Capital Projects Dashboard - Citywide Schedule History and Variance

This is the history all agency reported forecasts/actual project completion dates. Each row is the snapshot of data taken on each reporting period. The 'completion date type' column shows if the 'completion date' is either a forecast or actual date. Over time, a project would have one or more forecasted completion dates before it is actually completed. The 'variance' is the day difference between 'completion date' of each row and its prior reporting period. This dataset is part of the Capital Projects Dashboard.

City Government Mayor's Office of Operations (OPS) Dataset 95tx-snak 10 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 3960
Reporting Period
202605
Managing Agency
DDC
Pid
3960
Agency Project Name
Astoria Restrooms and Elevators Upgrade
Current Phase
Construction
Completion Date
2028-08-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
414
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO BUDGETARY CONSTRAINTS
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3961
Reporting Period
202305
Managing Agency
DDC
Pid
3961
Agency Project Name
BBJ Queens Garage - Construction of new multi-level Garage with Community Space
Current Phase
Close-out
Completion Date
2023-06-26T00:00:00.000
Completion Date Type
Actual
Data Date
2023-09-01T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3962
Reporting Period
202305
Managing Agency
DDC
Pid
3962
Agency Project Name
Belt Parkway Barrier Reconstruction at Sunrise Highway
Current Phase
Design
Completion Date
2027-02-08T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3962
Reporting Period
202309
Managing Agency
DDC
Pid
3962
Agency Project Name
Belt Parkway Barrier Reconstruction at Sunrise Highway
Current Phase
Design
Completion Date
2027-02-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3962
Reporting Period
202401
Managing Agency
DDC
Pid
3962
Agency Project Name
Belt Parkway Barrier Reconstruction at Sunrise Highway
Current Phase
Design
Completion Date
2027-02-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3962
Reporting Period
202405
Managing Agency
DDC
Pid
3962
Agency Project Name
Belt Parkway Barrier Reconstruction at Sunrise Highway
Current Phase
Design
Completion Date
2027-02-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 3962
Reporting Period
202409
Managing Agency
DDC
Pid
3962
Agency Project Name
Belt Parkway Barrier Reconstruction at Sunrise Highway
Current Phase
Design
Completion Date
2027-02-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 3962
Reporting Period
202501
Managing Agency
DDC
Pid
3962
Agency Project Name
Belt Parkway Barrier Reconstruction at Sunrise Highway
Current Phase
Design
Completion Date
2027-05-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
91
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 3962
Reporting Period
202505
Managing Agency
DDC
Pid
3962
Agency Project Name
Belt Parkway Barrier Reconstruction at Sunrise Highway
Current Phase
Design
Completion Date
2027-05-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 3962
Reporting Period
202509
Managing Agency
DDC
Pid
3962
Agency Project Name
Belt Parkway Barrier Reconstruction at Sunrise Highway
Current Phase
Design
Completion Date
2027-10-19T00:00:00.000
Completion Date Type
Forecast
Variance Day
162
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 3962
Reporting Period
202601
Managing Agency
DDC
Pid
3962
Agency Project Name
Belt Parkway Barrier Reconstruction at Sunrise Highway
Current Phase
Design
Completion Date
2027-10-19T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 3962
Reporting Period
202605
Managing Agency
DDC
Pid
3962
Agency Project Name
Belt Parkway Barrier Reconstruction at Sunrise Highway
Current Phase
Design
Completion Date
2028-02-22T00:00:00.000
Completion Date Type
Forecast
Variance Day
126
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3963
Reporting Period
202305
Managing Agency
DDC
Pid
3963
Agency Project Name
ARLINGTON BRANCH RENOVATION
Current Phase
Design
Completion Date
2026-10-23T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3963
Reporting Period
202309
Managing Agency
DDC
Pid
3963
Agency Project Name
ARLINGTON BRANCH RENOVATION
Current Phase
Design
Completion Date
2027-01-21T00:00:00.000
Completion Date Type
Forecast
Variance Day
90
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3963
Reporting Period
202401
Managing Agency
DDC
Pid
3963
Agency Project Name
ARLINGTON BRANCH RENOVATION
Current Phase
Design
Completion Date
2027-01-21T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3963
Reporting Period
202405
Managing Agency
DDC
Pid
3963
Agency Project Name
ARLINGTON BRANCH RENOVATION
Current Phase
Design
Completion Date
2027-06-07T00:00:00.000
Completion Date Type
Forecast
Variance Day
137
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 3963
Reporting Period
202409
Managing Agency
DDC
Pid
3963
Agency Project Name
ARLINGTON BRANCH RENOVATION
Current Phase
Design
Completion Date
2027-09-22T00:00:00.000
Completion Date Type
Forecast
Variance Day
107
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 3963
Reporting Period
202501
Managing Agency
DDC
Pid
3963
Agency Project Name
ARLINGTON BRANCH RENOVATION
Current Phase
Construction Procurement
Completion Date
2027-09-22T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 3963
Reporting Period
202505
Managing Agency
DDC
Pid
3963
Agency Project Name
ARLINGTON BRANCH RENOVATION
Current Phase
Construction Procurement
Completion Date
2028-01-03T00:00:00.000
Completion Date Type
Forecast
Variance Day
103
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 3963
Reporting Period
202509
Managing Agency
DDC
Pid
3963
Agency Project Name
ARLINGTON BRANCH RENOVATION
Current Phase
Construction Procurement
Completion Date
2028-01-03T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 3963
Reporting Period
202601
Managing Agency
DDC
Pid
3963
Agency Project Name
ARLINGTON BRANCH RENOVATION
Current Phase
Construction Procurement
Completion Date
2028-06-02T00:00:00.000
Completion Date Type
Forecast
Variance Day
151
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 3963
Reporting Period
202605
Managing Agency
DDC
Pid
3963
Agency Project Name
ARLINGTON BRANCH RENOVATION
Current Phase
Construction
Completion Date
2028-08-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
88
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3964
Reporting Period
202305
Managing Agency
DDC
Pid
3964
Agency Project Name
Curb to curb reconstruction of 2 blocks of Broadway (between W 38th and W 40th Streets) to build out Broadway Boulevard Plaza and Shared Street.
Current Phase
Design
Completion Date
2028-04-21T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3964
Reporting Period
202309
Managing Agency
DDC
Pid
3964
Agency Project Name
Curb to curb reconstruction of 2 blocks of Broadway (between W 38th and W 40th Streets) to build out Broadway Boulevard Plaza and Shared Street.
Current Phase
Design
Completion Date
2028-06-02T00:00:00.000
Completion Date Type
Forecast
Variance Day
42
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3964
Reporting Period
202401
Managing Agency
DDC
Pid
3964
Agency Project Name
Curb to curb reconstruction of 2 blocks of Broadway (between W 38th and W 40th Streets) to build out Broadway Boulevard Plaza and Shared Street.
Current Phase
Design
Completion Date
2028-06-02T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3964
Reporting Period
202405
Managing Agency
DDC
Pid
3964
Agency Project Name
Curb to curb reconstruction of 2 blocks of Broadway (between W 38th and W 40th Streets) to build out Broadway Boulevard Plaza and Shared Street.
Current Phase
Design
Completion Date
2028-06-02T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 3964
Reporting Period
202409
Managing Agency
DDC
Pid
3964
Agency Project Name
Curb to curb reconstruction of 2 blocks of Broadway (between W 38th and W 40th Streets) to build out Broadway Boulevard Plaza and Shared Street.
Current Phase
Design
Completion Date
2028-06-02T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 3964
Reporting Period
202501
Managing Agency
DDC
Pid
3964
Agency Project Name
Curb to curb reconstruction of 2 blocks of Broadway (between W 38th and W 40th Streets) to build out Broadway Boulevard Plaza and Shared Street.
Current Phase
Design
Completion Date
2028-06-02T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 3964
Reporting Period
202505
Managing Agency
DDC
Pid
3964
Agency Project Name
Curb to curb reconstruction of 2 blocks of Broadway (between W 38th and W 40th Streets) to build out Broadway Boulevard Plaza and Shared Street.
Current Phase
Design
Completion Date
2029-12-17T00:00:00.000
Completion Date Type
Forecast
Variance Day
563
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 3964
Reporting Period
202509
Managing Agency
DDC
Pid
3964
Agency Project Name
Curb to curb reconstruction of 2 blocks of Broadway (between W 38th and W 40th Streets) to build out Broadway Boulevard Plaza and Shared Street.
Current Phase
Design
Completion Date
2030-04-24T00:00:00.000
Completion Date Type
Forecast
Variance Day
128
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 3964
Reporting Period
202601
Managing Agency
DDC
Pid
3964
Agency Project Name
Curb to curb reconstruction of 2 blocks of Broadway (between W 38th and W 40th Streets) to build out Broadway Boulevard Plaza and Shared Street.
Current Phase
Design
Completion Date
2031-07-22T00:00:00.000
Completion Date Type
Forecast
Variance Day
454
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 3964
Reporting Period
202605
Managing Agency
DDC
Pid
3964
Agency Project Name
Curb to curb reconstruction of 2 blocks of Broadway (between W 38th and W 40th Streets) to build out Broadway Boulevard Plaza and Shared Street.
Current Phase
Design
Completion Date
2031-07-22T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3965
Reporting Period
202305
Managing Agency
DDC
Pid
3965
Agency Project Name
Broadway Interior Renovation
Current Phase
Construction
Completion Date
2023-10-31T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3965
Reporting Period
202309
Managing Agency
DDC
Pid
3965
Agency Project Name
Broadway Interior Renovation
Current Phase
Construction
Completion Date
2023-10-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2023-09-01T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3965
Reporting Period
202401
Managing Agency
DDC
Pid
3965
Agency Project Name
Broadway Interior Renovation
Current Phase
Construction
Completion Date
2023-10-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2023-09-01T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3965
Reporting Period
202405
Managing Agency
DDC
Pid
3965
Agency Project Name
Broadway Interior Renovation
Current Phase
Construction
Completion Date
2023-10-31T00:00:00.000
Completion Date Type
Actual
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3966
Reporting Period
202305
Managing Agency
DDC
Pid
3966
Agency Project Name
Bronx Animal Care Center
Current Phase
Construction
Completion Date
2025-02-28T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3966
Reporting Period
202309
Managing Agency
DDC
Pid
3966
Agency Project Name
Bronx Animal Care Center
Current Phase
Construction
Completion Date
2025-02-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3966
Reporting Period
202401
Managing Agency
DDC
Pid
3966
Agency Project Name
Bronx Animal Care Center
Current Phase
Construction
Completion Date
2025-02-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3966
Reporting Period
202405
Managing Agency
DDC
Pid
3966
Agency Project Name
Bronx Animal Care Center
Current Phase
Construction
Completion Date
2025-09-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
199
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN HAZARDOUS CONDITIONS
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 3966
Reporting Period
202409
Managing Agency
DDC
Pid
3966
Agency Project Name
Bronx Animal Care Center
Current Phase
Construction
Completion Date
2025-09-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 3966
Reporting Period
202501
Managing Agency
DDC
Pid
3966
Agency Project Name
Bronx Animal Care Center
Current Phase
Construction
Completion Date
2025-09-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 3966
Reporting Period
202505
Managing Agency
DDC
Pid
3966
Agency Project Name
Bronx Animal Care Center
Current Phase
Construction
Completion Date
2026-01-05T00:00:00.000
Completion Date Type
Forecast
Variance Day
112
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 3966
Reporting Period
202509
Managing Agency
DDC
Pid
3966
Agency Project Name
Bronx Animal Care Center
Current Phase
Construction
Completion Date
2026-03-04T00:00:00.000
Completion Date Type
Forecast
Variance Day
58
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 3966
Reporting Period
202601
Managing Agency
DDC
Pid
3966
Agency Project Name
Bronx Animal Care Center
Current Phase
Construction
Completion Date
2026-07-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
149
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 3966
Reporting Period
202605
Managing Agency
DDC
Pid
3966
Agency Project Name
Bronx Animal Care Center
Current Phase
Construction
Completion Date
2026-11-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
122
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3967
Reporting Period
202305
Managing Agency
DDC
Pid
3967
Agency Project Name
851 GRAND CONCOURSE - FACADE REPAIRS LOCAL LAW 11
Current Phase
Construction Procurement
Completion Date
2027-02-28T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3967
Reporting Period
202309
Managing Agency
DDC
Pid
3967
Agency Project Name
851 GRAND CONCOURSE - FACADE REPAIRS LOCAL LAW 11
Current Phase
Construction Procurement
Completion Date
2027-02-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3967
Reporting Period
202401
Managing Agency
DDC
Pid
3967
Agency Project Name
851 GRAND CONCOURSE - FACADE REPAIRS LOCAL LAW 11
Current Phase
Construction Procurement
Completion Date
2027-02-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3967
Reporting Period
202405
Managing Agency
DDC
Pid
3967
Agency Project Name
851 GRAND CONCOURSE - FACADE REPAIRS LOCAL LAW 11
Current Phase
Construction
Completion Date
2026-06-28T00:00:00.000
Completion Date Type
Forecast
Variance Day
-245
Data Date
2024-07-18T00:00:00.000