Capital Projects Dashboard - Citywide Schedule History and Variance

This is the history all agency reported forecasts/actual project completion dates. Each row is the snapshot of data taken on each reporting period. The 'completion date type' column shows if the 'completion date' is either a forecast or actual date. Over time, a project would have one or more forecasted completion dates before it is actually completed. The 'variance' is the day difference between 'completion date' of each row and its prior reporting period. This dataset is part of the Capital Projects Dashboard.

City Government Mayor's Office of Operations (OPS) Dataset 95tx-snak 10 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4176
Reporting Period
202501
Managing Agency
DDC
Pid
4176
Agency Project Name
STORM SEWER IN KING STREET, SI
Current Phase
Design
Completion Date
2031-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-03-03T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4176
Reporting Period
202505
Managing Agency
DDC
Pid
4176
Agency Project Name
STORM SEWER IN KING STREET, SI
Current Phase
Design
Completion Date
2031-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-03-03T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4176
Reporting Period
202509
Managing Agency
DDC
Pid
4176
Agency Project Name
STORM SEWER IN KING STREET, SI
Current Phase
Design
Completion Date
2031-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4176
Reporting Period
202601
Managing Agency
DDC
Pid
4176
Agency Project Name
STORM SEWER IN KING STREET, SI
Current Phase
Design
Completion Date
2031-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-20T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4176
Reporting Period
202605
Managing Agency
DDC
Pid
4176
Agency Project Name
STORM SEWER IN KING STREET, SI
Current Phase
Design
Completion Date
2031-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-20T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4177
Reporting Period
202305
Managing Agency
DDC
Pid
4177
Agency Project Name
NEW UTRECH LIBRARY MAJOR RENOVATIONS
Current Phase
Pre-Design
Completion Date
2029-02-27T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4177
Reporting Period
202309
Managing Agency
DDC
Pid
4177
Agency Project Name
NEW UTRECH LIBRARY MAJOR RENOVATIONS
Current Phase
Pre-Design
Completion Date
2029-04-27T00:00:00.000
Completion Date Type
Forecast
Variance Day
59
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4177
Reporting Period
202401
Managing Agency
DDC
Pid
4177
Agency Project Name
NEW UTRECH LIBRARY MAJOR RENOVATIONS
Current Phase
Pre-Design
Completion Date
2029-04-27T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4177
Reporting Period
202405
Managing Agency
DDC
Pid
4177
Agency Project Name
NEW UTRECH LIBRARY MAJOR RENOVATIONS
Current Phase
Design
Completion Date
2029-08-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
108
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN HAZARDOUS CONDITIONS
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4177
Reporting Period
202409
Managing Agency
DDC
Pid
4177
Agency Project Name
NEW UTRECH LIBRARY MAJOR RENOVATIONS
Current Phase
Design
Completion Date
2029-08-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4177
Reporting Period
202501
Managing Agency
DDC
Pid
4177
Agency Project Name
NEW UTRECH LIBRARY MAJOR RENOVATIONS
Current Phase
Design
Completion Date
2029-08-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4177
Reporting Period
202505
Managing Agency
DDC
Pid
4177
Agency Project Name
NEW UTRECH LIBRARY MAJOR RENOVATIONS
Current Phase
Design
Completion Date
2029-08-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4177
Reporting Period
202509
Managing Agency
DDC
Pid
4177
Agency Project Name
NEW UTRECH LIBRARY MAJOR RENOVATIONS
Current Phase
Design
Completion Date
2029-08-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4177
Reporting Period
202601
Managing Agency
DDC
Pid
4177
Agency Project Name
NEW UTRECH LIBRARY MAJOR RENOVATIONS
Current Phase
Design
Completion Date
2029-08-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4177
Reporting Period
202605
Managing Agency
DDC
Pid
4177
Agency Project Name
NEW UTRECH LIBRARY MAJOR RENOVATIONS
Current Phase
Design
Completion Date
2029-08-13T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4178
Reporting Period
202305
Managing Agency
DDC
Pid
4178
Agency Project Name
signature theater ph 3
Current Phase
Construction
Completion Date
2024-06-30T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4178
Reporting Period
202309
Managing Agency
DDC
Pid
4178
Agency Project Name
signature theater ph 3
Current Phase
Construction
Completion Date
2024-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2023-09-01T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4178
Reporting Period
202401
Managing Agency
DDC
Pid
4178
Agency Project Name
signature theater ph 3
Current Phase
Construction
Completion Date
2024-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2023-09-01T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4178
Reporting Period
202405
Managing Agency
DDC
Pid
4178
Agency Project Name
signature theater ph 3
Current Phase
Construction
Completion Date
2024-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4178
Reporting Period
202409
Managing Agency
DDC
Pid
4178
Agency Project Name
signature theater ph 3
Current Phase
Construction
Completion Date
2024-06-30T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4178
Reporting Period
202501
Managing Agency
DDC
Pid
4178
Agency Project Name
signature theater ph 3
Current Phase
Construction
Completion Date
2025-09-19T00:00:00.000
Completion Date Type
Forecast
Variance Day
446
Data Date
2025-03-03T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4178
Reporting Period
202505
Managing Agency
DDC
Pid
4178
Agency Project Name
signature theater ph 3
Current Phase
Construction
Completion Date
2025-09-19T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-03-03T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4178
Reporting Period
202509
Managing Agency
DDC
Pid
4178
Agency Project Name
signature theater ph 3
Current Phase
Construction
Completion Date
2027-09-19T00:00:00.000
Completion Date Type
Forecast
Variance Day
730
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4178
Reporting Period
202601
Managing Agency
DDC
Pid
4178
Agency Project Name
signature theater ph 3
Current Phase
Construction
Completion Date
2027-09-19T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-20T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4178
Reporting Period
202605
Managing Agency
DDC
Pid
4178
Agency Project Name
signature theater ph 3
Current Phase
Construction
Completion Date
2027-09-19T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-20T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4179
Reporting Period
202305
Managing Agency
DDC
Pid
4179
Agency Project Name
60 CENTRE ST. - RECONSTRUCTION
Current Phase
Design
Completion Date
2028-11-01T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4179
Reporting Period
202309
Managing Agency
DDC
Pid
4179
Agency Project Name
60 CENTRE ST. - RECONSTRUCTION
Current Phase
Design
Completion Date
2028-11-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4179
Reporting Period
202401
Managing Agency
DDC
Pid
4179
Agency Project Name
60 CENTRE ST. - RECONSTRUCTION
Current Phase
Design
Completion Date
2028-11-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4179
Reporting Period
202405
Managing Agency
DDC
Pid
4179
Agency Project Name
60 CENTRE ST. - RECONSTRUCTION
Current Phase
Design
Completion Date
2028-11-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4179
Reporting Period
202409
Managing Agency
DDC
Pid
4179
Agency Project Name
60 CENTRE ST. - RECONSTRUCTION
Current Phase
Design
Completion Date
2028-11-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4179
Reporting Period
202501
Managing Agency
DDC
Pid
4179
Agency Project Name
60 CENTRE ST. - RECONSTRUCTION
Current Phase
Design
Completion Date
2028-07-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
-123
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4179
Reporting Period
202505
Managing Agency
DDC
Pid
4179
Agency Project Name
60 CENTRE ST. - RECONSTRUCTION
Current Phase
Design
Completion Date
2029-02-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
215
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4179
Reporting Period
202509
Managing Agency
DDC
Pid
4179
Agency Project Name
60 CENTRE ST. - RECONSTRUCTION
Current Phase
Design
Completion Date
2029-02-01T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4179
Reporting Period
202601
Managing Agency
DDC
Pid
4179
Agency Project Name
60 CENTRE ST. - RECONSTRUCTION
Current Phase
Design
Completion Date
2029-07-09T00:00:00.000
Completion Date Type
Forecast
Variance Day
158
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4179
Reporting Period
202605
Managing Agency
DDC
Pid
4179
Agency Project Name
60 CENTRE ST. - RECONSTRUCTION
Current Phase
Design
Completion Date
2029-11-09T00:00:00.000
Completion Date Type
Forecast
Variance Day
123
Reason For Forecast Completion Change
PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4180
Reporting Period
202305
Managing Agency
DDC
Pid
4180
Agency Project Name
New York Public Library Pedestrian Improvements
Current Phase
Design
Completion Date
2029-05-02T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4180
Reporting Period
202309
Managing Agency
DDC
Pid
4180
Agency Project Name
New York Public Library Pedestrian Improvements
Current Phase
Design
Completion Date
2029-05-02T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4180
Reporting Period
202401
Managing Agency
DDC
Pid
4180
Agency Project Name
New York Public Library Pedestrian Improvements
Current Phase
Design
Completion Date
2029-05-02T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-02-16T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4180
Reporting Period
202405
Managing Agency
DDC
Pid
4180
Agency Project Name
New York Public Library Pedestrian Improvements
Current Phase
Design
Completion Date
2029-05-02T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202409
Reporting Period: 202409 • Managing Agency: DDC • Pid: 4180
Reporting Period
202409
Managing Agency
DDC
Pid
4180
Agency Project Name
New York Public Library Pedestrian Improvements
Current Phase
Design
Completion Date
2029-05-02T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-11-07T00:00:00.000
202501
Reporting Period: 202501 • Managing Agency: DDC • Pid: 4180
Reporting Period
202501
Managing Agency
DDC
Pid
4180
Agency Project Name
New York Public Library Pedestrian Improvements
Current Phase
Design
Completion Date
2029-05-02T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-02-26T00:00:00.000
202505
Reporting Period: 202505 • Managing Agency: DDC • Pid: 4180
Reporting Period
202505
Managing Agency
DDC
Pid
4180
Agency Project Name
New York Public Library Pedestrian Improvements
Current Phase
Design
Completion Date
2029-05-02T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-05-30T00:00:00.000
202509
Reporting Period: 202509 • Managing Agency: DDC • Pid: 4180
Reporting Period
202509
Managing Agency
DDC
Pid
4180
Agency Project Name
New York Public Library Pedestrian Improvements
Current Phase
Design
Completion Date
2029-05-02T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2025-10-23T00:00:00.000
202601
Reporting Period: 202601 • Managing Agency: DDC • Pid: 4180
Reporting Period
202601
Managing Agency
DDC
Pid
4180
Agency Project Name
New York Public Library Pedestrian Improvements
Current Phase
Design
Completion Date
2029-05-02T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2026-03-16T00:00:00.000
202605
Reporting Period: 202605 • Managing Agency: DDC • Pid: 4180
Reporting Period
202605
Managing Agency
DDC
Pid
4180
Agency Project Name
New York Public Library Pedestrian Improvements
Current Phase
Design
Completion Date
2032-05-04T00:00:00.000
Completion Date Type
Forecast
Variance Day
1098
Data Date
2026-06-23T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4181
Reporting Period
202305
Managing Agency
DDC
Pid
4181
Agency Project Name
NEW STRM/SAN SWRS IN WILLOW AVE., SI
Current Phase
Construction
Completion Date
2023-12-29T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000
202309
Reporting Period: 202309 • Managing Agency: DDC • Pid: 4181
Reporting Period
202309
Managing Agency
DDC
Pid
4181
Agency Project Name
NEW STRM/SAN SWRS IN WILLOW AVE., SI
Current Phase
Construction
Completion Date
2023-12-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-01-04T00:00:00.000
202401
Reporting Period: 202401 • Managing Agency: DDC • Pid: 4181
Reporting Period
202401
Managing Agency
DDC
Pid
4181
Agency Project Name
NEW STRM/SAN SWRS IN WILLOW AVE., SI
Current Phase
Construction
Completion Date
2023-12-29T00:00:00.000
Completion Date Type
Forecast
Variance Day
0
Data Date
2024-01-04T00:00:00.000
202405
Reporting Period: 202405 • Managing Agency: DDC • Pid: 4181
Reporting Period
202405
Managing Agency
DDC
Pid
4181
Agency Project Name
NEW STRM/SAN SWRS IN WILLOW AVE., SI
Current Phase
Construction
Completion Date
2023-12-29T00:00:00.000
Completion Date Type
Actual
Variance Day
0
Data Date
2024-07-18T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DDC • Pid: 4182
Reporting Period
202305
Managing Agency
DDC
Pid
4182
Agency Project Name
Design-Bid-Build Green Infrastructure Precast Porous Concrete Panels within the Bronx River and Westchester Creek Watersheds
Current Phase
Design
Completion Date
2027-08-10T00:00:00.000
Completion Date Type
Forecast
Data Date
2023-09-01T00:00:00.000