Capital Projects Dashboard - Citywide Schedule History and Variance

This is the history all agency reported forecasts/actual project completion dates. Each row is the snapshot of data taken on each reporting period. The 'completion date type' column shows if the 'completion date' is either a forecast or actual date. Over time, a project would have one or more forecasted completion dates before it is actually completed. The 'variance' is the day difference between 'completion date' of each row and its prior reporting period. This dataset is part of the Capital Projects Dashboard.

City Government Mayor's Office of Operations (OPS) Dataset 95tx-snak 10 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4338
Reporting Period
202601
Managing Agency
DDC
Pid
4338
Agency Project Name
Harper Street Administration Building Reconstruction
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4338
Reporting Period
202605
Managing Agency
DDC
Pid
4338
Agency Project Name
Harper Street Administration Building Reconstruction
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4339
Reporting Period
202305
Managing Agency
DDC
Pid
4339
Agency Project Name
CROTON ABOVE GROUND STRUCTURE AND LANDSCAPING
Current Phase
Construction
Completion Date
2024-07-03T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4339
Reporting Period
202309
Managing Agency
DDC
Pid
4339
Agency Project Name
CROTON ABOVE GROUND STRUCTURE AND LANDSCAPING
Current Phase
Construction
Completion Date
2024-09-05T00:00:00.000
Completion Date Type
Forecast
Variance Day
64
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4339
Reporting Period
202401
Managing Agency
DDC
Pid
4339
Agency Project Name
CROTON ABOVE GROUND STRUCTURE AND LANDSCAPING
Current Phase
Construction
Completion Date
2024-09-05T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4339
Reporting Period
202405
Managing Agency
DDC
Pid
4339
Agency Project Name
CROTON ABOVE GROUND STRUCTURE AND LANDSCAPING
Current Phase
Construction
Completion Date
2024-09-05T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4339
Reporting Period
202409
Managing Agency
DDC
Pid
4339
Agency Project Name
CROTON ABOVE GROUND STRUCTURE AND LANDSCAPING
Current Phase
Construction
Completion Date
2025-02-27T00:00:00.000
Completion Date Type
Forecast
Variance Day
175
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNAVAILABILITY OF PRODUCT
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4339
Reporting Period
202501
Managing Agency
DDC
Pid
4339
Agency Project Name
CROTON ABOVE GROUND STRUCTURE AND LANDSCAPING
Current Phase
Construction
Completion Date
2025-04-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
62
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4339
Reporting Period
202505
Managing Agency
DDC
Pid
4339
Agency Project Name
CROTON ABOVE GROUND STRUCTURE AND LANDSCAPING
Current Phase
Construction
Completion Date
2025-10-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
184
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4339
Reporting Period
202509
Managing Agency
DDC
Pid
4339
Agency Project Name
CROTON ABOVE GROUND STRUCTURE AND LANDSCAPING
Current Phase
Construction
Completion Date
2025-11-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
30
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4339
Reporting Period
202601
Managing Agency
DDC
Pid
4339
Agency Project Name
CROTON ABOVE GROUND STRUCTURE AND LANDSCAPING
Current Phase
Construction
Completion Date
2026-04-03T00:00:00.000
Completion Date Type
Forecast
Variance Day
124
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO SCHEDULING OF UTILITY WORK
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4339
Reporting Period
202605
Managing Agency
DDC
Pid
4339
Agency Project Name
CROTON ABOVE GROUND STRUCTURE AND LANDSCAPING
Current Phase
Close-out
Completion Date
2026-06-15T00:00:00.000
Completion Date Type
Actual
Variance Day
73
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO SCHEDULING OF UTILITY WORK
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4340
Reporting Period
202305
Managing Agency
DDC
Pid
4340
Agency Project Name
CROTON FILTRATION PLANT
Current Phase
Construction
Completion Date
2024-07-03T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4340
Reporting Period
202309
Managing Agency
DDC
Pid
4340
Agency Project Name
CROTON FILTRATION PLANT
Current Phase
Construction
Completion Date
2024-09-05T00:00:00.000
Completion Date Type
Forecast
Variance Day
64
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4340
Reporting Period
202401
Managing Agency
DDC
Pid
4340
Agency Project Name
CROTON FILTRATION PLANT
Current Phase
Construction
Completion Date
2024-09-05T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4340
Reporting Period
202405
Managing Agency
DDC
Pid
4340
Agency Project Name
CROTON FILTRATION PLANT
Current Phase
Construction
Completion Date
2024-09-05T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4340
Reporting Period
202409
Managing Agency
DDC
Pid
4340
Agency Project Name
CROTON FILTRATION PLANT
Current Phase
Construction
Completion Date
2025-02-27T00:00:00.000
Completion Date Type
Forecast
Variance Day
175
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNAVAILABILITY OF PRODUCT
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4340
Reporting Period
202501
Managing Agency
DDC
Pid
4340
Agency Project Name
CROTON FILTRATION PLANT
Current Phase
Construction
Completion Date
2025-04-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
62
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4340
Reporting Period
202505
Managing Agency
DDC
Pid
4340
Agency Project Name
CROTON FILTRATION PLANT
Current Phase
Construction
Completion Date
2025-10-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
184
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4340
Reporting Period
202509
Managing Agency
DDC
Pid
4340
Agency Project Name
CROTON FILTRATION PLANT
Current Phase
Construction
Completion Date
2025-11-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
30
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4340
Reporting Period
202601
Managing Agency
DDC
Pid
4340
Agency Project Name
CROTON FILTRATION PLANT
Current Phase
Construction
Completion Date
2026-04-03T00:00:00.000
Completion Date Type
Forecast
Variance Day
124
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO SCHEDULING OF UTILITY WORK
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4340
Reporting Period
202605
Managing Agency
DDC
Pid
4340
Agency Project Name
CROTON FILTRATION PLANT
Current Phase
Close-out
Completion Date
2026-06-15T00:00:00.000
Completion Date Type
Actual
Variance Day
73
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO SCHEDULING OF UTILITY WORK
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4341
Reporting Period
202305
Managing Agency
DDC
Pid
4341
Agency Project Name
Queens County Farm Museum Phase 2 Restoration
Current Phase
Construction Procurement
Completion Date
2025-12-28T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4341
Reporting Period
202309
Managing Agency
DDC
Pid
4341
Agency Project Name
Queens County Farm Museum Phase 2 Restoration
Current Phase
Construction Procurement
Completion Date
2025-12-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4341
Reporting Period
202401
Managing Agency
DDC
Pid
4341
Agency Project Name
Queens County Farm Museum Phase 2 Restoration
Current Phase
Construction Procurement
Completion Date
2025-12-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4341
Reporting Period
202405
Managing Agency
DDC
Pid
4341
Agency Project Name
Queens County Farm Museum Phase 2 Restoration
Current Phase
Construction Procurement
Completion Date
2026-09-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
247
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO BUDGETARY CONSTRAINTS
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4341
Reporting Period
202409
Managing Agency
DDC
Pid
4341
Agency Project Name
Queens County Farm Museum Phase 2 Restoration
Current Phase
Construction Procurement
Completion Date
2026-09-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4341
Reporting Period
202501
Managing Agency
DDC
Pid
4341
Agency Project Name
Queens County Farm Museum Phase 2 Restoration
Current Phase
Construction Procurement
Completion Date
2026-10-22T00:00:00.000
Completion Date Type
Forecast
Variance Day
51
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4341
Reporting Period
202505
Managing Agency
DDC
Pid
4341
Agency Project Name
Queens County Farm Museum Phase 2 Restoration
Current Phase
Construction Procurement
Completion Date
2026-12-03T00:00:00.000
Completion Date Type
Forecast
Variance Day
42
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4341
Reporting Period
202509
Managing Agency
DDC
Pid
4341
Agency Project Name
Queens County Farm Museum Phase 2 Restoration
Current Phase
Construction
Completion Date
2026-12-03T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4341
Reporting Period
202601
Managing Agency
DDC
Pid
4341
Agency Project Name
Queens County Farm Museum Phase 2 Restoration
Current Phase
Construction
Completion Date
2026-12-03T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4341
Reporting Period
202605
Managing Agency
DDC
Pid
4341
Agency Project Name
Queens County Farm Museum Phase 2 Restoration
Current Phase
Construction
Completion Date
2027-07-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
239
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4342
Reporting Period
202305
Managing Agency
DDC
Pid
4342
Agency Project Name
Renovations at Corona Health Center
Current Phase
Construction Procurement
Completion Date
2025-10-30T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4342
Reporting Period
202309
Managing Agency
DDC
Pid
4342
Agency Project Name
Renovations at Corona Health Center
Current Phase
Construction Procurement
Completion Date
2025-10-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4342
Reporting Period
202401
Managing Agency
DDC
Pid
4342
Agency Project Name
Renovations at Corona Health Center
Current Phase
Construction Procurement
Completion Date
2025-10-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4342
Reporting Period
202405
Managing Agency
DDC
Pid
4342
Agency Project Name
Renovations at Corona Health Center
Current Phase
Construction
Completion Date
2026-04-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
166
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4342
Reporting Period
202409
Managing Agency
DDC
Pid
4342
Agency Project Name
Renovations at Corona Health Center
Current Phase
Construction
Completion Date
2026-04-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4342
Reporting Period
202501
Managing Agency
DDC
Pid
4342
Agency Project Name
Renovations at Corona Health Center
Current Phase
Construction
Completion Date
2026-04-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4342
Reporting Period
202505
Managing Agency
DDC
Pid
4342
Agency Project Name
Renovations at Corona Health Center
Current Phase
Construction
Completion Date
2026-04-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4342
Reporting Period
202509
Managing Agency
DDC
Pid
4342
Agency Project Name
Renovations at Corona Health Center
Current Phase
Construction
Completion Date
2026-04-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4342
Reporting Period
202601
Managing Agency
DDC
Pid
4342
Agency Project Name
Renovations at Corona Health Center
Current Phase
Construction
Completion Date
2026-04-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4342
Reporting Period
202605
Managing Agency
DDC
Pid
4342
Agency Project Name
Renovations at Corona Health Center
Current Phase
Construction
Completion Date
2026-04-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4343
Reporting Period
202305
Managing Agency
DDC
Pid
4343
Agency Project Name
Downtown Art-70 East 4th ST.Renovation
Current Phase
Construction
Completion Date
2024-04-03T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4343
Reporting Period
202309
Managing Agency
DDC
Pid
4343
Agency Project Name
Downtown Art-70 East 4th ST.Renovation
Current Phase
Construction
Completion Date
2024-04-03T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-01-04T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4343
Reporting Period
202401
Managing Agency
DDC
Pid
4343
Agency Project Name
Downtown Art-70 East 4th ST.Renovation
Current Phase
Construction
Completion Date
2024-04-03T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-01-04T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4343
Reporting Period
202405
Managing Agency
DDC
Pid
4343
Agency Project Name
Downtown Art-70 East 4th ST.Renovation
Current Phase
Construction
Completion Date
2024-01-11T00:00:00.000
Completion Date Type
Actual
Variance Day
-83
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4344
Reporting Period
202305
Managing Agency
DDC
Pid
4344
Agency Project Name
Studio Museum in Harlem New Building
Current Phase
Construction
Completion Date
2024-06-30T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4344
Reporting Period
202309
Managing Agency
DDC
Pid
4344
Agency Project Name
Studio Museum in Harlem New Building
Current Phase
Construction
Completion Date
2024-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2023-09-01T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4344
Reporting Period
202401
Managing Agency
DDC
Pid
4344
Agency Project Name
Studio Museum in Harlem New Building
Current Phase
Construction
Completion Date
2024-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2023-09-01T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4344
Reporting Period
202405
Managing Agency
DDC
Pid
4344
Agency Project Name
Studio Museum in Harlem New Building
Current Phase
Construction
Completion Date
2024-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000