Capital Projects Dashboard - Citywide Schedule History and Variance

This is the history all agency reported forecasts/actual project completion dates. Each row is the snapshot of data taken on each reporting period. The 'completion date type' column shows if the 'completion date' is either a forecast or actual date. Over time, a project would have one or more forecasted completion dates before it is actually completed. The 'variance' is the day difference between 'completion date' of each row and its prior reporting period. This dataset is part of the Capital Projects Dashboard.

City Government Mayor's Office of Operations (OPS) Dataset 95tx-snak 10 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3877
Reporting Period
202305
Managing Agency
DDC
Pid
3877
Agency Project Name
70 MULBERRY STREET - RECONSTRUCTION
Current Phase
Design
Completion Date
2028-03-29T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3877
Reporting Period
202309
Managing Agency
DDC
Pid
3877
Agency Project Name
70 MULBERRY STREET - RECONSTRUCTION
Current Phase
Design
Completion Date
2028-03-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3877
Reporting Period
202401
Managing Agency
DDC
Pid
3877
Agency Project Name
70 MULBERRY STREET - RECONSTRUCTION
Current Phase
Design
Completion Date
2028-03-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3877
Reporting Period
202405
Managing Agency
DDC
Pid
3877
Agency Project Name
70 MULBERRY STREET - RECONSTRUCTION
Current Phase
Design
Completion Date
2028-09-25T00:00:00.000
Completion Date Type
Forecast
Variance Day
180
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 3877
Reporting Period
202409
Managing Agency
DDC
Pid
3877
Agency Project Name
70 MULBERRY STREET - RECONSTRUCTION
Current Phase
Design
Completion Date
2028-12-24T00:00:00.000
Completion Date Type
Forecast
Variance Day
90
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 3877
Reporting Period
202501
Managing Agency
DDC
Pid
3877
Agency Project Name
70 MULBERRY STREET - RECONSTRUCTION
Current Phase
Design
Completion Date
2029-04-09T00:00:00.000
Completion Date Type
Forecast
Variance Day
106
Reason For Forecast Completion Change
PROJECT DELAYED PENDING APPROVAL OF NECESSARY PERMITS
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 3877
Reporting Period
202505
Managing Agency
DDC
Pid
3877
Agency Project Name
70 MULBERRY STREET - RECONSTRUCTION
Current Phase
Design
Completion Date
2029-06-22T00:00:00.000
Completion Date Type
Forecast
Variance Day
74
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 3877
Reporting Period
202509
Managing Agency
DDC
Pid
3877
Agency Project Name
70 MULBERRY STREET - RECONSTRUCTION
Current Phase
Construction Procurement
Completion Date
2029-06-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
7
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 3877
Reporting Period
202601
Managing Agency
DDC
Pid
3877
Agency Project Name
70 MULBERRY STREET - RECONSTRUCTION
Current Phase
Construction Procurement
Completion Date
2029-10-26T00:00:00.000
Completion Date Type
Forecast
Variance Day
119
Reason For Forecast Completion Change
PROJECT DELAYED PENDING APPROVAL OF NECESSARY PERMITS
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 3877
Reporting Period
202605
Managing Agency
DDC
Pid
3877
Agency Project Name
70 MULBERRY STREET - RECONSTRUCTION
Current Phase
Construction Procurement
Completion Date
2030-02-04T00:00:00.000
Completion Date Type
Forecast
Variance Day
101
Reason For Forecast Completion Change
PROJECT DELAYED PENDING APPROVAL OF NECESSARY PERMITS
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3878
Reporting Period
202305
Managing Agency
DDC
Pid
3878
Agency Project Name
Astoria Bath House Sewer and Plumbing Restoration
Current Phase
Close-out
Completion Date
2023-05-19T00:00:00.000
Completion Date Type
Actual
Data Date
2023-09-01T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3879
Reporting Period
202305
Managing Agency
DDC
Pid
3879
Agency Project Name
Dismantal of Brooklyn Detention Facility
Current Phase
Construction
Completion Date
2023-12-15T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3879
Reporting Period
202309
Managing Agency
DDC
Pid
3879
Agency Project Name
Dismantal of Brooklyn Detention Facility
Current Phase
Construction
Completion Date
2024-02-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
76
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3879
Reporting Period
202401
Managing Agency
DDC
Pid
3879
Agency Project Name
Dismantal of Brooklyn Detention Facility
Current Phase
Construction
Completion Date
2024-02-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3879
Reporting Period
202405
Managing Agency
DDC
Pid
3879
Agency Project Name
Dismantal of Brooklyn Detention Facility
Current Phase
Construction
Completion Date
2024-04-19T00:00:00.000
Completion Date Type
Actual
Variance Day
50
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3880
Reporting Period
202305
Managing Agency
DDC
Pid
3880
Agency Project Name
BBJ Construction of New Brooklyn Detention Facility
Current Phase
Design
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3880
Reporting Period
202309
Managing Agency
DDC
Pid
3880
Agency Project Name
BBJ Construction of New Brooklyn Detention Facility
Current Phase
Design
Completion Date Type
Forecast
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3880
Reporting Period
202401
Managing Agency
DDC
Pid
3880
Agency Project Name
BBJ Construction of New Brooklyn Detention Facility
Current Phase
Design
Completion Date Type
Forecast
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3880
Reporting Period
202405
Managing Agency
DDC
Pid
3880
Agency Project Name
BBJ Construction of New Brooklyn Detention Facility
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 3880
Reporting Period
202409
Managing Agency
DDC
Pid
3880
Agency Project Name
BBJ Construction of New Brooklyn Detention Facility
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 3880
Reporting Period
202501
Managing Agency
DDC
Pid
3880
Agency Project Name
BBJ Construction of New Brooklyn Detention Facility
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 3880
Reporting Period
202505
Managing Agency
DDC
Pid
3880
Agency Project Name
BBJ Construction of New Brooklyn Detention Facility
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2025-02-26T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 3880
Reporting Period
202509
Managing Agency
DDC
Pid
3880
Agency Project Name
BBJ Construction of New Brooklyn Detention Facility
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 3880
Reporting Period
202601
Managing Agency
DDC
Pid
3880
Agency Project Name
BBJ Construction of New Brooklyn Detention Facility
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 3880
Reporting Period
202605
Managing Agency
DDC
Pid
3880
Agency Project Name
BBJ Construction of New Brooklyn Detention Facility
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3881
Reporting Period
202305
Managing Agency
DDC
Pid
3881
Agency Project Name
Dismantal of Manhattan Detention Facility
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3881
Reporting Period
202309
Managing Agency
DDC
Pid
3881
Agency Project Name
Dismantal of Manhattan Detention Facility
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3881
Reporting Period
202401
Managing Agency
DDC
Pid
3881
Agency Project Name
Dismantal of Manhattan Detention Facility
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3881
Reporting Period
202405
Managing Agency
DDC
Pid
3881
Agency Project Name
Dismantal of Manhattan Detention Facility
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 3881
Reporting Period
202409
Managing Agency
DDC
Pid
3881
Agency Project Name
Dismantal of Manhattan Detention Facility
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 3881
Reporting Period
202501
Managing Agency
DDC
Pid
3881
Agency Project Name
Dismantal of Manhattan Detention Facility
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 3881
Reporting Period
202505
Managing Agency
DDC
Pid
3881
Agency Project Name
Dismantal of Manhattan Detention Facility
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2025-02-26T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 3881
Reporting Period
202509
Managing Agency
DDC
Pid
3881
Agency Project Name
Dismantal of Manhattan Detention Facility
Current Phase
Close-out
Completion Date
2025-03-10T00:00:00.000
Completion Date Type
Actual
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3882
Reporting Period
202305
Managing Agency
DDC
Pid
3882
Agency Project Name
Dismantal of Queens Detention Facility
Current Phase
Construction
Completion Date
2023-12-29T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3882
Reporting Period
202309
Managing Agency
DDC
Pid
3882
Agency Project Name
Dismantal of Queens Detention Facility
Current Phase
Construction
Completion Date
2024-02-18T00:00:00.000
Completion Date Type
Forecast
Variance Day
51
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3882
Reporting Period
202401
Managing Agency
DDC
Pid
3882
Agency Project Name
Dismantal of Queens Detention Facility
Current Phase
Construction
Completion Date
2024-02-18T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3882
Reporting Period
202405
Managing Agency
DDC
Pid
3882
Agency Project Name
Dismantal of Queens Detention Facility
Current Phase
Construction
Completion Date
2024-04-22T00:00:00.000
Completion Date Type
Actual
Variance Day
64
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3883
Reporting Period
202305
Managing Agency
DDC
Pid
3883
Agency Project Name
Dismantal of Bronx Detention Facility
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3883
Reporting Period
202309
Managing Agency
DDC
Pid
3883
Agency Project Name
Dismantal of Bronx Detention Facility
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3883
Reporting Period
202401
Managing Agency
DDC
Pid
3883
Agency Project Name
Dismantal of Bronx Detention Facility
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3883
Reporting Period
202405
Managing Agency
DDC
Pid
3883
Agency Project Name
Dismantal of Bronx Detention Facility
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 3883
Reporting Period
202409
Managing Agency
DDC
Pid
3883
Agency Project Name
Dismantal of Bronx Detention Facility
Current Phase
Construction
Completion Date
2024-07-25T00:00:00.000
Completion Date Type
Actual
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3884
Reporting Period
202305
Managing Agency
DDC
Pid
3884
Agency Project Name
Renovation of George R Vierno Center (GRVC) at Rikers Island
Current Phase
Close-out
Completion Date
2023-06-30T00:00:00.000
Completion Date Type
Actual
Data Date
2023-09-01T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3885
Reporting Period
202305
Managing Agency
DDC
Pid
3885
Agency Project Name
Renovation of Rose M. Singer Center (RMSC) at Rikers Island
Current Phase
Close-out
Completion Date
2023-06-30T00:00:00.000
Completion Date Type
Actual
Data Date
2023-09-01T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3886
Reporting Period
202305
Managing Agency
DDC
Pid
3886
Agency Project Name
Renovation of Robert N. Davoren Complex (RNDC) at Rikers Island
Current Phase
Close-out
Completion Date
2023-06-30T00:00:00.000
Completion Date Type
Actual
Data Date
2023-09-01T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3887
Reporting Period
202305
Managing Agency
DDC
Pid
3887
Agency Project Name
Renovation of North Infirmary Command (NIC) at Rikers Island
Current Phase
Close-out
Completion Date
2023-02-28T00:00:00.000
Completion Date Type
Actual
Data Date
2023-09-01T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3888
Reporting Period
202305
Managing Agency
DDC
Pid
3888
Agency Project Name
Renovation of Various Complexes at Rikers Island
Current Phase
Construction
Completion Date
2024-07-17T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3888
Reporting Period
202309
Managing Agency
DDC
Pid
3888
Agency Project Name
Renovation of Various Complexes at Rikers Island
Current Phase
Construction
Completion Date
2024-07-17T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-01-04T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3888
Reporting Period
202401
Managing Agency
DDC
Pid
3888
Agency Project Name
Renovation of Various Complexes at Rikers Island
Current Phase
Construction
Completion Date
2024-07-17T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-01-04T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3888
Reporting Period
202405
Managing Agency
DDC
Pid
3888
Agency Project Name
Renovation of Various Complexes at Rikers Island
Current Phase
Construction
Completion Date
2023-12-28T00:00:00.000
Completion Date Type
Actual
Variance Day
-202
Data Date
2024-07-18T00:00:00.000