Capital Projects Dashboard - Citywide Schedule History and Variance

This is the history all agency reported forecasts/actual project completion dates. Each row is the snapshot of data taken on each reporting period. The 'completion date type' column shows if the 'completion date' is either a forecast or actual date. Over time, a project would have one or more forecasted completion dates before it is actually completed. The 'variance' is the day difference between 'completion date' of each row and its prior reporting period. This dataset is part of the Capital Projects Dashboard.

City Government Mayor's Office of Operations (OPS) Dataset 95tx-snak 10 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4402
Reporting Period
202401
Managing Agency
DDC
Pid
4402
Agency Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 2
Current Phase
Design
Completion Date
2030-08-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4402
Reporting Period
202405
Managing Agency
DDC
Pid
4402
Agency Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 2
Current Phase
Design
Completion Date
2031-08-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
362
Reason For Forecast Completion Change
PROJECT DELAYED PENDING APPROVAL OF NECESSARY PERMITS
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4402
Reporting Period
202409
Managing Agency
DDC
Pid
4402
Agency Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 2
Current Phase
Design
Completion Date
2031-08-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4402
Reporting Period
202501
Managing Agency
DDC
Pid
4402
Agency Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 2
Current Phase
Design
Completion Date
2031-08-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4402
Reporting Period
202505
Managing Agency
DDC
Pid
4402
Agency Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 2
Current Phase
Design
Completion Date
2032-08-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
366
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4402
Reporting Period
202509
Managing Agency
DDC
Pid
4402
Agency Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 2
Current Phase
Design
Completion Date
2032-08-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4402
Reporting Period
202601
Managing Agency
DDC
Pid
4402
Agency Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 2
Current Phase
Design
Completion Date
2032-08-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4402
Reporting Period
202605
Managing Agency
DDC
Pid
4402
Agency Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 2
Current Phase
Design
Completion Date
2032-08-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4403
Reporting Period
202305
Managing Agency
DDC
Pid
4403
Agency Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 3
Current Phase
Design
Completion Date
2032-08-30T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4403
Reporting Period
202309
Managing Agency
DDC
Pid
4403
Agency Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 3
Current Phase
Design
Completion Date
2032-08-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4403
Reporting Period
202401
Managing Agency
DDC
Pid
4403
Agency Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 3
Current Phase
Design
Completion Date
2032-08-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4403
Reporting Period
202405
Managing Agency
DDC
Pid
4403
Agency Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 3
Current Phase
Design
Completion Date
2032-08-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4403
Reporting Period
202409
Managing Agency
DDC
Pid
4403
Agency Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 3
Current Phase
Design
Completion Date
2032-08-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4403
Reporting Period
202501
Managing Agency
DDC
Pid
4403
Agency Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 3
Current Phase
Design
Completion Date
2032-08-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4403
Reporting Period
202505
Managing Agency
DDC
Pid
4403
Agency Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 3
Current Phase
Design
Completion Date
2034-08-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
713
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4403
Reporting Period
202509
Managing Agency
DDC
Pid
4403
Agency Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 3
Current Phase
Design
Completion Date
2034-08-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4403
Reporting Period
202601
Managing Agency
DDC
Pid
4403
Agency Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 3
Current Phase
Design
Completion Date
2034-08-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4403
Reporting Period
202605
Managing Agency
DDC
Pid
4403
Agency Project Name
RECONSTRUCTION OF QUEENS BLVD - PHASE 3
Current Phase
Design
Completion Date
2034-08-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4404
Reporting Period
202305
Managing Agency
DDC
Pid
4404
Agency Project Name
VIT CLAY PIPE SEWERS - STATEN ISLAND
Current Phase
Construction Procurement
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4404
Reporting Period
202309
Managing Agency
DDC
Pid
4404
Agency Project Name
VIT CLAY PIPE SEWERS - STATEN ISLAND
Current Phase
Construction Procurement
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4404
Reporting Period
202401
Managing Agency
DDC
Pid
4404
Agency Project Name
VIT CLAY PIPE SEWERS - STATEN ISLAND
Current Phase
Construction Procurement
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4404
Reporting Period
202405
Managing Agency
DDC
Pid
4404
Agency Project Name
VIT CLAY PIPE SEWERS - STATEN ISLAND
Current Phase
Construction Procurement
Completion Date Type
Forecast
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4404
Reporting Period
202409
Managing Agency
DDC
Pid
4404
Agency Project Name
VIT CLAY PIPE SEWERS - STATEN ISLAND
Current Phase
Construction Procurement
Completion Date
2017-06-26T00:00:00.000
Completion Date Type
Actual
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4405
Reporting Period
202305
Managing Agency
DDC
Pid
4405
Agency Project Name
RECONSTRUCTION OF EXISTING SEWERS, STATEN ISLAND
Current Phase
Construction Procurement
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4405
Reporting Period
202309
Managing Agency
DDC
Pid
4405
Agency Project Name
RECONSTRUCTION OF EXISTING SEWERS, STATEN ISLAND
Current Phase
Construction Procurement
Completion Date Type
Forecast
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4405
Reporting Period
202401
Managing Agency
DDC
Pid
4405
Agency Project Name
RECONSTRUCTION OF EXISTING SEWERS, STATEN ISLAND
Current Phase
Construction Procurement
Completion Date Type
Forecast
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4405
Reporting Period
202405
Managing Agency
DDC
Pid
4405
Agency Project Name
RECONSTRUCTION OF EXISTING SEWERS, STATEN ISLAND
Current Phase
Construction Procurement
Completion Date Type
Forecast
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4405
Reporting Period
202409
Managing Agency
DDC
Pid
4405
Agency Project Name
RECONSTRUCTION OF EXISTING SEWERS, STATEN ISLAND
Current Phase
Construction Procurement
Completion Date
2019-07-14T00:00:00.000
Completion Date Type
Actual
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4406
Reporting Period
202305
Managing Agency
DDC
Pid
4406
Agency Project Name
Water Main Lining Contract, Citywide
Current Phase
Construction
Completion Date
2024-03-15T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4406
Reporting Period
202309
Managing Agency
DDC
Pid
4406
Agency Project Name
Water Main Lining Contract, Citywide
Current Phase
Construction
Completion Date
2024-03-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4406
Reporting Period
202401
Managing Agency
DDC
Pid
4406
Agency Project Name
Water Main Lining Contract, Citywide
Current Phase
Construction
Completion Date
2024-03-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4406
Reporting Period
202405
Managing Agency
DDC
Pid
4406
Agency Project Name
Water Main Lining Contract, Citywide
Current Phase
Construction
Completion Date
2025-03-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
365
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4406
Reporting Period
202409
Managing Agency
DDC
Pid
4406
Agency Project Name
Water Main Lining Contract, Citywide
Current Phase
Construction
Completion Date
2025-03-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4406
Reporting Period
202501
Managing Agency
DDC
Pid
4406
Agency Project Name
Water Main Lining Contract, Citywide
Current Phase
Construction
Completion Date
2025-03-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4406
Reporting Period
202505
Managing Agency
DDC
Pid
4406
Agency Project Name
Water Main Lining Contract, Citywide
Current Phase
Construction
Completion Date
2026-03-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
365
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4406
Reporting Period
202509
Managing Agency
DDC
Pid
4406
Agency Project Name
Water Main Lining Contract, Citywide
Current Phase
Close-out
Completion Date
2025-03-11T00:00:00.000
Completion Date Type
Actual
Variance Day
-369
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4407
Reporting Period
202305
Managing Agency
DDC
Pid
4407
Agency Project Name
WATER MAIN REPLACEMENT IN 222 STREET, QUEENS
Current Phase
Design
Completion Date
2029-07-13T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4407
Reporting Period
202309
Managing Agency
DDC
Pid
4407
Agency Project Name
WATER MAIN REPLACEMENT IN 222 STREET, QUEENS
Current Phase
Design
Completion Date
2029-07-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4407
Reporting Period
202401
Managing Agency
DDC
Pid
4407
Agency Project Name
WATER MAIN REPLACEMENT IN 222 STREET, QUEENS
Current Phase
Design
Completion Date
2029-07-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4407
Reporting Period
202405
Managing Agency
DDC
Pid
4407
Agency Project Name
WATER MAIN REPLACEMENT IN 222 STREET, QUEENS
Current Phase
Design
Completion Date
2030-07-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
365
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4407
Reporting Period
202409
Managing Agency
DDC
Pid
4407
Agency Project Name
WATER MAIN REPLACEMENT IN 222 STREET, QUEENS
Current Phase
Design
Completion Date
2030-07-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4407
Reporting Period
202501
Managing Agency
DDC
Pid
4407
Agency Project Name
WATER MAIN REPLACEMENT IN 222 STREET, QUEENS
Current Phase
Design
Completion Date
2030-07-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4407
Reporting Period
202505
Managing Agency
DDC
Pid
4407
Agency Project Name
WATER MAIN REPLACEMENT IN 222 STREET, QUEENS
Current Phase
Design
Completion Date
2030-07-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4407
Reporting Period
202509
Managing Agency
DDC
Pid
4407
Agency Project Name
WATER MAIN REPLACEMENT IN 222 STREET, QUEENS
Current Phase
Design
Completion Date
2030-07-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4407
Reporting Period
202601
Managing Agency
DDC
Pid
4407
Agency Project Name
WATER MAIN REPLACEMENT IN 222 STREET, QUEENS
Current Phase
Design
Completion Date
2030-07-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4407
Reporting Period
202605
Managing Agency
DDC
Pid
4407
Agency Project Name
WATER MAIN REPLACEMENT IN 222 STREET, QUEENS
Current Phase
Design
Completion Date
2030-07-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4408
Reporting Period
202305
Managing Agency
DDC
Pid
4408
Agency Project Name
Water Main work in Central Park West between West 81st Street and West 85th Street and other locations
Current Phase
Design
Completion Date
2028-04-10T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4408
Reporting Period
202309
Managing Agency
DDC
Pid
4408
Agency Project Name
Water Main work in Central Park West between West 81st Street and West 85th Street and other locations
Current Phase
Design
Completion Date
2028-04-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4408
Reporting Period
202401
Managing Agency
DDC
Pid
4408
Agency Project Name
Water Main work in Central Park West between West 81st Street and West 85th Street and other locations
Current Phase
Design
Completion Date
2028-04-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4408
Reporting Period
202405
Managing Agency
DDC
Pid
4408
Agency Project Name
Water Main work in Central Park West between West 81st Street and West 85th Street and other locations
Current Phase
Design
Completion Date
2028-04-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000