Capital Projects Dashboard - Citywide Schedule History and Variance

This is the history all agency reported forecasts/actual project completion dates. Each row is the snapshot of data taken on each reporting period. The 'completion date type' column shows if the 'completion date' is either a forecast or actual date. Over time, a project would have one or more forecasted completion dates before it is actually completed. The 'variance' is the day difference between 'completion date' of each row and its prior reporting period. This dataset is part of the Capital Projects Dashboard.

City Government Mayor's Office of Operations (OPS) Dataset 95tx-snak 10 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4083
Reporting Period
202605
Managing Agency
DDC
Pid
4083
Agency Project Name
GOWANUS CANAL 1 ST TURNING BASIN
Current Phase
Construction Procurement
Completion Date
2028-10-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4084
Reporting Period
202305
Managing Agency
DDC
Pid
4084
Agency Project Name
Gravesend Façade & Foundation Upgrade
Current Phase
Design
Completion Date
2025-12-23T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4084
Reporting Period
202309
Managing Agency
DDC
Pid
4084
Agency Project Name
Gravesend Façade & Foundation Upgrade
Current Phase
Construction Procurement
Completion Date
2025-12-23T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4084
Reporting Period
202401
Managing Agency
DDC
Pid
4084
Agency Project Name
Gravesend Façade & Foundation Upgrade
Current Phase
Construction Procurement
Completion Date
2025-12-23T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4084
Reporting Period
202405
Managing Agency
DDC
Pid
4084
Agency Project Name
Gravesend Façade & Foundation Upgrade
Current Phase
Construction Procurement
Completion Date
2025-12-23T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4084
Reporting Period
202409
Managing Agency
DDC
Pid
4084
Agency Project Name
Gravesend Façade & Foundation Upgrade
Current Phase
Construction Procurement
Completion Date
2026-03-18T00:00:00.000
Completion Date Type
Forecast
Variance Day
85
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4084
Reporting Period
202501
Managing Agency
DDC
Pid
4084
Agency Project Name
Gravesend Façade & Foundation Upgrade
Current Phase
Construction
Completion Date
2026-04-27T00:00:00.000
Completion Date Type
Forecast
Variance Day
40
Reason For Forecast Completion Change
PROJECT DELAYED PENDING RELEASE OF NEW TECHNOLOGY
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4084
Reporting Period
202505
Managing Agency
DDC
Pid
4084
Agency Project Name
Gravesend Façade & Foundation Upgrade
Current Phase
Construction
Completion Date
2026-04-27T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4084
Reporting Period
202509
Managing Agency
DDC
Pid
4084
Agency Project Name
Gravesend Façade & Foundation Upgrade
Current Phase
Construction
Completion Date
2026-04-27T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4084
Reporting Period
202601
Managing Agency
DDC
Pid
4084
Agency Project Name
Gravesend Façade & Foundation Upgrade
Current Phase
Construction
Completion Date
2026-04-27T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4084
Reporting Period
202605
Managing Agency
DDC
Pid
4084
Agency Project Name
Gravesend Façade & Foundation Upgrade
Current Phase
Construction
Completion Date
2026-04-27T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4085
Reporting Period
202305
Managing Agency
DDC
Pid
4085
Agency Project Name
GI - GRAVESEND BAY CSO - PHASE I
Current Phase
Design
Completion Date
2027-03-29T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4085
Reporting Period
202309
Managing Agency
DDC
Pid
4085
Agency Project Name
GI - GRAVESEND BAY CSO - PHASE I
Current Phase
Design
Completion Date
2027-03-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4085
Reporting Period
202401
Managing Agency
DDC
Pid
4085
Agency Project Name
GI - GRAVESEND BAY CSO - PHASE I
Current Phase
Design
Completion Date
2027-03-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4085
Reporting Period
202405
Managing Agency
DDC
Pid
4085
Agency Project Name
GI - GRAVESEND BAY CSO - PHASE I
Current Phase
Design
Completion Date
2028-12-20T00:00:00.000
Completion Date Type
Forecast
Variance Day
632
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4085
Reporting Period
202409
Managing Agency
DDC
Pid
4085
Agency Project Name
GI - GRAVESEND BAY CSO - PHASE I
Current Phase
Design
Completion Date
2029-06-23T00:00:00.000
Completion Date Type
Forecast
Variance Day
185
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4085
Reporting Period
202501
Managing Agency
DDC
Pid
4085
Agency Project Name
GI - GRAVESEND BAY CSO - PHASE I
Current Phase
Design
Completion Date
2029-06-23T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4085
Reporting Period
202505
Managing Agency
DDC
Pid
4085
Agency Project Name
GI - GRAVESEND BAY CSO - PHASE I
Current Phase
Design
Completion Date
2029-08-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
69
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4085
Reporting Period
202509
Managing Agency
DDC
Pid
4085
Agency Project Name
GI - GRAVESEND BAY CSO - PHASE I
Current Phase
Construction Procurement
Completion Date
2029-01-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
-213
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4085
Reporting Period
202601
Managing Agency
DDC
Pid
4085
Agency Project Name
GI - GRAVESEND BAY CSO - PHASE I
Current Phase
Construction Procurement
Completion Date
2029-01-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4085
Reporting Period
202605
Managing Agency
DDC
Pid
4085
Agency Project Name
GI - GRAVESEND BAY CSO - PHASE I
Current Phase
Construction Procurement
Completion Date
2030-01-10T00:00:00.000
Completion Date Type
Forecast
Variance Day
345
Reason For Forecast Completion Change
PROJECT DELAYED PENDING APPROVAL OF NECESSARY PERMITS
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4086
Reporting Period
202305
Managing Agency
DDC
Pid
4086
Agency Project Name
GI - GRAVESEND BAY CSO - PHASE II
Current Phase
Construction Procurement
Completion Date
2025-11-15T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4086
Reporting Period
202309
Managing Agency
DDC
Pid
4086
Agency Project Name
GI - GRAVESEND BAY CSO - PHASE II
Current Phase
Construction
Completion Date
2025-11-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
-2
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4086
Reporting Period
202401
Managing Agency
DDC
Pid
4086
Agency Project Name
GI - GRAVESEND BAY CSO - PHASE II
Current Phase
Construction
Completion Date
2025-11-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4086
Reporting Period
202405
Managing Agency
DDC
Pid
4086
Agency Project Name
GI - GRAVESEND BAY CSO - PHASE II
Current Phase
Construction
Completion Date
2025-11-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4086
Reporting Period
202409
Managing Agency
DDC
Pid
4086
Agency Project Name
GI - GRAVESEND BAY CSO - PHASE II
Current Phase
Construction
Completion Date
2025-11-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4086
Reporting Period
202501
Managing Agency
DDC
Pid
4086
Agency Project Name
GI - GRAVESEND BAY CSO - PHASE II
Current Phase
Construction
Completion Date
2025-11-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4086
Reporting Period
202505
Managing Agency
DDC
Pid
4086
Agency Project Name
GI - GRAVESEND BAY CSO - PHASE II
Current Phase
Construction
Completion Date
2025-11-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4086
Reporting Period
202509
Managing Agency
DDC
Pid
4086
Agency Project Name
GI - GRAVESEND BAY CSO - PHASE II
Current Phase
Construction
Completion Date
2025-11-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4086
Reporting Period
202601
Managing Agency
DDC
Pid
4086
Agency Project Name
GI - GRAVESEND BAY CSO - PHASE II
Current Phase
Construction
Completion Date
2026-08-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
275
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO SCHEDULING OF UTILITY WORK
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4086
Reporting Period
202605
Managing Agency
DDC
Pid
4086
Agency Project Name
GI - GRAVESEND BAY CSO - PHASE II
Current Phase
Construction
Completion Date
2026-08-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4087
Reporting Period
202305
Managing Agency
DDC
Pid
4087
Agency Project Name
GI - GRAVESEND BAY CSO - PHASE III
Current Phase
Design
Completion Date
2026-12-09T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4087
Reporting Period
202309
Managing Agency
DDC
Pid
4087
Agency Project Name
GI - GRAVESEND BAY CSO - PHASE III
Current Phase
Design
Completion Date
2027-12-09T00:00:00.000
Completion Date Type
Forecast
Variance Day
365
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4087
Reporting Period
202401
Managing Agency
DDC
Pid
4087
Agency Project Name
GI - GRAVESEND BAY CSO - PHASE III
Current Phase
Design
Completion Date
2027-12-09T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4087
Reporting Period
202405
Managing Agency
DDC
Pid
4087
Agency Project Name
GI - GRAVESEND BAY CSO - PHASE III
Current Phase
Design
Completion Date
2027-04-05T00:00:00.000
Completion Date Type
Forecast
Variance Day
-248
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4087
Reporting Period
202409
Managing Agency
DDC
Pid
4087
Agency Project Name
GI - GRAVESEND BAY CSO - PHASE III
Current Phase
Construction Procurement
Completion Date
2028-11-16T00:00:00.000
Completion Date Type
Forecast
Variance Day
591
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4087
Reporting Period
202501
Managing Agency
DDC
Pid
4087
Agency Project Name
GI - GRAVESEND BAY CSO - PHASE III
Current Phase
Construction Procurement
Completion Date
2028-11-16T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4087
Reporting Period
202505
Managing Agency
DDC
Pid
4087
Agency Project Name
GI - GRAVESEND BAY CSO - PHASE III
Current Phase
Construction Procurement
Completion Date
2029-02-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
77
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4087
Reporting Period
202509
Managing Agency
DDC
Pid
4087
Agency Project Name
GI - GRAVESEND BAY CSO - PHASE III
Current Phase
Construction
Completion Date
2029-02-18T00:00:00.000
Completion Date Type
Forecast
Variance Day
17
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4087
Reporting Period
202601
Managing Agency
DDC
Pid
4087
Agency Project Name
GI - GRAVESEND BAY CSO - PHASE III
Current Phase
Construction
Completion Date
2029-02-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
-3
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4087
Reporting Period
202605
Managing Agency
DDC
Pid
4087
Agency Project Name
GI - GRAVESEND BAY CSO - PHASE III
Current Phase
Construction
Completion Date
2029-02-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4088
Reporting Period
202305
Managing Agency
DDC
Pid
4088
Agency Project Name
GI-OWLS HEAD TRIBUTARY DRAINAGE AREAS, BROOKLYN
Current Phase
Design
Completion Date
2027-04-01T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4088
Reporting Period
202309
Managing Agency
DDC
Pid
4088
Agency Project Name
GI-OWLS HEAD TRIBUTARY DRAINAGE AREAS, BROOKLYN
Current Phase
Design
Completion Date
2029-08-04T00:00:00.000
Completion Date Type
Forecast
Variance Day
856
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4088
Reporting Period
202401
Managing Agency
DDC
Pid
4088
Agency Project Name
GI-OWLS HEAD TRIBUTARY DRAINAGE AREAS, BROOKLYN
Current Phase
Design
Completion Date
2029-08-04T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4088
Reporting Period
202405
Managing Agency
DDC
Pid
4088
Agency Project Name
GI-OWLS HEAD TRIBUTARY DRAINAGE AREAS, BROOKLYN
Current Phase
Design
Completion Date
2029-08-04T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4088
Reporting Period
202409
Managing Agency
DDC
Pid
4088
Agency Project Name
GI-OWLS HEAD TRIBUTARY DRAINAGE AREAS, BROOKLYN
Current Phase
Design
Completion Date
2029-08-04T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4088
Reporting Period
202501
Managing Agency
DDC
Pid
4088
Agency Project Name
GI-OWLS HEAD TRIBUTARY DRAINAGE AREAS, BROOKLYN
Current Phase
Design
Completion Date
2029-08-04T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4088
Reporting Period
202505
Managing Agency
DDC
Pid
4088
Agency Project Name
GI-OWLS HEAD TRIBUTARY DRAINAGE AREAS, BROOKLYN
Current Phase
Design
Completion Date
2031-02-04T00:00:00.000
Completion Date Type
Forecast
Variance Day
549
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4088
Reporting Period
202509
Managing Agency
DDC
Pid
4088
Agency Project Name
GI-OWLS HEAD TRIBUTARY DRAINAGE AREAS, BROOKLYN
Current Phase
Design
Completion Date
2031-02-04T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4088
Reporting Period
202601
Managing Agency
DDC
Pid
4088
Agency Project Name
GI-OWLS HEAD TRIBUTARY DRAINAGE AREAS, BROOKLYN
Current Phase
Design
Completion Date
2031-02-04T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000