Capital Projects Dashboard - Citywide Schedule History and Variance

This is the history all agency reported forecasts/actual project completion dates. Each row is the snapshot of data taken on each reporting period. The 'completion date type' column shows if the 'completion date' is either a forecast or actual date. Over time, a project would have one or more forecasted completion dates before it is actually completed. The 'variance' is the day difference between 'completion date' of each row and its prior reporting period. This dataset is part of the Capital Projects Dashboard.

City Government Mayor's Office of Operations (OPS) Dataset 95tx-snak 10 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 3972
Reporting Period
202601
Managing Agency
DDC
Pid
3972
Agency Project Name
Brooklyn Children's Museum Retaining Wall
Current Phase
Construction
Completion Date
2026-05-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 3972
Reporting Period
202605
Managing Agency
DDC
Pid
3972
Agency Project Name
Brooklyn Children's Museum Retaining Wall
Current Phase
Construction
Completion Date
2026-08-17T00:00:00.000
Completion Date Type
Forecast
Variance Day
80
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3973
Reporting Period
202305
Managing Agency
DDC
Pid
3973
Agency Project Name
Brooklyn Historic Society HVAC Replacement
Current Phase
Construction Procurement
Completion Date
2025-05-26T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3973
Reporting Period
202309
Managing Agency
DDC
Pid
3973
Agency Project Name
Brooklyn Historic Society HVAC Replacement
Current Phase
Construction Procurement
Completion Date
2025-12-27T00:00:00.000
Completion Date Type
Forecast
Variance Day
215
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3973
Reporting Period
202401
Managing Agency
DDC
Pid
3973
Agency Project Name
Brooklyn Historic Society HVAC Replacement
Current Phase
Construction Procurement
Completion Date
2025-12-27T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3973
Reporting Period
202405
Managing Agency
DDC
Pid
3973
Agency Project Name
Brooklyn Historic Society HVAC Replacement
Current Phase
Construction Procurement
Completion Date
2026-03-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
94
Reason For Forecast Completion Change
PROJECT DELAYED PENDING APPROVAL OF NECESSARY PERMITS
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 3973
Reporting Period
202409
Managing Agency
DDC
Pid
3973
Agency Project Name
Brooklyn Historic Society HVAC Replacement
Current Phase
Construction
Completion Date
2026-03-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 3973
Reporting Period
202501
Managing Agency
DDC
Pid
3973
Agency Project Name
Brooklyn Historic Society HVAC Replacement
Current Phase
Construction
Completion Date
2026-03-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 3973
Reporting Period
202505
Managing Agency
DDC
Pid
3973
Agency Project Name
Brooklyn Historic Society HVAC Replacement
Current Phase
Construction
Completion Date
2026-07-20T00:00:00.000
Completion Date Type
Forecast
Variance Day
111
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 3973
Reporting Period
202509
Managing Agency
DDC
Pid
3973
Agency Project Name
Brooklyn Historic Society HVAC Replacement
Current Phase
Construction
Completion Date
2026-07-20T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 3973
Reporting Period
202601
Managing Agency
DDC
Pid
3973
Agency Project Name
Brooklyn Historic Society HVAC Replacement
Current Phase
Construction
Completion Date
2026-07-20T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 3973
Reporting Period
202605
Managing Agency
DDC
Pid
3973
Agency Project Name
Brooklyn Historic Society HVAC Replacement
Current Phase
Close-out
Completion Date
2026-05-08T00:00:00.000
Completion Date Type
Actual
Variance Day
-73
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3974
Reporting Period
202305
Managing Agency
DDC
Pid
3974
Agency Project Name
Brooklyn Supreme Court Facade Rehabilitation
Current Phase
Design
Completion Date
2026-10-23T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3974
Reporting Period
202309
Managing Agency
DDC
Pid
3974
Agency Project Name
Brooklyn Supreme Court Facade Rehabilitation
Current Phase
Design
Completion Date
2027-06-22T00:00:00.000
Completion Date Type
Forecast
Variance Day
242
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3974
Reporting Period
202401
Managing Agency
DDC
Pid
3974
Agency Project Name
Brooklyn Supreme Court Facade Rehabilitation
Current Phase
Design
Completion Date
2027-06-22T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3974
Reporting Period
202405
Managing Agency
DDC
Pid
3974
Agency Project Name
Brooklyn Supreme Court Facade Rehabilitation
Current Phase
Design
Completion Date
2027-06-22T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 3974
Reporting Period
202409
Managing Agency
DDC
Pid
3974
Agency Project Name
Brooklyn Supreme Court Facade Rehabilitation
Current Phase
Design
Completion Date
2027-06-22T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 3974
Reporting Period
202501
Managing Agency
DDC
Pid
3974
Agency Project Name
Brooklyn Supreme Court Facade Rehabilitation
Current Phase
Construction Procurement
Completion Date
2027-06-22T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 3974
Reporting Period
202505
Managing Agency
DDC
Pid
3974
Agency Project Name
Brooklyn Supreme Court Facade Rehabilitation
Current Phase
Construction Procurement
Completion Date
2027-06-22T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 3974
Reporting Period
202509
Managing Agency
DDC
Pid
3974
Agency Project Name
Brooklyn Supreme Court Facade Rehabilitation
Current Phase
Construction
Completion Date
2027-09-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
85
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 3974
Reporting Period
202601
Managing Agency
DDC
Pid
3974
Agency Project Name
Brooklyn Supreme Court Facade Rehabilitation
Current Phase
Construction
Completion Date
2027-09-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 3974
Reporting Period
202605
Managing Agency
DDC
Pid
3974
Agency Project Name
Brooklyn Supreme Court Facade Rehabilitation
Current Phase
Construction
Completion Date
2028-03-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
198
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN HAZARDOUS CONDITION
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3975
Reporting Period
202305
Managing Agency
DDC
Pid
3975
Agency Project Name
Brooklyn Supreme court 360 Adams Fire Alarms
Current Phase
Design
Completion Date
2031-12-30T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3975
Reporting Period
202309
Managing Agency
DDC
Pid
3975
Agency Project Name
Brooklyn Supreme court 360 Adams Fire Alarms
Current Phase
Design
Completion Date
2032-09-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
275
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3975
Reporting Period
202401
Managing Agency
DDC
Pid
3975
Agency Project Name
Brooklyn Supreme court 360 Adams Fire Alarms
Current Phase
Design
Completion Date
2032-09-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3975
Reporting Period
202405
Managing Agency
DDC
Pid
3975
Agency Project Name
Brooklyn Supreme court 360 Adams Fire Alarms
Current Phase
Construction Procurement
Completion Date
2032-09-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 3975
Reporting Period
202409
Managing Agency
DDC
Pid
3975
Agency Project Name
Brooklyn Supreme court 360 Adams Fire Alarms
Current Phase
Construction Procurement
Completion Date
2032-09-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 3975
Reporting Period
202501
Managing Agency
DDC
Pid
3975
Agency Project Name
Brooklyn Supreme court 360 Adams Fire Alarms
Current Phase
Construction Procurement
Completion Date
2032-09-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-03-03T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 3975
Reporting Period
202505
Managing Agency
DDC
Pid
3975
Agency Project Name
Brooklyn Supreme court 360 Adams Fire Alarms
Current Phase
Construction Procurement
Completion Date
2032-09-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-03-03T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 3975
Reporting Period
202509
Managing Agency
DDC
Pid
3975
Agency Project Name
Brooklyn Supreme court 360 Adams Fire Alarms
Current Phase
Construction Procurement
Completion Date
2032-09-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 3975
Reporting Period
202601
Managing Agency
DDC
Pid
3975
Agency Project Name
Brooklyn Supreme court 360 Adams Fire Alarms
Current Phase
Construction Procurement
Completion Date
2032-09-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-20T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 3975
Reporting Period
202605
Managing Agency
DDC
Pid
3975
Agency Project Name
Brooklyn Supreme court 360 Adams Fire Alarms
Current Phase
Construction Procurement
Completion Date
2032-09-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-20T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3976
Reporting Period
202305
Managing Agency
DDC
Pid
3976
Agency Project Name
BROWNSVILLE PEDESTRIAN SAFETY IMPROVEMENTS
Current Phase
Design
Completion Date
2027-05-27T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3976
Reporting Period
202309
Managing Agency
DDC
Pid
3976
Agency Project Name
BROWNSVILLE PEDESTRIAN SAFETY IMPROVEMENTS
Current Phase
Design
Completion Date
2027-07-26T00:00:00.000
Completion Date Type
Forecast
Variance Day
60
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3976
Reporting Period
202401
Managing Agency
DDC
Pid
3976
Agency Project Name
BROWNSVILLE PEDESTRIAN SAFETY IMPROVEMENTS
Current Phase
Design
Completion Date
2027-07-26T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3976
Reporting Period
202405
Managing Agency
DDC
Pid
3976
Agency Project Name
BROWNSVILLE PEDESTRIAN SAFETY IMPROVEMENTS
Current Phase
Design
Completion Date
2027-07-26T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 3976
Reporting Period
202409
Managing Agency
DDC
Pid
3976
Agency Project Name
BROWNSVILLE PEDESTRIAN SAFETY IMPROVEMENTS
Current Phase
Design
Completion Date
2028-01-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
188
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 3976
Reporting Period
202501
Managing Agency
DDC
Pid
3976
Agency Project Name
BROWNSVILLE PEDESTRIAN SAFETY IMPROVEMENTS
Current Phase
Design
Completion Date
2028-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
152
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 3976
Reporting Period
202505
Managing Agency
DDC
Pid
3976
Agency Project Name
BROWNSVILLE PEDESTRIAN SAFETY IMPROVEMENTS
Current Phase
Design
Completion Date
2028-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 3976
Reporting Period
202509
Managing Agency
DDC
Pid
3976
Agency Project Name
BROWNSVILLE PEDESTRIAN SAFETY IMPROVEMENTS
Current Phase
Design
Completion Date
2029-05-04T00:00:00.000
Completion Date Type
Forecast
Variance Day
308
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 3976
Reporting Period
202601
Managing Agency
DDC
Pid
3976
Agency Project Name
BROWNSVILLE PEDESTRIAN SAFETY IMPROVEMENTS
Current Phase
Design
Completion Date
2029-05-04T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 3976
Reporting Period
202605
Managing Agency
DDC
Pid
3976
Agency Project Name
BROWNSVILLE PEDESTRIAN SAFETY IMPROVEMENTS
Current Phase
Design
Completion Date
2029-05-04T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3977
Reporting Period
202305
Managing Agency
DDC
Pid
3977
Agency Project Name
BRUNER AND ELY
Current Phase
Design
Completion Date
2028-02-14T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3977
Reporting Period
202309
Managing Agency
DDC
Pid
3977
Agency Project Name
BRUNER AND ELY
Current Phase
Construction Procurement
Completion Date
2028-02-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3977
Reporting Period
202401
Managing Agency
DDC
Pid
3977
Agency Project Name
BRUNER AND ELY
Current Phase
Construction Procurement
Completion Date
2028-02-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3977
Reporting Period
202405
Managing Agency
DDC
Pid
3977
Agency Project Name
BRUNER AND ELY
Current Phase
Construction Procurement
Completion Date
2028-02-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 3977
Reporting Period
202409
Managing Agency
DDC
Pid
3977
Agency Project Name
BRUNER AND ELY
Current Phase
Construction Procurement
Completion Date
2028-02-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 3977
Reporting Period
202501
Managing Agency
DDC
Pid
3977
Agency Project Name
BRUNER AND ELY
Current Phase
Construction Procurement
Completion Date
2028-02-14T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 3977
Reporting Period
202505
Managing Agency
DDC
Pid
3977
Agency Project Name
BRUNER AND ELY
Current Phase
Construction Procurement
Completion Date
2028-02-24T00:00:00.000
Completion Date Type
Forecast
Variance Day
10
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 3977
Reporting Period
202509
Managing Agency
DDC
Pid
3977
Agency Project Name
BRUNER AND ELY
Current Phase
Construction Procurement
Completion Date
2028-03-12T00:00:00.000
Completion Date Type
Forecast
Variance Day
17
Data Date
2025-10-23T00:00:00.000