Capital Projects Dashboard - Citywide Schedule History and Variance

This is the history all agency reported forecasts/actual project completion dates. Each row is the snapshot of data taken on each reporting period. The 'completion date type' column shows if the 'completion date' is either a forecast or actual date. Over time, a project would have one or more forecasted completion dates before it is actually completed. The 'variance' is the day difference between 'completion date' of each row and its prior reporting period. This dataset is part of the Capital Projects Dashboard.

City Government Mayor's Office of Operations (OPS) Dataset 95tx-snak 10 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 3858
Reporting Period
202509
Managing Agency
DDC
Pid
3858
Agency Project Name
Complex Upgrades Ped Ramps-Queens & Staten Island
Current Phase
Construction
Completion Date
2026-06-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 3858
Reporting Period
202601
Managing Agency
DDC
Pid
3858
Agency Project Name
Complex Upgrades Ped Ramps-Queens & Staten Island
Current Phase
Construction
Completion Date
2026-06-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 3858
Reporting Period
202605
Managing Agency
DDC
Pid
3858
Agency Project Name
Complex Upgrades Ped Ramps-Queens & Staten Island
Current Phase
Construction
Completion Date
2026-06-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3859
Reporting Period
202305
Managing Agency
DDC
Pid
3859
Agency Project Name
Complex Upgrades Ped Ramp - Queens
Current Phase
Design
Completion Date
2026-07-28T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3859
Reporting Period
202309
Managing Agency
DDC
Pid
3859
Agency Project Name
Complex Upgrades Ped Ramp - Queens
Current Phase
Design
Completion Date
2026-07-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3859
Reporting Period
202401
Managing Agency
DDC
Pid
3859
Agency Project Name
Complex Upgrades Ped Ramp - Queens
Current Phase
Design
Completion Date
2026-07-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3859
Reporting Period
202405
Managing Agency
DDC
Pid
3859
Agency Project Name
Complex Upgrades Ped Ramp - Queens
Current Phase
Construction Procurement
Completion Date
2026-09-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
49
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 3859
Reporting Period
202409
Managing Agency
DDC
Pid
3859
Agency Project Name
Complex Upgrades Ped Ramp - Queens
Current Phase
Construction Procurement
Completion Date
2026-11-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
60
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 3859
Reporting Period
202501
Managing Agency
DDC
Pid
3859
Agency Project Name
Complex Upgrades Ped Ramp - Queens
Current Phase
Construction
Completion Date
2027-01-12T00:00:00.000
Completion Date Type
Forecast
Variance Day
59
Reason For Forecast Completion Change
PROJECT DELAYED PENDING APPROVAL OF NECESSARY PERMITS
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 3859
Reporting Period
202505
Managing Agency
DDC
Pid
3859
Agency Project Name
Complex Upgrades Ped Ramp - Queens
Current Phase
Construction
Completion Date
2027-06-11T00:00:00.000
Completion Date Type
Forecast
Variance Day
150
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 3859
Reporting Period
202509
Managing Agency
DDC
Pid
3859
Agency Project Name
Complex Upgrades Ped Ramp - Queens
Current Phase
Construction
Completion Date
2027-06-11T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 3859
Reporting Period
202601
Managing Agency
DDC
Pid
3859
Agency Project Name
Complex Upgrades Ped Ramp - Queens
Current Phase
Construction
Completion Date
2027-06-11T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 3859
Reporting Period
202605
Managing Agency
DDC
Pid
3859
Agency Project Name
Complex Upgrades Ped Ramp - Queens
Current Phase
Construction
Completion Date
2027-06-11T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3860
Reporting Period
202305
Managing Agency
DDC
Pid
3860
Agency Project Name
Simple Upgrades Ped Ramps- Queens
Current Phase
Construction
Completion Date
2024-08-06T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3860
Reporting Period
202309
Managing Agency
DDC
Pid
3860
Agency Project Name
Simple Upgrades Ped Ramps- Queens
Current Phase
Construction
Completion Date
2024-08-06T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3860
Reporting Period
202401
Managing Agency
DDC
Pid
3860
Agency Project Name
Simple Upgrades Ped Ramps- Queens
Current Phase
Construction
Completion Date
2024-08-06T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3860
Reporting Period
202405
Managing Agency
DDC
Pid
3860
Agency Project Name
Simple Upgrades Ped Ramps- Queens
Current Phase
Construction
Completion Date
2024-08-06T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 3860
Reporting Period
202409
Managing Agency
DDC
Pid
3860
Agency Project Name
Simple Upgrades Ped Ramps- Queens
Current Phase
Construction
Completion Date
2024-07-31T00:00:00.000
Completion Date Type
Actual
Variance Day
-6
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3861
Reporting Period
202305
Managing Agency
DDC
Pid
3861
Agency Project Name
Simple Upgrades Ped Ramps- Brooklyn and Staten Island
Current Phase
Construction
Completion Date
2025-07-08T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3861
Reporting Period
202309
Managing Agency
DDC
Pid
3861
Agency Project Name
Simple Upgrades Ped Ramps- Brooklyn and Staten Island
Current Phase
Construction
Completion Date
2025-07-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3861
Reporting Period
202401
Managing Agency
DDC
Pid
3861
Agency Project Name
Simple Upgrades Ped Ramps- Brooklyn and Staten Island
Current Phase
Construction
Completion Date
2025-07-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3861
Reporting Period
202405
Managing Agency
DDC
Pid
3861
Agency Project Name
Simple Upgrades Ped Ramps- Brooklyn and Staten Island
Current Phase
Construction
Completion Date
2025-07-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 3861
Reporting Period
202409
Managing Agency
DDC
Pid
3861
Agency Project Name
Simple Upgrades Ped Ramps- Brooklyn and Staten Island
Current Phase
Construction
Completion Date
2025-07-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 3861
Reporting Period
202501
Managing Agency
DDC
Pid
3861
Agency Project Name
Simple Upgrades Ped Ramps- Brooklyn and Staten Island
Current Phase
Construction
Completion Date
2025-07-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 3861
Reporting Period
202505
Managing Agency
DDC
Pid
3861
Agency Project Name
Simple Upgrades Ped Ramps- Brooklyn and Staten Island
Current Phase
Construction
Completion Date
2025-07-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 3861
Reporting Period
202509
Managing Agency
DDC
Pid
3861
Agency Project Name
Simple Upgrades Ped Ramps- Brooklyn and Staten Island
Current Phase
Close-out
Completion Date
2025-07-07T00:00:00.000
Completion Date Type
Actual
Variance Day
-1
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3862
Reporting Period
202305
Managing Agency
DDC
Pid
3862
Agency Project Name
Pedestrian Ramp Upgrades at 89 non-standard locations in Manhattan and the Bronx
Current Phase
Pre-Design
Completion Date
2028-09-14T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3862
Reporting Period
202309
Managing Agency
DDC
Pid
3862
Agency Project Name
Pedestrian Ramp Upgrades at 89 non-standard locations in Manhattan and the Bronx
Current Phase
Pre-Design
Completion Date
2028-09-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3862
Reporting Period
202401
Managing Agency
DDC
Pid
3862
Agency Project Name
Pedestrian Ramp Upgrades at 89 non-standard locations in Manhattan and the Bronx
Current Phase
Pre-Design
Completion Date
2028-09-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3862
Reporting Period
202405
Managing Agency
DDC
Pid
3862
Agency Project Name
Pedestrian Ramp Upgrades at 89 non-standard locations in Manhattan and the Bronx
Current Phase
Design
Completion Date
2028-09-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 3862
Reporting Period
202409
Managing Agency
DDC
Pid
3862
Agency Project Name
Pedestrian Ramp Upgrades at 89 non-standard locations in Manhattan and the Bronx
Current Phase
Design
Completion Date
2028-09-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 3862
Reporting Period
202501
Managing Agency
DDC
Pid
3862
Agency Project Name
Pedestrian Ramp Upgrades at 89 non-standard locations in Manhattan and the Bronx
Current Phase
Design
Completion Date
2028-09-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 3862
Reporting Period
202505
Managing Agency
DDC
Pid
3862
Agency Project Name
Pedestrian Ramp Upgrades at 89 non-standard locations in Manhattan and the Bronx
Current Phase
Design
Completion Date
2028-09-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 3862
Reporting Period
202509
Managing Agency
DDC
Pid
3862
Agency Project Name
Pedestrian Ramp Upgrades at 89 non-standard locations in Manhattan and the Bronx
Current Phase
Design
Completion Date
2028-09-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 3862
Reporting Period
202601
Managing Agency
DDC
Pid
3862
Agency Project Name
Pedestrian Ramp Upgrades at 89 non-standard locations in Manhattan and the Bronx
Current Phase
Design
Completion Date
2029-09-12T00:00:00.000
Completion Date Type
Forecast
Variance Day
363
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 3862
Reporting Period
202605
Managing Agency
DDC
Pid
3862
Agency Project Name
Pedestrian Ramp Upgrades at 89 non-standard locations in Manhattan and the Bronx
Current Phase
Design
Completion Date
2029-09-12T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3863
Reporting Period
202305
Managing Agency
DDC
Pid
3863
Agency Project Name
Simple Upgrades Ped Ramps - Brooklyn and Staten Island
Current Phase
Construction Procurement
Completion Date
2026-06-27T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3863
Reporting Period
202309
Managing Agency
DDC
Pid
3863
Agency Project Name
Simple Upgrades Ped Ramps - Brooklyn and Staten Island
Current Phase
Construction Procurement
Completion Date
2026-06-27T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3863
Reporting Period
202401
Managing Agency
DDC
Pid
3863
Agency Project Name
Simple Upgrades Ped Ramps - Brooklyn and Staten Island
Current Phase
Construction Procurement
Completion Date
2026-06-27T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3863
Reporting Period
202405
Managing Agency
DDC
Pid
3863
Agency Project Name
Simple Upgrades Ped Ramps - Brooklyn and Staten Island
Current Phase
Construction Procurement
Completion Date
2026-09-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
80
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO BUDGETARY CONSTRAINTS
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 3863
Reporting Period
202409
Managing Agency
DDC
Pid
3863
Agency Project Name
Simple Upgrades Ped Ramps - Brooklyn and Staten Island
Current Phase
Construction
Completion Date
2026-09-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 3863
Reporting Period
202501
Managing Agency
DDC
Pid
3863
Agency Project Name
Simple Upgrades Ped Ramps - Brooklyn and Staten Island
Current Phase
Construction
Completion Date
2026-09-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 3863
Reporting Period
202505
Managing Agency
DDC
Pid
3863
Agency Project Name
Simple Upgrades Ped Ramps - Brooklyn and Staten Island
Current Phase
Construction
Completion Date
2026-09-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 3863
Reporting Period
202509
Managing Agency
DDC
Pid
3863
Agency Project Name
Simple Upgrades Ped Ramps - Brooklyn and Staten Island
Current Phase
Construction
Completion Date
2026-09-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 3863
Reporting Period
202601
Managing Agency
DDC
Pid
3863
Agency Project Name
Simple Upgrades Ped Ramps - Brooklyn and Staten Island
Current Phase
Construction
Completion Date
2026-09-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 3863
Reporting Period
202605
Managing Agency
DDC
Pid
3863
Agency Project Name
Simple Upgrades Ped Ramps - Brooklyn and Staten Island
Current Phase
Construction
Completion Date
2026-09-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3864
Reporting Period
202305
Managing Agency
DDC
Pid
3864
Agency Project Name
Reconstruction of Beach Channel Drive -- Phase B
Current Phase
Design
Completion Date
2029-09-13T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3864
Reporting Period
202309
Managing Agency
DDC
Pid
3864
Agency Project Name
Reconstruction of Beach Channel Drive -- Phase B
Current Phase
Design
Completion Date
2030-09-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
365
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3864
Reporting Period
202401
Managing Agency
DDC
Pid
3864
Agency Project Name
Reconstruction of Beach Channel Drive -- Phase B
Current Phase
Design
Completion Date
2030-09-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3864
Reporting Period
202405
Managing Agency
DDC
Pid
3864
Agency Project Name
Reconstruction of Beach Channel Drive -- Phase B
Current Phase
Design
Completion Date
2030-09-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000