Capital Projects Dashboard - Citywide Schedule History and Variance

This is the history all agency reported forecasts/actual project completion dates. Each row is the snapshot of data taken on each reporting period. The 'completion date type' column shows if the 'completion date' is either a forecast or actual date. Over time, a project would have one or more forecasted completion dates before it is actually completed. The 'variance' is the day difference between 'completion date' of each row and its prior reporting period. This dataset is part of the Capital Projects Dashboard.

City Government Mayor's Office of Operations (OPS) Dataset 95tx-snak 10 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202401
Reporting Period: 202401 • Managing Agency: DEP • Pid: 4758
Reporting Period
202401
Managing Agency
DEP
Pid
4758
Agency Project Name
GI-CD11
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2024-05-08T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DEP • Pid: 4758
Reporting Period
202405
Managing Agency
DEP
Pid
4758
Agency Project Name
GI-CD11
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2024-07-23T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DEP • Pid: 4758
Reporting Period
202409
Managing Agency
DEP
Pid
4758
Agency Project Name
GI-CD11
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2024-11-14T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DEP • Pid: 4758
Reporting Period
202501
Managing Agency
DEP
Pid
4758
Agency Project Name
GI-CD11
Current Phase
Construction Procurement
Completion Date Type
Forecast
Data Date
2025-03-07T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DEP • Pid: 4758
Reporting Period
202505
Managing Agency
DEP
Pid
4758
Agency Project Name
GI-CD11
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2025-06-20T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DEP • Pid: 4758
Reporting Period
202509
Managing Agency
DEP
Pid
4758
Agency Project Name
GI-CD11
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2025-11-05T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DEP • Pid: 4758
Reporting Period
202601
Managing Agency
DEP
Pid
4758
Agency Project Name
GI-CD11
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2026-04-23T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DEP • Pid: 4758
Reporting Period
202605
Managing Agency
DEP
Pid
4758
Agency Project Name
GI-CD11
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2026-06-26T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DEP • Pid: 4759
Reporting Period
202401
Managing Agency
DEP
Pid
4759
Agency Project Name
GI-CONS-3
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2024-05-08T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DEP • Pid: 4759
Reporting Period
202405
Managing Agency
DEP
Pid
4759
Agency Project Name
GI-CONS-3
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2024-07-23T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DEP • Pid: 4759
Reporting Period
202409
Managing Agency
DEP
Pid
4759
Agency Project Name
GI-CONS-3
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2024-11-14T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DEP • Pid: 4759
Reporting Period
202501
Managing Agency
DEP
Pid
4759
Agency Project Name
GI-CONS-3
Current Phase
Construction
Completion Date
2026-08-21T00:00:00.000
Completion Date Type
Forecast
Data Date
2025-03-07T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DEP • Pid: 4759
Reporting Period
202505
Managing Agency
DEP
Pid
4759
Agency Project Name
GI-CONS-3
Current Phase
Construction
Completion Date
2026-08-21T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-06-20T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DEP • Pid: 4759
Reporting Period
202509
Managing Agency
DEP
Pid
4759
Agency Project Name
GI-CONS-3
Current Phase
Construction
Completion Date
2026-08-21T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-11-05T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DEP • Pid: 4759
Reporting Period
202601
Managing Agency
DEP
Pid
4759
Agency Project Name
GI-CONS-3
Current Phase
Construction
Completion Date
2026-08-21T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-04-23T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DEP • Pid: 4759
Reporting Period
202605
Managing Agency
DEP
Pid
4759
Agency Project Name
GI-CONS-3
Current Phase
Close-out
Completion Date
2026-05-21T00:00:00.000
Completion Date Type
Actual
Variance Day
-92
Data Date
2026-06-26T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DEP • Pid: 4760
Reporting Period
202401
Managing Agency
DEP
Pid
4760
Agency Project Name
GI-CONS-4
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2024-05-08T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DEP • Pid: 4760
Reporting Period
202405
Managing Agency
DEP
Pid
4760
Agency Project Name
GI-CONS-4
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2024-07-23T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DEP • Pid: 4760
Reporting Period
202409
Managing Agency
DEP
Pid
4760
Agency Project Name
GI-CONS-4
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2024-11-14T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DEP • Pid: 4760
Reporting Period
202501
Managing Agency
DEP
Pid
4760
Agency Project Name
GI-CONS-4
Current Phase
Design
Completion Date Type
Forecast
Data Date
2025-03-07T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DEP • Pid: 4760
Reporting Period
202505
Managing Agency
DEP
Pid
4760
Agency Project Name
GI-CONS-4
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2025-06-20T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DEP • Pid: 4760
Reporting Period
202509
Managing Agency
DEP
Pid
4760
Agency Project Name
GI-CONS-4
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2025-11-05T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DEP • Pid: 4760
Reporting Period
202601
Managing Agency
DEP
Pid
4760
Agency Project Name
GI-CONS-4
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2026-04-23T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DEP • Pid: 4760
Reporting Period
202605
Managing Agency
DEP
Pid
4760
Agency Project Name
GI-CONS-4
Current Phase
Design
Completion Date
2030-05-31T00:00:00.000
Completion Date Type
Forecast
Data Date
2026-06-26T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DEP • Pid: 4761
Reporting Period
202401
Managing Agency
DEP
Pid
4761
Agency Project Name
GI-CONS-5
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2024-05-08T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DEP • Pid: 4761
Reporting Period
202405
Managing Agency
DEP
Pid
4761
Agency Project Name
GI-CONS-5
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2024-07-23T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DEP • Pid: 4761
Reporting Period
202409
Managing Agency
DEP
Pid
4761
Agency Project Name
GI-CONS-5
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2024-11-14T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DEP • Pid: 4761
Reporting Period
202501
Managing Agency
DEP
Pid
4761
Agency Project Name
GI-CONS-5
Current Phase
Construction Procurement
Completion Date
2027-03-01T00:00:00.000
Completion Date Type
Forecast
Data Date
2025-03-07T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DEP • Pid: 4761
Reporting Period
202505
Managing Agency
DEP
Pid
4761
Agency Project Name
GI-CONS-5
Current Phase
Construction Procurement
Completion Date
2027-03-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-06-20T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DEP • Pid: 4761
Reporting Period
202509
Managing Agency
DEP
Pid
4761
Agency Project Name
GI-CONS-5
Current Phase
Construction Procurement
Completion Date
2027-03-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-11-05T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DEP • Pid: 4761
Reporting Period
202601
Managing Agency
DEP
Pid
4761
Agency Project Name
GI-CONS-5
Current Phase
Construction Procurement
Completion Date
2027-03-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-04-23T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DEP • Pid: 4761
Reporting Period
202605
Managing Agency
DEP
Pid
4761
Agency Project Name
GI-CONS-5
Current Phase
Construction
Completion Date
2027-03-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-26T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DEP • Pid: 4762
Reporting Period
202401
Managing Agency
DEP
Pid
4762
Agency Project Name
GI-CONS-6
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2024-05-08T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DEP • Pid: 4762
Reporting Period
202405
Managing Agency
DEP
Pid
4762
Agency Project Name
GI-CONS-6
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2024-07-23T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DEP • Pid: 4762
Reporting Period
202409
Managing Agency
DEP
Pid
4762
Agency Project Name
GI-CONS-6
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2024-11-14T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DEP • Pid: 4762
Reporting Period
202501
Managing Agency
DEP
Pid
4762
Agency Project Name
GI-CONS-6
Current Phase
Design
Completion Date Type
Forecast
Data Date
2025-03-07T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DEP • Pid: 4762
Reporting Period
202505
Managing Agency
DEP
Pid
4762
Agency Project Name
GI-CONS-6
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2025-06-20T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DEP • Pid: 4762
Reporting Period
202509
Managing Agency
DEP
Pid
4762
Agency Project Name
GI-CONS-6
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2025-11-05T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DEP • Pid: 4762
Reporting Period
202601
Managing Agency
DEP
Pid
4762
Agency Project Name
GI-CONS-6
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2026-04-23T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DEP • Pid: 4762
Reporting Period
202605
Managing Agency
DEP
Pid
4762
Agency Project Name
GI-CONS-6
Current Phase
Design
Completion Date
2030-05-31T00:00:00.000
Completion Date Type
Forecast
Data Date
2026-06-26T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DEP • Pid: 4763
Reporting Period
202401
Managing Agency
DEP
Pid
4763
Agency Project Name
GI-CONS-7
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2024-05-08T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DEP • Pid: 4763
Reporting Period
202405
Managing Agency
DEP
Pid
4763
Agency Project Name
GI-CONS-7
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2024-07-23T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DEP • Pid: 4763
Reporting Period
202409
Managing Agency
DEP
Pid
4763
Agency Project Name
GI-CONS-7
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2024-11-14T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DEP • Pid: 4763
Reporting Period
202501
Managing Agency
DEP
Pid
4763
Agency Project Name
GI-CONS-7
Current Phase
Design
Completion Date Type
Forecast
Data Date
2025-03-07T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DEP • Pid: 4763
Reporting Period
202505
Managing Agency
DEP
Pid
4763
Agency Project Name
GI-CONS-7
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2025-06-20T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DEP • Pid: 4763
Reporting Period
202509
Managing Agency
DEP
Pid
4763
Agency Project Name
GI-CONS-7
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2025-11-05T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DEP • Pid: 4763
Reporting Period
202601
Managing Agency
DEP
Pid
4763
Agency Project Name
GI-CONS-7
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2026-04-23T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DEP • Pid: 4763
Reporting Period
202605
Managing Agency
DEP
Pid
4763
Agency Project Name
GI-CONS-7
Current Phase
Design
Completion Date
2030-05-31T00:00:00.000
Completion Date Type
Forecast
Data Date
2026-06-26T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DEP • Pid: 4764
Reporting Period
202401
Managing Agency
DEP
Pid
4764
Agency Project Name
Newtown Creek Gateway to Greenpoint
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2024-05-08T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DEP • Pid: 4764
Reporting Period
202405
Managing Agency
DEP
Pid
4764
Agency Project Name
Newtown Creek Gateway to Greenpoint
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2024-07-23T00:00:00.000