Capital Projects Dashboard - Citywide Schedule History and Variance

This is the history all agency reported forecasts/actual project completion dates. Each row is the snapshot of data taken on each reporting period. The 'completion date type' column shows if the 'completion date' is either a forecast or actual date. Over time, a project would have one or more forecasted completion dates before it is actually completed. The 'variance' is the day difference between 'completion date' of each row and its prior reporting period. This dataset is part of the Capital Projects Dashboard.

City Government Mayor's Office of Operations (OPS) Dataset 95tx-snak 10 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 3952
Reporting Period
202601
Managing Agency
DDC
Pid
3952
Agency Project Name
4TH AVE. SAFETY IMPROVEMENTS PHASE II-VISION ZERO
Current Phase
Construction
Completion Date
2026-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
181
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 3952
Reporting Period
202605
Managing Agency
DDC
Pid
3952
Agency Project Name
4TH AVE. SAFETY IMPROVEMENTS PHASE II-VISION ZERO
Current Phase
Construction
Completion Date
2026-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3953
Reporting Period
202305
Managing Agency
DDC
Pid
3953
Agency Project Name
Hollis Interior Renovation
Current Phase
Construction Procurement
Completion Date
2026-02-02T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3953
Reporting Period
202309
Managing Agency
DDC
Pid
3953
Agency Project Name
Hollis Interior Renovation
Current Phase
Construction Procurement
Completion Date
2026-06-02T00:00:00.000
Completion Date Type
Forecast
Variance Day
120
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3953
Reporting Period
202401
Managing Agency
DDC
Pid
3953
Agency Project Name
Hollis Interior Renovation
Current Phase
Construction Procurement
Completion Date
2026-06-02T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3953
Reporting Period
202405
Managing Agency
DDC
Pid
3953
Agency Project Name
Hollis Interior Renovation
Current Phase
Construction Procurement
Completion Date
2026-07-27T00:00:00.000
Completion Date Type
Forecast
Variance Day
55
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 3953
Reporting Period
202409
Managing Agency
DDC
Pid
3953
Agency Project Name
Hollis Interior Renovation
Current Phase
Construction
Completion Date
2026-03-16T00:00:00.000
Completion Date Type
Forecast
Variance Day
-133
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 3953
Reporting Period
202501
Managing Agency
DDC
Pid
3953
Agency Project Name
Hollis Interior Renovation
Current Phase
Construction
Completion Date
2026-03-16T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 3953
Reporting Period
202505
Managing Agency
DDC
Pid
3953
Agency Project Name
Hollis Interior Renovation
Current Phase
Construction
Completion Date
2026-02-16T00:00:00.000
Completion Date Type
Forecast
Variance Day
-28
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 3953
Reporting Period
202509
Managing Agency
DDC
Pid
3953
Agency Project Name
Hollis Interior Renovation
Current Phase
Construction
Completion Date
2026-09-16T00:00:00.000
Completion Date Type
Forecast
Variance Day
212
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 3953
Reporting Period
202601
Managing Agency
DDC
Pid
3953
Agency Project Name
Hollis Interior Renovation
Current Phase
Construction
Completion Date
2027-05-07T00:00:00.000
Completion Date Type
Forecast
Variance Day
233
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 3953
Reporting Period
202605
Managing Agency
DDC
Pid
3953
Agency Project Name
Hollis Interior Renovation
Current Phase
Construction
Completion Date
2027-09-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
146
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN HAZARDOUS CONDITION
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3954
Reporting Period
202305
Managing Agency
DDC
Pid
3954
Agency Project Name
REPLACEMENT OF 72" TRUNK WM IN FLATBUSH AVE
Current Phase
Construction
Completion Date
2023-09-29T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3954
Reporting Period
202309
Managing Agency
DDC
Pid
3954
Agency Project Name
REPLACEMENT OF 72" TRUNK WM IN FLATBUSH AVE
Current Phase
Construction
Completion Date
2024-03-12T00:00:00.000
Completion Date Type
Forecast
Variance Day
165
Data Date
2024-01-04T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3954
Reporting Period
202401
Managing Agency
DDC
Pid
3954
Agency Project Name
REPLACEMENT OF 72" TRUNK WM IN FLATBUSH AVE
Current Phase
Construction
Completion Date
2024-03-12T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-01-04T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3954
Reporting Period
202405
Managing Agency
DDC
Pid
3954
Agency Project Name
REPLACEMENT OF 72" TRUNK WM IN FLATBUSH AVE
Current Phase
Construction
Completion Date
2024-03-12T00:00:00.000
Completion Date Type
Actual
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3955
Reporting Period
202305
Managing Agency
DDC
Pid
3955
Agency Project Name
8 E 3rd Street Shelter kitchen
Current Phase
Close-out
Completion Date
2023-08-18T00:00:00.000
Completion Date Type
Actual
Data Date
2023-09-01T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3956
Reporting Period
202305
Managing Agency
DDC
Pid
3956
Agency Project Name
96th Street Exterior Renovation
Current Phase
Close-out
Completion Date
2023-04-17T00:00:00.000
Completion Date Type
Actual
Data Date
2023-09-01T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3957
Reporting Period
202305
Managing Agency
DDC
Pid
3957
Agency Project Name
St. Ann's Warehouse:Tobacco Warehouse renovation-E
Current Phase
Construction
Completion Date
2023-11-30T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3957
Reporting Period
202309
Managing Agency
DDC
Pid
3957
Agency Project Name
St. Ann's Warehouse:Tobacco Warehouse renovation-E
Current Phase
Construction
Completion Date
2023-11-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2023-09-01T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3957
Reporting Period
202401
Managing Agency
DDC
Pid
3957
Agency Project Name
St. Ann's Warehouse:Tobacco Warehouse renovation-E
Current Phase
Construction
Completion Date
2023-11-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2023-09-01T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3957
Reporting Period
202405
Managing Agency
DDC
Pid
3957
Agency Project Name
St. Ann's Warehouse:Tobacco Warehouse renovation-E
Current Phase
Construction
Completion Date
2023-11-10T00:00:00.000
Completion Date Type
Actual
Variance Day
-20
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3958
Reporting Period
202305
Managing Agency
DDC
Pid
3958
Agency Project Name
Aguilar Facade Restoration
Current Phase
Construction
Completion Date
2024-09-16T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3958
Reporting Period
202309
Managing Agency
DDC
Pid
3958
Agency Project Name
Aguilar Facade Restoration
Current Phase
Construction
Completion Date
2024-09-16T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3958
Reporting Period
202401
Managing Agency
DDC
Pid
3958
Agency Project Name
Aguilar Facade Restoration
Current Phase
Construction
Completion Date
2024-09-16T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3958
Reporting Period
202405
Managing Agency
DDC
Pid
3958
Agency Project Name
Aguilar Facade Restoration
Current Phase
Construction
Completion Date
2024-12-16T00:00:00.000
Completion Date Type
Forecast
Variance Day
91
Reason For Forecast Completion Change
PROJECT DELAYED RESULTING FROM CONTRACTOR DEFAULT
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 3958
Reporting Period
202409
Managing Agency
DDC
Pid
3958
Agency Project Name
Aguilar Facade Restoration
Current Phase
Construction
Completion Date
2025-03-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
103
Reason For Forecast Completion Change
PROJECT DELAYED RESULTING FROM CONTRACTOR DEFAULT
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 3958
Reporting Period
202501
Managing Agency
DDC
Pid
3958
Agency Project Name
Aguilar Facade Restoration
Current Phase
Construction
Completion Date
2025-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
93
Reason For Forecast Completion Change
PROJECT DELAYED RESULTING FROM CONTRACTOR DEFAULT
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 3958
Reporting Period
202505
Managing Agency
DDC
Pid
3958
Agency Project Name
Aguilar Facade Restoration
Current Phase
Construction
Completion Date
2025-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 3958
Reporting Period
202509
Managing Agency
DDC
Pid
3958
Agency Project Name
Aguilar Facade Restoration
Current Phase
Construction
Completion Date
2025-12-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
168
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 3958
Reporting Period
202601
Managing Agency
DDC
Pid
3958
Agency Project Name
Aguilar Facade Restoration
Current Phase
Construction
Completion Date
2026-05-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
165
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 3958
Reporting Period
202605
Managing Agency
DDC
Pid
3958
Agency Project Name
Aguilar Facade Restoration
Current Phase
Construction
Completion Date
2026-09-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
124
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3959
Reporting Period
202305
Managing Agency
DDC
Pid
3959
Agency Project Name
Complex Upgrades Ped Ramps - Brooklyn
Current Phase
Construction Procurement
Completion Date
2025-12-10T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3959
Reporting Period
202309
Managing Agency
DDC
Pid
3959
Agency Project Name
Complex Upgrades Ped Ramps - Brooklyn
Current Phase
Construction
Completion Date
2025-12-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3959
Reporting Period
202401
Managing Agency
DDC
Pid
3959
Agency Project Name
Complex Upgrades Ped Ramps - Brooklyn
Current Phase
Construction
Completion Date
2025-12-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3959
Reporting Period
202405
Managing Agency
DDC
Pid
3959
Agency Project Name
Complex Upgrades Ped Ramps - Brooklyn
Current Phase
Construction
Completion Date
2025-12-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 3959
Reporting Period
202409
Managing Agency
DDC
Pid
3959
Agency Project Name
Complex Upgrades Ped Ramps - Brooklyn
Current Phase
Construction
Completion Date
2025-12-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 3959
Reporting Period
202501
Managing Agency
DDC
Pid
3959
Agency Project Name
Complex Upgrades Ped Ramps - Brooklyn
Current Phase
Construction
Completion Date
2025-12-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 3959
Reporting Period
202505
Managing Agency
DDC
Pid
3959
Agency Project Name
Complex Upgrades Ped Ramps - Brooklyn
Current Phase
Construction
Completion Date
2025-12-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 3959
Reporting Period
202509
Managing Agency
DDC
Pid
3959
Agency Project Name
Complex Upgrades Ped Ramps - Brooklyn
Current Phase
Construction
Completion Date
2025-12-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 3959
Reporting Period
202601
Managing Agency
DDC
Pid
3959
Agency Project Name
Complex Upgrades Ped Ramps - Brooklyn
Current Phase
Close-out
Completion Date
2025-12-10T00:00:00.000
Completion Date Type
Actual
Variance Day
0
Data Date
2026-03-20T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3960
Reporting Period
202305
Managing Agency
DDC
Pid
3960
Agency Project Name
Astoria Restrooms and Elevators Upgrade
Current Phase
Design
Completion Date
2028-04-27T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3960
Reporting Period
202309
Managing Agency
DDC
Pid
3960
Agency Project Name
Astoria Restrooms and Elevators Upgrade
Current Phase
Design
Completion Date
2028-04-27T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3960
Reporting Period
202401
Managing Agency
DDC
Pid
3960
Agency Project Name
Astoria Restrooms and Elevators Upgrade
Current Phase
Design
Completion Date
2028-04-27T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3960
Reporting Period
202405
Managing Agency
DDC
Pid
3960
Agency Project Name
Astoria Restrooms and Elevators Upgrade
Current Phase
Design
Completion Date
2027-03-02T00:00:00.000
Completion Date Type
Forecast
Variance Day
-422
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 3960
Reporting Period
202409
Managing Agency
DDC
Pid
3960
Agency Project Name
Astoria Restrooms and Elevators Upgrade
Current Phase
Design
Completion Date
2027-05-23T00:00:00.000
Completion Date Type
Forecast
Variance Day
82
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 3960
Reporting Period
202501
Managing Agency
DDC
Pid
3960
Agency Project Name
Astoria Restrooms and Elevators Upgrade
Current Phase
Construction Procurement
Completion Date
2027-11-23T00:00:00.000
Completion Date Type
Forecast
Variance Day
184
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 3960
Reporting Period
202505
Managing Agency
DDC
Pid
3960
Agency Project Name
Astoria Restrooms and Elevators Upgrade
Current Phase
Construction Procurement
Completion Date
2027-11-23T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 3960
Reporting Period
202509
Managing Agency
DDC
Pid
3960
Agency Project Name
Astoria Restrooms and Elevators Upgrade
Current Phase
Construction
Completion Date
2027-07-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
-132
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 3960
Reporting Period
202601
Managing Agency
DDC
Pid
3960
Agency Project Name
Astoria Restrooms and Elevators Upgrade
Current Phase
Construction
Completion Date
2027-07-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000