Capital Projects Dashboard - Citywide Schedule History and Variance

This is the history all agency reported forecasts/actual project completion dates. Each row is the snapshot of data taken on each reporting period. The 'completion date type' column shows if the 'completion date' is either a forecast or actual date. Over time, a project would have one or more forecasted completion dates before it is actually completed. The 'variance' is the day difference between 'completion date' of each row and its prior reporting period. This dataset is part of the Capital Projects Dashboard.

City Government Mayor's Office of Operations (OPS) Dataset 95tx-snak 10 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202505
Reporting Period: 202505 • Managing Agency: DCAS • Pid: 4684
Reporting Period
202505
Managing Agency
DCAS
Pid
4684
Agency Project Name
FDNY- Solar PV at FDNY Academy Building 12
Current Phase
Construction
Completion Date
2025-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-06-18T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DCAS • Pid: 4684
Reporting Period
202509
Managing Agency
DCAS
Pid
4684
Agency Project Name
FDNY- Solar PV at FDNY Academy Building 12
Current Phase
Construction
Completion Date
2026-06-30T00:00:00.000
Completion Date Type
Actual
Variance Day
365
Data Date
2025-11-17T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DCAS • Pid: 4685
Reporting Period
202401
Managing Agency
DCAS
Pid
4685
Agency Project Name
OCME Center for Forensic Science-Energy Efficiency Upgrades
Current Phase
Pre-Design
Completion Date
2026-12-30T00:00:00.000
Completion Date Type
Forecast
Data Date
2024-05-02T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DCAS • Pid: 4685
Reporting Period
202405
Managing Agency
DCAS
Pid
4685
Agency Project Name
OCME Center for Forensic Science-Energy Efficiency Upgrades
Current Phase
Pre-Design
Completion Date
2026-12-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-11T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DCAS • Pid: 4685
Reporting Period
202409
Managing Agency
DCAS
Pid
4685
Agency Project Name
OCME Center for Forensic Science-Energy Efficiency Upgrades
Current Phase
Construction Procurement
Completion Date
2026-12-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-01T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DCAS • Pid: 4685
Reporting Period
202501
Managing Agency
DCAS
Pid
4685
Agency Project Name
OCME Center for Forensic Science-Energy Efficiency Upgrades
Current Phase
Design
Completion Date
2026-12-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-03-04T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DCAS • Pid: 4685
Reporting Period
202505
Managing Agency
DCAS
Pid
4685
Agency Project Name
OCME Center for Forensic Science-Energy Efficiency Upgrades
Current Phase
Construction
Completion Date
2027-04-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
121
Data Date
2025-06-18T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DCAS • Pid: 4685
Reporting Period
202509
Managing Agency
DCAS
Pid
4685
Agency Project Name
OCME Center for Forensic Science-Energy Efficiency Upgrades
Current Phase
Construction
Completion Date
2027-04-30T00:00:00.000
Completion Date Type
Actual
Variance Day
0
Data Date
2025-11-17T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DCAS • Pid: 4686
Reporting Period
202401
Managing Agency
DCAS
Pid
4686
Agency Project Name
OCME Brooklyn Chief Medical Examiner Office
Current Phase
Pre-Design
Completion Date
2027-03-01T00:00:00.000
Completion Date Type
Forecast
Data Date
2024-05-02T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DCAS • Pid: 4686
Reporting Period
202405
Managing Agency
DCAS
Pid
4686
Agency Project Name
OCME Brooklyn Chief Medical Examiner Office
Current Phase
Pre-Design
Completion Date
2027-03-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-11T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DCAS • Pid: 4686
Reporting Period
202409
Managing Agency
DCAS
Pid
4686
Agency Project Name
OCME Brooklyn Chief Medical Examiner Office
Current Phase
Pre-Design
Completion Date
2027-03-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-01T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DCAS • Pid: 4686
Reporting Period
202501
Managing Agency
DCAS
Pid
4686
Agency Project Name
OCME Brooklyn Chief Medical Examiner Office
Current Phase
Pre-Design
Completion Date
2027-05-01T00:00:00.000
Completion Date Type
Actual
Variance Day
61
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2025-03-04T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DCAS • Pid: 4687
Reporting Period
202401
Managing Agency
DCAS
Pid
4687
Agency Project Name
OCME Queens Chief Medical Examiner-Energy Efficient upgrades
Current Phase
Pre-Design
Completion Date
2027-03-10T00:00:00.000
Completion Date Type
Forecast
Data Date
2024-05-02T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DCAS • Pid: 4687
Reporting Period
202405
Managing Agency
DCAS
Pid
4687
Agency Project Name
OCME Queens Chief Medical Examiner-Energy Efficient upgrades
Current Phase
Pre-Design
Completion Date
2027-03-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-11T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DCAS • Pid: 4687
Reporting Period
202409
Managing Agency
DCAS
Pid
4687
Agency Project Name
OCME Queens Chief Medical Examiner-Energy Efficient upgrades
Current Phase
Pre-Design
Completion Date
2027-03-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-01T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DCAS • Pid: 4687
Reporting Period
202501
Managing Agency
DCAS
Pid
4687
Agency Project Name
OCME Queens Chief Medical Examiner-Energy Efficient upgrades
Current Phase
Pre-Design
Completion Date
2027-03-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-03-04T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DCAS • Pid: 4687
Reporting Period
202505
Managing Agency
DCAS
Pid
4687
Agency Project Name
OCME Queens Chief Medical Examiner-Energy Efficient upgrades
Current Phase
Construction
Completion Date
2027-03-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-06-18T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DCAS • Pid: 4687
Reporting Period
202509
Managing Agency
DCAS
Pid
4687
Agency Project Name
OCME Queens Chief Medical Examiner-Energy Efficient upgrades
Current Phase
Construction
Completion Date
2027-03-10T00:00:00.000
Completion Date Type
Actual
Variance Day
0
Data Date
2025-11-17T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DCAS • Pid: 4688
Reporting Period
202401
Managing Agency
DCAS
Pid
4688
Agency Project Name
DER-SI Campus
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2024-05-02T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DCAS • Pid: 4688
Reporting Period
202405
Managing Agency
DCAS
Pid
4688
Agency Project Name
DER-SI Campus
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2024-07-11T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DCAS • Pid: 4688
Reporting Period
202409
Managing Agency
DCAS
Pid
4688
Agency Project Name
DER-SI Campus
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2024-11-01T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DCAS • Pid: 4688
Reporting Period
202501
Managing Agency
DCAS
Pid
4688
Agency Project Name
DER-SI Campus
Current Phase
Pre-Design
Completion Date
2028-03-01T00:00:00.000
Completion Date Type
Actual
Data Date
2025-03-04T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DCAS • Pid: 4689
Reporting Period
202401
Managing Agency
DCAS
Pid
4689
Agency Project Name
Building Maintenance Services (BMS) Facility Comprehensive Energy Upgrade
Current Phase
Pre-Design
Completion Date
2027-06-05T00:00:00.000
Completion Date Type
Forecast
Data Date
2024-05-02T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DCAS • Pid: 4689
Reporting Period
202405
Managing Agency
DCAS
Pid
4689
Agency Project Name
Building Maintenance Services (BMS) Facility Comprehensive Energy Upgrade
Current Phase
Pre-Design
Completion Date
2027-06-05T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-11T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DCAS • Pid: 4689
Reporting Period
202409
Managing Agency
DCAS
Pid
4689
Agency Project Name
Building Maintenance Services (BMS) Facility Comprehensive Energy Upgrade
Current Phase
Construction Procurement
Completion Date
2027-12-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
179
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION
Data Date
2024-11-01T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DCAS • Pid: 4689
Reporting Period
202501
Managing Agency
DCAS
Pid
4689
Agency Project Name
Building Maintenance Services (BMS) Facility Comprehensive Energy Upgrade
Current Phase
Design
Completion Date
2026-07-30T00:00:00.000
Completion Date Type
Actual
Variance Day
-489
Data Date
2025-03-04T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DCAS • Pid: 4690
Reporting Period
202401
Managing Agency
DCAS
Pid
4690
Agency Project Name
360 ADAMS ST - ADA IMPROVEMENTS
Current Phase
Construction Procurement
Completion Date
2028-01-25T00:00:00.000
Completion Date Type
Forecast
Data Date
2024-05-02T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DCAS • Pid: 4690
Reporting Period
202405
Managing Agency
DCAS
Pid
4690
Agency Project Name
360 ADAMS ST - ADA IMPROVEMENTS
Current Phase
Construction Procurement
Completion Date
2028-01-25T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-11T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DCAS • Pid: 4690
Reporting Period
202409
Managing Agency
DCAS
Pid
4690
Agency Project Name
360 ADAMS ST - ADA IMPROVEMENTS
Current Phase
Construction Procurement
Completion Date
2028-01-25T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-01T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DCAS • Pid: 4690
Reporting Period
202501
Managing Agency
DCAS
Pid
4690
Agency Project Name
360 ADAMS ST - ADA IMPROVEMENTS
Current Phase
Construction Procurement
Completion Date
2028-01-25T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-03-04T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DCAS • Pid: 4690
Reporting Period
202505
Managing Agency
DCAS
Pid
4690
Agency Project Name
360 ADAMS ST - ADA IMPROVEMENTS
Current Phase
Construction Procurement
Completion Date
2028-01-25T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-06-18T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DCAS • Pid: 4690
Reporting Period
202509
Managing Agency
DCAS
Pid
4690
Agency Project Name
360 ADAMS ST - ADA IMPROVEMENTS
Current Phase
Construction Procurement
Completion Date
2028-01-25T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-11-17T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DCAS • Pid: 4690
Reporting Period
202601
Managing Agency
DCAS
Pid
4690
Agency Project Name
360 ADAMS ST - ADA IMPROVEMENTS
Current Phase
Construction Procurement
Completion Date
2029-01-25T00:00:00.000
Completion Date Type
Forecast
Variance Day
366
Reason For Forecast Completion Change
PROJECT DELAYED PENDING APPROVAL OF NECESSARY PERMITS
Data Date
2026-04-15T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DCAS • Pid: 4690
Reporting Period
202605
Managing Agency
DCAS
Pid
4690
Agency Project Name
360 ADAMS ST - ADA IMPROVEMENTS
Current Phase
Construction Procurement
Completion Date
2029-01-25T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-05-28T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DCAS • Pid: 4691
Reporting Period
202401
Managing Agency
DCAS
Pid
4691
Agency Project Name
851 GRAND CONCOURSE - ADA COMPLIANCE
Current Phase
Design
Completion Date
2027-11-19T00:00:00.000
Completion Date Type
Forecast
Data Date
2024-05-02T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DCAS • Pid: 4691
Reporting Period
202405
Managing Agency
DCAS
Pid
4691
Agency Project Name
851 GRAND CONCOURSE - ADA COMPLIANCE
Current Phase
Design
Completion Date
2027-11-19T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-11T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DCAS • Pid: 4691
Reporting Period
202409
Managing Agency
DCAS
Pid
4691
Agency Project Name
851 GRAND CONCOURSE - ADA COMPLIANCE
Current Phase
Design
Completion Date
2027-11-19T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-01T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DCAS • Pid: 4691
Reporting Period
202501
Managing Agency
DCAS
Pid
4691
Agency Project Name
851 GRAND CONCOURSE - ADA COMPLIANCE
Current Phase
Design
Completion Date
2028-12-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
407
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2025-03-04T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DCAS • Pid: 4691
Reporting Period
202505
Managing Agency
DCAS
Pid
4691
Agency Project Name
851 GRAND CONCOURSE - ADA COMPLIANCE
Current Phase
Design
Completion Date
2028-12-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-06-18T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DCAS • Pid: 4691
Reporting Period
202509
Managing Agency
DCAS
Pid
4691
Agency Project Name
851 GRAND CONCOURSE - ADA COMPLIANCE
Current Phase
Design
Completion Date
2029-12-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
365
Data Date
2025-11-17T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DCAS • Pid: 4691
Reporting Period
202601
Managing Agency
DCAS
Pid
4691
Agency Project Name
851 GRAND CONCOURSE - ADA COMPLIANCE
Current Phase
Design
Completion Date
2029-12-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-04-15T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DCAS • Pid: 4691
Reporting Period
202605
Managing Agency
DCAS
Pid
4691
Agency Project Name
851 GRAND CONCOURSE - ADA COMPLIANCE
Current Phase
Design
Completion Date
2029-12-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-05-28T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DCAS • Pid: 4692
Reporting Period
202401
Managing Agency
DCAS
Pid
4692
Agency Project Name
215 E 161st 2nd Fl Court Room Conversion
Current Phase
Construction Procurement
Completion Date
2025-05-30T00:00:00.000
Completion Date Type
Forecast
Data Date
2024-05-02T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DCAS • Pid: 4692
Reporting Period
202405
Managing Agency
DCAS
Pid
4692
Agency Project Name
215 E 161st 2nd Fl Court Room Conversion
Current Phase
Construction Procurement
Completion Date
2025-05-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-11T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DCAS • Pid: 4692
Reporting Period
202409
Managing Agency
DCAS
Pid
4692
Agency Project Name
215 E 161st 2nd Fl Court Room Conversion
Current Phase
Construction
Completion Date
2025-05-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-01T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DCAS • Pid: 4692
Reporting Period
202501
Managing Agency
DCAS
Pid
4692
Agency Project Name
215 E 161st 2nd Fl Court Room Conversion
Current Phase
Construction
Completion Date
2025-07-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
61
Reason For Forecast Completion Change
PROJECT DELAYED PENDING APPROVAL OF NECESSARY PERMITS
Data Date
2025-03-04T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DCAS • Pid: 4692
Reporting Period
202505
Managing Agency
DCAS
Pid
4692
Agency Project Name
215 E 161st 2nd Fl Court Room Conversion
Current Phase
Construction
Completion Date
2025-12-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
153
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2025-06-18T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DCAS • Pid: 4692
Reporting Period
202509
Managing Agency
DCAS
Pid
4692
Agency Project Name
215 E 161st 2nd Fl Court Room Conversion
Current Phase
Construction
Completion Date
2026-02-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
33
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION
Data Date
2025-11-17T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DCAS • Pid: 4692
Reporting Period
202601
Managing Agency
DCAS
Pid
4692
Agency Project Name
215 E 161st 2nd Fl Court Room Conversion
Current Phase
Construction
Completion Date
2026-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
149
Data Date
2026-04-15T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DCAS • Pid: 4692
Reporting Period
202605
Managing Agency
DCAS
Pid
4692
Agency Project Name
215 E 161st 2nd Fl Court Room Conversion
Current Phase
Construction
Completion Date
2026-08-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
45
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION
Data Date
2026-05-28T00:00:00.000