Capital Projects Dashboard - Citywide Schedule History and Variance

This is the history all agency reported forecasts/actual project completion dates. Each row is the snapshot of data taken on each reporting period. The 'completion date type' column shows if the 'completion date' is either a forecast or actual date. Over time, a project would have one or more forecasted completion dates before it is actually completed. The 'variance' is the day difference between 'completion date' of each row and its prior reporting period. This dataset is part of the Capital Projects Dashboard.

City Government Mayor's Office of Operations (OPS) Dataset 95tx-snak 10 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4373
Reporting Period
202505
Managing Agency
DDC
Pid
4373
Agency Project Name
Court Square Pedestrian Improvements
Current Phase
Design
Completion Date
2029-05-02T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4373
Reporting Period
202509
Managing Agency
DDC
Pid
4373
Agency Project Name
Court Square Pedestrian Improvements
Current Phase
Design
Completion Date
2029-09-12T00:00:00.000
Completion Date Type
Forecast
Variance Day
133
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4373
Reporting Period
202601
Managing Agency
DDC
Pid
4373
Agency Project Name
Court Square Pedestrian Improvements
Current Phase
Design
Completion Date
2030-09-11T00:00:00.000
Completion Date Type
Forecast
Variance Day
364
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4373
Reporting Period
202605
Managing Agency
DDC
Pid
4373
Agency Project Name
Court Square Pedestrian Improvements
Current Phase
Design
Completion Date
2030-09-11T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4374
Reporting Period
202305
Managing Agency
DDC
Pid
4374
Agency Project Name
Distribution Water Main replacement work in 43rd Avenue between National Street and 104th Street, as well as other locations listed in Page 3 of the attached CPI. Borough of Queens.
Current Phase
Construction Procurement
Completion Date
2026-07-15T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4374
Reporting Period
202309
Managing Agency
DDC
Pid
4374
Agency Project Name
Distribution Water Main replacement work in 43rd Avenue between National Street and 104th Street, as well as other locations listed in Page 3 of the attached CPI. Borough of Queens.
Current Phase
Construction Procurement
Completion Date
2026-07-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4374
Reporting Period
202401
Managing Agency
DDC
Pid
4374
Agency Project Name
Distribution Water Main replacement work in 43rd Avenue between National Street and 104th Street, as well as other locations listed in Page 3 of the attached CPI. Borough of Queens.
Current Phase
Construction Procurement
Completion Date
2026-07-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4374
Reporting Period
202405
Managing Agency
DDC
Pid
4374
Agency Project Name
Distribution Water Main replacement work in 43rd Avenue between National Street and 104th Street, as well as other locations listed in Page 3 of the attached CPI. Borough of Queens.
Current Phase
Construction Procurement
Completion Date
2026-11-03T00:00:00.000
Completion Date Type
Forecast
Variance Day
111
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO BUDGETARY CONSTRAINTS
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4374
Reporting Period
202409
Managing Agency
DDC
Pid
4374
Agency Project Name
Distribution Water Main replacement work in 43rd Avenue between National Street and 104th Street, as well as other locations listed in Page 3 of the attached CPI. Borough of Queens.
Current Phase
Construction Procurement
Completion Date
2026-11-03T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4374
Reporting Period
202501
Managing Agency
DDC
Pid
4374
Agency Project Name
Distribution Water Main replacement work in 43rd Avenue between National Street and 104th Street, as well as other locations listed in Page 3 of the attached CPI. Borough of Queens.
Current Phase
Construction
Completion Date
2026-11-03T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4374
Reporting Period
202505
Managing Agency
DDC
Pid
4374
Agency Project Name
Distribution Water Main replacement work in 43rd Avenue between National Street and 104th Street, as well as other locations listed in Page 3 of the attached CPI. Borough of Queens.
Current Phase
Construction
Completion Date
2026-11-03T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4374
Reporting Period
202509
Managing Agency
DDC
Pid
4374
Agency Project Name
Distribution Water Main replacement work in 43rd Avenue between National Street and 104th Street, as well as other locations listed in Page 3 of the attached CPI. Borough of Queens.
Current Phase
Construction
Completion Date
2026-11-03T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4374
Reporting Period
202601
Managing Agency
DDC
Pid
4374
Agency Project Name
Distribution Water Main replacement work in 43rd Avenue between National Street and 104th Street, as well as other locations listed in Page 3 of the attached CPI. Borough of Queens.
Current Phase
Construction
Completion Date
2026-11-03T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4374
Reporting Period
202605
Managing Agency
DDC
Pid
4374
Agency Project Name
Distribution Water Main replacement work in 43rd Avenue between National Street and 104th Street, as well as other locations listed in Page 3 of the attached CPI. Borough of Queens.
Current Phase
Construction
Completion Date
2026-11-03T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4375
Reporting Period
202305
Managing Agency
DDC
Pid
4375
Agency Project Name
Distribution Water Main work in Jay Avenue between Borden Avenue and 66th Street, as well as other locations listed in Page 3 of the attached CPI. Borough of Queens.
Current Phase
Construction
Completion Date
2024-09-14T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4375
Reporting Period
202309
Managing Agency
DDC
Pid
4375
Agency Project Name
Distribution Water Main work in Jay Avenue between Borden Avenue and 66th Street, as well as other locations listed in Page 3 of the attached CPI. Borough of Queens.
Current Phase
Construction
Completion Date
2024-09-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4375
Reporting Period
202401
Managing Agency
DDC
Pid
4375
Agency Project Name
Distribution Water Main work in Jay Avenue between Borden Avenue and 66th Street, as well as other locations listed in Page 3 of the attached CPI. Borough of Queens.
Current Phase
Construction
Completion Date
2024-09-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4375
Reporting Period
202405
Managing Agency
DDC
Pid
4375
Agency Project Name
Distribution Water Main work in Jay Avenue between Borden Avenue and 66th Street, as well as other locations listed in Page 3 of the attached CPI. Borough of Queens.
Current Phase
Construction
Completion Date
2024-06-28T00:00:00.000
Completion Date Type
Actual
Variance Day
-78
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4376
Reporting Period
202305
Managing Agency
DDC
Pid
4376
Agency Project Name
Southern Bronx Multi-Site Safety Improvements
Current Phase
Design
Completion Date
2026-11-29T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4376
Reporting Period
202309
Managing Agency
DDC
Pid
4376
Agency Project Name
Southern Bronx Multi-Site Safety Improvements
Current Phase
Design
Completion Date
2026-11-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4376
Reporting Period
202401
Managing Agency
DDC
Pid
4376
Agency Project Name
Southern Bronx Multi-Site Safety Improvements
Current Phase
Design
Completion Date
2026-11-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4376
Reporting Period
202405
Managing Agency
DDC
Pid
4376
Agency Project Name
Southern Bronx Multi-Site Safety Improvements
Current Phase
Design
Completion Date
2026-11-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4376
Reporting Period
202409
Managing Agency
DDC
Pid
4376
Agency Project Name
Southern Bronx Multi-Site Safety Improvements
Current Phase
Design
Completion Date
2027-09-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
289
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4376
Reporting Period
202501
Managing Agency
DDC
Pid
4376
Agency Project Name
Southern Bronx Multi-Site Safety Improvements
Current Phase
Design
Completion Date
2027-09-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4376
Reporting Period
202505
Managing Agency
DDC
Pid
4376
Agency Project Name
Southern Bronx Multi-Site Safety Improvements
Current Phase
Design
Completion Date
2027-09-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4376
Reporting Period
202509
Managing Agency
DDC
Pid
4376
Agency Project Name
Southern Bronx Multi-Site Safety Improvements
Current Phase
Design
Completion Date
2027-09-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4376
Reporting Period
202601
Managing Agency
DDC
Pid
4376
Agency Project Name
Southern Bronx Multi-Site Safety Improvements
Current Phase
Design
Completion Date
2028-09-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
367
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4376
Reporting Period
202605
Managing Agency
DDC
Pid
4376
Agency Project Name
Southern Bronx Multi-Site Safety Improvements
Current Phase
Design
Completion Date
2028-09-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4377
Reporting Period
202305
Managing Agency
DDC
Pid
4377
Agency Project Name
Northwest Bronx School Safety Improvements
Current Phase
Design
Completion Date
2027-05-25T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4377
Reporting Period
202309
Managing Agency
DDC
Pid
4377
Agency Project Name
Northwest Bronx School Safety Improvements
Current Phase
Design
Completion Date
2027-09-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
112
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4377
Reporting Period
202401
Managing Agency
DDC
Pid
4377
Agency Project Name
Northwest Bronx School Safety Improvements
Current Phase
Design
Completion Date
2027-09-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4377
Reporting Period
202405
Managing Agency
DDC
Pid
4377
Agency Project Name
Northwest Bronx School Safety Improvements
Current Phase
Design
Completion Date
2027-09-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4377
Reporting Period
202409
Managing Agency
DDC
Pid
4377
Agency Project Name
Northwest Bronx School Safety Improvements
Current Phase
Design
Completion Date
2028-10-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
392
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4377
Reporting Period
202501
Managing Agency
DDC
Pid
4377
Agency Project Name
Northwest Bronx School Safety Improvements
Current Phase
Design
Completion Date
2028-10-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4377
Reporting Period
202505
Managing Agency
DDC
Pid
4377
Agency Project Name
Northwest Bronx School Safety Improvements
Current Phase
Design
Completion Date
2028-10-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4377
Reporting Period
202509
Managing Agency
DDC
Pid
4377
Agency Project Name
Northwest Bronx School Safety Improvements
Current Phase
Design
Completion Date
2029-09-04T00:00:00.000
Completion Date Type
Forecast
Variance Day
329
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4377
Reporting Period
202601
Managing Agency
DDC
Pid
4377
Agency Project Name
Northwest Bronx School Safety Improvements
Current Phase
Design
Completion Date
2029-09-04T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4377
Reporting Period
202605
Managing Agency
DDC
Pid
4377
Agency Project Name
Northwest Bronx School Safety Improvements
Current Phase
Design
Completion Date
2029-09-04T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4378
Reporting Period
202305
Managing Agency
DDC
Pid
4378
Agency Project Name
64 E. Fourth Street Buillding Renovation
Current Phase
Construction
Completion Date
2023-11-20T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4378
Reporting Period
202309
Managing Agency
DDC
Pid
4378
Agency Project Name
64 E. Fourth Street Buillding Renovation
Current Phase
Construction
Completion Date
2024-02-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
101
Data Date
2024-01-04T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4378
Reporting Period
202401
Managing Agency
DDC
Pid
4378
Agency Project Name
64 E. Fourth Street Buillding Renovation
Current Phase
Construction
Completion Date
2024-02-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-01-04T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4378
Reporting Period
202405
Managing Agency
DDC
Pid
4378
Agency Project Name
64 E. Fourth Street Buillding Renovation
Current Phase
Construction
Completion Date
2023-12-22T00:00:00.000
Completion Date Type
Actual
Variance Day
-69
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4379
Reporting Period
202305
Managing Agency
DDC
Pid
4379
Agency Project Name
NYPD: REPLACEMENT OF FRONT DESKS/ BRONX PRECINCTS
Current Phase
Construction
Completion Date
2023-12-15T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4379
Reporting Period
202309
Managing Agency
DDC
Pid
4379
Agency Project Name
NYPD: REPLACEMENT OF FRONT DESKS/ BRONX PRECINCTS
Current Phase
Construction
Completion Date
2024-02-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
76
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4379
Reporting Period
202401
Managing Agency
DDC
Pid
4379
Agency Project Name
NYPD: REPLACEMENT OF FRONT DESKS/ BRONX PRECINCTS
Current Phase
Construction
Completion Date
2024-02-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4379
Reporting Period
202405
Managing Agency
DDC
Pid
4379
Agency Project Name
NYPD: REPLACEMENT OF FRONT DESKS/ BRONX PRECINCTS
Current Phase
Construction
Completion Date
2024-09-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
214
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4379
Reporting Period
202409
Managing Agency
DDC
Pid
4379
Agency Project Name
NYPD: REPLACEMENT OF FRONT DESKS/ BRONX PRECINCTS
Current Phase
Construction
Completion Date
2024-11-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
61
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4379
Reporting Period
202501
Managing Agency
DDC
Pid
4379
Agency Project Name
NYPD: REPLACEMENT OF FRONT DESKS/ BRONX PRECINCTS
Current Phase
Construction
Completion Date
2025-03-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
121
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4379
Reporting Period
202505
Managing Agency
DDC
Pid
4379
Agency Project Name
NYPD: REPLACEMENT OF FRONT DESKS/ BRONX PRECINCTS
Current Phase
Construction
Completion Date
2025-04-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
30
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4379
Reporting Period
202509
Managing Agency
DDC
Pid
4379
Agency Project Name
NYPD: REPLACEMENT OF FRONT DESKS/ BRONX PRECINCTS
Current Phase
Construction
Completion Date
2025-10-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
183
Data Date
2025-10-23T00:00:00.000