Capital Projects Dashboard - Citywide Schedule History and Variance

This is the history all agency reported forecasts/actual project completion dates. Each row is the snapshot of data taken on each reporting period. The 'completion date type' column shows if the 'completion date' is either a forecast or actual date. Over time, a project would have one or more forecasted completion dates before it is actually completed. The 'variance' is the day difference between 'completion date' of each row and its prior reporting period. This dataset is part of the Capital Projects Dashboard.

City Government Mayor's Office of Operations (OPS) Dataset 95tx-snak 10 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 5481
Reporting Period
202409
Managing Agency
DDC
Pid
5481
Agency Project Name
Bowne House Interior Renovation
Current Phase
Design
Completion Date
2027-07-19T00:00:00.000
Completion Date Type
Forecast
Variance Day
70
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO BUDGETARY CONSTRAINTS
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 5481
Reporting Period
202501
Managing Agency
DDC
Pid
5481
Agency Project Name
Bowne House Interior Renovation
Current Phase
Design
Completion Date
2027-07-19T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 5481
Reporting Period
202505
Managing Agency
DDC
Pid
5481
Agency Project Name
Bowne House Interior Renovation
Current Phase
Design
Completion Date
2028-01-21T00:00:00.000
Completion Date Type
Forecast
Variance Day
186
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 5481
Reporting Period
202509
Managing Agency
DDC
Pid
5481
Agency Project Name
Bowne House Interior Renovation
Current Phase
Design
Completion Date
2028-01-21T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 5481
Reporting Period
202601
Managing Agency
DDC
Pid
5481
Agency Project Name
Bowne House Interior Renovation
Current Phase
Design
Completion Date
2028-04-21T00:00:00.000
Completion Date Type
Forecast
Variance Day
91
Reason For Forecast Completion Change
PROJECT DELAYED PENDING RESOLUTION OF LEGAL ISSUES
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 5481
Reporting Period
202605
Managing Agency
DDC
Pid
5481
Agency Project Name
Bowne House Interior Renovation
Current Phase
Construction Procurement
Completion Date
2028-04-21T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 5482
Reporting Period
202405
Managing Agency
DDC
Pid
5482
Agency Project Name
Southeast Queens Initiative Program
Current Phase
Design
Completion Date
2032-07-14T00:00:00.000
Completion Date Type
Forecast
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 5482
Reporting Period
202409
Managing Agency
DDC
Pid
5482
Agency Project Name
Southeast Queens Initiative Program
Current Phase
Design
Completion Date
2032-07-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 5482
Reporting Period
202501
Managing Agency
DDC
Pid
5482
Agency Project Name
Southeast Queens Initiative Program
Current Phase
Design
Completion Date
2032-07-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 5482
Reporting Period
202505
Managing Agency
DDC
Pid
5482
Agency Project Name
Southeast Queens Initiative Program
Current Phase
Construction Procurement
Completion Date
2032-07-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 5482
Reporting Period
202509
Managing Agency
DDC
Pid
5482
Agency Project Name
Southeast Queens Initiative Program
Current Phase
Construction Procurement
Completion Date
2032-07-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 5482
Reporting Period
202601
Managing Agency
DDC
Pid
5482
Agency Project Name
Southeast Queens Initiative Program
Current Phase
Construction Procurement
Completion Date
2032-07-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 5482
Reporting Period
202605
Managing Agency
DDC
Pid
5482
Agency Project Name
Southeast Queens Initiative Program
Current Phase
Construction Procurement
Completion Date
2032-07-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 5483
Reporting Period
202405
Managing Agency
DDC
Pid
5483
Agency Project Name
This study aims to provide solutions to mitigate flooding and sewer backups in the Stapleton & Clifton neighborhoods of Staten Island.
Current Phase
Design
Completion Date Type
Forecast
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 5483
Reporting Period
202409
Managing Agency
DDC
Pid
5483
Agency Project Name
This study aims to provide solutions to mitigate flooding and sewer backups in the Stapleton & Clifton neighborhoods of Staten Island.
Current Phase
Design
Completion Date
2029-06-25T00:00:00.000
Completion Date Type
Forecast
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 5483
Reporting Period
202501
Managing Agency
DDC
Pid
5483
Agency Project Name
This study aims to provide solutions to mitigate flooding and sewer backups in the Stapleton & Clifton neighborhoods of Staten Island.
Current Phase
Design
Completion Date
2029-06-25T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-03-03T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 5483
Reporting Period
202505
Managing Agency
DDC
Pid
5483
Agency Project Name
This study aims to provide solutions to mitigate flooding and sewer backups in the Stapleton & Clifton neighborhoods of Staten Island.
Current Phase
Design
Completion Date
2029-06-25T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-03-03T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 5483
Reporting Period
202509
Managing Agency
DDC
Pid
5483
Agency Project Name
This study aims to provide solutions to mitigate flooding and sewer backups in the Stapleton & Clifton neighborhoods of Staten Island.
Current Phase
Design
Completion Date Type
Forecast
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 5483
Reporting Period
202601
Managing Agency
DDC
Pid
5483
Agency Project Name
This study aims to provide solutions to mitigate flooding and sewer backups in the Stapleton & Clifton neighborhoods of Staten Island.
Current Phase
Design
Completion Date Type
Forecast
Data Date
2026-03-20T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 5483
Reporting Period
202605
Managing Agency
DDC
Pid
5483
Agency Project Name
This study aims to provide solutions to mitigate flooding and sewer backups in the Stapleton & Clifton neighborhoods of Staten Island.
Current Phase
Design
Completion Date Type
Forecast
Data Date
2026-03-20T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 5604
Reporting Period
202409
Managing Agency
DDC
Pid
5604
Agency Project Name
Emergency Sewer Lining Contract, Citywide
Current Phase
Construction Procurement
Completion Date
2026-06-30T00:00:00.000
Completion Date Type
Forecast
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 5604
Reporting Period
202501
Managing Agency
DDC
Pid
5604
Agency Project Name
Emergency Sewer Lining Contract, Citywide
Current Phase
Construction Procurement
Completion Date
2026-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 5604
Reporting Period
202505
Managing Agency
DDC
Pid
5604
Agency Project Name
Emergency Sewer Lining Contract, Citywide
Current Phase
Construction Procurement
Completion Date
2026-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 5604
Reporting Period
202509
Managing Agency
DDC
Pid
5604
Agency Project Name
Emergency Sewer Lining Contract, Citywide
Current Phase
Construction Procurement
Completion Date
2026-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 5605
Reporting Period
202409
Managing Agency
DDC
Pid
5605
Agency Project Name
Reconstruction of Ave J and E 81st Street.
Current Phase
Design
Completion Date
2029-04-29T00:00:00.000
Completion Date Type
Forecast
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 5605
Reporting Period
202501
Managing Agency
DDC
Pid
5605
Agency Project Name
Reconstruction of Ave J and E 81st Street.
Current Phase
Design
Completion Date
2029-04-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 5605
Reporting Period
202505
Managing Agency
DDC
Pid
5605
Agency Project Name
Reconstruction of Ave J and E 81st Street.
Current Phase
Design
Completion Date
2029-04-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 5605
Reporting Period
202509
Managing Agency
DDC
Pid
5605
Agency Project Name
Reconstruction of Ave J and E 81st Street.
Current Phase
Design
Completion Date
2029-10-12T00:00:00.000
Completion Date Type
Forecast
Variance Day
166
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 5605
Reporting Period
202601
Managing Agency
DDC
Pid
5605
Agency Project Name
Reconstruction of Ave J and E 81st Street.
Current Phase
Design
Completion Date
2029-10-12T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 5605
Reporting Period
202605
Managing Agency
DDC
Pid
5605
Agency Project Name
Reconstruction of Ave J and E 81st Street.
Current Phase
Design
Completion Date
2029-12-20T00:00:00.000
Completion Date Type
Forecast
Variance Day
69
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO BUDGETARY CONSTRAINTS
Data Date
2026-06-23T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 5606
Reporting Period
202409
Managing Agency
DDC
Pid
5606
Agency Project Name
North Brooklyn Pedestrian Safety and Public Space Improvements
Current Phase
Design
Completion Date
2029-06-19T00:00:00.000
Completion Date Type
Forecast
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 5606
Reporting Period
202501
Managing Agency
DDC
Pid
5606
Agency Project Name
North Brooklyn Pedestrian Safety and Public Space Improvements
Current Phase
Design
Completion Date
2030-06-19T00:00:00.000
Completion Date Type
Forecast
Variance Day
365
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO BUDGETARY CONSTRAINTS
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 5606
Reporting Period
202505
Managing Agency
DDC
Pid
5606
Agency Project Name
North Brooklyn Pedestrian Safety and Public Space Improvements
Current Phase
Design
Completion Date
2029-07-19T00:00:00.000
Completion Date Type
Forecast
Variance Day
-335
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 5606
Reporting Period
202509
Managing Agency
DDC
Pid
5606
Agency Project Name
North Brooklyn Pedestrian Safety and Public Space Improvements
Current Phase
Design
Completion Date
2029-07-19T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 5606
Reporting Period
202601
Managing Agency
DDC
Pid
5606
Agency Project Name
North Brooklyn Pedestrian Safety and Public Space Improvements
Current Phase
Design
Completion Date
2029-07-19T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 5606
Reporting Period
202605
Managing Agency
DDC
Pid
5606
Agency Project Name
North Brooklyn Pedestrian Safety and Public Space Improvements
Current Phase
Design
Completion Date
2030-02-19T00:00:00.000
Completion Date Type
Forecast
Variance Day
215
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO BUDGETARY CONSTRAINTS
Data Date
2026-06-23T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 5607
Reporting Period
202409
Managing Agency
DDC
Pid
5607
Agency Project Name
FY24 Prior Notice Sidewalks - Bronx
Current Phase
Design
Completion Date
2027-01-10T00:00:00.000
Completion Date Type
Forecast
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 5607
Reporting Period
202501
Managing Agency
DDC
Pid
5607
Agency Project Name
FY24 Prior Notice Sidewalks - Bronx
Current Phase
Construction Procurement
Completion Date
2027-01-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 5607
Reporting Period
202505
Managing Agency
DDC
Pid
5607
Agency Project Name
FY24 Prior Notice Sidewalks - Bronx
Current Phase
Construction Procurement
Completion Date
2027-01-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 5607
Reporting Period
202509
Managing Agency
DDC
Pid
5607
Agency Project Name
FY24 Prior Notice Sidewalks - Bronx
Current Phase
Construction
Completion Date
2027-01-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 5607
Reporting Period
202601
Managing Agency
DDC
Pid
5607
Agency Project Name
FY24 Prior Notice Sidewalks - Bronx
Current Phase
Construction
Completion Date
2027-01-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 5607
Reporting Period
202605
Managing Agency
DDC
Pid
5607
Agency Project Name
FY24 Prior Notice Sidewalks - Bronx
Current Phase
Construction
Completion Date
2027-01-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 5608
Reporting Period
202409
Managing Agency
DDC
Pid
5608
Agency Project Name
This project will reconstruct the E 169th Street step street.
Current Phase
Design
Completion Date
2029-08-14T00:00:00.000
Completion Date Type
Forecast
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 5608
Reporting Period
202501
Managing Agency
DDC
Pid
5608
Agency Project Name
This project will reconstruct the E 169th Street step street.
Current Phase
Design
Completion Date
2029-08-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 5608
Reporting Period
202505
Managing Agency
DDC
Pid
5608
Agency Project Name
This project will reconstruct the E 169th Street step street.
Current Phase
Design
Completion Date
2029-08-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 5608
Reporting Period
202509
Managing Agency
DDC
Pid
5608
Agency Project Name
This project will reconstruct the E 169th Street step street.
Current Phase
Design
Completion Date
2029-08-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 5608
Reporting Period
202601
Managing Agency
DDC
Pid
5608
Agency Project Name
This project will reconstruct the E 169th Street step street.
Current Phase
Design
Completion Date
2029-08-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 5608
Reporting Period
202605
Managing Agency
DDC
Pid
5608
Agency Project Name
This project will reconstruct the E 169th Street step street.
Current Phase
Design
Completion Date
2029-08-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 5609
Reporting Period
202409
Managing Agency
DDC
Pid
5609
Agency Project Name
Kings Bay Library Upgrade
Current Phase
Design
Completion Date
2027-04-26T00:00:00.000
Completion Date Type
Forecast
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 5609
Reporting Period
202501
Managing Agency
DDC
Pid
5609
Agency Project Name
Kings Bay Library Upgrade
Current Phase
Design
Completion Date
2027-04-26T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000