Capital Projects Dashboard - Citywide Schedule History and Variance

This is the history all agency reported forecasts/actual project completion dates. Each row is the snapshot of data taken on each reporting period. The 'completion date type' column shows if the 'completion date' is either a forecast or actual date. Over time, a project would have one or more forecasted completion dates before it is actually completed. The 'variance' is the day difference between 'completion date' of each row and its prior reporting period. This dataset is part of the Capital Projects Dashboard.

City Government Mayor's Office of Operations (OPS) Dataset 95tx-snak 10 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4140
Reporting Period
202509
Managing Agency
DDC
Pid
4140
Agency Project Name
Inwood 10th Avenue Safety Improvements
Current Phase
Design
Completion Date
2029-06-24T00:00:00.000
Completion Date Type
Forecast
Variance Day
122
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4140
Reporting Period
202601
Managing Agency
DDC
Pid
4140
Agency Project Name
Inwood 10th Avenue Safety Improvements
Current Phase
Design
Completion Date
2029-11-23T00:00:00.000
Completion Date Type
Forecast
Variance Day
152
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4140
Reporting Period
202605
Managing Agency
DDC
Pid
4140
Agency Project Name
Inwood 10th Avenue Safety Improvements
Current Phase
Design
Completion Date
2029-11-23T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4141
Reporting Period
202305
Managing Agency
DDC
Pid
4141
Agency Project Name
JAMAICA BAY GREENWAY-PAERDEGAT AVE N CONNECTOR
Current Phase
Construction Procurement
Completion Date
2026-04-02T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4141
Reporting Period
202309
Managing Agency
DDC
Pid
4141
Agency Project Name
JAMAICA BAY GREENWAY-PAERDEGAT AVE N CONNECTOR
Current Phase
Construction Procurement
Completion Date
2025-09-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
-185
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4141
Reporting Period
202401
Managing Agency
DDC
Pid
4141
Agency Project Name
JAMAICA BAY GREENWAY-PAERDEGAT AVE N CONNECTOR
Current Phase
Construction Procurement
Completion Date
2025-09-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4141
Reporting Period
202405
Managing Agency
DDC
Pid
4141
Agency Project Name
JAMAICA BAY GREENWAY-PAERDEGAT AVE N CONNECTOR
Current Phase
Construction Procurement
Completion Date
2026-02-09T00:00:00.000
Completion Date Type
Forecast
Variance Day
133
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO BUDGETARY CONSTRAINTS
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4141
Reporting Period
202409
Managing Agency
DDC
Pid
4141
Agency Project Name
JAMAICA BAY GREENWAY-PAERDEGAT AVE N CONNECTOR
Current Phase
Construction
Completion Date
2026-06-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
112
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4141
Reporting Period
202501
Managing Agency
DDC
Pid
4141
Agency Project Name
JAMAICA BAY GREENWAY-PAERDEGAT AVE N CONNECTOR
Current Phase
Construction
Completion Date
2026-06-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4141
Reporting Period
202505
Managing Agency
DDC
Pid
4141
Agency Project Name
JAMAICA BAY GREENWAY-PAERDEGAT AVE N CONNECTOR
Current Phase
Construction
Completion Date
2026-06-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4141
Reporting Period
202509
Managing Agency
DDC
Pid
4141
Agency Project Name
JAMAICA BAY GREENWAY-PAERDEGAT AVE N CONNECTOR
Current Phase
Construction
Completion Date
2026-06-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4141
Reporting Period
202601
Managing Agency
DDC
Pid
4141
Agency Project Name
JAMAICA BAY GREENWAY-PAERDEGAT AVE N CONNECTOR
Current Phase
Construction
Completion Date
2026-06-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4141
Reporting Period
202605
Managing Agency
DDC
Pid
4141
Agency Project Name
JAMAICA BAY GREENWAY-PAERDEGAT AVE N CONNECTOR
Current Phase
Construction
Completion Date
2026-07-31T00:00:00.000
Completion Date Type
Forecast
Variance Day
60
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4142
Reporting Period
202305
Managing Agency
DDC
Pid
4142
Agency Project Name
Central Courts Building:120 Schermerhorn St.
Current Phase
Construction
Completion Date
2024-05-17T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4142
Reporting Period
202309
Managing Agency
DDC
Pid
4142
Agency Project Name
Central Courts Building:120 Schermerhorn St.
Current Phase
Construction
Completion Date
2024-05-17T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4142
Reporting Period
202401
Managing Agency
DDC
Pid
4142
Agency Project Name
Central Courts Building:120 Schermerhorn St.
Current Phase
Construction
Completion Date
2024-05-17T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4142
Reporting Period
202405
Managing Agency
DDC
Pid
4142
Agency Project Name
Central Courts Building:120 Schermerhorn St.
Current Phase
Construction
Completion Date
2024-10-03T00:00:00.000
Completion Date Type
Forecast
Variance Day
139
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN HAZARDOUS CONDITIONS
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4142
Reporting Period
202409
Managing Agency
DDC
Pid
4142
Agency Project Name
Central Courts Building:120 Schermerhorn St.
Current Phase
Construction
Completion Date
2024-10-25T00:00:00.000
Completion Date Type
Actual
Variance Day
22
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4143
Reporting Period
202305
Managing Agency
DDC
Pid
4143
Agency Project Name
East 3rd Street Shelter Building Upgrade
Current Phase
Design
Completion Date
2026-11-17T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4143
Reporting Period
202309
Managing Agency
DDC
Pid
4143
Agency Project Name
East 3rd Street Shelter Building Upgrade
Current Phase
Design
Completion Date
2026-11-17T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4143
Reporting Period
202401
Managing Agency
DDC
Pid
4143
Agency Project Name
East 3rd Street Shelter Building Upgrade
Current Phase
Design
Completion Date
2026-11-17T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4143
Reporting Period
202405
Managing Agency
DDC
Pid
4143
Agency Project Name
East 3rd Street Shelter Building Upgrade
Current Phase
Design
Completion Date
2027-05-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
194
Reason For Forecast Completion Change
PROJECT DELAYED PENDING APPROVAL OF NECESSARY PERMITS
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4143
Reporting Period
202409
Managing Agency
DDC
Pid
4143
Agency Project Name
East 3rd Street Shelter Building Upgrade
Current Phase
Design
Completion Date
2027-05-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4143
Reporting Period
202501
Managing Agency
DDC
Pid
4143
Agency Project Name
East 3rd Street Shelter Building Upgrade
Current Phase
Construction Procurement
Completion Date
2028-08-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
436
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4143
Reporting Period
202505
Managing Agency
DDC
Pid
4143
Agency Project Name
East 3rd Street Shelter Building Upgrade
Current Phase
Construction Procurement
Completion Date
2028-08-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4143
Reporting Period
202509
Managing Agency
DDC
Pid
4143
Agency Project Name
East 3rd Street Shelter Building Upgrade
Current Phase
Construction Procurement
Completion Date
2028-08-08T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4143
Reporting Period
202601
Managing Agency
DDC
Pid
4143
Agency Project Name
East 3rd Street Shelter Building Upgrade
Current Phase
Construction Procurement
Completion Date
2028-04-02T00:00:00.000
Completion Date Type
Forecast
Variance Day
-128
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4143
Reporting Period
202605
Managing Agency
DDC
Pid
4143
Agency Project Name
East 3rd Street Shelter Building Upgrade
Current Phase
Construction
Completion Date
2028-04-02T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4144
Reporting Period
202305
Managing Agency
DDC
Pid
4144
Agency Project Name
Laurelton Roof Replacement
Current Phase
Construction
Completion Date
2024-08-12T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4144
Reporting Period
202309
Managing Agency
DDC
Pid
4144
Agency Project Name
Laurelton Roof Replacement
Current Phase
Construction
Completion Date
2024-08-12T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4144
Reporting Period
202401
Managing Agency
DDC
Pid
4144
Agency Project Name
Laurelton Roof Replacement
Current Phase
Construction
Completion Date
2024-08-12T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4144
Reporting Period
202405
Managing Agency
DDC
Pid
4144
Agency Project Name
Laurelton Roof Replacement
Current Phase
Construction
Completion Date
2024-08-12T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4144
Reporting Period
202409
Managing Agency
DDC
Pid
4144
Agency Project Name
Laurelton Roof Replacement
Current Phase
Construction
Completion Date
2024-07-22T00:00:00.000
Completion Date Type
Actual
Variance Day
-21
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4145
Reporting Period
202305
Managing Agency
DDC
Pid
4145
Agency Project Name
Leonard Roof Replacement
Current Phase
Construction
Completion Date
2024-07-25T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4145
Reporting Period
202309
Managing Agency
DDC
Pid
4145
Agency Project Name
Leonard Roof Replacement
Current Phase
Construction
Completion Date
2024-07-25T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4145
Reporting Period
202401
Managing Agency
DDC
Pid
4145
Agency Project Name
Leonard Roof Replacement
Current Phase
Construction
Completion Date
2024-07-25T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4145
Reporting Period
202405
Managing Agency
DDC
Pid
4145
Agency Project Name
Leonard Roof Replacement
Current Phase
Construction
Completion Date
2024-09-03T00:00:00.000
Completion Date Type
Forecast
Variance Day
40
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4145
Reporting Period
202409
Managing Agency
DDC
Pid
4145
Agency Project Name
Leonard Roof Replacement
Current Phase
Construction
Completion Date
2024-10-17T00:00:00.000
Completion Date Type
Actual
Variance Day
44
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4146
Reporting Period
202305
Managing Agency
DDC
Pid
4146
Agency Project Name
Lexington Avenue Pedestrian Safety Improvements
Current Phase
Pre-Design
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4146
Reporting Period
202309
Managing Agency
DDC
Pid
4146
Agency Project Name
Lexington Avenue Pedestrian Safety Improvements
Current Phase
Design
Completion Date Type
Forecast
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4146
Reporting Period
202401
Managing Agency
DDC
Pid
4146
Agency Project Name
Lexington Avenue Pedestrian Safety Improvements
Current Phase
Design
Completion Date Type
Forecast
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4146
Reporting Period
202405
Managing Agency
DDC
Pid
4146
Agency Project Name
Lexington Avenue Pedestrian Safety Improvements
Current Phase
Design
Completion Date Type
Forecast
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4146
Reporting Period
202409
Managing Agency
DDC
Pid
4146
Agency Project Name
Lexington Avenue Pedestrian Safety Improvements
Current Phase
Design
Completion Date Type
Forecast
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4146
Reporting Period
202501
Managing Agency
DDC
Pid
4146
Agency Project Name
Lexington Avenue Pedestrian Safety Improvements
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4146
Reporting Period
202505
Managing Agency
DDC
Pid
4146
Agency Project Name
Lexington Avenue Pedestrian Safety Improvements
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4146
Reporting Period
202509
Managing Agency
DDC
Pid
4146
Agency Project Name
Lexington Avenue Pedestrian Safety Improvements
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4146
Reporting Period
202601
Managing Agency
DDC
Pid
4146
Agency Project Name
Lexington Avenue Pedestrian Safety Improvements
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4146
Reporting Period
202605
Managing Agency
DDC
Pid
4146
Agency Project Name
Lexington Avenue Pedestrian Safety Improvements
Current Phase
Construction
Completion Date Type
Forecast
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4147
Reporting Period
202305
Managing Agency
DDC
Pid
4147
Agency Project Name
Lining Interceptor Assets in Rockaway
Current Phase
Design
Completion Date
2027-05-15T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4147
Reporting Period
202309
Managing Agency
DDC
Pid
4147
Agency Project Name
Lining Interceptor Assets in Rockaway
Current Phase
Design
Completion Date
2027-05-15T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000