Capital Projects Dashboard - Citywide Schedule History and Variance

This is the history all agency reported forecasts/actual project completion dates. Each row is the snapshot of data taken on each reporting period. The 'completion date type' column shows if the 'completion date' is either a forecast or actual date. Over time, a project would have one or more forecasted completion dates before it is actually completed. The 'variance' is the day difference between 'completion date' of each row and its prior reporting period. This dataset is part of the Capital Projects Dashboard.

City Government Mayor's Office of Operations (OPS) Dataset 95tx-snak 10 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3895
Reporting Period
202305
Managing Agency
DDC
Pid
3895
Agency Project Name
Façade Stabilization
Current Phase
Construction
Completion Date
2024-08-30T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3895
Reporting Period
202309
Managing Agency
DDC
Pid
3895
Agency Project Name
Façade Stabilization
Current Phase
Construction
Completion Date
2024-08-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2023-09-01T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3895
Reporting Period
202401
Managing Agency
DDC
Pid
3895
Agency Project Name
Façade Stabilization
Current Phase
Construction
Completion Date
2024-08-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2023-09-01T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3895
Reporting Period
202405
Managing Agency
DDC
Pid
3895
Agency Project Name
Façade Stabilization
Current Phase
Construction
Completion Date
2024-08-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 3895
Reporting Period
202409
Managing Agency
DDC
Pid
3895
Agency Project Name
Façade Stabilization
Current Phase
Construction
Completion Date
2024-08-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3896
Reporting Period
202305
Managing Agency
DDC
Pid
3896
Agency Project Name
Exterior envelope renovation
Current Phase
Pre-Design
Completion Date
2027-07-30T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3896
Reporting Period
202309
Managing Agency
DDC
Pid
3896
Agency Project Name
Exterior envelope renovation
Current Phase
Pre-Design
Completion Date
2027-07-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3896
Reporting Period
202401
Managing Agency
DDC
Pid
3896
Agency Project Name
Exterior envelope renovation
Current Phase
Pre-Design
Completion Date
2027-07-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3896
Reporting Period
202405
Managing Agency
DDC
Pid
3896
Agency Project Name
Washington Heights Health Center Envelop Renovation
Current Phase
Design
Completion Date
2028-01-11T00:00:00.000
Completion Date Type
Forecast
Variance Day
165
Reason For Forecast Completion Change
PROJECT DELAYED PENDING APPROVAL OF NECESSARY PERMITS
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 3896
Reporting Period
202409
Managing Agency
DDC
Pid
3896
Agency Project Name
Washington Heights Health Center Envelop Renovation
Current Phase
Design
Completion Date
2028-01-11T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 3896
Reporting Period
202501
Managing Agency
DDC
Pid
3896
Agency Project Name
Washington Heights Health Center Envelop Renovation
Current Phase
Design
Completion Date
2028-01-11T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 3896
Reporting Period
202505
Managing Agency
DDC
Pid
3896
Agency Project Name
Washington Heights Health Center Envelop Renovation
Current Phase
Design
Completion Date
2028-01-11T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 3896
Reporting Period
202509
Managing Agency
DDC
Pid
3896
Agency Project Name
Washington Heights Health Center Envelop Renovation
Current Phase
Close-out
Completion Date
2028-02-16T00:00:00.000
Completion Date Type
Forecast
Variance Day
36
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3897
Reporting Period
202305
Managing Agency
DDC
Pid
3897
Agency Project Name
444 Thomas Boyland Community Center
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3897
Reporting Period
202309
Managing Agency
DDC
Pid
3897
Agency Project Name
444 Thomas Boyland Community Center
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3897
Reporting Period
202401
Managing Agency
DDC
Pid
3897
Agency Project Name
444 Thomas Boyland Community Center
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3897
Reporting Period
202405
Managing Agency
DDC
Pid
3897
Agency Project Name
444 Thomas Boyland Community Center
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 3897
Reporting Period
202409
Managing Agency
DDC
Pid
3897
Agency Project Name
444 Thomas Boyland Community Center
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 3897
Reporting Period
202501
Managing Agency
DDC
Pid
3897
Agency Project Name
444 Thomas Boyland Community Center
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 3897
Reporting Period
202505
Managing Agency
DDC
Pid
3897
Agency Project Name
444 Thomas Boyland Community Center
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 3897
Reporting Period
202509
Managing Agency
DDC
Pid
3897
Agency Project Name
444 Thomas Boyland Community Center
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 3897
Reporting Period
202601
Managing Agency
DDC
Pid
3897
Agency Project Name
444 Thomas Boyland Community Center
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 3897
Reporting Period
202605
Managing Agency
DDC
Pid
3897
Agency Project Name
444 Thomas Boyland Community Center
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3898
Reporting Period
202305
Managing Agency
DDC
Pid
3898
Agency Project Name
CLARENDON OUTDOOR PLAZA
Current Phase
Construction
Completion Date
2023-10-31T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3898
Reporting Period
202309
Managing Agency
DDC
Pid
3898
Agency Project Name
CLARENDON OUTDOOR PLAZA
Current Phase
Construction
Completion Date
2023-10-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2023-09-01T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3898
Reporting Period
202401
Managing Agency
DDC
Pid
3898
Agency Project Name
CLARENDON OUTDOOR PLAZA
Current Phase
Construction
Completion Date
2023-10-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2023-09-01T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3898
Reporting Period
202405
Managing Agency
DDC
Pid
3898
Agency Project Name
CLARENDON OUTDOOR PLAZA
Current Phase
Construction
Completion Date
2023-10-31T00:00:00.000
Completion Date Type
Actual
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3899
Reporting Period
202305
Managing Agency
DDC
Pid
3899
Agency Project Name
SARATOGA LIBRARY BUILDING ENVELOPE REHABILITATION
Current Phase
Construction
Completion Date
2023-09-29T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3899
Reporting Period
202309
Managing Agency
DDC
Pid
3899
Agency Project Name
SARATOGA LIBRARY BUILDING ENVELOPE REHABILITATION
Current Phase
Construction
Completion Date
2023-09-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2023-09-01T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3899
Reporting Period
202401
Managing Agency
DDC
Pid
3899
Agency Project Name
SARATOGA LIBRARY BUILDING ENVELOPE REHABILITATION
Current Phase
Construction
Completion Date
2023-09-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2023-09-01T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3899
Reporting Period
202405
Managing Agency
DDC
Pid
3899
Agency Project Name
SARATOGA LIBRARY BUILDING ENVELOPE REHABILITATION
Current Phase
Construction
Completion Date
2023-10-17T00:00:00.000
Completion Date Type
Actual
Variance Day
18
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3900
Reporting Period
202305
Managing Agency
DDC
Pid
3900
Agency Project Name
EASTERN PARKWAY LIBRARY MAJOR RENOVATIONS
Current Phase
Design
Completion Date
2026-11-30T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3900
Reporting Period
202309
Managing Agency
DDC
Pid
3900
Agency Project Name
EASTERN PARKWAY LIBRARY MAJOR RENOVATIONS
Current Phase
Design
Completion Date
2027-04-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
149
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3900
Reporting Period
202401
Managing Agency
DDC
Pid
3900
Agency Project Name
EASTERN PARKWAY LIBRARY MAJOR RENOVATIONS
Current Phase
Design
Completion Date
2027-04-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3900
Reporting Period
202405
Managing Agency
DDC
Pid
3900
Agency Project Name
EASTERN PARKWAY LIBRARY MAJOR RENOVATIONS
Current Phase
Construction Procurement
Completion Date
2027-08-16T00:00:00.000
Completion Date Type
Forecast
Variance Day
110
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 3900
Reporting Period
202409
Managing Agency
DDC
Pid
3900
Agency Project Name
EASTERN PARKWAY LIBRARY MAJOR RENOVATIONS
Current Phase
Construction Procurement
Completion Date
2027-11-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
77
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 3900
Reporting Period
202501
Managing Agency
DDC
Pid
3900
Agency Project Name
EASTERN PARKWAY LIBRARY MAJOR RENOVATIONS
Current Phase
Construction Procurement
Completion Date
2027-11-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 3900
Reporting Period
202505
Managing Agency
DDC
Pid
3900
Agency Project Name
EASTERN PARKWAY LIBRARY MAJOR RENOVATIONS
Current Phase
Construction Procurement
Completion Date
2028-01-03T00:00:00.000
Completion Date Type
Forecast
Variance Day
63
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 3900
Reporting Period
202509
Managing Agency
DDC
Pid
3900
Agency Project Name
EASTERN PARKWAY LIBRARY MAJOR RENOVATIONS
Current Phase
Construction
Completion Date
2027-07-22T00:00:00.000
Completion Date Type
Forecast
Variance Day
-165
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 3900
Reporting Period
202601
Managing Agency
DDC
Pid
3900
Agency Project Name
EASTERN PARKWAY LIBRARY MAJOR RENOVATIONS
Current Phase
Construction
Completion Date
2027-07-22T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 3900
Reporting Period
202605
Managing Agency
DDC
Pid
3900
Agency Project Name
EASTERN PARKWAY LIBRARY MAJOR RENOVATIONS
Current Phase
Construction
Completion Date
2027-11-21T00:00:00.000
Completion Date Type
Forecast
Variance Day
122
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN HAZARDOUS CONDITION
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3901
Reporting Period
202305
Managing Agency
DDC
Pid
3901
Agency Project Name
WASHINGTON IRVING BRANCH RENOVATION
Current Phase
Design
Completion Date
2028-04-15T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3901
Reporting Period
202309
Managing Agency
DDC
Pid
3901
Agency Project Name
WASHINGTON IRVING BRANCH RENOVATION
Current Phase
Design
Completion Date
2028-04-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3901
Reporting Period
202401
Managing Agency
DDC
Pid
3901
Agency Project Name
WASHINGTON IRVING BRANCH RENOVATION
Current Phase
Design
Completion Date
2028-04-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3901
Reporting Period
202405
Managing Agency
DDC
Pid
3901
Agency Project Name
WASHINGTON IRVING BRANCH RENOVATION
Current Phase
Design
Completion Date
2028-04-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 3901
Reporting Period
202409
Managing Agency
DDC
Pid
3901
Agency Project Name
WASHINGTON IRVING BRANCH RENOVATION
Current Phase
Design
Completion Date
2028-04-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 3901
Reporting Period
202501
Managing Agency
DDC
Pid
3901
Agency Project Name
WASHINGTON IRVING BRANCH RENOVATION
Current Phase
Design
Completion Date
2028-04-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 3901
Reporting Period
202505
Managing Agency
DDC
Pid
3901
Agency Project Name
WASHINGTON IRVING BRANCH RENOVATION
Current Phase
Design
Completion Date
2028-04-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 3901
Reporting Period
202509
Managing Agency
DDC
Pid
3901
Agency Project Name
WASHINGTON IRVING BRANCH RENOVATION
Current Phase
Design
Completion Date
2029-07-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
454
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 3901
Reporting Period
202601
Managing Agency
DDC
Pid
3901
Agency Project Name
WASHINGTON IRVING BRANCH RENOVATION
Current Phase
Design
Completion Date
2030-01-20T00:00:00.000
Completion Date Type
Forecast
Variance Day
191
Data Date
2026-03-16T00:00:00.000