Capital Projects Dashboard - Citywide Schedule History and Variance

This is the history all agency reported forecasts/actual project completion dates. Each row is the snapshot of data taken on each reporting period. The 'completion date type' column shows if the 'completion date' is either a forecast or actual date. Over time, a project would have one or more forecasted completion dates before it is actually completed. The 'variance' is the day difference between 'completion date' of each row and its prior reporting period. This dataset is part of the Capital Projects Dashboard.

City Government Mayor's Office of Operations (OPS) Dataset 95tx-snak 10 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 3997
Reporting Period
202501
Managing Agency
DDC
Pid
3997
Agency Project Name
Coastal Resiliency -- Parallel Conveyances
Current Phase
Construction
Completion Date
2026-09-11T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 3997
Reporting Period
202505
Managing Agency
DDC
Pid
3997
Agency Project Name
Coastal Resiliency -- Parallel Conveyances
Current Phase
Construction
Completion Date
2026-09-11T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 3997
Reporting Period
202509
Managing Agency
DDC
Pid
3997
Agency Project Name
Coastal Resiliency -- Parallel Conveyances
Current Phase
Construction
Completion Date
2026-09-11T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 3997
Reporting Period
202601
Managing Agency
DDC
Pid
3997
Agency Project Name
Coastal Resiliency -- Parallel Conveyances
Current Phase
Construction
Completion Date
2026-09-11T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 3997
Reporting Period
202605
Managing Agency
DDC
Pid
3997
Agency Project Name
Coastal Resiliency -- Parallel Conveyances
Current Phase
Construction
Completion Date
2026-09-11T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3998
Reporting Period
202305
Managing Agency
DDC
Pid
3998
Agency Project Name
COMBINED SEWER IN 70TH STREET, QUEENS
Current Phase
Construction
Completion Date
2024-04-30T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3998
Reporting Period
202309
Managing Agency
DDC
Pid
3998
Agency Project Name
COMBINED SEWER IN 70TH STREET, QUEENS
Current Phase
Construction
Completion Date
2024-04-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3998
Reporting Period
202401
Managing Agency
DDC
Pid
3998
Agency Project Name
COMBINED SEWER IN 70TH STREET, QUEENS
Current Phase
Construction
Completion Date
2024-04-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3998
Reporting Period
202405
Managing Agency
DDC
Pid
3998
Agency Project Name
COMBINED SEWER IN 70TH STREET, QUEENS
Current Phase
Construction
Completion Date
2024-04-18T00:00:00.000
Completion Date Type
Actual
Variance Day
-12
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 3999
Reporting Period
202305
Managing Agency
DDC
Pid
3999
Agency Project Name
PACIFIC PARK PROJECT PHASE II
Current Phase
Construction
Completion Date
2025-09-25T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 3999
Reporting Period
202309
Managing Agency
DDC
Pid
3999
Agency Project Name
PACIFIC PARK PROJECT PHASE II
Current Phase
Construction
Completion Date
2025-11-12T00:00:00.000
Completion Date Type
Forecast
Variance Day
48
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 3999
Reporting Period
202401
Managing Agency
DDC
Pid
3999
Agency Project Name
PACIFIC PARK PROJECT PHASE II
Current Phase
Construction
Completion Date
2025-11-12T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 3999
Reporting Period
202405
Managing Agency
DDC
Pid
3999
Agency Project Name
PACIFIC PARK PROJECT PHASE II
Current Phase
Construction
Completion Date
2025-11-12T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 3999
Reporting Period
202409
Managing Agency
DDC
Pid
3999
Agency Project Name
PACIFIC PARK PROJECT PHASE II
Current Phase
Construction
Completion Date
2025-11-12T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 3999
Reporting Period
202501
Managing Agency
DDC
Pid
3999
Agency Project Name
PACIFIC PARK PROJECT PHASE II
Current Phase
Construction
Completion Date
2025-11-12T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 3999
Reporting Period
202505
Managing Agency
DDC
Pid
3999
Agency Project Name
PACIFIC PARK PROJECT PHASE II
Current Phase
Construction
Completion Date
2025-11-12T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 3999
Reporting Period
202509
Managing Agency
DDC
Pid
3999
Agency Project Name
PACIFIC PARK PROJECT PHASE II
Current Phase
Construction
Completion Date
2025-11-12T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 3999
Reporting Period
202601
Managing Agency
DDC
Pid
3999
Agency Project Name
PACIFIC PARK PROJECT PHASE II
Current Phase
Construction
Completion Date
2027-06-19T00:00:00.000
Completion Date Type
Forecast
Variance Day
584
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO SCHEDULING OF UTILITY WORK
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 3999
Reporting Period
202605
Managing Agency
DDC
Pid
3999
Agency Project Name
PACIFIC PARK PROJECT PHASE II
Current Phase
Construction
Completion Date
2027-06-19T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4000
Reporting Period
202305
Managing Agency
DDC
Pid
4000
Agency Project Name
COMBINED SEWER & GUNITING IN WEST BROADWAY
Current Phase
Construction
Completion Date
2024-05-01T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4000
Reporting Period
202309
Managing Agency
DDC
Pid
4000
Agency Project Name
COMBINED SEWER & GUNITING IN WEST BROADWAY
Current Phase
Construction
Completion Date
2024-05-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4000
Reporting Period
202401
Managing Agency
DDC
Pid
4000
Agency Project Name
COMBINED SEWER & GUNITING IN WEST BROADWAY
Current Phase
Construction
Completion Date
2024-05-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4000
Reporting Period
202405
Managing Agency
DDC
Pid
4000
Agency Project Name
COMBINED SEWER & GUNITING IN WEST BROADWAY
Current Phase
Construction
Completion Date
2024-04-23T00:00:00.000
Completion Date Type
Actual
Variance Day
-8
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4001
Reporting Period
202305
Managing Agency
DDC
Pid
4001
Agency Project Name
COMBINED SEWER REPLACEMENT IN PRESIDENT STREET, BK
Current Phase
Construction
Completion Date
2025-09-09T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4001
Reporting Period
202309
Managing Agency
DDC
Pid
4001
Agency Project Name
COMBINED SEWER REPLACEMENT IN PRESIDENT STREET, BK
Current Phase
Construction
Completion Date
2025-09-09T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4001
Reporting Period
202401
Managing Agency
DDC
Pid
4001
Agency Project Name
COMBINED SEWER REPLACEMENT IN PRESIDENT STREET, BK
Current Phase
Construction
Completion Date
2025-09-09T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4001
Reporting Period
202405
Managing Agency
DDC
Pid
4001
Agency Project Name
COMBINED SEWER REPLACEMENT IN PRESIDENT STREET, BK
Current Phase
Construction
Completion Date
2025-09-09T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4001
Reporting Period
202409
Managing Agency
DDC
Pid
4001
Agency Project Name
COMBINED SEWER REPLACEMENT IN PRESIDENT STREET, BK
Current Phase
Construction
Completion Date
2025-09-09T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4001
Reporting Period
202501
Managing Agency
DDC
Pid
4001
Agency Project Name
COMBINED SEWER REPLACEMENT IN PRESIDENT STREET, BK
Current Phase
Construction
Completion Date
2025-09-09T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4001
Reporting Period
202505
Managing Agency
DDC
Pid
4001
Agency Project Name
COMBINED SEWER REPLACEMENT IN PRESIDENT STREET, BK
Current Phase
Construction
Completion Date
2025-09-09T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4001
Reporting Period
202509
Managing Agency
DDC
Pid
4001
Agency Project Name
COMBINED SEWER REPLACEMENT IN PRESIDENT STREET, BK
Current Phase
Construction
Completion Date
2026-07-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
325
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4001
Reporting Period
202601
Managing Agency
DDC
Pid
4001
Agency Project Name
COMBINED SEWER REPLACEMENT IN PRESIDENT STREET, BK
Current Phase
Close-out
Completion Date
2025-11-12T00:00:00.000
Completion Date Type
Actual
Variance Day
-261
Data Date
2026-03-20T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4002
Reporting Period
202305
Managing Agency
DDC
Pid
4002
Agency Project Name
LAH - Louis Armstrong House - Administration Facil
Current Phase
Construction Procurement
Completion Date
2025-11-10T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4002
Reporting Period
202309
Managing Agency
DDC
Pid
4002
Agency Project Name
LAH - Louis Armstrong House - Administration Facil
Current Phase
Construction Procurement
Completion Date
2026-01-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
52
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4002
Reporting Period
202401
Managing Agency
DDC
Pid
4002
Agency Project Name
LAH - Louis Armstrong House - Administration Facil
Current Phase
Construction Procurement
Completion Date
2026-01-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4002
Reporting Period
202405
Managing Agency
DDC
Pid
4002
Agency Project Name
LAH - Louis Armstrong House - Administration Facil
Current Phase
Construction Procurement
Completion Date
2026-01-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4002
Reporting Period
202409
Managing Agency
DDC
Pid
4002
Agency Project Name
LAH - Louis Armstrong House - Administration Facil
Current Phase
Construction Procurement
Completion Date
2026-06-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
151
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO BUDGETARY CONSTRAINTS
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4002
Reporting Period
202501
Managing Agency
DDC
Pid
4002
Agency Project Name
LAH - Louis Armstrong House - Administration Facil
Current Phase
Construction
Completion Date
2026-06-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4002
Reporting Period
202505
Managing Agency
DDC
Pid
4002
Agency Project Name
LAH - Louis Armstrong House - Administration Facil
Current Phase
Construction
Completion Date
2026-06-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4002
Reporting Period
202509
Managing Agency
DDC
Pid
4002
Agency Project Name
LAH - Louis Armstrong House - Administration Facil
Current Phase
Construction
Completion Date
2026-07-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
60
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4002
Reporting Period
202601
Managing Agency
DDC
Pid
4002
Agency Project Name
LAH - Louis Armstrong House - Administration Facil
Current Phase
Construction
Completion Date
2026-07-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4002
Reporting Period
202605
Managing Agency
DDC
Pid
4002
Agency Project Name
LAH - Louis Armstrong House - Administration Facil
Current Phase
Construction
Completion Date
2026-09-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
61
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4003
Reporting Period
202305
Managing Agency
DDC
Pid
4003
Agency Project Name
COMPLEX PED. RAMPS - TRANSIT AUTHORITY, BX & MN
Current Phase
Construction
Completion Date
2023-11-15T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4003
Reporting Period
202309
Managing Agency
DDC
Pid
4003
Agency Project Name
COMPLEX PED. RAMPS - TRANSIT AUTHORITY, BX & MN
Current Phase
Construction
Completion Date
2023-11-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2023-09-01T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4003
Reporting Period
202401
Managing Agency
DDC
Pid
4003
Agency Project Name
COMPLEX PED. RAMPS - TRANSIT AUTHORITY, BX & MN
Current Phase
Construction
Completion Date
2023-11-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2023-09-01T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4003
Reporting Period
202405
Managing Agency
DDC
Pid
4003
Agency Project Name
COMPLEX PED. RAMPS - TRANSIT AUTHORITY, BX & MN
Current Phase
Construction
Completion Date
2023-10-26T00:00:00.000
Completion Date Type
Actual
Variance Day
-20
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4004
Reporting Period
202305
Managing Agency
DDC
Pid
4004
Agency Project Name
CITYWIDE COMPLEX PEDESTRIAN RAMPS-TA, BK & QNS
Current Phase
Construction Procurement
Completion Date
2025-09-08T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4004
Reporting Period
202309
Managing Agency
DDC
Pid
4004
Agency Project Name
CITYWIDE COMPLEX PEDESTRIAN RAMPS-TA, BK & QNS
Current Phase
Construction
Completion Date
2025-09-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4004
Reporting Period
202401
Managing Agency
DDC
Pid
4004
Agency Project Name
CITYWIDE COMPLEX PEDESTRIAN RAMPS-TA, BK & QNS
Current Phase
Construction
Completion Date
2025-09-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4004
Reporting Period
202405
Managing Agency
DDC
Pid
4004
Agency Project Name
CITYWIDE COMPLEX PEDESTRIAN RAMPS-TA, BK & QNS
Current Phase
Construction
Completion Date
2025-09-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000