Capital Projects Dashboard - Citywide Schedule History and Variance

This is the history all agency reported forecasts/actual project completion dates. Each row is the snapshot of data taken on each reporting period. The 'completion date type' column shows if the 'completion date' is either a forecast or actual date. Over time, a project would have one or more forecasted completion dates before it is actually completed. The 'variance' is the day difference between 'completion date' of each row and its prior reporting period. This dataset is part of the Capital Projects Dashboard.

City Government Mayor's Office of Operations (OPS) Dataset 95tx-snak 10 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4385
Reporting Period
202309
Managing Agency
DDC
Pid
4385
Agency Project Name
TRENCH RESTORATION QUEENS & THE BRONX
Current Phase
Construction
Completion Date
2024-10-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4385
Reporting Period
202401
Managing Agency
DDC
Pid
4385
Agency Project Name
TRENCH RESTORATION QUEENS & THE BRONX
Current Phase
Construction
Completion Date
2024-10-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4385
Reporting Period
202405
Managing Agency
DDC
Pid
4385
Agency Project Name
TRENCH RESTORATION QUEENS & THE BRONX
Current Phase
Construction
Completion Date
2024-10-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4385
Reporting Period
202409
Managing Agency
DDC
Pid
4385
Agency Project Name
TRENCH RESTORATION QUEENS & THE BRONX
Current Phase
Construction
Completion Date
2024-10-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4385
Reporting Period
202501
Managing Agency
DDC
Pid
4385
Agency Project Name
TRENCH RESTORATION QUEENS & THE BRONX
Current Phase
Construction
Completion Date
2025-05-16T00:00:00.000
Completion Date Type
Forecast
Variance Day
213
Reason For Forecast Completion Change
PROJECT DELAYED PENDING APPROVAL OF NECESSARY PERMITS
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4385
Reporting Period
202505
Managing Agency
DDC
Pid
4385
Agency Project Name
TRENCH RESTORATION QUEENS & THE BRONX
Current Phase
Construction
Completion Date
2025-05-16T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4385
Reporting Period
202509
Managing Agency
DDC
Pid
4385
Agency Project Name
TRENCH RESTORATION QUEENS & THE BRONX
Current Phase
Close-out
Completion Date
2025-07-03T00:00:00.000
Completion Date Type
Actual
Variance Day
48
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4386
Reporting Period
202305
Managing Agency
DDC
Pid
4386
Agency Project Name
TRUNK WATER MAIN in 2nd Ave. ( SHAFT 32B)
Current Phase
Construction
Completion Date
2025-01-23T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4386
Reporting Period
202309
Managing Agency
DDC
Pid
4386
Agency Project Name
TRUNK WATER MAIN in 2nd Ave. ( SHAFT 32B)
Current Phase
Construction
Completion Date
2025-01-23T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4386
Reporting Period
202401
Managing Agency
DDC
Pid
4386
Agency Project Name
TRUNK WATER MAIN in 2nd Ave. ( SHAFT 32B)
Current Phase
Construction
Completion Date
2025-01-23T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4386
Reporting Period
202405
Managing Agency
DDC
Pid
4386
Agency Project Name
TRUNK WATER MAIN in 2nd Ave. ( SHAFT 32B)
Current Phase
Construction
Completion Date
2025-01-23T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4386
Reporting Period
202409
Managing Agency
DDC
Pid
4386
Agency Project Name
TRUNK WATER MAIN in 2nd Ave. ( SHAFT 32B)
Current Phase
Construction
Completion Date
2026-04-23T00:00:00.000
Completion Date Type
Forecast
Variance Day
455
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4386
Reporting Period
202501
Managing Agency
DDC
Pid
4386
Agency Project Name
TRUNK WATER MAIN in 2nd Ave. ( SHAFT 32B)
Current Phase
Construction
Completion Date
2026-10-23T00:00:00.000
Completion Date Type
Forecast
Variance Day
183
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4386
Reporting Period
202505
Managing Agency
DDC
Pid
4386
Agency Project Name
TRUNK WATER MAIN in 2nd Ave. ( SHAFT 32B)
Current Phase
Construction
Completion Date
2026-10-23T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4386
Reporting Period
202509
Managing Agency
DDC
Pid
4386
Agency Project Name
TRUNK WATER MAIN in 2nd Ave. ( SHAFT 32B)
Current Phase
Construction
Completion Date
2026-10-23T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4386
Reporting Period
202601
Managing Agency
DDC
Pid
4386
Agency Project Name
TRUNK WATER MAIN in 2nd Ave. ( SHAFT 32B)
Current Phase
Construction
Completion Date
2026-10-23T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4386
Reporting Period
202605
Managing Agency
DDC
Pid
4386
Agency Project Name
TRUNK WATER MAIN in 2nd Ave. ( SHAFT 32B)
Current Phase
Construction
Completion Date
2026-10-23T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4387
Reporting Period
202305
Managing Agency
DDC
Pid
4387
Agency Project Name
REPLACEMENT OF TRUNK WATER MAINS IN ATLANTIC AVE
Current Phase
Close-out
Completion Date
2023-05-31T00:00:00.000
Completion Date Type
Actual
Data Date
2023-09-01T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4388
Reporting Period
202305
Managing Agency
DDC
Pid
4388
Agency Project Name
WM REPLMT EAST NEW YORK AVE
Current Phase
Construction
Completion Date
2024-09-09T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4388
Reporting Period
202309
Managing Agency
DDC
Pid
4388
Agency Project Name
WM REPLMT EAST NEW YORK AVE
Current Phase
Construction
Completion Date
2024-09-09T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4388
Reporting Period
202401
Managing Agency
DDC
Pid
4388
Agency Project Name
WM REPLMT EAST NEW YORK AVE
Current Phase
Construction
Completion Date
2024-09-09T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4388
Reporting Period
202405
Managing Agency
DDC
Pid
4388
Agency Project Name
WM REPLMT EAST NEW YORK AVE
Current Phase
Construction
Completion Date
2024-09-09T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4388
Reporting Period
202409
Managing Agency
DDC
Pid
4388
Agency Project Name
WM REPLMT EAST NEW YORK AVE
Current Phase
Construction
Completion Date
2025-09-05T00:00:00.000
Completion Date Type
Forecast
Variance Day
361
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4388
Reporting Period
202501
Managing Agency
DDC
Pid
4388
Agency Project Name
WM REPLMT EAST NEW YORK AVE
Current Phase
Construction
Completion Date
2025-09-05T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4388
Reporting Period
202505
Managing Agency
DDC
Pid
4388
Agency Project Name
WM REPLMT EAST NEW YORK AVE
Current Phase
Construction
Completion Date
2025-09-05T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4388
Reporting Period
202509
Managing Agency
DDC
Pid
4388
Agency Project Name
WM REPLMT EAST NEW YORK AVE
Current Phase
Construction
Completion Date
2026-09-05T00:00:00.000
Completion Date Type
Forecast
Variance Day
365
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4388
Reporting Period
202601
Managing Agency
DDC
Pid
4388
Agency Project Name
WM REPLMT EAST NEW YORK AVE
Current Phase
Construction
Completion Date
2026-09-05T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4388
Reporting Period
202605
Managing Agency
DDC
Pid
4388
Agency Project Name
WM REPLMT EAST NEW YORK AVE
Current Phase
Construction
Completion Date
2026-09-05T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4389
Reporting Period
202305
Managing Agency
DDC
Pid
4389
Agency Project Name
COMBINED SEWER AND CHAMBERS IN 7TH STREET, BK
Current Phase
Construction
Completion Date
2024-05-10T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4389
Reporting Period
202309
Managing Agency
DDC
Pid
4389
Agency Project Name
COMBINED SEWER AND CHAMBERS IN 7TH STREET, BK
Current Phase
Construction
Completion Date
2024-05-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4389
Reporting Period
202401
Managing Agency
DDC
Pid
4389
Agency Project Name
COMBINED SEWER AND CHAMBERS IN 7TH STREET, BK
Current Phase
Construction
Completion Date
2024-05-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4389
Reporting Period
202405
Managing Agency
DDC
Pid
4389
Agency Project Name
COMBINED SEWER AND CHAMBERS IN 7TH STREET, BK
Current Phase
Construction
Completion Date
2024-11-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
204
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO SCHEDULING OF UTILITY WORK
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4389
Reporting Period
202409
Managing Agency
DDC
Pid
4389
Agency Project Name
COMBINED SEWER AND CHAMBERS IN 7TH STREET, BK
Current Phase
Construction
Completion Date
2024-11-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4389
Reporting Period
202501
Managing Agency
DDC
Pid
4389
Agency Project Name
COMBINED SEWER AND CHAMBERS IN 7TH STREET, BK
Current Phase
Construction
Completion Date
2025-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
212
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4389
Reporting Period
202505
Managing Agency
DDC
Pid
4389
Agency Project Name
COMBINED SEWER AND CHAMBERS IN 7TH STREET, BK
Current Phase
Construction
Completion Date
2025-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4389
Reporting Period
202509
Managing Agency
DDC
Pid
4389
Agency Project Name
COMBINED SEWER AND CHAMBERS IN 7TH STREET, BK
Current Phase
Construction
Completion Date
2025-12-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
184
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4389
Reporting Period
202601
Managing Agency
DDC
Pid
4389
Agency Project Name
COMBINED SEWER AND CHAMBERS IN 7TH STREET, BK
Current Phase
Construction
Completion Date
2026-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
181
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4389
Reporting Period
202605
Managing Agency
DDC
Pid
4389
Agency Project Name
COMBINED SEWER AND CHAMBERS IN 7TH STREET, BK
Current Phase
Construction
Completion Date
2026-09-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
92
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4390
Reporting Period
202305
Managing Agency
DDC
Pid
4390
Agency Project Name
UNION TURNPIKE CENTER MEDIAN REPLACEMENT
Current Phase
Construction
Completion Date
2024-08-20T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4390
Reporting Period
202309
Managing Agency
DDC
Pid
4390
Agency Project Name
UNION TURNPIKE CENTER MEDIAN REPLACEMENT
Current Phase
Construction
Completion Date
2024-08-20T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4390
Reporting Period
202401
Managing Agency
DDC
Pid
4390
Agency Project Name
UNION TURNPIKE CENTER MEDIAN REPLACEMENT
Current Phase
Construction
Completion Date
2024-08-20T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4390
Reporting Period
202405
Managing Agency
DDC
Pid
4390
Agency Project Name
UNION TURNPIKE CENTER MEDIAN REPLACEMENT
Current Phase
Construction
Completion Date
2024-08-20T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4390
Reporting Period
202409
Managing Agency
DDC
Pid
4390
Agency Project Name
UNION TURNPIKE CENTER MEDIAN REPLACEMENT
Current Phase
Construction
Completion Date
2024-08-20T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4390
Reporting Period
202501
Managing Agency
DDC
Pid
4390
Agency Project Name
UNION TURNPIKE CENTER MEDIAN REPLACEMENT
Current Phase
Close-out
Completion Date
2024-08-20T00:00:00.000
Completion Date Type
Actual
Variance Day
0
Data Date
2025-03-03T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4391
Reporting Period
202305
Managing Agency
DDC
Pid
4391
Agency Project Name
Manhattan Pet Adoption Center
Current Phase
Construction
Completion Date
2023-11-30T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4391
Reporting Period
202309
Managing Agency
DDC
Pid
4391
Agency Project Name
Manhattan Pet Adoption Center
Current Phase
Construction
Completion Date
2024-02-07T00:00:00.000
Completion Date Type
Forecast
Variance Day
69
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4391
Reporting Period
202401
Managing Agency
DDC
Pid
4391
Agency Project Name
Manhattan Pet Adoption Center
Current Phase
Construction
Completion Date
2024-02-07T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4391
Reporting Period
202405
Managing Agency
DDC
Pid
4391
Agency Project Name
Manhattan Pet Adoption Center
Current Phase
Construction
Completion Date
2024-02-28T00:00:00.000
Completion Date Type
Actual
Variance Day
21
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4392
Reporting Period
202305
Managing Agency
DDC
Pid
4392
Agency Project Name
Complex Upgrades Ped Ramps - Brooklyn
Current Phase
Design
Completion Date
2026-06-05T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4392
Reporting Period
202309
Managing Agency
DDC
Pid
4392
Agency Project Name
Complex Upgrades Ped Ramps - Brooklyn
Current Phase
Design
Completion Date
2027-02-04T00:00:00.000
Completion Date Type
Forecast
Variance Day
244
Data Date
2024-02-16T00:00:00.000