:00.000
Constructionprojectedcom
2015-02-01T00:00:00.000
Constructionadjustedcompletion
2015-05-01T00:00:00.000
Constructionactualcompletion
2015-01-01T00:00:00.000
Totalfunding
$871,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Mayoral
Name
Various locations in the Bronx
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Bronx
VIEW LOCATION
1054
Trackerid: 1054 • Fmsid: 846 P-1PNYT16 • Title: Bronx Street Tree Planting FY13 - Community Boards 9-12 (XG-412M)
Trackerid
1054
Fmsid
846 P-1PNYT16
Title
Bronx Street Tree Planting FY13 - Community Boards 9-12 (XG-412M)
Summary
This project will plant new trees in Community Boards 9-12 in the Bronx.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2012-03-01T00:00:00.000
Designprojectedcompletion
2012-03-01T00:00:00.000
Designactualcompletion
2012-04-01T00:00:00.000
Procurementstart
2012-04-01T00:00:00.000
Procurementprojectedcompletion
2012-12-01T00:00:00.000
Procurementactualcompletion
2012-11-01T00:00:00.000
Constructionstart
2013-02-01T00:00:00.000
Constructionprojectedcom
2013-08-01T00:00:00.000
Constructionadjustedcompletion
2013-08-01T00:00:00.000
Constructionactualcompletion
2013-08-01T00:00:00.000
Totalfunding
$984,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Mayoral
Name
Various locations in the Bronx
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Bronx
VIEW LOCATION
8750
Trackerid: 8750 • Fmsid: 846 P-1TRE18A • Title: Bronx Street Tree Planting FY18 - Community Boards 1-8
Trackerid
8750
Fmsid
846 P-1TRE18A
Title
Bronx Street Tree Planting FY18 - Community Boards 1-8
Summary
This project will plant new trees in Community Boards 1-8 in the Bronx.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2017-06-01T00:00:00.000
Designprojectedcompletion
2017-08-01T00:00:00.000
Designadjustedcompletion
2018-08-01T00:00:00.000
Designactualcompletion
2018-07-01T00:00:00.000
Procurementstart
2018-07-01T00:00:00.000
Procurementprojectedcompletion
2019-04-01T00:00:00.000
Procurementadjustedcompletion
2019-09-01T00:00:00.000
Procurementactualcompletion
2019-09-01T00:00:00.000
Constructionstart
2019-10-01T00:00:00.000
Constructionprojectedcom
2020-10-01T00:00:00.000
Constructionadjustedcompletion
2021-01-01T00:00:00.000
Constructionactualcompletion
2021-01-01T00:00:00.000
Totalfunding
$2,972,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Mayoral
Name
Various locations in the Bronx
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Bronx
VIEW LOCATION
6589
Trackerid: 6589 • Fmsid: 846 P-1TRE15A • Title: Bronx Street Tree Planting FY15 - Community Boards 1-8
Trackerid
6589
Fmsid
846 P-1TRE15A
Title
Bronx Street Tree Planting FY15 - Community Boards 1-8
Summary
This project will plant new trees in Community Boards 1-8 in the Bronx.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2014-07-01T00:00:00.000
Designprojectedcompletion
2014-08-01T00:00:00.000
Designactualcompletion
2014-08-01T00:00:00.000
Procurementstart
2014-08-01T00:00:00.000
Procurementprojectedcompletion
2015-05-01T00:00:00.000
Procurementactualcompletion
2015-05-01T00:00:00.000
Constructionstart
2015-04-01T00:00:00.000
Constructionprojectedcom
2016-04-01T00:00:00.000
Constructionactualcompletion
2016-02-01T00:00:00.000
Totalfunding
$1,639,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
City CouncilMayoralPrivate
Name
Various locations in the Bronx
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Bronx
VIEW LOCATION
6604
Trackerid: 6604 • Fmsid: 846 P-1PNYT19 • Title: Bronx Street Tree Planting FY15 - Community Boards 9-12
Trackerid
6604
Fmsid
846 P-1PNYT19
Title
Bronx Street Tree Planting FY15 - Community Boards 9-12
Summary
This project will plant new trees in Community Boards 9-12 in the Bronx.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2014-07-01T00:00:00.000
Designprojectedcompletion
2014-08-01T00:00:00.000
Designactualcompletion
2014-08-01T00:00:00.000
Procurementstart
2014-08-01T00:00:00.000
Procurementprojectedcompletion
2015-05-01T00:00:00.000
Procurementactualcompletion
2015-05-01T00:00:00.000
Constructionstart
2015-04-01T00:00:00.000
Constructionprojectedcom
2016-04-01T00:00:00.000
Constructionactualcompletion
2016-04-01T00:00:00.000
Totalfunding
$1,658,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Mayoral
Name
Various locations in the Bronx
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Bronx
VIEW LOCATION
8529
Trackerid: 8529 • Fmsid: 846 P-1TRE17A • Title: Bronx Street Tree Planting FY17 - Community Boards 1-8
Trackerid
8529
Fmsid
846 P-1TRE17A
Title
Bronx Street Tree Planting FY17 - Community Boards 1-8
Summary
This project will plant new trees in Community Boards 1-8 in the Bronx.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2016-06-01T00:00:00.000
Designprojectedcompletion
2016-06-01T00:00:00.000
Designactualcompletion
2016-07-01T00:00:00.000
Procurementstart
2016-07-01T00:00:00.000
Procurementprojectedcompletion
2017-04-01T00:00:00.000
Procurementactualcompletion
2017-03-01T00:00:00.000
Constructionstart
2017-04-01T00:00:00.000
Constructionprojectedcom
2018-10-01T00:00:00.000
Constructionadjustedcompletion
2018-10-01T00:00:00.000
Constructionactualcompletion
2018-06-01T00:00:00.000
Totalfunding
$2,164,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
City CouncilMayoralPrivate
Name
Various locations in the Bronx
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Bronx
VIEW LOCATION
8530
Trackerid: 8530 • Fmsid: 846 P-1PNYT21 • Title: Bronx Street Tree Planting FY17 - Community Boards 9-12
Trackerid
8530
Fmsid
846 P-1PNYT21
Title
Bronx Street Tree Planting FY17 - Community Boards 9-12
Summary
This project will plant new trees in Community Boards 9-12 in the Bronx.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2016-06-01T00:00:00.000
Designprojectedcompletion
2016-06-01T00:00:00.000
Designactualcompletion
2016-07-01T00:00:00.000
Procurementstart
2016-07-01T00:00:00.000
Procurementprojectedcompletion
2017-04-01T00:00:00.000
Procurementactualcompletion
2017-04-01T00:00:00.000
Constructionstart
2017-04-01T00:00:00.000
Constructionprojectedcom
2018-10-01T00:00:00.000
Constructionadjustedcompletion
2018-10-01T00:00:00.000
Constructionactualcompletion
2018-06-01T00:00:00.000
Totalfunding
$2,036,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Mayoral
Name
Various locations in the Bronx
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Bronx
VIEW LOCATION
7172
Trackerid: 7172 • Fmsid: 846 P-1TRE16A • Title: Bronx Street Tree Planting FY16 - Community Boards 1-8
Trackerid
7172
Fmsid
846 P-1TRE16A
Title
Bronx Street Tree Planting FY16 - Community Boards 1-8
Summary
This project will plant new trees in Community Boards 1-8 in the Bronx.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2015-03-01T00:00:00.000
Designprojectedcompletion
2015-05-01T00:00:00.000
Designactualcompletion
2015-05-01T00:00:00.000
Procurementstart
2015-05-01T00:00:00.000
Procurementprojectedcompletion
2016-02-01T00:00:00.000
Procurementactualcompletion
2015-12-01T00:00:00.000
Constructionstart
2016-03-01T00:00:00.000
Constructionprojectedcom
2017-09-01T00:00:00.000
Constructionactualcompletion
2017-08-01T00:00:00.000
Totalfunding
$1,299,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Mayoral, Private
Name
Various locations in the Bronx
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Bronx
VIEW LOCATION
7180
Trackerid: 7180 • Fmsid: 846 P-1PNYT20 • Title: Bronx Street Tree Planting FY16 - Community Boards 9-12
Trackerid
7180
Fmsid
846 P-1PNYT20
Title
Bronx Street Tree Planting FY16 - Community Boards 9-12
Summary
This project will plant new trees in Community Boards 9-12 in the Bronx.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2015-03-01T00:00:00.000
Designprojectedcompletion
2015-05-01T00:00:00.000
Designactualcompletion
2015-05-01T00:00:00.000
Procurementstart
2015-05-01T00:00:00.000
Procurementprojectedcompletion
2016-02-01T00:00:00.000
Procurementactualcompletion
2015-12-01T00:00:00.000
Constructionstart
2016-03-01T00:00:00.000
Constructionprojectedcom
2017-09-01T00:00:00.000
Constructionactualcompletion
2017-08-01T00:00:00.000
Totalfunding
$1,447,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Mayoral
Name
Various locations in the Bronx
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Bronx
VIEW LOCATION
9150
Trackerid: 9150 • Fmsid: 846 P-6TRSD19 • Title: Bronx and Manhattan Tree-Damaged Sidewalk Reconstruction FY19
Trackerid
9150
Fmsid
846 P-6TRSD19
Title
Bronx and Manhattan Tree-Damaged Sidewalk Reconstruction FY19
Summary
This project will reconstruct sidewalks damaged by adjacent city-owned trees in the Bronx and Manhattan.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2018-03-01T00:00:00.000
Designprojectedcompletion
2018-05-01T00:00:00.000
Designactualcompletion
2018-04-01T00:00:00.000
Procurementstart
2018-04-01T00:00:00.000
Procurementprojectedcompletion
2019-01-01T00:00:00.000
Procurementadjustedcompletion
2019-09-01T00:00:00.000
Procurementactualcompletion
2019-08-01T00:00:00.000
Constructionstart
2019-08-01T00:00:00.000
Constructionprojectedcom
2021-08-01T00:00:00.000
Constructionadjustedcompletion
2021-08-01T00:00:00.000
Constructionactualcompletion
2021-02-01T00:00:00.000
Totalfunding
$2,160,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Mayoral
Name
Various locations in the Bronx and Manhattan
Parkid
NA
Latitude
0.0
Longitude
0.0
VIEW LOCATION
9418
Trackerid: 9418 • Fmsid: 846 P-6EABTRA • Title: Bronx and Manhattan Emerald Ash Borer (EAB) Related Tree Removal
Trackerid
9418
Fmsid
846 P-6EABTRA
Title
Bronx and Manhattan Emerald Ash Borer (EAB) Related Tree Removal
Summary
This project will remove trees with emerald ash borer (EAB) in the Bronx and Manhattan.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2019-02-01T00:00:00.000
Designprojectedcompletion
2019-04-01T00:00:00.000
Designactualcompletion
2019-04-01T00:00:00.000
Procurementstart
2019-04-01T00:00:00.000
Procurementprojectedcompletion
2019-12-01T00:00:00.000
Procurementadjustedcompletion
2020-12-01T00:00:00.000
Procurementactualcompletion
2020-12-01T00:00:00.000
Constructionstart
2021-04-01T00:00:00.000
Constructionprojectedcom
2023-03-01T00:00:00.000
Constructionadjustedcompletion
2023-03-01T00:00:00.000
Constructionactualcompletion
2023-03-01T00:00:00.000
Totalfunding
$317,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Mayoral
Name
Various locations in the Bronx and Manhattan
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Citywide
VIEW LOCATION
10925
Trackerid: 10925 • Title: Bronx and Manhattan Retaining Wall Reconstruction and Rock Face Stabilization • Currentphase: proposed
Trackerid
10925
Title
Bronx and Manhattan Retaining Wall Reconstruction and Rock Face Stabilization
Summary
This project will reconstruct retaining walls and stabilize rock faces at various locations in Bronx and Manhattan.
Currentphase
proposed
Designpercentcomplete
0.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Totalfunding
Greater than $10 million
Projectliaison
Contact Us
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Mayoral
Name
Various locations in The Bronx and Manhattan
Parkid
NA
Latitude
40.845801
Longitude
-73.9319792
Borough
Citywide
VIEW LOCATION
7227
Trackerid: 7227 • Fmsid: 846 P-6PNYR31 • Title: Bronx and Queens Reforestation FY16
Trackerid
7227
Fmsid
846 P-6PNYR31
Title
Bronx and Queens Reforestation FY16
Summary
This project will remove invasive trees, shrubs, plants and vines; excavate and clear sites; remove tree stumps; prepare tree pits; furnish, plant, maintain and replace trees; install native seed mixes; and install osprey nests in the Bronx and Queens.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2015-07-01T00:00:00.000
Designprojectedcompletion
2015-09-01T00:00:00.000
Designadjustedcompletion
2015-11-01T00:00:00.000
Designactualcompletion
2015-11-01T00:00:00.000
Procurementstart
2015-11-01T00:00:00.000
Procurementprojectedcompletion
2016-08-01T00:00:00.000
Procurementactualcompletion
2016-07-01T00:00:00.000
Constructionstart
2016-07-01T00:00:00.000
Constructionprojectedcom
2019-01-01T00:00:00.000
Constructionadjustedcompletion
2019-01-01T00:00:00.000
Constructionactualcompletion
2019-01-01T00:00:00.000
Totalfunding
$1,100,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
City CouncilMayoral
Name
Various locations in the Bronx and Queens
Parkid
NA
Latitude
0.0
Longitude
0.0
VIEW LOCATION
9468
Trackerid: 9468 • Fmsid: 846 P-6NRGF01 • Title: Bronx and Queens Reforestation FY20
Trackerid
9468
Fmsid
846 P-6NRGF01
Title
Bronx and Queens Reforestation FY20
Summary
This project will remove invasive species and plant new and replacement trees in the Bronx and Queens.
Currentphase
construction
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
50.73
Designstart
2019-05-01T00:00:00.000
Designprojectedcompletion
2019-08-01T00:00:00.000
Designadjustedcompletion
2023-04-01T00:00:00.000
Designactualcompletion
2023-04-01T00:00:00.000
Procurementstart
2023-04-01T00:00:00.000
Procurementprojectedcompletion
2021-06-01T00:00:00.000
Procurementadjustedcompletion
2024-05-01T00:00:00.000
Procurementactualcompletion
2024-06-01T00:00:00.000
Constructionstart
2024-09-01T00:00:00.000
Constructionprojectedcom
2027-09-01T00:00:00.000
Totalfunding
$1,170,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
City CouncilMayoral
Name
Various locations in the Bronx and Queens
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Citywide
VIEW LOCATION
9358
Trackerid: 9358 • Fmsid: 846 P-6REF20B • Title: Queens Community Boards 8-14 and Bronx Reforestation FY20
Trackerid
9358
Fmsid
846 P-6REF20B
Title
Queens Community Boards 8-14 and Bronx Reforestation FY20
Summary
This project will remove invasive species and plant new and replacement trees in the Bronx, and in Queens Community Boards 8-14.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2018-10-01T00:00:00.000
Designprojectedcompletion
2019-02-01T00:00:00.000
Designactualcompletion
2019-03-01T00:00:00.000
Procurementstart
2019-03-01T00:00:00.000
Procurementprojectedcompletion
2019-12-01T00:00:00.000
Procurementadjustedcompletion
2021-06-01T00:00:00.000
Procurementactualcompletion
2021-04-01T00:00:00.000
Constructionstart
2021-06-01T00:00:00.000
Constructionprojectedcom
2023-12-01T00:00:00.000
Constructionadjustedcompletion
2023-12-01T00:00:00.000
Constructionactualcompletion
2023-11-01T00:00:00.000
Totalfunding
$1,133,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Mayoral
Name
Various locations in the Bronx and Queens
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Citywide
VIEW LOCATION
5962
Trackerid: 5962 • Fmsid: 846 P-6PNYR17 • Title: Bronx and Queens Reforestation FY10
Trackerid
5962
Fmsid
846 P-6PNYR17
Title
Bronx and Queens Reforestation FY10
Summary
This multisite contract will plant new and replacement trees in the Bronx and Queens.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2012-07-01T00:00:00.000
Designprojectedcompletion
2013-01-01T00:00:00.000
Designactualcompletion
2012-12-01T00:00:00.000
Procurementstart
2012-12-01T00:00:00.000
Procurementprojectedcompletion
2013-09-01T00:00:00.000
Procurementactualcompletion
2013-02-01T00:00:00.000
Constructionstart
2013-03-01T00:00:00.000
Constructionprojectedcom
2015-06-01T00:00:00.000
Constructionactualcompletion
2015-05-01T00:00:00.000
Totalfunding
$733,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Mayoral
Name
Various locations in the Bronx and Queens.
Parkid
NA
Latitude
0.0
Longitude
0.0
VIEW LOCATION
9244
Trackerid: 9244 • Fmsid: 846 P-6REMT37 • Title: Bronx, Manhattan and Queens Sandy-Related and Risk Management Tree Removal FY19
Trackerid
9244
Fmsid
846 P-6REMT37
Title
Bronx, Manhattan and Queens Sandy-Related and Risk Management Tree Removal FY19
Summary
This project will remove trees damaged by Hurricane Sandy in the Bronx, Manhattan and Queens.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2018-08-01T00:00:00.000
Designprojectedcompletion
2018-11-01T00:00:00.000
Designactualcompletion
2018-09-01T00:00:00.000
Procurementstart
2018-09-01T00:00:00.000
Procurementprojectedcompletion
2019-06-01T00:00:00.000
Procurementactualcompletion
2019-03-01T00:00:00.000
Constructionstart
2018-09-01T00:00:00.000
Constructionprojectedcom
2019-09-01T00:00:00.000
Constructionactualcompletion
2019-09-01T00:00:00.000
Totalfunding
$277,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Mayoral
Name
Various locations in the Bronx, Manhattan and Queens
Parkid
NA
Latitude
0.0
Longitude
0.0
VIEW LOCATION
8776
Trackerid: 8776 • Fmsid: 846 P-6TRBXMQ • Title: Bronx, Manhattan and Queens Park Trees Planting and Replacement
Trackerid
8776
Fmsid
846 P-6TRBXMQ
Title
Bronx, Manhattan and Queens Park Trees Planting and Replacement
Summary
This project will plant new park trees in the Bronx, Manhattan and Queens.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2017-06-01T00:00:00.000
Designprojectedcompletion
2017-12-01T00:00:00.000
Designadjustedcompletion
2018-07-01T00:00:00.000
Designactualcompletion
2018-08-01T00:00:00.000
Procurementstart
2018-08-01T00:00:00.000
Procurementprojectedcompletion
2019-05-01T00:00:00.000
Procurementadjustedcompletion
2019-10-01T00:00:00.000
Procurementactualcompletion
2019-09-01T00:00:00.000
Constructionstart
2019-10-01T00:00:00.000
Constructionprojectedcom
2021-04-01T00:00:00.000
Constructionadjustedcompletion
2021-04-01T00:00:00.000
Constructionactualcompletion
2021-04-01T00:00:00.000
Totalfunding
$2,979,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Mayoral
Name
Various locations in the Bronx, Manhattan and Queens
Parkid
NA
Latitude
0.0
Longitude
0.0
VIEW LOCATION
8806
Trackerid: 8806 • Fmsid: 846 P-6PNYR37 • Title: Bronx, Manhattan and Queens Reforestation FY18
Trackerid
8806
Fmsid
846 P-6PNYR37
Title
Bronx, Manhattan and Queens Reforestation FY18
Summary
This project will remove invasive species and plant new and replacement trees in the Bronx, Manhattan and Queens.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2017-08-01T00:00:00.000
Designprojectedcompletion
2017-12-01T00:00:00.000
Designactualcompletion
2018-01-01T00:00:00.000
Procurementstart
2018-01-01T00:00:00.000
Procurementprojectedcompletion
2018-10-01T00:00:00.000
Procurementactualcompletion
2018-10-01T00:00:00.000
Constructionstart
2018-11-01T00:00:00.000
Constructionprojectedcom
2021-05-01T00:00:00.000
Constructionactualcompletion
2021-05-01T00:00:00.000
Totalfunding
$1,051,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Mayoral
Name
Various locations in the Bronx, Manhattan and Queens
Parkid
NA
Latitude
0.0
Longitude
0.0
VIEW LOCATION
8517
Trackerid: 8517 • Fmsid: 846 SANDY6-18 • Title: Bronx, Manhattan and Queens Sandy-Related Risk Management and Tree Removal
Trackerid
8517
Fmsid
846 SANDY6-18
Title
Bronx, Manhattan and Queens Sandy-Related Risk Management and Tree Removal
Summary
This project will remove Hurricane Sandy-damaged trees in the Bronx, Manhattan and Queens.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2016-05-01T00:00:00.000
Designprojectedcompletion
2016-06-01T00:00:00.000
Designactualcompletion
2016-11-01T00:00:00.000
Procurementstart
2016-11-01T00:00:00.000
Procurementprojectedcompletion
2017-07-01T00:00:00.000
Procurementactualcompletion
2017-06-01T00:00:00.000
Constructionstart
2017-09-01T00:00:00.000
Constructionprojectedcom
2018-09-01T00:00:00.000
Constructionadjustedcompletion
2018-12-01T00:00:00.000
Constructionactualcompletion
2018-09-01T00:00:00.000
Totalfunding
$594,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
FederalMayoral
Name
Various locations in the Bronx, Manhattan and Queens
Parkid
NA
Latitude
0.0
Longitude
0.0
VIEW LOCATION
8685
Trackerid: 8685 • Fmsid: 846 P-6SANDT1 • Currentphase: completed
Trackerid
8685
Fmsid
846 P-6SANDT1
Title
Bronx, Manhattan and Queens Sandy-Related Park Tree Planting and Replacement FY18
Summary
This project will plant new trees in parks affected by Hurricane Sandy in the Bronx, Manhattan and Queens.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2017-03-01T00:00:00.000
Designprojectedcompletion
2017-06-01T00:00:00.000
Designadjustedcompletion
2018-07-01T00:00:00.000
Designactualcompletion
2018-08-01T00:00:00.000
Procurementstart
2018-08-01T00:00:00.000
Procurementprojectedcompletion
2019-05-01T00:00:00.000
Procurementadjustedcompletion
2019-10-01T00:00:00.000
Procurementactualcompletion
2019-09-01T00:00:00.000
Constructionstart
2019-10-01T00:00:00.000
Constructionprojectedcom
2021-04-01T00:00:00.000
Constructionadjustedcompletion
2021-04-01T00:00:00.000
Constructionactualcompletion
2021-04-01T00:00:00.000
Totalfunding
$2,275,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Mayoral
Name
Various locations in the Bronx, Manhattan and Queens.
Parkid
NA
Latitude
0.0
Longitude
0.0
VIEW LOCATION
9157
Trackerid: 9157 • Fmsid: 846 P-1TRE19A • Title: Bronx Street Tree Planting FY19 - Community Boards 1-8
Trackerid
9157
Fmsid
846 P-1TRE19A
Title
Bronx Street Tree Planting FY19 - Community Boards 1-8
Summary
This project will plant street trees in Community Boards 1-8 in the Bronx.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2018-04-01T00:00:00.000
Designprojectedcompletion
2018-08-01T00:00:00.000
Designactualcompletion
2018-05-01T00:00:00.000
Procurementstart
2018-05-01T00:00:00.000
Procurementprojectedcompletion
2019-02-01T00:00:00.000
Procurementactualcompletion
2019-01-01T00:00:00.000
Constructionstart
2018-10-01T00:00:00.000
Constructionprojectedcom
2019-05-01T00:00:00.000
Constructionactualcompletion
2019-01-01T00:00:00.000
Totalfunding
$868,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Mayoral
Name
Various locations in the Bronx.
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Bronx
VIEW LOCATION
5943
Trackerid: 5943 • Fmsid: 846 P-1TREE06 • Title: Bronx Street Tree Planting FY13 - Community Boards 9-12 (XG-213M)
Trackerid
5943
Fmsid
846 P-1TREE06
Title
Bronx Street Tree Planting FY13 - Community Boards 9-12 (XG-213M)
Summary
This project will plant trees in Community Boards 9-12 in the Bronx.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2012-07-01T00:00:00.000
Designprojectedcompletion
2012-12-01T00:00:00.000
Designactualcompletion
2012-07-01T00:00:00.000
Procurementstart
2012-07-01T00:00:00.000
Procurementprojectedcompletion
2013-04-01T00:00:00.000
Procurementactualcompletion
2013-01-01T00:00:00.000
Constructionstart
2013-02-01T00:00:00.000
Constructionprojectedcom
2014-02-01T00:00:00.000
Constructionadjustedcompletion
2014-02-01T00:00:00.000
Constructionactualcompletion
2014-02-01T00:00:00.000
Totalfunding
$1,566,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Mayoral, Private
Name
Various Locations, Bronx
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Bronx
VIEW LOCATION
11148
Trackerid: 11148 • Title: Bronx Street Tree Planting FY27, CBs 1-7 • Summary: This project will plant and replace street trees in The Bronx.
Trackerid
11148
Title
Bronx Street Tree Planting FY27, CBs 1-7
Summary
This project will plant and replace street trees in The Bronx.
Currentphase
proposed
Designpercentcomplete
0.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Totalfunding
Less than $1 million
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
City Council
Name
Various Locations, Bronx
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Bronx
VIEW LOCATION
11220
Trackerid: 11220 • Fmsid: 846 P-1TRS27A • Title: Bronx Street Tree Planting FY27, CBs 8, 11, 12
Trackerid
11220
Fmsid
846 P-1TRS27A
Title
Bronx Street Tree Planting FY27, CBs 8, 11, 12
Summary
This project will plant and replace street trees in The Bronx.
Currentphase
procurement
Designpercentcomplete
100.0
Procurementpercentcomplete
5.0
Constructionpercentcomplete
0.0
Designstart
2026-01-01T00:00:00.000
Designprojectedcompletion
2026-11-01T00:00:00.000
Designactualcompletion
2026-02-01T00:00:00.000
Procurementstart
1776-07-01T00:00:00.000
Procurementprojectedcompletion
1777-07-01T00:00:00.000
Totalfunding
Between $3 million and $5 million
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Mayoral
Name
Various Locations, Bronx
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Bronx
VIEW LOCATION
11056
Trackerid: 11056 • Fmsid: 846 P-6SWRC23 • Currentphase: construction
Trackerid
11056
Fmsid
846 P-6SWRC23
Title
Bronx and Manhattan Tree-Damaged Sidewalk Reconstruction FY23 (Renewal CNYG-2423M)
Summary
This project will reconstruct sidewalks damaged by adjacent city-owned trees in Bronx and Manhattan.
Currentphase
construction
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
0.0
Designstart
2025-07-01T00:00:00.000
Designprojectedcompletion
2026-01-01T00:00:00.000
Designactualcompletion
2025-11-01T00:00:00.000
Procurementstart
2025-11-01T00:00:00.000
Procurementactualcompletion
2026-09-01T00:00:00.000
Constructionstart
2026-08-01T00:00:00.000
Constructionprojectedcom
2028-08-01T00:00:00.000
Totalfunding
$4,346,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Mayoral
Name
Various locations, Bronx and Manhattan
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Citywide
VIEW LOCATION
10558
Trackerid: 10558 • Fmsid: 846 P-6TRS23A • Title: Bronx and Manhattan Tree-Damaged Sidewalk Reconstruction FY23
Trackerid
10558
Fmsid
846 P-6TRS23A
Title
Bronx and Manhattan Tree-Damaged Sidewalk Reconstruction FY23
Summary
This project will reconstruct sidewalks damaged by adjacent city-owned trees in Bronx and Manhattan.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2023-03-01T00:00:00.000
Designprojectedcompletion
2023-12-01T00:00:00.000
Designactualcompletion
2023-06-01T00:00:00.000
Procurementstart
2023-06-01T00:00:00.000
Procurementprojectedcompletion
2024-06-01T00:00:00.000
Procurementadjustedcompletion
2024-06-01T00:00:00.000
Procurementactualcompletion
2024-06-01T00:00:00.000
Constructionstart
2024-08-01T00:00:00.000
Constructionprojectedcom
2026-08-01T00:00:00.000
Constructionactualcompletion
2026-03-01T00:00:00.000
Totalfunding
$3,575,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
City CouncilMayoral
Name
Various locations, Bronx and Manhattan
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Citywide
VIEW LOCATION
10554
Trackerid: 10554 • Fmsid: 846 P-2TRS23A • Currentphase: construction
Trackerid
10554
Fmsid
846 P-2TRS23A
Title
Brooklyn Tree-Damaged Sidewalk Reconstruction FY23 Community Boards 1, 2, 6, 7, 10-14
Summary
This project will reconstruct sidewalks damaged by adjacent city-owned trees in Community Boards 1, 2, 6, 7, 10, 11, 12, 13 and 14 in Brooklyn.
Currentphase
construction
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
42.97
Designstart
2023-03-01T00:00:00.000
Designprojectedcompletion
2023-12-01T00:00:00.000
Designactualcompletion
2023-06-01T00:00:00.000
Procurementstart
2023-06-01T00:00:00.000
Procurementprojectedcompletion
2024-05-01T00:00:00.000
Procurementadjustedcompletion
2024-12-01T00:00:00.000
Procurementactualcompletion
2024-12-01T00:00:00.000
Constructionstart
2025-01-01T00:00:00.000
Constructionprojectedcom
2027-01-01T00:00:00.000
Totalfunding
$3,033,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
City CouncilMayoral
Name
Various locations, Brooklyn
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Brooklyn
VIEW LOCATION
10507
Trackerid: 10507 • Fmsid: 846 P-2TRSD23 • Currentphase: completed
Trackerid
10507
Fmsid
846 P-2TRSD23
Title
Brooklyn Tree-Damaged Sidewalk Reconstruction FY23 - Community Boards 3, 4, 5, 8, 9, 15, 16, 17, 18
Summary
This project will reconstruct sidewalks damaged by adjacent city-owned trees in Community Boards 3, 4, 5, 8, 9, 15, 16, 17 and 18 in Brooklyn.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2023-03-01T00:00:00.000
Designprojectedcompletion
2023-12-01T00:00:00.000
Designactualcompletion
2023-06-01T00:00:00.000
Procurementstart
2023-06-01T00:00:00.000
Procurementprojectedcompletion
2024-06-01T00:00:00.000
Procurementadjustedcompletion
2024-06-01T00:00:00.000
Procurementactualcompletion
2024-06-01T00:00:00.000
Constructionstart
2024-05-01T00:00:00.000
Constructionprojectedcom
2026-05-01T00:00:00.000
Constructionactualcompletion
2026-05-01T00:00:00.000
Totalfunding
$2,983,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
City CouncilMayoral
Name
Various Locations, Brooklyn
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Brooklyn
VIEW LOCATION
11054
Trackerid: 11054 • Fmsid: 846 P-2SWRC23 • Currentphase: construction
Trackerid
11054
Fmsid
846 P-2SWRC23
Title
Brooklyn Tree-Damaged Sidewalk Reconstruction FY23 (Renewal BG-923M) - Community Boards 3, 4, 5, 8, 9, 15, 16, 17, 18
Summary
This project will reconstruct sidewalks damaged by adjacent city-owned trees in Community Boards 3, 4, 5, 8, 9, 15, 16, 17 and 18 in Brooklyn.
Currentphase
construction
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
0.0
Designstart
2025-07-01T00:00:00.000
Designprojectedcompletion
2026-01-01T00:00:00.000
Designactualcompletion
2025-11-01T00:00:00.000
Procurementstart
2025-11-01T00:00:00.000
Procurementactualcompletion
2026-05-01T00:00:00.000
Constructionstart
2026-05-01T00:00:00.000
Constructionprojectedcom
2028-05-01T00:00:00.000
Totalfunding
$6,551,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Mayoral
Name
Various Locations, Brooklyn
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Brooklyn
VIEW LOCATION
11147
Trackerid: 11147 • Title: Brooklyn Street Tree Planting FY27 - Community Boards 1, 7, 14 • Summary: This project will plant street trees in Brooklyn - Community Boards 1, 7, 14
Trackerid
11147
Title
Brooklyn Street Tree Planting FY27 - Community Boards 1, 7, 14
Summary
This project will plant street trees in Brooklyn - Community Boards 1, 7, 14
Currentphase
proposed
Designpercentcomplete
0.0
Procurementpercentcomplete
0.0
Constructionpercentcomplete
0.0
Totalfunding
Less than $1 million
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
City Council
Name
Various Locations, Brooklyn
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Brooklyn
VIEW LOCATION
11149
Trackerid: 11149 • Fmsid: 846 P-2TRE27A • Title: Brooklyn Street Tree Planting FY27 - Community Boards 2-5, 8-10, 15-16
Trackerid
11149
Fmsid
846 P-2TRE27A
Title
Brooklyn Street Tree Planting FY27 - Community Boards 2-5, 8-10, 15-16
Summary
This project will plant new and replacement tree in Brooklyn, Community Boards 2-5, 8-10, 15-16.
Currentphase
procurement
Designpercentcomplete
100.0
Procurementpercentcomplete
5.0
Constructionpercentcomplete
0.0
Designstart
2026-01-01T00:00:00.000
Designprojectedcompletion
2026-11-01T00:00:00.000
Designactualcompletion
2026-02-01T00:00:00.000
Procurementstart
1776-07-01T00:00:00.000
Procurementprojectedcompletion
1777-07-01T00:00:00.000
Totalfunding
Between $5 million and $10 million
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
City CouncilMayoral
Name
Various Locations, Brooklyn
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Brooklyn
VIEW LOCATION
11221
Trackerid: 11221 • Fmsid: 846 P-2TRS27B • Title: Brooklyn Street Tree Planting FY27 - Community Boards 11, 12, 17, 18
Trackerid
11221
Fmsid
846 P-2TRS27B
Title
Brooklyn Street Tree Planting FY27 - Community Boards 11, 12, 17, 18
Summary
This project will plant new and replacement tree in Brooklyn, Community Boards 11, 12, 17, 18
Currentphase
procurement
Designpercentcomplete
100.0
Procurementpercentcomplete
5.0
Constructionpercentcomplete
0.0
Designstart
2026-01-01T00:00:00.000
Designprojectedcompletion
2026-11-01T00:00:00.000
Designactualcompletion
2026-02-01T00:00:00.000
Procurementstart
1776-07-01T00:00:00.000
Procurementprojectedcompletion
1777-07-01T00:00:00.000
Totalfunding
Between $5 million and $10 million
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Mayoral
Name
Various Locations, Brooklyn
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Brooklyn
VIEW LOCATION
11225
Trackerid: 11225 • Fmsid: 846 P-2TRS27A • Title: Brooklyn Street Tree Planting FY27 - Community Boards 6, 13
Trackerid
11225
Fmsid
846 P-2TRS27A
Title
Brooklyn Street Tree Planting FY27 - Community Boards 6, 13
Summary
This project will plant new and replacement tree in Brooklyn, Community Boards 6 & 13.
Currentphase
procurement
Designpercentcomplete
100.0
Procurementpercentcomplete
5.0
Constructionpercentcomplete
0.0
Designstart
2026-01-01T00:00:00.000
Designprojectedcompletion
2026-11-01T00:00:00.000
Designactualcompletion
2026-02-01T00:00:00.000
Procurementstart
1776-07-01T00:00:00.000
Procurementprojectedcompletion
1777-07-01T00:00:00.000
Totalfunding
Between $1 million and $3 million
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Borough PresidentMayoral
Name
Various Locations, Brooklyn
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Brooklyn
VIEW LOCATION
5945
Trackerid: 5945 • Fmsid: 846 P-2TREE23 • Title: Brooklyn Street Tree Planting FY11 - Community Boards 7,10-15,17,18 (BG-511MR)
Trackerid
5945
Fmsid
846 P-2TREE23
Title
Brooklyn Street Tree Planting FY11 - Community Boards 7,10-15,17,18 (BG-511MR)
Summary
This project will plant street trees in Community Boards 7, 10-15, 17 and 18 in Brooklyn.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2012-09-01T00:00:00.000
Designprojectedcompletion
2013-06-01T00:00:00.000
Designactualcompletion
2012-11-01T00:00:00.000
Procurementstart
2012-11-01T00:00:00.000
Procurementprojectedcompletion
2013-08-01T00:00:00.000
Procurementactualcompletion
2013-05-01T00:00:00.000
Constructionstart
2013-09-01T00:00:00.000
Constructionprojectedcom
2014-09-01T00:00:00.000
Constructionadjustedcompletion
2015-04-01T00:00:00.000
Constructionactualcompletion
2015-04-01T00:00:00.000
Totalfunding
$1,471,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Mayoral, Private
Name
Various locations, Brooklyn
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Brooklyn
VIEW LOCATION
5946
Trackerid: 5946 • Fmsid: 846 P-2PNYT22 • Title: Brooklyn Street Tree Planting FY13 - Community Boards 5,16,17,18
Trackerid
5946
Fmsid
846 P-2PNYT22
Title
Brooklyn Street Tree Planting FY13 - Community Boards 5,16,17,18
Summary
This project will plant trees in Community Boards 5 &16-18 in Brooklyn.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2012-07-01T00:00:00.000
Designprojectedcompletion
2012-12-01T00:00:00.000
Designactualcompletion
2012-07-01T00:00:00.000
Procurementstart
2012-07-01T00:00:00.000
Procurementprojectedcompletion
2013-04-01T00:00:00.000
Procurementactualcompletion
2013-02-01T00:00:00.000
Constructionstart
2013-03-01T00:00:00.000
Constructionprojectedcom
2014-03-01T00:00:00.000
Constructionadjustedcompletion
2014-03-01T00:00:00.000
Constructionactualcompletion
2014-03-01T00:00:00.000
Totalfunding
$1,334,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Mayoral
Name
Various locations, Brooklyn
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Brooklyn
VIEW LOCATION
5947
Trackerid: 5947 • Fmsid: 846 P-2TREE22 • Title: Brooklyn Street Tree Planting FY13 - Community Boards 1-6,8,9,16
Trackerid
5947
Fmsid
846 P-2TREE22
Title
Brooklyn Street Tree Planting FY13 - Community Boards 1-6,8,9,16
Summary
This project will plant trees in Community Boards 1-4, 6, 8, 9, & 16 in Brooklyn.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2012-07-01T00:00:00.000
Designprojectedcompletion
2012-12-01T00:00:00.000
Designactualcompletion
2013-01-01T00:00:00.000
Procurementstart
2013-01-01T00:00:00.000
Procurementprojectedcompletion
2013-10-01T00:00:00.000
Procurementactualcompletion
2013-04-01T00:00:00.000
Constructionstart
2013-04-01T00:00:00.000
Constructionprojectedcom
2014-04-01T00:00:00.000
Constructionactualcompletion
2014-04-01T00:00:00.000
Totalfunding
$1,689,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
City CouncilMayoralPrivate
Name
Various locations, Brooklyn
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Brooklyn
VIEW LOCATION
2071
Trackerid: 2071 • Fmsid: 846 P-2PNYR02 • Title: Brooklyn Street Tree Planting & Invasive Species Removal FY11
Trackerid
2071
Fmsid
846 P-2PNYR02
Title
Brooklyn Street Tree Planting & Invasive Species Removal FY11
Summary
This project will plant street trees and remove invasive species at various locations in Brooklyn.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2011-05-01T00:00:00.000
Designactualcompletion
2011-10-01T00:00:00.000
Procurementstart
2011-10-01T00:00:00.000
Procurementprojectedcompletion
2012-07-01T00:00:00.000
Procurementactualcompletion
2012-05-01T00:00:00.000
Constructionstart
2012-06-01T00:00:00.000
Constructionprojectedcom
2014-09-01T00:00:00.000
Constructionadjustedcompletion
2014-04-01T00:00:00.000
Constructionactualcompletion
2014-04-01T00:00:00.000
Totalfunding
$599,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Mayoral
Name
Various locations, Brooklyn
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Brooklyn
VIEW LOCATION
6137
Trackerid: 6137 • Fmsid: 846 P-2TRE14B • Title: Brooklyn Street Tree Planting FY14 - Community Boards 5,9,16,17,18
Trackerid
6137
Fmsid
846 P-2TRE14B
Title
Brooklyn Street Tree Planting FY14 - Community Boards 5,9,16,17,18
Summary
This project will plant new street trees in Community Boards 5, 9, 16, 17 and 18 in Brooklyn.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2013-04-01T00:00:00.000
Designprojectedcompletion
2013-05-01T00:00:00.000
Designactualcompletion
2013-06-01T00:00:00.000
Procurementstart
2013-06-01T00:00:00.000
Procurementprojectedcompletion
2014-03-01T00:00:00.000
Procurementactualcompletion
2014-02-01T00:00:00.000
Constructionstart
2014-03-01T00:00:00.000
Constructionprojectedcom
2015-03-01T00:00:00.000
Constructionadjustedcompletion
2015-03-01T00:00:00.000
Constructionactualcompletion
2015-03-01T00:00:00.000
Totalfunding
$2,044,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Borough PresidentMayoral
Name
Various locations, Brooklyn
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Brooklyn
VIEW LOCATION
6138
Trackerid: 6138 • Fmsid: 846 P-2PNYT23 • Title: Brooklyn Street Tree Planting FY14 - Community Boards 7,10-15
Trackerid
6138
Fmsid
846 P-2PNYT23
Title
Brooklyn Street Tree Planting FY14 - Community Boards 7,10-15
Summary
This project will plant street trees in Community Boards 7, and 10 through 15 in Brooklyn.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2013-04-01T00:00:00.000
Designprojectedcompletion
2013-05-01T00:00:00.000
Designactualcompletion
2013-06-01T00:00:00.000
Procurementstart
2013-06-01T00:00:00.000
Procurementprojectedcompletion
2014-03-01T00:00:00.000
Procurementactualcompletion
2014-02-01T00:00:00.000
Constructionstart
2014-03-01T00:00:00.000
Constructionprojectedcom
2015-03-01T00:00:00.000
Constructionadjustedcompletion
2015-03-01T00:00:00.000
Constructionactualcompletion
2015-03-01T00:00:00.000
Totalfunding
$2,695,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Borough PresidentMayoral
Name
Various locations, Brooklyn
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Brooklyn
VIEW LOCATION
6139
Trackerid: 6139 • Fmsid: 846 P-2TRE14A • Title: Brooklyn Street Tree Planting FY14 - Community Boards 1-6,8
Trackerid
6139
Fmsid
846 P-2TRE14A
Title
Brooklyn Street Tree Planting FY14 - Community Boards 1-6,8
Summary
This project will plant new street trees in Community Boards 1 through 6, and 8 in Brooklyn.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2013-04-01T00:00:00.000
Designprojectedcompletion
2013-05-01T00:00:00.000
Designactualcompletion
2013-06-01T00:00:00.000
Procurementstart
2013-06-01T00:00:00.000
Procurementprojectedcompletion
2014-03-01T00:00:00.000
Procurementactualcompletion
2014-02-01T00:00:00.000
Constructionstart
2014-03-01T00:00:00.000
Constructionprojectedcom
2015-03-01T00:00:00.000
Constructionactualcompletion
2015-03-01T00:00:00.000
Totalfunding
$2,596,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Borough PresidentCity CouncilMayoralPrivate
Name
Various locations, Brooklyn
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Brooklyn
VIEW LOCATION
6229
Trackerid: 6229 • Fmsid: 846 P-2SRISKM • Title: Brooklyn Sandy-Related Tree Replacement
Trackerid
6229
Fmsid
846 P-2SRISKM
Title
Brooklyn Sandy-Related Tree Replacement
Summary
This project will replace trees removed due to Hurricane Sandy damage in Brooklyn.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2013-12-01T00:00:00.000
Designprojectedcompletion
2013-12-01T00:00:00.000
Designactualcompletion
2014-01-01T00:00:00.000
Procurementstart
2014-01-01T00:00:00.000
Procurementprojectedcompletion
2014-10-01T00:00:00.000
Procurementactualcompletion
2014-07-01T00:00:00.000
Constructionstart
2014-12-01T00:00:00.000
Constructionprojectedcom
2015-11-01T00:00:00.000
Constructionactualcompletion
2015-11-01T00:00:00.000
Totalfunding
$2,450,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
FederalMayoral
Name
Various locations, Brooklyn
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Brooklyn
VIEW LOCATION
6600
Trackerid: 6600 • Fmsid: 846 P-2TRE15A • Title: Brooklyn Street Tree Planting FY15 - Community Boards 1-4
Trackerid
6600
Fmsid
846 P-2TRE15A
Title
Brooklyn Street Tree Planting FY15 - Community Boards 1-4
Summary
This project will plant street trees in Community Boards 1 through 4 in Brooklyn.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2014-07-01T00:00:00.000
Designprojectedcompletion
2014-08-01T00:00:00.000
Designactualcompletion
2014-08-01T00:00:00.000
Procurementstart
2014-08-01T00:00:00.000
Procurementprojectedcompletion
2015-05-01T00:00:00.000
Procurementadjustedcompletion
2015-07-01T00:00:00.000
Procurementactualcompletion
2015-07-01T00:00:00.000
Constructionstart
2015-04-01T00:00:00.000
Constructionprojectedcom
2016-04-01T00:00:00.000
Constructionactualcompletion
2016-04-01T00:00:00.000
Totalfunding
$2,213,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Borough PresidentCity CouncilMayoralPrivate
Name
Various locations, Brooklyn
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Brooklyn
VIEW LOCATION
6601
Trackerid: 6601 • Fmsid: 846 P-2PNYT25 • Title: Brooklyn Street Tree Planting FY15 - Community Boards 5,8,9,16,17
Trackerid
6601
Fmsid
846 P-2PNYT25
Title
Brooklyn Street Tree Planting FY15 - Community Boards 5,8,9,16,17
Summary
This project will plant street trees in Community Boards 5, 8, 9, 16 and 17 in Brooklyn.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2014-07-01T00:00:00.000
Designprojectedcompletion
2014-08-01T00:00:00.000
Designactualcompletion
2014-08-01T00:00:00.000
Procurementstart
2014-08-01T00:00:00.000
Procurementprojectedcompletion
2015-05-01T00:00:00.000
Procurementactualcompletion
2015-05-01T00:00:00.000
Constructionstart
2015-04-01T00:00:00.000
Constructionprojectedcom
2016-04-01T00:00:00.000
Constructionadjustedcompletion
2016-10-01T00:00:00.000
Constructionactualcompletion
2016-07-01T00:00:00.000
Totalfunding
$1,621,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Mayoral
Name
Various locations, Brooklyn
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Brooklyn
VIEW LOCATION
6602
Trackerid: 6602 • Fmsid: 846 P-2TRE15B • Title: Brooklyn Street Tree Planting FY15 - Community Boards 6,7,10,12
Trackerid
6602
Fmsid
846 P-2TRE15B
Title
Brooklyn Street Tree Planting FY15 - Community Boards 6,7,10,12
Summary
This project will plant street trees in Community Boards 6, 7, 10 and 12 in Brooklyn.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2014-07-01T00:00:00.000
Designprojectedcompletion
2014-08-01T00:00:00.000
Designactualcompletion
2014-08-01T00:00:00.000
Procurementstart
2014-08-01T00:00:00.000
Procurementprojectedcompletion
2015-05-01T00:00:00.000
Procurementactualcompletion
2015-05-01T00:00:00.000
Constructionstart
2015-04-01T00:00:00.000
Constructionprojectedcom
2016-04-01T00:00:00.000
Constructionadjustedcompletion
2016-06-01T00:00:00.000
Constructionactualcompletion
2016-06-01T00:00:00.000
Totalfunding
$1,679,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
City CouncilMayoralPrivate
Name
Various locations, Brooklyn
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Brooklyn
VIEW LOCATION
6603
Trackerid: 6603 • Fmsid: 846 P-2PNYT24 • Title: Brooklyn Street Tree Planting FY15 - Community Boards 11,13-15,18
Trackerid
6603
Fmsid
846 P-2PNYT24
Title
Brooklyn Street Tree Planting FY15 - Community Boards 11,13-15,18
Summary
This project will plant street trees in Community Boards 11, 13, 14, 15 and 18 in Brooklyn.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2014-07-01T00:00:00.000
Designprojectedcompletion
2014-08-01T00:00:00.000
Designactualcompletion
2014-08-01T00:00:00.000
Procurementstart
2014-08-01T00:00:00.000
Procurementprojectedcompletion
2015-05-01T00:00:00.000
Procurementactualcompletion
2015-05-01T00:00:00.000
Constructionstart
2015-04-01T00:00:00.000
Constructionprojectedcom
2016-04-01T00:00:00.000
Constructionactualcompletion
2016-04-01T00:00:00.000
Totalfunding
$1,498,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Mayoral
Name
Various locations, Brooklyn
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Brooklyn
VIEW LOCATION
8516
Trackerid: 8516 • Fmsid: 846 SANDY6-17 • Title: Brooklyn and Staten Island Sandy-Related and Risk Management Tree Removal
Trackerid
8516
Fmsid
846 SANDY6-17
Title
Brooklyn and Staten Island Sandy-Related and Risk Management Tree Removal
Summary
This project will remove trees damaged from Hurricane Sandy and for Risk Management in the Boroughs of Brooklyn and Staten Island.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2016-05-01T00:00:00.000
Designprojectedcompletion
2016-06-01T00:00:00.000
Designactualcompletion
2016-11-01T00:00:00.000
Procurementstart
2016-11-01T00:00:00.000
Procurementprojectedcompletion
2017-07-01T00:00:00.000
Procurementactualcompletion
2017-07-01T00:00:00.000
Constructionstart
2017-09-01T00:00:00.000
Constructionprojectedcom
2018-09-01T00:00:00.000
Constructionadjustedcompletion
2018-09-01T00:00:00.000
Constructionactualcompletion
2018-09-01T00:00:00.000
Totalfunding
$1,440,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
FederalMayoral
Name
Various locations, Brooklyn and Staten Island
Parkid
NA
Latitude
0.0
Longitude
0.0
VIEW LOCATION
10910
Trackerid: 10910 • Fmsid: 846 P-6EABTRD • Title: Brooklyn and Staten Island Emerald Ash Borer (EAB) Related Tree Removal FY25
Trackerid
10910
Fmsid
846 P-6EABTRD
Title
Brooklyn and Staten Island Emerald Ash Borer (EAB) Related Tree Removal FY25
Summary
This project will remove trees hosted by Emerald Ash Borer (EAB) in Brooklyn and Staten Island.
Currentphase
construction
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
5.35
Designstart
2024-09-01T00:00:00.000
Designprojectedcompletion
2025-01-01T00:00:00.000
Designactualcompletion
2024-11-01T00:00:00.000
Procurementstart
2025-04-01T00:00:00.000
Procurementprojectedcompletion
2026-04-01T00:00:00.000
Procurementactualcompletion
2026-02-01T00:00:00.000
Constructionstart
2026-03-01T00:00:00.000
Constructionprojectedcom
2029-02-01T00:00:00.000
Totalfunding
$4,953,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Mayoral
Name
Various Locations, Brooklyn and Staten Island
Parkid
NA
Latitude
0.0
Longitude
0.0
Borough
Citywide
VIEW LOCATION
6146
Trackerid: 6146 • Fmsid: 846 P-6PNYR25 • Title: Brooklyn and Staten Island Reforestation FY14
Trackerid
6146
Fmsid
846 P-6PNYR25
Title
Brooklyn and Staten Island Reforestation FY14
Summary
This multisite contract will remove invasive species and plant new trees in Brooklyn and Staten Island.
Currentphase
completed
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2013-05-01T00:00:00.000
Designprojectedcompletion
2013-06-01T00:00:00.000
Designactualcompletion
2013-08-01T00:00:00.000
Procurementstart
2013-08-01T00:00:00.000
Procurementprojectedcompletion
2014-05-01T00:00:00.000
Procurementactualcompletion
2014-05-01T00:00:00.000
Constructionstart
2014-05-01T00:00:00.000
Constructionprojectedcom
2016-11-01T00:00:00.000
Constructionactualcompletion
2016-11-01T00:00:00.000
Totalfunding
$1,383,000
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Mayoral
Name
Various locations, Brooklyn and Staten Island
Parkid
NA
Latitude
0.0
Longitude
0.0
VIEW LOCATION