Capital Projects Dashboard - Citywide Schedule History and Variance

This is the history all agency reported forecasts/actual project completion dates. Each row is the snapshot of data taken on each reporting period. The 'completion date type' column shows if the 'completion date' is either a forecast or actual date. Over time, a project would have one or more forecasted completion dates before it is actually completed. The 'variance' is the day difference between 'completion date' of each row and its prior reporting period. This dataset is part of the Capital Projects Dashboard.

City Government Mayor's Office of Operations (OPS) Dataset 95tx-snak 10 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4445
Reporting Period
202605
Managing Agency
DDC
Pid
4445
Agency Project Name
FY24 Non-Standard Pedestrian Ramp Installations - Brooklyn and Staten Island
Current Phase
Design
Completion Date
2029-04-22T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4446
Reporting Period
202309
Managing Agency
DDC
Pid
4446
Agency Project Name
FY24 Non-Standard Pedestrian Ramp Installations - Manhattan, Bronx, and Queens
Current Phase
Pre-Design
Completion Date
2028-11-08T00:00:00.000
Completion Date Type
Forecast
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4446
Reporting Period
202401
Managing Agency
DDC
Pid
4446
Agency Project Name
FY24 Non-Standard Pedestrian Ramp Installations - Manhattan, Bronx, and Queens
Current Phase
Pre-Design
Completion Date
2028-11-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4446
Reporting Period
202405
Managing Agency
DDC
Pid
4446
Agency Project Name
FY24 Non-Standard Pedestrian Ramp Installations - Manhattan, Bronx, and Queens
Current Phase
Pre-Design
Completion Date
2028-11-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4446
Reporting Period
202409
Managing Agency
DDC
Pid
4446
Agency Project Name
FY24 Non-Standard Pedestrian Ramp Installations - Manhattan, Bronx, and Queens
Current Phase
Design
Completion Date
2029-06-07T00:00:00.000
Completion Date Type
Forecast
Variance Day
211
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4446
Reporting Period
202501
Managing Agency
DDC
Pid
4446
Agency Project Name
FY24 Non-Standard Pedestrian Ramp Installations - Manhattan, Bronx, and Queens
Current Phase
Design
Completion Date
2029-06-07T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4446
Reporting Period
202505
Managing Agency
DDC
Pid
4446
Agency Project Name
FY24 Non-Standard Pedestrian Ramp Installations - Manhattan, Bronx, and Queens
Current Phase
Design
Completion Date
2029-06-07T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4446
Reporting Period
202509
Managing Agency
DDC
Pid
4446
Agency Project Name
FY24 Non-Standard Pedestrian Ramp Installations - Manhattan, Bronx, and Queens
Current Phase
Design
Completion Date
2029-06-07T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4446
Reporting Period
202601
Managing Agency
DDC
Pid
4446
Agency Project Name
FY24 Non-Standard Pedestrian Ramp Installations - Manhattan, Bronx, and Queens
Current Phase
Design
Completion Date
2029-06-07T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4446
Reporting Period
202605
Managing Agency
DDC
Pid
4446
Agency Project Name
FY24 Non-Standard Pedestrian Ramp Installations - Manhattan, Bronx, and Queens
Current Phase
Design
Completion Date
2029-06-07T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4447
Reporting Period
202309
Managing Agency
DDC
Pid
4447
Agency Project Name
Pedestrian Ramp Upgrades at 90 non-standard locations in Brooklyn and Queens.
Current Phase
Pre-Design
Completion Date
2028-08-22T00:00:00.000
Completion Date Type
Forecast
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4447
Reporting Period
202401
Managing Agency
DDC
Pid
4447
Agency Project Name
Pedestrian Ramp Upgrades at 90 non-standard locations in Brooklyn and Queens.
Current Phase
Pre-Design
Completion Date
2028-08-22T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4447
Reporting Period
202405
Managing Agency
DDC
Pid
4447
Agency Project Name
Pedestrian Ramp Upgrades at 90 non-standard locations in Brooklyn and Queens.
Current Phase
Design
Completion Date
2028-08-22T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4447
Reporting Period
202409
Managing Agency
DDC
Pid
4447
Agency Project Name
Pedestrian Ramp Upgrades at 90 non-standard locations in Brooklyn and Queens.
Current Phase
Design
Completion Date
2028-08-22T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4447
Reporting Period
202501
Managing Agency
DDC
Pid
4447
Agency Project Name
Pedestrian Ramp Upgrades at 90 non-standard locations in Brooklyn and Queens.
Current Phase
Design
Completion Date
2028-08-22T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4447
Reporting Period
202505
Managing Agency
DDC
Pid
4447
Agency Project Name
Pedestrian Ramp Upgrades at 90 non-standard locations in Brooklyn and Queens.
Current Phase
Design
Completion Date
2028-08-22T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4447
Reporting Period
202509
Managing Agency
DDC
Pid
4447
Agency Project Name
Pedestrian Ramp Upgrades at 90 non-standard locations in Brooklyn and Queens.
Current Phase
Design
Completion Date
2029-06-27T00:00:00.000
Completion Date Type
Forecast
Variance Day
309
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4447
Reporting Period
202601
Managing Agency
DDC
Pid
4447
Agency Project Name
Pedestrian Ramp Upgrades at 90 non-standard locations in Brooklyn and Queens.
Current Phase
Design
Completion Date
2029-06-27T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4447
Reporting Period
202605
Managing Agency
DDC
Pid
4447
Agency Project Name
Pedestrian Ramp Upgrades at 90 non-standard locations in Brooklyn and Queens.
Current Phase
Design
Completion Date
2029-06-27T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4448
Reporting Period
202309
Managing Agency
DDC
Pid
4448
Agency Project Name
HWPR24 Series Standard Ped Ramp Upgrades
Current Phase
Design
Completion Date
2027-05-19T00:00:00.000
Completion Date Type
Forecast
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4448
Reporting Period
202401
Managing Agency
DDC
Pid
4448
Agency Project Name
HWPR24 Series Standard Ped Ramp Upgrades
Current Phase
Design
Completion Date
2027-05-19T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4448
Reporting Period
202405
Managing Agency
DDC
Pid
4448
Agency Project Name
HWPR24 Series Standard Ped Ramp Upgrades
Current Phase
Construction Procurement
Completion Date
2027-01-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
-124
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4448
Reporting Period
202409
Managing Agency
DDC
Pid
4448
Agency Project Name
HWPR24 Series Standard Ped Ramp Upgrades
Current Phase
Construction Procurement
Completion Date
2027-01-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4448
Reporting Period
202501
Managing Agency
DDC
Pid
4448
Agency Project Name
HWPR24 Series Standard Ped Ramp Upgrades
Current Phase
Construction Procurement
Completion Date
2027-05-04T00:00:00.000
Completion Date Type
Forecast
Variance Day
109
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4448
Reporting Period
202505
Managing Agency
DDC
Pid
4448
Agency Project Name
HWPR24 Series Standard Ped Ramp Upgrades
Current Phase
Construction Procurement
Completion Date
2027-05-04T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4448
Reporting Period
202509
Managing Agency
DDC
Pid
4448
Agency Project Name
HWPR24 Series Standard Ped Ramp Upgrades
Current Phase
Construction
Completion Date
2027-08-03T00:00:00.000
Completion Date Type
Forecast
Variance Day
91
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4448
Reporting Period
202601
Managing Agency
DDC
Pid
4448
Agency Project Name
HWPR24 Series Standard Ped Ramp Upgrades
Current Phase
Construction
Completion Date
2027-08-03T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4448
Reporting Period
202605
Managing Agency
DDC
Pid
4448
Agency Project Name
HWPR24 Series Standard Ped Ramp Upgrades
Current Phase
Construction
Completion Date
2027-08-03T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4449
Reporting Period
202309
Managing Agency
DDC
Pid
4449
Agency Project Name
HWPR24 Series Standard Pedestrian Ramp Upgrades
Current Phase
Design
Completion Date
2027-05-29T00:00:00.000
Completion Date Type
Forecast
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4449
Reporting Period
202401
Managing Agency
DDC
Pid
4449
Agency Project Name
HWPR24 Series Standard Pedestrian Ramp Upgrades
Current Phase
Design
Completion Date
2027-05-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4449
Reporting Period
202405
Managing Agency
DDC
Pid
4449
Agency Project Name
HWPR24 Series Standard Pedestrian Ramp Upgrades
Current Phase
Construction Procurement
Completion Date
2027-05-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4449
Reporting Period
202409
Managing Agency
DDC
Pid
4449
Agency Project Name
HWPR24 Series Standard Pedestrian Ramp Upgrades
Current Phase
Construction Procurement
Completion Date
2027-05-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4449
Reporting Period
202501
Managing Agency
DDC
Pid
4449
Agency Project Name
HWPR24 Series Standard Pedestrian Ramp Upgrades
Current Phase
Construction Procurement
Completion Date
2027-05-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4449
Reporting Period
202505
Managing Agency
DDC
Pid
4449
Agency Project Name
HWPR24 Series Standard Pedestrian Ramp Upgrades
Current Phase
Construction Procurement
Completion Date
2028-04-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
320
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4449
Reporting Period
202509
Managing Agency
DDC
Pid
4449
Agency Project Name
HWPR24 Series Standard Pedestrian Ramp Upgrades
Current Phase
Construction Procurement
Completion Date
2028-04-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4449
Reporting Period
202601
Managing Agency
DDC
Pid
4449
Agency Project Name
HWPR24 Series Standard Pedestrian Ramp Upgrades
Current Phase
Construction Procurement
Completion Date
2028-06-03T00:00:00.000
Completion Date Type
Forecast
Variance Day
51
Reason For Forecast Completion Change
PROJECT DELAYED RESULTING FROM CONTRACTOR DEFAULT
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4449
Reporting Period
202605
Managing Agency
DDC
Pid
4449
Agency Project Name
HWPR24 Series Standard Pedestrian Ramp Upgrades
Current Phase
Construction
Completion Date
2028-06-03T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4450
Reporting Period
202309
Managing Agency
DDC
Pid
4450
Agency Project Name
This project will add safety and transit access improvements at the intersection of White Plains Road and Mace Avenue. This project will take advantage of work already planned in DEP’s HED-581 project to replace distribution water mains in Mace Ave.
Current Phase
Pre-Design
Completion Date
2028-02-09T00:00:00.000
Completion Date Type
Forecast
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4450
Reporting Period
202401
Managing Agency
DDC
Pid
4450
Agency Project Name
This project will add safety and transit access improvements at the intersection of White Plains Road and Mace Avenue. This project will take advantage of work already planned in DEP’s HED-581 project to replace distribution water mains in Mace Ave.
Current Phase
Pre-Design
Completion Date
2028-02-09T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4450
Reporting Period
202405
Managing Agency
DDC
Pid
4450
Agency Project Name
This project will add safety and transit access improvements at the intersection of White Plains Road and Mace Avenue. This project will take advantage of work already planned in DEP’s HED-581 project to replace distribution water mains in Mace Ave.
Current Phase
Design
Completion Date
2028-08-16T00:00:00.000
Completion Date Type
Forecast
Variance Day
189
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4450
Reporting Period
202409
Managing Agency
DDC
Pid
4450
Agency Project Name
This project will add safety and transit access improvements at the intersection of White Plains Road and Mace Avenue. This project will take advantage of work already planned in DEP’s HED-581 project to replace distribution water mains in Mace Ave.
Current Phase
Design
Completion Date
2028-08-16T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4450
Reporting Period
202501
Managing Agency
DDC
Pid
4450
Agency Project Name
This project will add safety and transit access improvements at the intersection of White Plains Road and Mace Avenue. This project will take advantage of work already planned in DEP’s HED-581 project to replace distribution water mains in Mace Ave.
Current Phase
Design
Completion Date
2028-08-16T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4450
Reporting Period
202505
Managing Agency
DDC
Pid
4450
Agency Project Name
This project will add safety and transit access improvements at the intersection of White Plains Road and Mace Avenue. This project will take advantage of work already planned in DEP’s HED-581 project to replace distribution water mains in Mace Ave.
Current Phase
Design
Completion Date
2028-08-16T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4450
Reporting Period
202509
Managing Agency
DDC
Pid
4450
Agency Project Name
This project will add safety and transit access improvements at the intersection of White Plains Road and Mace Avenue. This project will take advantage of work already planned in DEP’s HED-581 project to replace distribution water mains in Mace Ave.
Current Phase
Design
Completion Date
2028-08-16T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4450
Reporting Period
202601
Managing Agency
DDC
Pid
4450
Agency Project Name
This project will add safety and transit access improvements at the intersection of White Plains Road and Mace Avenue. This project will take advantage of work already planned in DEP’s HED-581 project to replace distribution water mains in Mace Ave.
Current Phase
Design
Completion Date
2028-08-16T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4450
Reporting Period
202605
Managing Agency
DDC
Pid
4450
Agency Project Name
This project will add safety and transit access improvements at the intersection of White Plains Road and Mace Avenue. This project will take advantage of work already planned in DEP’s HED-581 project to replace distribution water mains in Mace Ave.
Current Phase
Design
Completion Date
2029-08-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
363
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO BUDGETARY CONSTRAINTS
Data Date
2026-06-23T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4451
Reporting Period
202309
Managing Agency
DDC
Pid
4451
Agency Project Name
HVAC System Replacement
Current Phase
Pre-Design
Completion Date
2027-05-05T00:00:00.000
Completion Date Type
Forecast
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4451
Reporting Period
202401
Managing Agency
DDC
Pid
4451
Agency Project Name
HVAC System Replacement
Current Phase
Pre-Design
Completion Date
2027-05-05T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4451
Reporting Period
202405
Managing Agency
DDC
Pid
4451
Agency Project Name
HVAC System Replacement
Current Phase
Pre-Design
Completion Date
2027-05-05T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4451
Reporting Period
202409
Managing Agency
DDC
Pid
4451
Agency Project Name
HVAC System Replacement
Current Phase
Design
Completion Date
2027-09-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
148
Data Date
2024-11-07T00:00:00.000