Capital Projects Dashboard - Citywide Schedule History and Variance

This is the history all agency reported forecasts/actual project completion dates. Each row is the snapshot of data taken on each reporting period. The 'completion date type' column shows if the 'completion date' is either a forecast or actual date. Over time, a project would have one or more forecasted completion dates before it is actually completed. The 'variance' is the day difference between 'completion date' of each row and its prior reporting period. This dataset is part of the Capital Projects Dashboard.

City Government Mayor's Office of Operations (OPS) Dataset 95tx-snak 10 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4077
Reporting Period
202409
Managing Agency
DDC
Pid
4077
Agency Project Name
FY24 Standard Pedestrian Ramp Installations at Priority Unramped Locations Citywide
Current Phase
Construction Procurement
Completion Date
2027-06-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
350
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4077
Reporting Period
202501
Managing Agency
DDC
Pid
4077
Agency Project Name
FY24 Standard Pedestrian Ramp Installations at Priority Unramped Locations Citywide
Current Phase
Construction Procurement
Completion Date
2027-06-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4077
Reporting Period
202505
Managing Agency
DDC
Pid
4077
Agency Project Name
FY24 Standard Pedestrian Ramp Installations at Priority Unramped Locations Citywide
Current Phase
Construction
Completion Date
2027-06-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4077
Reporting Period
202509
Managing Agency
DDC
Pid
4077
Agency Project Name
FY24 Standard Pedestrian Ramp Installations at Priority Unramped Locations Citywide
Current Phase
Construction
Completion Date
2027-06-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4077
Reporting Period
202601
Managing Agency
DDC
Pid
4077
Agency Project Name
FY24 Standard Pedestrian Ramp Installations at Priority Unramped Locations Citywide
Current Phase
Construction
Completion Date
2027-06-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4077
Reporting Period
202605
Managing Agency
DDC
Pid
4077
Agency Project Name
FY24 Standard Pedestrian Ramp Installations at Priority Unramped Locations Citywide
Current Phase
Construction
Completion Date
2027-06-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4078
Reporting Period
202305
Managing Agency
DDC
Pid
4078
Agency Project Name
Brooklyn District 6 Sanitation Garage: Rehab.
Current Phase
Construction Procurement
Completion Date
2027-10-27T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4078
Reporting Period
202309
Managing Agency
DDC
Pid
4078
Agency Project Name
Brooklyn District 6 Sanitation Garage: Rehab.
Current Phase
Construction Procurement
Completion Date
2027-10-27T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2023-09-01T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4078
Reporting Period
202401
Managing Agency
DDC
Pid
4078
Agency Project Name
Brooklyn District 6 Sanitation Garage: Rehab.
Current Phase
Construction Procurement
Completion Date
2027-10-27T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2023-09-01T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4078
Reporting Period
202405
Managing Agency
DDC
Pid
4078
Agency Project Name
Brooklyn District 6 Sanitation Garage: Rehab.
Current Phase
Construction Procurement
Completion Date
2027-10-27T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4078
Reporting Period
202409
Managing Agency
DDC
Pid
4078
Agency Project Name
Brooklyn District 6 Sanitation Garage: Rehab.
Current Phase
Construction Procurement
Completion Date
2027-10-27T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4079
Reporting Period
202305
Managing Agency
DDC
Pid
4079
Agency Project Name
George Bruce Interior, Pr Roof and Boiler upgrade
Current Phase
Design
Completion Date
2026-11-10T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4079
Reporting Period
202309
Managing Agency
DDC
Pid
4079
Agency Project Name
George Bruce Interior, Pr Roof and Boiler upgrade
Current Phase
Design
Completion Date
2026-11-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4079
Reporting Period
202401
Managing Agency
DDC
Pid
4079
Agency Project Name
George Bruce Interior, Pr Roof and Boiler upgrade
Current Phase
Design
Completion Date
2026-11-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4079
Reporting Period
202405
Managing Agency
DDC
Pid
4079
Agency Project Name
George Bruce Library Exterior Renovation
Current Phase
Design
Completion Date
2027-04-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
151
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4079
Reporting Period
202409
Managing Agency
DDC
Pid
4079
Agency Project Name
George Bruce Library Exterior Renovation
Current Phase
Design
Completion Date
2027-11-04T00:00:00.000
Completion Date Type
Forecast
Variance Day
208
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4079
Reporting Period
202501
Managing Agency
DDC
Pid
4079
Agency Project Name
George Bruce Library Exterior Renovation
Current Phase
Design
Completion Date
2028-03-16T00:00:00.000
Completion Date Type
Forecast
Variance Day
133
Reason For Forecast Completion Change
PROJECT DELAYED PENDING APPROVAL OF NECESSARY PERMITS
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4079
Reporting Period
202505
Managing Agency
DDC
Pid
4079
Agency Project Name
George Bruce Library Exterior Renovation
Current Phase
Design
Completion Date
2028-05-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
76
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4079
Reporting Period
202509
Managing Agency
DDC
Pid
4079
Agency Project Name
George Bruce Library Exterior Renovation
Current Phase
Design
Completion Date
2028-04-03T00:00:00.000
Completion Date Type
Forecast
Variance Day
-58
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4079
Reporting Period
202601
Managing Agency
DDC
Pid
4079
Agency Project Name
George Bruce Library Exterior Renovation
Current Phase
Design
Completion Date
2029-01-26T00:00:00.000
Completion Date Type
Forecast
Variance Day
298
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4079
Reporting Period
202605
Managing Agency
DDC
Pid
4079
Agency Project Name
George Bruce Library Exterior Renovation
Current Phase
Construction Procurement
Completion Date
2029-01-26T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4080
Reporting Period
202305
Managing Agency
DDC
Pid
4080
Agency Project Name
George Bruce HVAC, Boiler,BMS & Fire Alarm Upgrade
Current Phase
Construction
Completion Date
2023-11-30T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4080
Reporting Period
202309
Managing Agency
DDC
Pid
4080
Agency Project Name
George Bruce HVAC, Boiler,BMS & Fire Alarm Upgrade
Current Phase
Construction
Completion Date
2024-02-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
91
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4080
Reporting Period
202401
Managing Agency
DDC
Pid
4080
Agency Project Name
George Bruce HVAC, Boiler,BMS & Fire Alarm Upgrade
Current Phase
Construction
Completion Date
2024-02-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4080
Reporting Period
202405
Managing Agency
DDC
Pid
4080
Agency Project Name
George Bruce HVAC, Boiler,BMS & Fire Alarm Upgrade
Current Phase
Construction
Completion Date
2024-07-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
153
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNAVAILABILITY OF PRODUCT
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4080
Reporting Period
202409
Managing Agency
DDC
Pid
4080
Agency Project Name
George Bruce HVAC, Boiler,BMS & Fire Alarm Upgrade
Current Phase
Construction
Completion Date
2025-01-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
183
Reason For Forecast Completion Change
PROJECT DELAYED PENDING APPROVAL OF NECESSARY PERMITS
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4080
Reporting Period
202501
Managing Agency
DDC
Pid
4080
Agency Project Name
George Bruce HVAC, Boiler,BMS & Fire Alarm Upgrade
Current Phase
Construction
Completion Date
2025-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
151
Reason For Forecast Completion Change
PROJECT DELAYED PENDING APPROVAL OF NECESSARY PERMITS
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4080
Reporting Period
202505
Managing Agency
DDC
Pid
4080
Agency Project Name
George Bruce HVAC, Boiler,BMS & Fire Alarm Upgrade
Current Phase
Construction
Completion Date
2025-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4080
Reporting Period
202509
Managing Agency
DDC
Pid
4080
Agency Project Name
George Bruce HVAC, Boiler,BMS & Fire Alarm Upgrade
Current Phase
Construction
Completion Date
2025-12-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
183
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4080
Reporting Period
202601
Managing Agency
DDC
Pid
4080
Agency Project Name
George Bruce HVAC, Boiler,BMS & Fire Alarm Upgrade
Current Phase
Construction
Completion Date
2026-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
182
Reason For Forecast Completion Change
PROJECT DELAYED PENDING APPROVAL OF NECESSARY PERMITS
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4080
Reporting Period
202605
Managing Agency
DDC
Pid
4080
Agency Project Name
George Bruce HVAC, Boiler,BMS & Fire Alarm Upgrade
Current Phase
Construction
Completion Date
2026-10-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
122
Reason For Forecast Completion Change
PROJECT DELAYED PENDING APPROVAL OF NECESSARY PERMITS
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4081
Reporting Period
202305
Managing Agency
DDC
Pid
4081
Agency Project Name
GI - DSGN & CONST OF BIOSWALES & GREENSTREETS, QUE
Current Phase
Construction Procurement
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4081
Reporting Period
202309
Managing Agency
DDC
Pid
4081
Agency Project Name
GI - DSGN & CONST OF BIOSWALES & GREENSTREETS, QUE
Current Phase
Construction Procurement
Completion Date Type
Forecast
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4081
Reporting Period
202401
Managing Agency
DDC
Pid
4081
Agency Project Name
GI - DSGN & CONST OF BIOSWALES & GREENSTREETS, QUE
Current Phase
Construction Procurement
Completion Date Type
Forecast
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4081
Reporting Period
202405
Managing Agency
DDC
Pid
4081
Agency Project Name
GI - DSGN & CONST OF BIOSWALES & GREENSTREETS, QUE
Current Phase
Construction Procurement
Completion Date Type
Forecast
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4081
Reporting Period
202409
Managing Agency
DDC
Pid
4081
Agency Project Name
GI - DSGN & CONST OF BIOSWALES & GREENSTREETS, QUE
Current Phase
Construction Procurement
Completion Date Type
Forecast
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4081
Reporting Period
202501
Managing Agency
DDC
Pid
4081
Agency Project Name
GI - DSGN & CONST OF BIOSWALES & GREENSTREETS, QUE
Current Phase
Construction Procurement
Completion Date Type
Forecast
Data Date
2025-03-03T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4082
Reporting Period
202305
Managing Agency
DDC
Pid
4082
Agency Project Name
GREEN INFRASTRUCTURE IN TI-003 & TI-023 EAST RIVER
Current Phase
Construction
Completion Date
2024-03-09T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4082
Reporting Period
202309
Managing Agency
DDC
Pid
4082
Agency Project Name
GREEN INFRASTRUCTURE IN TI-003 & TI-023 EAST RIVER
Current Phase
Construction
Completion Date
2024-03-09T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4082
Reporting Period
202401
Managing Agency
DDC
Pid
4082
Agency Project Name
GREEN INFRASTRUCTURE IN TI-003 & TI-023 EAST RIVER
Current Phase
Construction
Completion Date
2024-03-09T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4082
Reporting Period
202405
Managing Agency
DDC
Pid
4082
Agency Project Name
GREEN INFRASTRUCTURE IN TI-003 & TI-023 EAST RIVER
Current Phase
Construction
Completion Date
2024-06-28T00:00:00.000
Completion Date Type
Actual
Variance Day
111
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4083
Reporting Period
202305
Managing Agency
DDC
Pid
4083
Agency Project Name
GOWANUS CANAL 1 ST TURNING BASIN
Current Phase
Design
Completion Date
2026-09-09T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4083
Reporting Period
202309
Managing Agency
DDC
Pid
4083
Agency Project Name
GOWANUS CANAL 1 ST TURNING BASIN
Current Phase
Design
Completion Date
2026-09-09T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4083
Reporting Period
202401
Managing Agency
DDC
Pid
4083
Agency Project Name
GOWANUS CANAL 1 ST TURNING BASIN
Current Phase
Design
Completion Date
2026-09-09T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4083
Reporting Period
202405
Managing Agency
DDC
Pid
4083
Agency Project Name
GOWANUS CANAL 1 ST TURNING BASIN
Current Phase
Design
Completion Date
2026-09-09T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4083
Reporting Period
202409
Managing Agency
DDC
Pid
4083
Agency Project Name
GOWANUS CANAL 1 ST TURNING BASIN
Current Phase
Design
Completion Date
2026-09-09T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4083
Reporting Period
202501
Managing Agency
DDC
Pid
4083
Agency Project Name
GOWANUS CANAL 1 ST TURNING BASIN
Current Phase
Construction Procurement
Completion Date
2026-10-26T00:00:00.000
Completion Date Type
Forecast
Variance Day
47
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4083
Reporting Period
202505
Managing Agency
DDC
Pid
4083
Agency Project Name
GOWANUS CANAL 1 ST TURNING BASIN
Current Phase
Construction Procurement
Completion Date
2026-10-26T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4083
Reporting Period
202509
Managing Agency
DDC
Pid
4083
Agency Project Name
GOWANUS CANAL 1 ST TURNING BASIN
Current Phase
Construction Procurement
Completion Date
2026-10-26T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4083
Reporting Period
202601
Managing Agency
DDC
Pid
4083
Agency Project Name
GOWANUS CANAL 1 ST TURNING BASIN
Current Phase
Construction Procurement
Completion Date
2028-10-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
736
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2026-03-16T00:00:00.000